Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Document details
Revised by: Reviewed by: Endorsed by:
-------------------------------------------- -------------------------------------- ------------------------------------- Jared Looker Irina Kliger Matthew Saviana
Regional Safety Manager Regional Environmental Project Director Manager
Content ID: APRB-IERP Revision No: 3 Revised: 07/11/2018
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Document Control
This Plan interfaces with the other associated plans, which together describe the proposed overall project management system for the Project.
The latest revision of this plan is available on the Fulton Hogan server. Distribution of this Plan by “hard copy” will be to those detailed on the distribution list above. If any unsigned hard copies of this document are printed, they are valid only on the day of printing.
The revision number is included at the bottom of each page. When revisions occur, the entire document will be issued with the revision number updated accordingly for each owner of a controlled copy.
Attachments and appendices to this Plan are revised independently of this Plan.
The relevant parts of this Plan are publicly available on the Fulton Hogan website, as required by Clause 98D(3) and (4) of the Protection of the Environment Operations (General) Regulation 2009.
Revision History
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 2 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Roads and Maritime Services approval and authorisation
Title Incident and Emergency Response Plan Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Accepted on behalf of NSW Roads and Maritime Services by
Peter Hawkins
Signed
Dated 08/11/18
Environmental Representative endorsement
Endorsed by the Environmental Representative
Toby Hobbs
Signed
Dated 08/11/18
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 3 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Table of Contents
List of tables.................................................................................................................................... 5
1. Introduction.............................................................................................................................. 6
1.1. Purpose and scope........................................................................................................... 6 1.2. Project description ............................................................................................................ 6
2. Planning................................................................................................................................... 7
2.1. Planning considerations.................................................................................................... 7 2.2. Emergency management organisational structure ............................................................ 7 2.3. Consultation...................................................................................................................... 8
3. Incident and emergency response ........................................................................................... 8
3.1. Incident and emergency response flowcharts ................................................................... 8 3.2. Site layout plans ............................................................................................................... 9 3.3. Emergency muster area.................................................................................................... 9 3.4. Emergency equipment ...................................................................................................... 9 3.5. Testing - desktop simulations/exercises/drills ................................................................. 10 3.6. Incident (vehicle/public/environmental – non-work related) ............................................. 10
4. Pollution incident response management............................................................................... 11
4.1. Pollution incident response management plan legislative requirements.......................... 11 4.2. Description and likelihood of hazards.............................................................................. 11 4.3. Pollution incident notification protocol ............................................................................. 11 4.4. Pre-emptive actions ........................................................................................................ 12 4.5. Contact details ................................................................................................................ 12 4.6. Inventory of pollutants..................................................................................................... 12 4.7. Communicating with neighbours and local community .................................................... 13 4.8. Minimising harm to persons on premises ........................................................................ 13 4.9. Maps............................................................................................................................... 13
5. Training.................................................................................................................................. 14
6. Responsibilities...................................................................................................................... 16
7. Revision................................................................................................................................. 16
8. Definitions.............................................................................................................................. 17
9. Procedures ............................................................................................................................ 17
10. Appendices............................................................................................................................ 17
Appendix A – Incident and emergency response contacts......................................................... 18 Appendix B – Incident and emergency response flowcharts ...................................................... 19 B01 - Incident and emergency response flowchart - initial response (R.E.A.C.T) ...................... 20 B02 - Incident and emergency response flowchart - emergency communications ..................... 22 B03 - Incident and emergency response flowchart - emergency evacuation.............................. 24 B04 - Incident and emergency response flowchart - crisis management ................................... 26 B05 - Incident and emergency response flowchart – asbestos .................................................. 28 B06 - Incident and emergency response flowchart - bomb threat or other serious threat........... 29 B07 - Incident and emergency response flowchart - breach of aviation airspace obstacle limitation surface (OLS)............................................................................................................. 30 B08 - Incident and emergency response flowchart - plane or object landing in work area ......... 31 B09 - Incident and emergency response flowchart - bushfire .................................................... 32
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 4 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B10 - Incident and emergency response flowchart - chemical - oil and fuel spills ...................... 33 B11 - Incident and emergency response flowchart - emergency situation at height ................... 34 B12 - Incident and emergency response flowchart - fall arrest .................................................. 36 B13 - Incident and emergency response flowchart - major fires or explosions........................... 37 B14 - Incident and emergency response flowchart - robbery or hostile intruder......................... 38 B15 - Incident and emergency response flowchart - serious injury ............................................ 39 B16 - Incident and emergency response flowchart - service strikes – electricity cables............. 41 B17 - Incident and emergency response flowchart - service strikes and leaks - gas.................. 42 B18 - Incident and emergency response flowchart – service strikes and leaks - water or sewerage pipes ......................................................................................................................... 43 B19 - Incident and emergency response flowchart - storms and flooding – process.................. 44 B20 - Incident and emergency response flowchart - trench collapse ......................................... 45 B21 - Incident and emergency response flowchart - vehicle accidents and plant rollovers ........ 46 Appendix C – Site layout plans.................................................................................................. 47 Appendix D – PIRMP legislative compliance matrix................................................................... 48 Appendix E – Environmental incidents and emergencies risk assessment ................................ 52 Appendix F – Pollution (or other environmental) incident notification protocol ........................... 55
List of tables
Table 1: EPC members ...........................................................................................................................................7
Table 2: Consultation plan .......................................................................................................................................8
Table 3: Core incident or emergency scenarios ......................................................................................................8
Table 4: Specific incident or emergency scenario flowcharts (see appendices of this Plan) ..................................8
Table 5: Potential pollutant inventory ....................................................................................................................12
Table 6: Training requirements..............................................................................................................................14
Table 7: RASCI chart.............................................................................................................................................16
Table 8: Definitions ................................................................................................................................................17
Glossary/Acronyms
APRb Albion Park Rail bypass, the Project
CEMP Construction Environmental Management Plan
EC Emergency Controller
EPC Emergency Planning Committee
ERT Emergency Response Team
IERP Incident and Emergency Response Plan
OLS Obstacle Limitation Surface
PIRMP Pollution Incident Response Management Plan
PMP Project Management Plan
POEO Act Protection of the Environment Operations Act 1997
POEO(G) Regulation
Protection of the Environment Operations (General) Regulation 2009.
SWMS Safe Work Method Statement
WRA Workplace Risk Assessment
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 5 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
1. Introduction
This Incident and Emergency Response Plan (IERP) applies to any incident or emergency occurring on Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats) (the Project), or involving Fulton Hogan’s personnel away from their regular place of work but while on company business.
This IERP shall be used in conjunction with the Workplace Health and Safety Management Plan (WHSMP), Construction Environmental Management Plan (CEMP) and the relevant sub-plans, Traffic and Transport Management Sub-plan and Aviation Method of Working Plan. Together these documents outline the mandatory requirements for preparing for, responding to and recovering from any safety or environmental incidents or emergencies, including where assistance from local emergency services is required.
This IERP shall also be used in conjunction with Fulton Hogan’s Incident Investigation, Reporting and Notification procedure, which provides umbrella guidance on corporate requirements for notification, recording, investigation and reporting of all incidents, including significant safety and environmental incidents.
This IERP has also been developed to ensure compliance with obligations under the State Disaster Plan (DISPLAN) and will work with Illawarra Emergency Management District.
These DISPLANs provides framework for escalating emergency response to an incident, where the relevant Emergency Services Incident Controller (in consultation with the local Emergency Management Committee) has determined that resources of the local emergency service provider are insufficient to deal with the threat.
This IERP has also been developed to ensure compliance with the requirements of Roads and Maritime Environmental Incident Classification and Reporting Procedure for the reporting of environmental incidents as detailed in Section 4.3 of this Plan.
1.1. Purpose and scope
This IERP describes the strategy for preparing, responding to and recovering from any safety or environmental incident during construction of the Project. It also provides an integrated approach to management of both environmental and safety incidents where the assistance of external emergency response agencies is required.
This IERP does not address the broader company response to critical incidents or crises. Crises are defined as events or developments, real or perceived, which threaten the viability of the company and have the potential to threaten the safety or wellbeing of workers and others, the environment, or the integrity, performance, reputation of the company. Where such incidents stem from project-based incidents or emergencies, they shall be managed in accordance with this Plan, The Project Management Plan (PMP) and the requirements of the Crisis Management Procedure.
1.2. Project description
The project is known as the Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats). The project would provide motorists with a more consistent travel experience between Sydney, Wollongong and the NSW South Coast. It would increase the capacity of the road network to cope with the additional traffic generated by current and future residential development in the area.
A detailed description of the Project is provided in the PMP.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 6 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
2. Planning
2.1. Planning considerations
The following aspects were identified as relevant considerations in the emergency management planning process:
Integration and consistency with local area DISPLAN
The impact of a major emergency on neighbouring facilities, businesses and community
Regular site visits by emergency services personnel to maintain familiarisation with the site (emergency) accesses and resources as it changes over time
Emergency communication protocols for the relevant agencies to ensure coordinated approach, specifically:
Emergency Response Agencies, (i.e. NSW Police, Ambulance Service, Fire Rescue and Hazmat, State Emergency Service or specialist emergency providers)
Roads and Maritime
SafeWork NSW
Wollongong City Council
Shellharbour City Council
Utilities such as Ausgrid, Telstra / Optus/ Jemena / Transgrid / AAPT / Nextgen / Caltex
Office of Environment and Heritage, and
Environment Protection Authority.
Detailed site layout plans showing key elements, such as emergency access/egress points, location of the firefighting equipment, etc.
The prestart, toolbox, induction registers of all persons at the workplace that will be used during emergency response drills
A callout list of personnel who will be contacted during emergency or incidents
Availability of adequate resources to provide effective emergency and incident response, and
Training to be provided to all personnel in incident and emergency response.
2.2. Emergency management organisational structure
The Emergency Planning Committee (EPC) for the Project consists of the following personnel:
Table 1: EPC members
EPC member Discipline / focus area
Project Director Entire Site
General Superintendent (EC) Entire Site
Safety Representative Entire Site
Environmental Manager (or delegate) Entire Site
The incident and emergency response contact list is included in Appendix A. This list shall be maintained by the Project Safety Manager so that contact details and roles detailed in the list are current, and shall be reviewed six monthly. This list shall be displayed in various prominent locations around the project, including but not limited to the site office area, site notice boards, lunchrooms and first aid rooms.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 7 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
2.3. Consultation
IERP consultation is to be undertaken with workplace staff, subcontractors and external agencies, including those responsible for emergency response, as outlined below:
Table 2: Consultation plan
Stakeholder Consultation Date Comments Received
Roads and Maritime TBA
Police TBA
Fire and rescue TBA
.
Ambulance service TBA
State Emergency Services TBA
Specialist Emergency Services As Required
The Project Team is to consider any comments received from stakeholders or emergency services for incorporation within this plan prior to its issue for implementation.
Regular communications shall be established with emergency services as/if required.
3. Incident and emergency response
3.1. Incident and emergency response flowcharts
For each potential incident or emergency scenario identified in the Workplace Risk Assessment (WRA), a corresponding incident or emergency flowchart is developed for the specific requirements of the Project. These flowcharts are provided in Appendix B of this Plan.
Where a task or activity occurs that has emergency response or first aid impacts which have not been identified in the WRA or in this Plan, these impacts shall be managed through the Safe Work Method Statements (SWMS) for the activity or through activity-level controls and considered during any subsequent reviews.
Below is a list of potential scenarios identified for the Project:
Table 3: Core incident or emergency scenarios
Core incident or emergency scenario flowcharts
Initial response (R.E.A.C.T) Emergency evacuation
Emergency communications Crisis management
Table 4: Specific incident or emergency scenario flowcharts (see appendices of this Plan)
Specific incident or emergency scenario flowcharts
Asbestos Robbery or hostile intruder
Bomb threat Service strikes and leaks – gas
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 8 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Bushfire Service strikes – electricity or power cables (underground or overhead)
Chemical oil and fuel spills Service strikes and leaks - water or sewerage pipes
Emergency situation at height Trench collapse
Fall arrest Vehicle accidents and plant rollover
Major fires or explosions Serious injury
Breach of aviation airspace Obstacle Limitation Surface (OLS)
Plane or object landing in work area
Storms and flooding - process
3.2. Site layout plans
The Safety Manager shall ensure that the site layout plans developed for the Project, as listed in Appendix C, are reviewed for currency at regular intervals, including after relocating the site resources. These Site layout plans shall be displayed on each site notice board and include information regarding:
Location of emergency equipment and first aid facilities
Location of site evacuation muster points
Site boundaries, roadways, buildings
Location of storage areas for dangerous goods and chemicals
Entrances and exits
Alternative entrances and exits
Emergency access points.
3.3. Emergency muster area
The workplace manager shall nominate emergency muster areas for the workplace. Each emergency muster area shall be clearly identified on the site layout plan. The muster area must consider:
The location of the work area
The availability of a large enough open/protected area to house all persons evacuated
The topography of the site in relation to ease of travel to the muster area, and
The location of emergency equipment such as first aid kits, stretcher, fire-fighting equipment, spill-kits etc.
During extreme risk or total fire ban days, a Bush Fire Survival Plan shall be completed at the Prestart and consulted to each area’s work crew.
3.4. Emergency equipment
With reference to the WRA and the Incident and Emergency Response Equipment Guidelines, the EPC shall determine the emergency equipment requirements for the project. These requirements shall then be checked against the Emergency Equipment Inspection Checklist. The Safety Manager shall ensure a Register of Emergency Equipment is maintained and emergency equipment is available and appropriately located in relation to work areas on site; and inspected, tested and maintained as necessary.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 9 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
3.5. Testing - desktop simulations/exercises/drills
The IERP, including all requirements of the PIRMP (refer Appendix D), shall be tested to ensure that the information is accurate and up to date, and that the IERP is capable of being implemented in a workable and effective manner.
Testing will be undertaken by way of:
Desktop simulations, and/or
Practical exercises/ drills.
For desktop simulations, the Environmental Manager (or delegate) shall organise relevant environmental desktop exercises to stimulate discussion of issues and review various aspects of the IERP.
Each desktop simulation shall be recorded. The record shall capture information, including (but not limited to) the:
Discussion items
Date of the desktop simulation
Name of the staff members who attended the desktop simulation
Attendance record.
For practical exercises/drills, the Safety Manager, in consultation with the EPC, shall ensure that a Drill Schedule is developed, maintained and adhered to at each site on the project. The Drill Schedule includes the dates on which the various hazards/risks identified in the IERP are scheduled to be tested, and when they have been tested.
The Safety Manager, in consultation with the EPC, shall arrange for practical exercises/ drills for both workers and subcontractors.
Following each practical exercise/ drill, the Safety Manager shall ensure that all persons observing and or evaluating drills complete an Incident and Emergency Response Drill Record. This Record captures a suite of information, including (but not limited to) the:
The scope of the drill
Date of the drill
Name of the staff members who conducted the drill
Name of the staff member who completed the drill record
Attendance record.
Desktop simulations or practical exercises/ drills shall be carried out:
Routinely at least once every 12 months
Within one (1) month of any pollution incident occurring. In the light of that incident, the intent is to assess whether the requirements of the PIRMP included in this IERP (refer Appendix D) are accurate and up to date, and the plan is still capable of being implemented in a workable and effective manner.
3.6. Incident (vehicle/public/environmental – non-work related)
Should there be an event requiring initial management by the project Emergency Response Team or interaction with the project or requiring initial support from the project, (e.g.- dozer or water cart) to assist with initial response to an incident, the relevant Emergency Flowcharts listed in table 3 and 4 and the Traffic Incident Response Plan will be utilised in the response and in conjunction with direction from any Emergency Service. (i.e.- police, SES, Fire etc).
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 10 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
4. Pollution incident response management
The purpose of this section is to address the requirements of the Protection of the Environment Operations Act 1997 (POEO Act) and Protection of the Environment Operations (General) Regulation 2009 (POEO (G) Regulation) not otherwise specifically addressed in this IERP.
4.1. Pollution incident response management plan legislative requirements
The specific legislative requirements for a Pollution Incident Response Management Plan (PIRMP) are set out in Part 5.7A of the POEO Act and Part 3A of the POEO (G) Regulation. These requirements and a cross reference are included in Appendix D to ‘readily identify’ where each requirement is met in this IERP, or otherwise.
4.2. Description and likelihood of hazards
The main hazards and risks to human health and the environment associated with project activities have been identified by completing an Environmental Incidents and Emergencies Risk Assessment. The risk assessment was undertaken in a workshop involving key project personnel and included consideration of the following:
Consequence and likelihood of hazards and risks to human health and the environment occurring;
Proximity to sensitive environment, (i.e. ‘no-go’ zones, or sensitive receivers, such as schools, retirement homes and farms).
Based on the pre-control hazard risk rating, the following hazards to human health and the environment were identified as ‘High’ risk:
Severe weather events
Illegal waste dumping (by others)
Vehicle collision
Chemical spill in waterway (onsite and offsite impact)
Primer/ primer-binder washed off pavement
Unauthorised washout of concrete trucks and pumps
Chemical spill on land (onsite impact)
Of these, the following hazards relate directly to pollution incidents:
Illegal waste dumping (by others)
Chemical spill in waterway (onsite and offsite impact)
Primer/ primer-binder washed off pavement
Unauthorised washout of concrete trucks and pumps
Chemical spill on land (onsite impact)
The results of the risk assessment are included in Appendix E of this IERP.
Refer to Section 4.4 for the pre-emptive actions (controls) to be taken to minimise or prevent any risk of harm to human health or the environment.
4.3. Pollution incident notification protocol
All pollution incidents or any other environmental incidents must be reported in accordance with the Pollution (or other Environmental) Incident Notification Protocol included in Appendix F of this Plan. This protocol is consistent with the environmental incident reporting requirements contained in the Roads and Maritime Environmental Incident Classification and Reporting Procedure.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 11 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
4.4. Pre-emptive actions
Pre-emptive actions to be taken to minimise or prevent any risk of harm to human health or the environment arising from project activities are included in the following project documentation:
Construction Environmental Management Plan (CEMP) and the relevant Sub-Plans
Environmental Work Method Statements, and
Construction Method Statements.
The above documents describe in detail the measures that will be taken to prevent or minimise any risks of harm to human health or the environment including:
Daily and weekly site environmental inspections
Ongoing environmental monitoring
Environmental audits
Task-specific risk assessments
Ongoing training of staff.
4.5. Contact details
The 24-hour contact details for the project personnel responsible for activating this plan and managing the response to all pollution incidents are included in Appendix A of this Plan. The contact details for reporting pollution incidents to the relevant authorities are also included in Appendix A.
4.6. Inventory of pollutants
The inventory of potential pollutants kept on premises or used in carrying out project activities will be included in the Safety Data Sheet Register located on the Fulton Hogan Intranet. A summary of the key potential pollutants is outlined below. Mobile sources of potential pollutants present onsite will include all refuelling vehicles and plant items which will be utilised throughout the works.
Table 5: Potential pollutant inventory
Potential Pollutant Maximum Quantity Storage Location
Diesel 8,000L Machinery, Bunded Areas, Fuel Pods, Refuelling Truck
Petrol 200L Machinery, Chemical Storage Containers
Hydraulic Fluid 500L Machinery, Chemical Storage Containers
AgLime 5t Bridge and Earthworks Compounds
Gypsum (powder) 15t Earthworks Compound
Engine Oil 200L Machinery, Chemical Storage Containers
Minor oils/lubricants 200L Machinery, Chemical Storage Containers
Spray Paint 50L Chemical Storage Containers
Oxy/Acetylene 200kg Bridge Compound (in cage, upright)
Contaminated waste ~2,000m3 In-situ
Form Oil 60L Bridge Compound
Curing Compound 1,500L Bridge and Earthworks Compounds
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 12 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Spray Seal (bitumen) 15,000L Spray seal contractor truck
Herbicides 10L Chemical Storage Containers
Turbid Water 5,000m3 Sediment Basins, excavations
Drill Slurry/Bentonite 2,000m3 Bridge and Earthworks Compounds
4.7. Communicating with neighbours and local community
Should a pollution incident occur that threatens to cause harm to human health or the environment, the following notification protocol will be followed:
Environmental and engineering staff in consultation with Community Liaison team will determine the community notification catchment depending on the nature of each incident and input from authorities.
Early warnings and regular updates ongoing as required will be issued by phone calls, web updates and door knocking to affected residents/receivers.
Notifications to affected residents will include details of incident, time frame of the impact and the mitigation measures put in place.
Instructions to residents to minimise health impact (i.e. for airborne chemicals residents will be advised to close windows and doors, to take extra care if they have respiratory issues, keep children inside and protect animals, where possible).
Sensitive receivers will receive priority notification of pollution incidents.
4.8. Minimising harm to persons on premises
Should a pollution incident occur that threatens to cause harm to persons on the premises this Plan will be activated.
4.9. Maps
Clause 98C (1) (k) of the POEO (G) Regulation, requires a detailed set of maps showing the following information:
The location of the premises to which the EPL relates
The surrounding area that is likely to be affected by a pollution incident
The location of potential pollutants on the premises
The location of any stormwater drains on the premises.
With the exception of the location of stormwater drains, all required information is shown on the Sensitive Area Plans included in Appendix A6 of the CEMP.
The location of stormwater drains will be shown on the most current set of Drainage Drawings, available on the Fulton Hogan server.
Since the Sensitive Area Plans and Drainage Drawings are subject to frequent change throughout construction, the reader is asked to refer directly to the respective document (as mentioned above) to ensure its currency, rather than appending it separately to this IERP.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 13 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
5. Training
The EPC shall determine the specific competencies required to adequately respond in an incident or emergency at each site, and the training required to achieve these competencies. Training shall conform to all project requirements depicted in the project’s Training Management Plan, including any environmental emergency response training. This process shall be tracked and managed in Fulton Hogan’s People Development Platform online application (PDPAU). Training shall be carried out to achieve the following emergency related competencies:
Table 6: Training requirements
Competency EC EPC ERT First Aider
Incident and emergency response – Level 2 – Emergency coordinator
Yes Yes (at least one member) Yes (at least one member) Recommended
Apply first aid Recommended Recommended Yes (at least one member) Yes
Crisis management Yes Yes (at least one member) Yes (at least one member) No
Emergency communications Yes Yes (at least one member) Yes No
Emergency evacuation Yes Yes (at least one member) Yes No
Initial response Yes Yes (at least one member) Yes Recommended
Serious injury Yes Yes (at least one member) Yes Yes
Asbestos Yes Recommended Yes (at least one member) No
Bomb Threat or Other Serious Threat Yes Recommended Yes (at least one member) No
Bushfire Yes Recommended Yes (at least one member) No
Emergency situation at height Yes Recommended Yes (at least one member) No
Chemical oil and fuel spill Yes Recommended Yes (at least one member) No
Fall arrest Yes Recommended Yes (at least one member) No
Major fire and explosion Yes Recommended Yes (at least one member) Recommended
Service strikes - Electricity cables Yes Recommended Yes (at least one member) No
Service strikes and leaks - Gas Yes Recommended Yes (at least one member) No
Service strikes and leaks - Water and sewerage Yes Recommended Yes (at least one member) No
Storms and flooding - process Yes Recommended Yes (at least one member) No
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 14 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Trench collapse Yes Recommended Yes (at least one member) No
Vehicle accidents and plant rollover Yes Recommended Yes (at least one member) No
Breach of aviation airspace OLS Yes Recommended Yes (at least one member) No
Plane or object landing in work area Yes Recommended Yes (at least one member) No
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 15 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
6. Responsibilities
Each job role within this plan has the following responsibilities for each task as per the RASCI model. For more information, refer to the RASCI Procedure.
Responsible for conducting work
Accountable and ultimately responsible for work, signs off on work before implementation
Supportive through provision of resources/implementation support
Consulted for information/perspective/capability relevant to the work
Informed of outcomes but need not be consulted.
Table 7: RASCI chart
Task
Pro
ject
Directo
r
EP
C
EC
ER
T
First aid
er
Appoint EPC, ERT, EC A R C I
Undertake external consultation A C R I
Develop incident and emergency response flowcharts A R I
Develop site layout plans A S R C I
Determine emergency muster areas A S R C
Develop resources and equipment A R C C I
Inspect resources and equipment A S R I R
Develop drill schedule A R C C
Test emergency procedures A S R C I
Train emergency response personnel A R S C
7. Revision
The IERP shall be maintained, reviewed and updated at least annually by the Safety Manager, in consultation with the Environmental Manager (or delegate). The plan shall also be reviewed following:
Testing which identifies changes to the IERP (refer Section 3.5)
An independent audit which recommends changes to the IERP
A relevant change to workplace activities or regulatory requirements
An emergency event.
In reviewing the IERP, workplace personnel involved or likely to be involved in incident management or response shall be consulted.
Changes to this IERP will be reviewed and approved by the Project Director and documented in the revision history section of this IERP. A copy of the updated plan and changes shall be distributed to all relevant stakeholders.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 16 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
8. Definitions
Table 8: Definitions
Term Definition
Coordination The bringing-together of agencies and individuals to ensure effective management. Coordination does not include the command or control of agencies and individuals.
Emergency An imminent threat or actual incident that poses significant harm to the safety or health of persons, property, the environment, the local community or adjacent traffic operations. An incident of this kind may result in the project seeking assistance from external emergency services agencies.
Emergency coordinator (EC)
The person appointed by the Project Director to lead project efforts during a significant incident or emergency.
Emergency muster area
An area that is set aside at each site for the assembly of persons in case of an evacuation.
Emergency response team (ERT)
A team of personnel at the project that is responsible, under the direction of the EC, for the preparation for, response to and recovery from significant incidents and emergencies.
Incident A localized event, either accidental or deliberate, which may result in injury, death or damage to property or the environment. An incident requires a normal response from project incident management personnel, and may also require a response from emergency services.
Recovery In relation to an emergency, the process of returning affected site personnel to their normal level of functioning following an emergency. This includes the welfare of persons as well as the safe reconstruction of the site.
9. Procedures
The following Procedures on Fulton Hogan Intranet, the Hub, and are available to external parties upon request:
Dangerous Goods & Hazardous Substances Procedure: Outlines the management of dangerous goods & hazardous substances.
Emergency Response Procedure: Outlines the emergency response of management during activities associated with a Project/Site/Department.
First Aid Procedure: This procedure outlines the management of first aid at Fulton Hogan workplaces.
Incident Critical Response Procedure: Outlines a when a critical response is required, the critical response team and steps to manage the incident.
Incident Investigation, Reporting & Notification Procedure: This procedure describes the incident/accident reporting and investigation requirements of Fulton Hogan Pty Ltd. Isolation Procedure: To provide guidance on the appropriate isolation procedure for plant undergoing maintenance, cleaning, repair or construction
Issue Resolution Procedure: Outlines how OH&S issues raised are progressed through resolution.
10. Appendices
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 17 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Appendix A – Incident and emergency response contacts
[SEPARATE DOCUMENT]
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 18 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Appendix A – Incident and Emergency Response Contacts
PART A: Workplace Details
Location of Activity / Worksite:
Site Address:
Nearest cross Street:
Emergency Assembly Point:
Albion Park Rail bypass
Illawarra Highway, Albion Park.
Princes Highway
Various as per site plans for individual locations
EMERGENCY CONTACT: 000 or 112 from mobiles
PART A1: Key Project Personnel
Title Name Contact Details
Project Director
General Superintendent
Traffic Manager
WHS Manager
Environmental Manager
Community Relations Manager
PART A2: Emergency Personnel
Title Name Contact Details
Emergency Controller (EC)
Deputy Emergency Controller
OccCorp – Injury Reporting
PART A3: First Aiders
Content ID: APRB-IERP.APP.A This is an uncontrolled copy if photocopied or unsigned. Revised: 02/11/2018 Revision: 2 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 1 of 3
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
PART B: EXTERNAL EMERGENCY CONTACTS
ORGANISATION/ POSITION/ NAME TELEPHONE No.
Injury Reporting: OccCorp (Maree Macaleer) 1 300 666 303
Medical Centre: Kiama Medical Practice, 88 Manning St, Kiama (02) 4232 3393
Hospital (emergency): Shelharbour Hospital – 15-17 Madigan Boulevard Mount
Warrigal SNSW 2528 (02) 4295 2500
Police
000 106 If hearing / speech impaired Ambulance
Fire
NSW State Emergency Services 13 25 00
NSW Office of Emergency Management (02) 9212 9200
Traffic
Transport Management Centre (Incident and Hazard Reporting)
Southern Region Traffic Operations Unit
13 17 00
(02) 4221 2448
Safe Work Authority
SafeWork NSW Assistance Service
After Hours Emergency Contact
Construction Hotline
13 10 50
13 10 50
(02) 9214 9220
Poisons Information Centre 13 11 26
Local Councils
Wollongong City Council (02) 4227 7111
Shellharbour City Council:
(Team Leader Environment)
(Environment Officer)
Illawarra Health District (02) 4222 5000
EAP Counselling – Employee Assistance Program 1300 687 327
EPA 1 800 337 068
Fauna Rescue (02) 6620 2100
WIRES Wildlife Rescue Organisation
NPWS – In circumstances where you cannot get in touch with WIRES Wildlife Rescue (South Coast)
13 000 WIRES (094 737)
0418 427 214
Heritage 1800 629 104
NPWS
OEH
NSW Heritage – reporting potential non-indigenous archaeological relic or site
1 800 629 104
131 555
(02) 9873 8500
Content ID: APRB-IERP.APP.A This is an uncontrolled copy if photocopied or unsigned. Revised: 02/11/2018 Revision: 2 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 2 of 3
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Services
Telstra 13 20 00
Optus 13 20 00
Jemena 1 800 200 487
Endeavour Energy 13 10 03
AAPT 1300 786 786
Nextgen 1800 099 299
Sydney Water 13 20 90
Content ID: APRB-IERP.APP.A This is an uncontrolled copy if photocopied or unsigned. Revised: 02/11/2018 Revision: 2 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 3 of 3
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Appendix B – Incident and emergency response flowcharts
B01 Initial response (R.E.A.C.T)
B02 Emergency communications
B03 Emergency evacuation
B04 Crisis management
B05 Asbestos
B06 Bomb threat or other serious threat
B07 Breach of aviation airspace Obstacle Limitation Surface (OLS)
B08 Plane or object landing in work area
B09 bushfire
B10 Chemical - oil and fuel spills
B11 Emergency situation at height
B12 Fall arrest
B13 Major fires or explosions
B14 Robbery or hostile intruder
B15 Serious injury
B16 Service strikes - electricity cables
B17 Service strikes and leaks - gas
B18 Service strikes and leaks - water or sewerage pipes
B19 Storms and flooding – process
B20 Trench collapse
B21 Vehicle accidents and plant rollovers
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 19 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B01 - Incident and emergency response flowchart - initial response (R.E.A.C.T)
Emergency response teamEmergency coordinatorWorker
Immediately alert the emergency coordinator
Can the incident be safely managed by
workplace personnel?
Control source of emergency if possible
Contain the problem and prevent the problem From
getting any bigger
Protect what is not damaged
Clean up
Initiate a 000 call, if required.
Provide the following information to emergency
services-· WHERE is the location?· WHAT happened?· WHEN did it happen?· WHO is involved?
Coordinate a response to the emergency
Implement and manage response activities
Leave the site and hand over responsibility to the emergency coordinator when the response is finished and the situation is
safe
Consult with the emergency coordinator
Authorise the recommencement of work
Investigate and report as per the incident notification,
reporting and investigation procedure
Yes
No
Respond Examine Assess Control Talk TM
Respond
Examine
Assess
Control
Talk
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 20 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Guidelines
Role Task Detail
Worker Immediately alert the emergency coordinator.
Refer to the emergency communication flowchart guidelines for further information on
how to transmit an emergency call sign. The workplace manager or emergency coordinator
are the primary points of contact for alerting emergency services.
Emergency coordinator
Initiate 000 call if required. Refer to the emergency communication flowchart guidelines for further information on
making a 000 call.
Coordinate a response to the emergency.
If possible, evaluate the most appropriate response to the emergency in consultation with
the safety/environment operatives, emergency warden(s) and emergency response team. The emergency coordinator shall ensure an initial response is actioned to mitigate immediate
environmental/safety risks, providing it is safe to do so. The immediate priority is the protection
and rescue of human life.
Authorise the recommencement of work.
No work shall be commenced in the affected area until:
the workplace manager, in consultation with the emergency coordinator, has
completed appropriate inspections
issues affecting the safety of persons have been rectified (for example,
damage to plant and equipment)
clearances have been provided from the appropriate authorities
the workplace manager has authorised recommencement of work.
Investigate and report as per the incident notification, reporting and
investigation procedure.
Refer to the incident notification, reporting and investigation procedure for further information.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 21 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B02 - Incident and emergency response flowchart - emergency communications
Emergency response teamEmergency coordinatorWorker
Set radio to general
construction or
operations channel
Depress the
transmission button.
Transmit “Emergency,
emergency,
emergency.”
Dial 000 and confirm
the required service:
· Police
· Fire
· Ambulance
Provide the following
information:
· WHERE is the
emergency?
· WHAT happened?
· WHEN did it happen?
· WHO is involved?
Ensure that you speak:
· Clearly
· Slowly
· Precisely
Do not hang up until the
operator tells you.
Release button and
wait for response.
Determine the
emergency
Provide support if
appropriate
Respond Examine Assess Control Talk TM
Media The MD, CEO and the National Communications are the only people authorised to speak on behalf of Fulton Hogan to the media.
If contacted by the Federal, State and/or local government representatives or media (including industry magazines) in relation to this project, Roads and Maritime Services is to be notified immediately of the name, phone number and media outlet of the journalist. No comments or statements are to be made to any media or political representative or their staff about the project.
Do not respond to any media questions
Do not say “No comment”
Do not agree to say anything ‘off the record’
Be polite
… Please call the Community Relations Manager on 1800 708 727…
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 22 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Guidelines
Role Task Detail
Worker Set radio to general construction or operations
channel.
On transmission of the emergency call sign, all radio
communication on the affected site (and other sites as
determined by the emergency controller) must immediately
cease. If there are multiple frequencies used on the site,
users will be directed to an emergency frequency. Information, directions and
evacuation processes will be communicated via this
frequency.
Transmit “emergency, emergency, emergency”.
Emergency coordinator Determine the emergency. Site personnel and the EC ensure that sufficient information is gathered on the
incident, from the initiator, to enable an informed decision to
be made as to the most appropriate response.
Dial 000 and confirm the required service: police, fire or
ambulance.
All calls to emergency services must clearly detail the nature of
the emergency and, where possible, the number of
casualties and type of their injuries.
Provide the following information:
Where is the emergency?
What happened?
When did it happen?
Who is involved?
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 23 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Content ID: APRB-IERP Revision: 3
This is an uncontrolled copy if photocopied or unsigned. Copyright © 2018, Fulton Hogan Ltd. All rights reserved.
Revised 07/11/2018 Page 24 of 55
B03 - Incident and emergency response flowchart - emergency evacuation
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Guidelines
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 25 of 55
Role Task Detail
Worker Do not make any statements Refer to the emergency to the press. communications flowchart for
further information.
Emergency coordinator Notify the appropriate All calls to emergency services services on 000. must clearly detail the nature of
the emergency and, where
Provide advice to and liaise possible, the number of
with emergency services. casualties and type of their injuries.
Announce evacuation. Using the site communication system, the EC or emergency warden shall direct all personnel to commence evacuation.
Emergency response team Ask any visitor or contractor Emergency warden(s) to evacuate to the emergency shall be responsible for ensuring muster area with you. all workplace direct employees,
subcontractors, visitors and others onsite have assembled at the nominated area and that personnel entering or leaving the site are continuously monitored.
Position a person in a safety A member of the emergency vest at the site entrance to response team shall meet direct emergency services. emergency services at an agreed
location and provide all necessary direction or advice to ensure emergency services are aware of the nature of the emergency and the necessary information to proceed to the affected area.
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B04 - Incident and emergency response flowchart - crisis management
Crises are defined as events or developments, real or perceived, which threaten the viability of the
company, have the potential to threaten the safety or wellbeing of workers and others, the
environment, or the integrity, performance, reputation of the company. Where such incidents stem
from workplace based incidents or emergencies, they shall be immediately managed in
accordance with the incident and emergency response procedure, however in parallel the
requirements of the crisis management procedure shall be implemented.
Worker Emergency response teamEmergency coordinator
Clear people away from the
scene, assess scene for
danger before giving
emergency assistance if
safe to do so
Contact the relevant
emergency services where
necessary
Remove all personnel from the
site including subcontractors
Contact regional safety /
environment manager and
general manager
Secure the site. Do not disturb
until the relevant government
regulator has given approval
Organise trauma counselling
and debriefing by
professional counselling
services
Do not make any statements to
the press
(Refer to dealing with the
media)
Do not make any admissions of
guilt. The matter will be under
investigation and management
will make a statement in due
course
Brief the crisis management
team (determined by
corporate office) when they
arrive at the scene and take
any actions, as required
Follow crisis management
team’s directions
Advise corporate team of
potential crisis
Respond Examine Assess Control Talk TM
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 26 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Guidelines
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 27 of 55
Role Task Detail
Emergency coordinator Clear people away from the Refer to the initial response scene, assess scene for danger (R.E.A.C.T.) flowchart for further before giving emergency information. assistance if safe to do so.
Contact the relevant Refer to the emergency emergency services where communications flowchart for necessary. further information.
The employee assistance program Organise trauma counselling
(EAP) is provided by Converge and debriefing by professional
International and any employee or counselling services. dependant may contact an EAP
counsellor directly on 1800 337
068. Refer to the incident and emergency response procedure for further information.
Brief the crisis management Refer to the crisis management team (determined by corporate procedure for further information office) when they arrive at the regarding the crisis scene and take any actions, as management team. required.
Emergency response team Remove all personnel from the Refer to the emergency site including subcontractors. evacuation flowchart for further
information.
Do not make any statements to Refer to the emergency the press (refer to dealing with communications flowchart for the media). further information.
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B05 - Incident and emergency response flowchart – asbestos
This flowchart must be followed if you come across a substance that you suspect or is known to contain asbestos.
What to look out for: Asbestos was used in a wide range of building products and materials up until the mid-1980s. Products that may contain asbestos include pipe lagging, boiler insulation, fire retardant material on steel work, sprayed insulation, asbestos cement sheet, asbestos cement moulded products (e.g. water pipes and telephone pit lining), and bitumen-based water proofing and vinyl floor tiles. See: http://www.deir.qld.gov.au/asbestos/general/where-found/photogallery.htm for photos of typical items containing asbestos.
Workers Emergency coordinator Emergency response team
Stop works.DO NOT handle the substance Set up a no-go zone around
the substance
If safe to do so make the asbestos safe in-situ.
e.g. wet down and/or cover exposed asbestos
DO NOT allow workers or the public to be exposed to any fibers.
Contact an occupational hygienist to identity the substance
Is it known that the material is asbestos?
Contact an asbestos removalist to dispose of the asbestos in
accordance with state asbestos removal and disposal licensing
requirements.
Yes
Advise the all clear.
No
Is the site clear of asbestos?
Yes
No
Respond Examine Assess Control Talk TM
Alert others in the area regarding the suspected presence of
asbestos
Notify the Emergency Coordinator regarding the suspected find and
any potential exposure to the material.
Review the asbestos removalist’s Asbestos Removal Plan using the Asbestos Removal Plan Review
Checklist before they commence works.
In the event of suspected exposure contact the Safety Operative to coordinate necessary medical
checks and an Industrial Hygienist to confirm material is asbestos..
Asbestos Confirmed?
Yes
No
Assume that the material is asbestos?
No
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 28 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B06 - Incident and emergency response flowchart - bomb threat or other serious threat
Emergency response teamEmergency coordinatorWorker
Keep the caller talking and note any details from the table below.
Try asking questions:· When will the bomb explode?· Where is it right now?· What does it look like?· What kind of bomb is it?· What will cause it to explode?· Did you place the bomb?· Why?· What is your address?· Where are you now?· What is your name?
Do NOT:· Aggravate the caller· Hang up, even after the call has
hung up· Make any statements to the
media· Disturb the area after the
incident
DO NOT touch the bomb
Notify emergency services on “000”
Evacuate the site and activate Major Fire Flowchart
Position a person in a safety vest at the site entrance to direct the
emergency services
Prevent others from entering the area.
Voice Speech Telephone Background Noises Man Well-spoken Accent Deep Local Music Machines
Woman Foul Stutter Raspy STD (beeps) Voices PA System
Child Incoherent Slurred Lisp Public phone Long distance Traffic
Youth Irrational Nasal Familiar Mobile Aircraft Motor
Taped Deep Drunk Loud/Soft Unknown Animals Street
Respond Examine Assess Control Talk TM
Has the bomb been located?
Yes
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 29 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B07 - Incident and emergency response flowchart - breach of aviation airspace obstacle limitation surface (OLS) Title
Emergency response teamEmergency coordinatorWorker
Ph
ase
Respond Examine Assess Control Talk TM
Contact Supervisor of work area and instruct that obstacle in the
OLS must be lowered or if a lighting plant shielded
immediately
Contact NOTAM (Notice to Airmen) and notify them of
breach of OLS
Instruct all works in in all OLS areas to cease until cleared by
NOTAM that work can commence
Lower obstacles or shield lighting plants as directed by supervisor
Cease all work until instructed by Supervisor that work can
commence
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 30 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B08 - Incident and emergency response flowchart - plane or object landing in work area Title
Emergency response teamEmergency coordinatorWorker
Phas
e
Respond Examine Assess Control Talk TM
Ensure work area is evacuated
Implement traffic managementif traffic is a hazard.
Determine if/how many person s are injured if any and render
assistance where possible and/or aid emergency services
Look out for leaking / spilling fuel or other flammable substances.
Determine whether to enact the Chemical, oil and fuel spill
flowchart if safe to do so and/or requested by the local authorities
.
Contact emergency services on 000 , if necessary.
Do not disturb the incident Scene. Secure site until after the Site has
been handed back to project by local authorities.
Escort local authorities/emergency services onto site
Assist local authorities/emergency services as requested/instructed
Immediately evacuate work area
All workers to vacate work area and assemble at muster points as
instructed by Emergency Coordinator/Supervisor
Initiate Crisis Management as required
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 31 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B09 - Incident and emergency response flowchart - bushfire
Emergency response teamEmergency coordinatorWorker
Respond Examine Assess Control Talk TM
Is the bushfire happening now?
Is it a severe, extreme or
catastrophic fire?
Activate the site’s bushfire plan located …………………. (insert)
Consult with the workplace manager to see if work will commence tomorrow in accordance to the
site’s bushfire plan
Inform all employees, potential visitors and the Client aware of the chosen Bushfire Plan:
PREPARE, ACT SURVIVE
Clear away flammable materials today so as to minimise risk should a bushfire occur tomorrow
Remove all valuable equipment and items from the site or high risk areas
Evacuate with haste to the pre-decided safety zone if it is too late to leave.
This site’s Safety Zone is:……………………………………………………. (insert)
Commence Fire Risk Management as per Bushfire Plan
No
No
Yes
Yes
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 32 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B10 - Incident and emergency response flowchart - chemical - oil and fuel spills
Emergency coordinator Emergency Response TeamWorker
Respond Examine Assess Control Talk TM
Are you familiar with the requirements for working with the spilt chemical safely and
correctly?
Make area safe, evacuate and apply First Aid if
necessary
Isolate source of spill (e.g. shut valve, crimp hose, stand up
container)
Yes
Is the spill a small volume and/or does not pose a
risk of harm to people or the environment?
Notify your Emergency
Coordinator for assistance
NoYes
Contact 000, Safety and Environment Managers
for support and notifications as necessary
Source and put on PPE.
Source spill response equipment
Contain, then clean-up the spill:· Booms, or compacted soil can
be used to contain flow and to prevent material from entering drainage inlets or waterways
· Pads and absorbent granules can be used to soak up the spill
Dispose of spill residues, contaminated soils and clean-up materials as per approved Waste Management Plan. DO NOT DISPOSE OF IN ANY ON-SITE BINS UNLESS THEY ARE DESIGNATED FOR CONTAMINATED/SPILL MATERIALS.
Contact your Environment Team for contamination assessment and disposal options.
No
Source SDS to identify correct safety and clean-up
requirements.
Isolate source of spill (e.g. shut valve, crimp hose) and protect/isolate downstream drainage
pits/channels if safe and possible.
Can the clean-up be conducted without posing a risk to our people or the
public?
Do we have adequate resources?
Clean-up by Fulton Hogan
Provide assistance to the emergency services if
needed and follow their directions
Contain, then clean-up the spill:· Prevent spilt material from entering sensitive areas such as
drainage inlets, waterways or vegetation.· Contain the spill by creating earthen bunds or using booms.
Floating hydrophobic booms can be used if the spill is on water and floats (i.e. is not emulsion or mixes into the water).
· Consider reuse of ponded spilt product.· Source absorbent material – Spills kit or trailer. Sand or dust
is a suitable alternative for larger spills. Use sparingly. · If any material enters the drainage system, use a vacuum
truck to suck up the spill. This can also be used for ponded spilt material.
Source and put on PPE
Yes
Yes
No
No
Clean-up by emergency services
Report ALL spills to your Supervisor and Environmental Manager
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 33 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B11 - Incident and emergency response flowchart - emergency situation at height
Emergency response teamEmergency coordinatorWorker
Pha
se
Respond Examine Assess Control Talk TM
Check for danger to you or the
injured person
Stay with injured person if
possible, and apply
required First Aid
Do not move the injured
person if possibleCall emergency services on 000
Advise the ERT and enlist help
Ensure the area is made safe
(block off or barricade if
necessary)
Do not move equipment unless it
poses a risk to the injured person
or others in the area. Wait for
emergency services
Position a person at the
site entrance to direct the
ambulance when it arrives
Report the injury to the ECConfirm if it is a minor
or serious injuryApply basic first aid
Serious
Minor
Provide emergency services with
relevant information, required
rescue from height and confirm
destination hospital
Notify the injured person’s
immediate employer
Wait until Emergency
services arrive for rescue
at Height with applicable
equipment, unless trained
emergency personnel on
site
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 34 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Guidelines
Role Task Detail
Emergency coordinator
Confirm if it is a minor or serious injury.
A minor injury is classified as an injury that can be treated by first aid. A serious injury is classified as an injury that required treatment by medical professionals.
Check for danger to you or the injured person.
If danger is present, do not put yourself at risk under any circumstances. If it is safe to prevent danger to injured person, do so.
Call emergency services on 000.
Refer to emergency communications flowchart for further information.
Provide emergency The EC shall ensure ambulance officers provide advice
services with on the hospital to which the ambulance is taking each
relevant information casualty and that the destination hospital is informed of the pending arrival of casualties. If necessary, the EC
and confirm shall alert the destination hospital of any source of destination hospital. contamination or any events that may become known as
a result of investigation. The EC shall ensure that emergency services are aware that the emergency will require rescue from heights and provide relevant facts.
Notify the injured person’s immediate employer.
The emergency coordinator shall notify the injured person’s immediate employer, who shall ensure next of kin are notified.
Emergency Position a person in A member of the emergency response team shall meet response a safety vest at the emergency services at an agreed location and provide all team site entrance to
direct the ambulance when it arrives.
necessary direction or advice to ensure emergency services are aware of the nature of the emergency and the necessary information to proceed to the affected area, so that the injured person can be rescued from height and provided with appropriate emergency treatment.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 35 of 55
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 36 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B12 - Incident and emergency response flowchart - fall arrest Title
Emergency coordinator Emergency response teamWorker
Ph
ase
Check for further danger to yourself, suspended person
or others.
Communicate with the suspended person, to determine if they are
conscious and/or injured.
Call “000”, if necessary.
Secure the area and alert the workplace manager and first
aider.
If It is possible and no further danger can occur, attempt to (i)
lift the fallen Person to safety, (ii) lower the person to safety, (iii)
retrieve the person using a EWP or similar
Encourage suspended person to use stirrups to stand up in, or
instruct them to move about, re-positioning the body to avoid
suspension trauma.
Position a person at workplace site entrance to direct emergency
services to area of incident.
Follow instructions of the emergency services.
Take the person to the doctor for examination immediately after
being rescued if emergency services are not called.
Respond Examine Assess Control Talk TM
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B13 - Incident and emergency response flowchart - major fires or explosions
Emergency response teamEmergency coordinatorWorker
Respond Examine Assess Control Talk TM
Close the door if you are in a building
Keep exit clear and stay low to avoid smoke inhalation
Activate the Emergency Evacuation Flowchart
Call “000” for emergency services if necessary.
Do not go back to site until told so by the Emergency
Coordinator
Give the Emergency Services team the SDS manifest
Position a person in a safety vest at the site
entrance to direct emergency services
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 37 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B14 - Incident and emergency response flowchart - robbery or hostile intruder
Worker Emergency response teamEmergency coordinator
Notify Police and Ambulance, if required on 000.
Complete a description of he intruder as soon as they leave
including where they went, their escape route and vehicle.
Position a person in a safety vest at the site entrance to
direct the emergency services.
Use the table below to build a description of the intruder.
Do not put yourself at risk.
Respond Examine Assess Control Talk TM
· Remain calm· Do exactly as told· Try to picture a description
of the intruder and their vehicle, if applicable.
Do not touch anything immediately after the event
Do not make ant statements to the media.
Do not confront or engage the intruder
Height Build Hair Eyes Gender Age Vehicle Short Light Brown Blue Male Child Registration
Medium Medium Blonde Brown Female Youth Colour
Tall Heavy Black Green Adult Type
Grey Hazel Make
Balding Model
Other
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 38 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B15 - Incident and emergency response flowchart - serious injury Title
Emergency response teamEmergency coordinatorWorker
Ph
ase
Respond Examine Assess Control Talk TM
Check for danger to you or the
injured person
Stay with injured person if
possible
Do not move the injured
person if possibleCall emergency services on 000
Advise the ERT and enlist help
Ensure the area is made safe
(block off or barricade if
necessary)
Do not move equipment unless it
poses a risk to the injured person
or others in the area. Wait for
emergency services
Position a person in a
safety vest at the site
entrance to direct the
ambulance when it arrives
Report the injury to the ECConfirm if it is a minor
or serious injuryApply basic first aid
Serious
Minor
Provide emergency services with
relevant information and confirm
destination hospital
Notify the injured person’s
immediate employer
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 39 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Guidelines
Role Task Detail
Emergency coordinator
Confirm if it is a minor or serious injury.
A minor injury is classified as an injury that can be treated by first aid. A serious injury is classified as an injury that required treatment by medical professionals.
Check for danger to you or the injured person.
If danger is present, do not put yourself at risk under any circumstances. If it is safe to prevent danger to injured person, do so.
Call emergency services on 000.
Refer to emergency communications flowchart for further information.
Provide emergency The EC shall ensure ambulance officers provide advice
services with on the hospital to which the ambulance is taking each
relevant information casualty and that the destination hospital is informed of the pending arrival of casualties. If necessary, the EC
and confirm shall alert the destination hospital of any source of destination hospital. contamination or any events that may become known as
a result of investigation.
Notify the injured person’s immediate employer.
The emergency coordinator shall notify the injured person’s immediate employer, who shall ensure next of kin are notified.
Emergency Position a person in A member of the emergency response team shall meet response a safety vest at the emergency services at an agreed location and provide all team site entrance to
direct the ambulance when it arrives.
necessary direction or advice to ensure emergency services are aware of the nature of the emergency and the necessary information to proceed to the affected area.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 40 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B16 - Incident and emergency response flowchart - service strikes – electricity cables
Do not handle / touch the exposed area
Evacuate the work area immediately
Notify the Manager and call “000” for Emergency Services if necessary
Administer First Aid if necessary
If you make contact or damage a service, STOP WORK IMMEDIATELY
The Manager will notify the relevant authorities including the service
distribution company
No work shall recommence until:· the service has been secured· the area has been made safe· a new excavation permit has been issued· authorisation is given to recommence work
General ResponseService Specific
Response
If applicable, operator (or driver) should remain inside the cabin
If it is essential to leave the cab or operator station due to fire or other life threatening reasons, jump clear of the
equipment
Do not touch the equipment and the ground at the same time
When moving away from the equipment, the operator should hop slowly, shuffle or
jump away from the plant (with feet together) until 10m away
Warn all other personnel / public to keep 10m clear of equipment
Warn all other personnel / public to keep 10m clear of equipment
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 41 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B17 - Incident and emergency response flowchart - service strikes and leaks - gas Title
Emergency response teamEmergency coordinatorWorker
Phas
e
Respond Examine Assess Control Talk TM
Do not handle / touch the exposed area.
Evacuate the work area immediately.
Call “000” for Emergency Services if necessary.
Administer first aid if necessary.
Call the service distribution company.
Do NOT recommence work until:· the service has been secured· the area has been made safe· a new excavation permit has
been issued· authorisation is given to
recommence work.
Shut the emergency stop valves on the gas tank or
mains.
Activate the Emergency Evacuation Flowchart.
Shut down the plant or equipment UNLESS this process may provide an ignition source for any
escaping gas.
Do not allow any smoking, naked lights, possible
ignition sources anywhere near the area.
Stop work immediately.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 42 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B18 - Incident and emergency response flowchart – service strikes and leaks - water or sewerage pipes
Emergency response teamEmergency coordinatorWorker
Respond Examine Assess Control Talk TM
Do not handle / touch the exposed area Evacuate the work area immediately
Call “000” for emergency services if necessary
Administer first aid if necessary
Call the service distribution company.
Do NOT recommence work until:· the service has been secured· the area has been made safe· a new excavation permit has been
issued· authorisation is given to
recommence work
Contain the spill (e.g. sewerage, muddy water) if possible and where
safe to do so
Contact the regional environmental manager if spill flows into a waterway,
drain or sensitive area.Attempt to stop or slow the flow.
Stop work immediately
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 43 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B19 - Incident and emergency response flowchart - storms and flooding – process
Emergency response teamEmergency coordinatorWorker
Respond Examine Assess Control Talk TM
Avoid driving, but if required, drive slowly and carefully with headlights on
Stay away from powerlines, trees and waterways during and after the storm
If l ightning is present, and you are caught in it outdoors;· Crouch down into a ball with both
feet on the ground· Alternately wait in rubber tyred
vehicle (don’t enter or exit the vehicle during the lightning)
· Avoid touching any water or metal objects
If f looding is present: · Do not enter floodwater with or
without a vehicle.· Stay away from waterways such as
streams and rivers. Avoid crossing bridges if water level is already high
If safe to do so, prior to anticipated flooding:· Move equipment, supplies and
waste to higher ground and secure those that may float and cause damage.
· Anchor any fuel tanks and turn off water, electricity and gas mains as required
If necessary, call emergency services for help
Determine safe locations for evacuation from flooding
Give the all clear to resume work
Before the storm hits:· Inspect and maintain erosion and
sediment controls, waste and chemical storage areas
· Ensure site drainage is established, clear and where relevant directed to water treatment controls
· Isolate plant, stow or tie down loose items
Evacuate to higher ground prior to flooding
Clean up
BoM upgrade from Flood Watch to Severe
Weather Warning
Yes
No
Assign emergency response team rolesFollow the directions of the Emergency
Coordinator
After danger has passed, determine if it is safe to commence clean up operations
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 44 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B20 - Incident and emergency response flowchart - trench collapse
Emergency response teamEmergency coordinatorWorker
Respond Examine Assess Control Talk TM
Contact “000” and emergency rescue services
(e.g. SES), if required.
PartiallyEstimate the person’s last known position.
Remove person from the trench and provide first
aid until emergency services
arrive.
Do not disturb area of incident and isolate area to avoid further
incidents.
No
Yes
Determine if the person is partially or
fully engulfed.Fully
Determine if it is safe to enter the
trench.
Determine if the person can be
reached by hand digging?
No
Can the person exit the trench without
assistance?
No
Dig the person out.
Wait for emergency
services and assist as able to.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 45 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
B21 - Incident and emergency response flowchart - vehicle accidents and plant rollovers
Emergency response teamEmergency coordinatorWorker
Respond Examine Assess Control Talk TM
Ensure vehicle is stable before assisting person.
Implement traffic managementif traffic is a hazard.
Determine if the person is injured and whether to follow the Serious
injury flowchart.
Look out for leaking / spilling fuel or other flammable substances.
Be ready with appropriate fire extinguisher in case of fire.
Determine whether to enact the Chemical, oil and fuel spill flowchart if safe to do so.
Contact emergency services on “000”, if necessary.
Do not disturb the vehicle / plant if the incident is identified as
notifiable. Secure site until after the investigation.
Turn off engine if safe to do so.
Avoid using anything that could cause ignition of fuel or fumes
(e.g. cigarettes)
Evacuate the scene
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 46 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Appendix C – Site layout plans
Project office located at Corner of Illawarra Highway and Princes Highway, Albion Park.
Note: A detailed site layout plan including the location of first aid equipment, waste/recycle bins, movement plans and muster points will be updated once the overall layout is finalised.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 47 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Appendix D – PIRMP legislative compliance matrix
The specific legislative requirements for a PIRMP are set out in Part 5.7A of the POEO Act and Part 3A of the POEO(G) Regulation. These requirements and a cross reference are included in the table below to ‘readily identify’ where each requirement is met in this IERP, or otherwise.
Section/ Clause No.
PIRMP legislative requirement IERP reference/ comment
POEO Act – Part 5.7A
Section 153A The holder of an environment protection licence must prepare a pollution incident response management plan.
The requirements of the PIRMP are satisfied by way of this IERP, as ‘readily identifiable’ in this table.
Section 153B The EPA may direct other persons at which industry is carried out to prepare a PIRMP.
Not applicable.
Section 153C A pollution incident response management plan must include the following:
(a) the procedures to be followed in notifying a pollution incident to:
(i) the owners or occupiers of premises in the vicinity of the premises, and
Section 4.7 Communicating with neighbours and local community
(ii) the local authority, and Section 4.3 Pollution incident notification protocol, and
Appendix F Pollution (or other Environmental) Incident Notification Protocol
(iii) any persons or authorities required to be notified by Part 5.7 of the POEO Act,
Section 4.3 Pollution incident notification protocol, and
Appendix F Pollution (or other Environmental) Incident Notification Protocol
(b) a detailed description of the action to be taken, immediately after a pollution incident, to reduce or control any pollution,
Section 3.1 Incident and emergency response flowcharts
Appendix B Incident and emergency response flowcharts e.g. Chemical, Oil and Fuel Spills – Major and Minor.
(c) the procedures to be followed for co-ordinating, with the authorities or persons that have been notified, any action taken in combating the pollution caused by the incident and, in particular, the persons through whom all communications are to be made,
Appendix A Incident and emergency response contacts
Section 3.1 Incident and Emergency Response Flowcharts
Appendix B Incident and emergency response flowcharts e.g. Chemical, Oil and Fuel Spills – Major and Minor.
Section 4.3 Pollution incident notification protocol, and
Appendix F Pollution (or other Environmental) Incident Notification Protocol
(d) any other matter required by the regulations.
Refer to POEO(G) Regulation Clause 98C below.
Section 153D The PIRMP must be kept at the premises to which it relates.
Document Control (page 2).
Section 153E The PIRMP must be tested in accordance with the regulations.
Refer to POEO(G) Regulation Clause 98E below.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 48 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Section 153F If a pollution incident occurs in the course of an activity so that material harm to the environment is caused or threatened, licensees must immediately implement the PIRMP.
Section 4.3 Pollution incident notification protocol, and
Appendix F Pollution (or other Environmental) Incident Notification Protocol
POEO(G) Regulation – Part 3A
Clause 98A In this Part: plan means a pollution incident response management plan required to be prepared under Part 5.7A of the Act.
Noted.
Clause 98B (1) A plan is to be in written form. The requirements of the PIRMP are satisfied by way of this IERP.
(2) A plan may form part of another document that is required to be prepared under or in accordance with any other law so long as the information required to be included in the plan is readily identifiable as such in that other document.
The requirements of the PIRMP are satisfied by way of this IERP.
Clause 98C The matters required under section 153C (d) of the Act to be included in a plan are as follows:
(a) a description of the hazards to human health or the environment associated with the activity to which the licence relates (the relevant activity),
Section 4.2 Description and likelihood of hazards, and
Appendix E Environmental Incidents and Emergencies Risk Assessment
(b) the likelihood of any such hazards occurring, including details of any conditions or events that could, or would, increase that likelihood,
Section 4.2 Description and likelihood of hazards, and
Appendix E Environmental Incidents and Emergencies Risk Assessment
(c) details of the pre-emptive action to be taken to minimise or prevent any risk of harm to human health or the environment arising out of the relevant activity,
Section 4.4 Pre-emptive Actions
(d) an inventory of potential pollutants on the premises or used in carrying out the relevant activity,
Section 4.6 Inventory of Pollutants
(e) the maximum quantity of any pollutant that is likely to be stored or held at particular locations (including underground tanks) at or on the premises to which the licence relates,
Section 4.6 Inventory of Pollutants
(f) a description of the safety equipment or other devices that are used to minimise the risks to human health or the environment and to contain or control a pollution incident,
Section 3.4 Emergency Equipment
(g) the names, positions and 24-hour contact details of those key individuals who:
(i) are responsible for activating the plan, and
Section 4.5 Contact Details, and
Appendix A Incident and emergency response contacts
(ii) are authorised to notify relevant authorities under section 148 of the Act,
Section 4.5 Contact Details, and
Appendix A Incident and emergency response
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 49 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
and contacts
(iii) are responsible for managing the response to a pollution incident,
Section 4.5 Contact Details, and
Appendix A Incident and emergency response contacts
(h) the contact details of each relevant authority referred to in section 148 of the Act,
Section 4.5 Contact Details, and
Appendix A Incident and emergency response contacts
(i) details of the mechanisms for providing early warnings and regular updates to the owners and occupiers of premises in the vicinity of the premises to which the licence relates or where the scheduled activity is carried on,
Section 4.7 Communicating with neighbours and local community
(j) the arrangements for minimising the risk of harm to any persons who are on the premises or who are present where the scheduled activity is being carried on,
Section 4.8 Minimising Harm to Persons on Premises
(k) a detailed map (or set of maps) showing the location of the premises to which the licence relates, the surrounding area that is likely to be affected by a pollution incident, the location of potential pollutants on the premises and the location of any stormwater drains on the premises,
Section 4.9 Maps
(l) a detailed description of how any Section 4.4 Pre-emptive Actions identified risk of harm to human health will Section 4.7 Communicating with neighbours be reduced, including (as a minimum) by and local community Section Section 3.1 means of early warnings, updates and the Incident and Emergency Response Flowcharts, action to be taken during or immediately and after a pollution incident to reduce that risk, Appendix B Incident and Emergency Response
Flowcharts e.g. Chemical, Oil and Fuel Spills – Major and Minor
Section 4.3 Pollution Incident Notification Protocol, and
Appendix F Pollution (or other Environmental) Incident Notification Protocol
(m) the nature and objectives of any staff training program in relation to the plan,
Section 3.5 Testing - Desktop Simulations, Exercises/ Drills
Section 5 - Training
(n) the dates on which the plan has been tested and the name of the person who carried out the test,
Section 3.5 Testing - Desktop Simulations, Exercises/ Drills
(o) the dates on which the plan is updated, Revision History (page 2)
(p) the manner in which the plan is to be tested and maintained.
Section 3.5 Testing - Desktop Simulations, Exercises/ Drills
Section 7 Revision
Clause 98D (1) A PIRMP is to be made readily available:
(a) to an authorised officer on request, and
(b) at the premises to which the relevant licence relates, or where the relevant activity takes place, to any person who is
Document Control (page 2)
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 50 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
responsible for implementing the plan.
(2) A plan is also to be made publicly available in the following manner within 14 days after it is prepared:
(a) in a prominent position on a publicly accessible website of the person who is required to prepare the plan,
Document Control (page 2).
(3) Subclause (2) applies only in relation to that part of a plan that includes the information required under:
(a) section 153C (a) of the Act, and
(b) clause 98C (1) (h) and (i) or (2) (b) and (c) (as the case requires).
Document Control (page 2).
(4) Any personal information within the meaning of the Privacy and Personal Information Protection Act 1998 is not required to be included in a plan that is made available to any person other than a person referred to in subclause (1).
Document Control (page 2).
Clause 98E (1) The testing of a PIRMP is to be carried out in such a manner as to ensure that the information included in the plan is accurate and up to date and the plan is capable of being implemented in a workable and effective manner.
(2) Any such test is to be carried out:
(a) routinely at least once every 12 months, and
(b) within 1 month of any pollution incident occurring in the course of an activity to which the licence relates so as to assess, in the light of that incident, whether the information included in the plan is accurate and up to date and the plan is still capable of being implemented in a workable and effective manner.
Section 3.5 Testing - Desktop Simulations, Exercises/ Drills
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 51 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Appendix E – Environmental incidents and emergencies risk assessment
Risk assessment methodology
The following HSQE operational risk matrix was used to evaluate the risk level associated with each of the hazards listed above.
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 52 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Main Hazards to human health or the environment Description of potential impact
Pre-control risk rating
Post-control risk rating
Severe weather events e.g. flooding, thunderstorm, dust storm.
Fallen trees, rock fall, landslides, damage to ERSED controls resulting in stormwater pollution, flooding, closure of motorway, damage to plant / equipment
High 21 High 17
Illegal waste dumping (by others) Land pollution and stormwater pollution, potential for health and visual impact High 18 Med 13
Spontaneous combustion of mulch stockpile
Bushfire, fire, smoke resulting in reduced visibility and/or closure of and/or long delays on the motorway
Med 13 Med 8
Fire/ bushfire/ grassfire Damage to property and stock, smoke resulting in reduced visibility and/or closure of the motorway.
High 18 Med 13
Vehicle collision Fuel spill, fire, explosion, closure of and/or long delays on the motorway High 24 High 18
Chemical or fuel spill in a waterway (onsite & offsite impact)
Pollution of waters, adverse impact on aquatic ecosystems, fish kills High 18 Low 5
Primer/ primer binder washed off pavement
Water pollution and potential for adverse impact on aquatic ecosystems, fish kills, land pollution.
High 18 Low 2
Discovery of friable asbestos on site Inhalation health hazard High 18 Low 5
Unauthorised washout of concrete trucks and pumps
Water pollution adverse impact on aquatic ecosystems High 17 Low 5
Chemical spill on land (onsite impact) Land pollution, contamination of groundwater, stormwater pollution High 16 Low 5
Incompatible storage of chemicals Fire, explosion, chemical spill, land and water pollution, odour, fumes. High 18 Low 2
Importation of contaminated materials by trucks and other plant
Land pollution, stormwater and groundwater contamination Med 14 Low 5
Unauthorised discharge of sediment laden water from site
Reduced water quality in local waterways, adverse impact on aquatic ecosystems.
Med 13 Low 5
Failure of erosion and sediment controls Reduced water quality in local waterways, adverse impact on aquatic ecosystems.
Med 13 Low 5
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 53 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Main Hazards to human health or the environment Description of potential impact
Pre-control risk rating
Post-control risk rating
Tannin leachate runoff Pollution of surface water by tannins, loss of amenity. Med 13 Low 2
Excavation/works outside of the approved project boundary
Loss of habitat, damage to EECs or loss of threatened species, adverse impact on aquatic ecosystems.
Med 13 Low 5
Blow out of concrete pump hose causing concrete spill
Water pollution and potential for adverse impact on aquatic ecosystems Med 13 Low 2
Clearing outside approved clearing limits
Damage to habitat, loss of threatened or endangered species Med 13 Low 5
Unexpected contaminated land find Land pollution. contamination of groundwater stormwater pollution Med 9 Low 5
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 54 of 55
Incident and Emergency Response Plan
Albion Park Rail bypass (Stage 2 – Princes Motorway between Yallah and Oak Flats)
Appendix F – Pollution (or other environmental) incident notification protocol
POLLUTION (OR OTHER ENVIRONMENTAL) INCIDENT OCCURS
Supervisor in Charge/Fulton Hogan staff/Subcontractor
calls Environmental Manager
immediately
0400 459 769
If not available call NSW Environmental Manager
0488 264 613
Environmental Manager, in consultation with NSW Environmental Manager, determines if the incident
poses a risk of material harm to the environment
Is there a risk of material harm to the environment ?
No
Yes
Environmental Manager notifies
InternallyAs soon as possible
but no later than 24 hours
ExternallyImmediately
General Manager Eastern Region
Authorities in order of priority:
EPA: 131 555
Central Coast Public Health Unit: (02) 4320 9730
SafeWork NSW: 131 050
Wollongong City Council: (02) 4227 7111
Shellharbour City Council: (02) 4221 6247/0419835683
or 0406 383 047
Fire and Rescue NSW: 1300 729 579
Note 1: if 000 was called first, you do not need to ring Fire and Rescue NSW again.
Note 2: evidence of notifications, i.e. reference numbers, must be obtained from all agencies listed above.
National Environment and Quality Manager
Implement corrective actions and record the incident in
Roads and Maritime Environmental Incident Report
Form and CAMs
Department of Planning and Environment Roads and Maritime Environmental Representative Project Verifier
Immediately means promptly and without
delay
Call 000 if the incident presents an immediate threat to human health or
property and follow FH emergency response procedures
Important:If a pollution incident occurs, all necessary actions should be taken to minimise the extent and any adverse effects of the release. These actions must be implemented as soon as it is safe to do so. If the incident presents an immediate threat to human health or property, Fire and Rescue NSW, the NSW Police and the NSW Ambulance Service must be contacted first by calling 000. Other agencies must still be contacted after that to satisfy POEO Act notification obligations.
Material harm means:· There is actual or potential harm
to health or safety of human beings or to ecosystems that is not trivial, or
· Actual or potential loss or property damage exceeds $10,000.
Project Director
Environmental Manager notifies: Department of Planning and
Environment Roads and Maritime Environmental Representative Project Verifier Any other relevant agencies
Content ID: APRB-IERP This is an uncontrolled copy if photocopied or unsigned. Revised 07/11/2018 Revision: 3 Copyright © 2018, Fulton Hogan Ltd. All rights reserved. Page 55 of 55