incose pmi simplifyingcomplexprojectmanagement2015!05!05publish

31
March 2015 Implementing SE and Advanced PM in Large and Co mplex Projects: The Case of A New Airport Opera tional Readiness Project Prof. Dov Dori, Prof Aaron Shenhar, Ori Orhof

Upload: ulick82

Post on 10-Mar-2016

224 views

Category:

Documents


0 download

DESCRIPTION

Interesting info

TRANSCRIPT

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 1/31

March 2015

Implementing SE and Advanced PM

in Large and Complex Projects:

The Case of A New Airport Operational Readiness Project

Prof. Dov Dori, Prof Aaron Shenhar, Ori Orhof

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 2/31

March 2015

לכ נים יחו לי  ?נעד-אה 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 3/31

March 2015

Systems Engineering

,מכא.טכנולוגהנדסת מערכות היא ניהול המושתת על ידע 

מערכות שתשתיתןמהנדס מערכות הוא אדם המנהל 

מהקונקורד לכיפת)ולכן עליו להיות מהנדס,טכנולוגית

(.'41ע,ברזל

3

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 4/31

4

ORAT - Organizational Readiness and Airport Transfer 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 5/31

5

ORAT - Operational Readiness and Airport Transfer 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 6/31

Complex Systems (Products) and Complex Projects 

Complex SystemsMultiplicity of diverse, connected, interdependent, and

adapting components

6

Complex Projects 

• Structural complexity

• Uncertainty

• Urgency• Dynamics

• Socio-Political 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 7/31

ORAT - Operational Readiness and Airport Transfer 

1st level – All airport

1. Departing passenger

2. Arriving passenger

3. Departing baggage

4. Arriving baggage

5. Departing cargo

6. Arriving cargo

7. Departing airplane

8. Arriving airplane

9. Transfer

10. Lateral processes

7

2nd level – Departing pax.

1. Arriving to airport

2. Traffic and parking

3. Entering to terminal

4. Security profiling

5. Check-in

6. Check-point

7. Passport control

8. Departure hall

9. Boarding

3rd level – Check-in

1. Regular

2. Oversized baggage

3. Supersized baggage

4. Overweight

5. Animals

6. Late passenger

7. Wheelchaired

8. Unaccompanied child

9. VIP

10. Diplomat

11. … 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 8/31

ORAT Project – Complex Product and Complex Project 

• Processes

 – 10 Core processes (1st level) – ~100 Secondary processes (2nd level)

 – ~700 Sub-processes (3rd level)

• Process planning

 – SOP (Standard Operating Procedure)

 – Procurement

 – IT

 – Bids (subcontracting and

concessionaries)

 – Construction changes

 – Recruitment

 – Instruction & training

8

Complex Systems

Multiplicity of diverse,

connected,

interdependent, and

adapting components

Complex Projects 

• Structural complexity

• Uncertainty

• Urgency

• Dynamics

• Socio-Political 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 9/31

Systems Engineering “Vee Model”

9 Source: SE Handbook, 2011 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 10/31

Vee Model Adapted for ORAT 

10

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 11/31

ORAT Processes = ORAT ComponentsSome Components are More Critical than the Others 

• Processes

 – 10 Core processes (1st level)

 – ~100 Secondary processes (2nd level)

 – ~700 Sub-processes (3rd level)

• Process planning – SOP –  Standard Operating Procedure

 – Purchasing

 – IT

 – Bids (subcontracting and concessionaries)

 – Construction changes

 – Recruitment

 – Instruction & training11

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 12/31

What is a Critical Component? 

A 'critical component' is defined as a unit of work at the

subproject level which imposes exceptional risk to the

success of the project. 

12

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 13/31

What is Project Success? 

Scope

ScheduleBudget

Scope

ScheduleBudget

Value

Project Governance - Efficiency 

Product Management - Effectiveness 

13

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 14/31

Efficiency Vs. Effectiveness 

• Product management  –  to do the right things –  Effectiveness (Scope, Value to the Customer)

• Project governance –  to do things right  –  Efficiency

(Budget and Schedule)

No project is ever a complete failure - it can always

serve as a bad example (Murphy’s book of laws - the futility factor ) 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 15/31

What is a Critical Component? 

A 'critical component' is defined as a unit of work at the

subproject level which imposes exceptional risk to the

success of the project.

The Success of the Project is:

1. The Efficiency of the project governance

2. The Effectiveness of the product 

15

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 16/31

Can’t see the forest for the trees 

Can’t see the trees for the forest 

16

Components of Complex Projects / Programs 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 17/31

Critical Components Analysis - CCA(The risks to the project’s success) 

1. The efficiency of the project governance – 

 Challenge (difficulty)

2. The effectiveness of the product –  Vitality (importance) 

17

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 18/31

The Challenge (Difficulty) to the Project 

• Uncertainty of the method (way) or goals

• Structural complexity

• Urgency

• Regulation

• Organizational Bureaucracy

• Lack of resources

18

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 19/31

The Vitality (Importance) to the Product 

• Value to the customer

• Competitive advantage

• Functional centrality 

19

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 20/31

Critical Components Analysis - CCA 

1. The efficiency of the project governance –  Challenge (difficulty)

2. The effectiveness of the product management –  Vitality (importance) 

20

Criticality Vitality Challenge Process 

Medium High 

Low 

Arriving to

airport 

Medium Medium Low Traffic and

parking 

High High High Check-in

(SSBD) 

High High High Passport

control 

Medium High Low Boarding 

Low Low Low Gardening 

CCA of Departing-Passenger process 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 21/31

The Dimension of Challenge and Vitality 

21

 

Challenge 

difficulty to the completion of the

component

Vitalityimportance to the success of the product

Internal

:Solution

The level of uncertainty of the solution

required to achieve the component

:Function

How central is the component to the

functionality of the product

External

:Constraints

Demands and constraints imposed byexternal to the project elements (e.g.

regulation, bureaucracy, management)

:Value

The contribution of the specificcomponent to the competitive

advantage of the product over its

immediate competition or the value it

provides to customers and users

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 22/31

Constraints Value

Function

Solution

Uncertainty

Essential

Central

Marginal

Unknown-Unknowns

Known-Unknowns

Known-Knowns

LimitingRestrictingBounding

Nice-to-Have Better-Have Must-Have

External         I      n       t      e      r      n      a        l

Vitality

Effectiveness of the product

Challenge

Efficiency of the project management

The Diamond of the Sub-Project Level

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 23/31

23

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 24/31

Constraints Value

Function

Solution Uncertainty

The Component’s Diamond Managerial Implications 

Early start (ASAP)Finish as soon as possible

Functional Tests

Early start (ASAP)

Stakeholder management

Regulation management

Risk management

Time & budget slacks

Early start (ASAP)

Functional modelling

POC and prototyping

Management Reviews

Learning and selectionism

Late design freeze

Time & budget slacks

Early start (ASAP)

Customers testing and feedback 

Marketing involvementProduct prototyping 

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 25/31

In Conclusion 

• Processes

 – 10 Core processes (1st level)

 – ~100 Secondary processes (2nd level)

 – ~700 Sub-processes (3rd level)

• Process planning – SOP –  Standard Operating Procedure

 – Purchasing

 – IT

 – Bids (subcontracting and concessionaries)

 – Construction changes

 – Recruitment

 – Instruction & training25

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 26/31

Vee Model Adapted for ORAT 

26

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 27/31

Critical Components Analysis - CCA(The risks to the project’s success) 

1. The efficiency of the project governance – 

 Challenge (difficulty)

2. The effectiveness of the product –  Vitality (importance) 

27

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 28/31

Constraints Value

Function

Solution

Uncertainty

Essential

Central

Marginal

Unknown-Unknowns

Known-Unknowns

Known-Knowns

LimitingRestrictingBounding

Nice-to-Have Better-Have Must-Have

External         I      n       t      e      r      n      a        l

Vitality

Effectiveness of the product

Challenge

Efficiency of the project management

The Diamond of the Sub-Project Level

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 29/31

Constraints Value

Function

Solution Uncertainty

Small Diamond Managerial Implications

Early start (ASAP)Finish as soon as possible

Functional Tests

Early start (ASAP)

Stakeholder management

Regulation management

Risk management

Time & budget slacks

Early start (ASAP)

Functional modellingPOC and prototyping

Management Reviews

Learning and selectionism

Late design freeze

Time & budget slacks

Early start (ASAP)

Customers testing and feedback 

Marketing involvementProduct prototyping 

Addi i l I d i

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 30/31

Additional Industries:

Complex Projects of Complex Systems (Products) 

30

?

7/21/2019 INCOSE PMI SimplifyingComplexProjectManagement2015!05!05Publish

http://slidepdf.com/reader/full/incose-pmi-simplifyingcomplexprojectmanagement20150505publish 31/31

?   י אם 

ו בל 

נים יח 

 כ 

יל

 

נעד-ה  

31

Implementing SE and Advanced PM in Large and Complex

Projects

Ori Orhof ori@orhof com