in the name of allah the most gracious the most merciful
DESCRIPTION
In the name of Allah the Most Gracious the Most Merciful. Construction Management and Planning. Float. Total Float is Calculated by Subtracting Early Start and Duration from the Activity’s Late Finish Time An Activity that has Zero Total Float is a Critical Activity - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/1.jpg)
In the name of Allah the Most Gracious the Most Merciful
![Page 2: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/2.jpg)
2
Construction Management and Planning
![Page 3: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/3.jpg)
Float Total Float is Calculated by Subtracting Early
Start and Duration from the Activity’s Late
Finish Time An Activity that has Zero Total Float is a Critical
Activity An Activity’s Start may be Critical Even Though
an Activity itself may not be Critical Start Float may be Calculated by Subtracting
an Activity’s Early Start Time from Its Late Start
Time
![Page 4: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/4.jpg)
Float Finish Float is Calculated by Subtracting an
Activity Early Finish Time from its Late Finish
Time
![Page 5: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/5.jpg)
Project Scheduling
Probabilistic PERT
![Page 6: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/6.jpg)
History of PERT
• Project Evaluation and Review Technique (PERT)–U S Navy (1958) for the POLARIS
missile program–Multiple task time estimates
(probabilistic nature)–Activity-on-arrow network construction–Non-repetitive jobs (R & D work)
6
![Page 7: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/7.jpg)
PERT Probability Approach to Project Scheduling
• Activity completion times are seldom known with certainty.
• Completion time estimates can be estimated using the Three Time Estimate approach. In this approach, three time estimates are required for each activity:
a = an optimistic time to perform the activity m = the most likely time to perform the activity b = a pessimistic time to perform the activity
![Page 8: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/8.jpg)
PERT
–pessimistic time (a) - the time the activity would take if things did not go well
–most likely time ( m) - the consensus best estimate of the activity’s duration
–optimistic time (b) - the time the activity would take if things did go well
8
![Page 9: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/9.jpg)
3-Time Estimate ApproachProbability Distribution
• With three time estimates, the activity completion time can be approximated by a Beta distribution.
• Beta distributions can come in a variety of shapes:
a m b ba mm a b
![Page 10: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/10.jpg)
Mean and Standard Deviation for Activity Completion Times
• The best estimate for the mean is a weighted average of the three time estimates with weights 1/6, 4/6, and 1/6 respectively on a, m, and b.
• Since most of the area is with the range from a to b (b-a), and since most of the area lies 3 standard deviations on either side of the mean (6 standard deviations total), then the standard deviation is approximated by Range/6.
6
a-b=deviation standard the=
6b+4m+a= timecompletionmean the=
![Page 11: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/11.jpg)
The three assumptions imply that the overall
project completion time is normally distributed,
with:
The Project Completion Time Distribution
= Sum of the ’s on the critical path
2 = Sum of the 2 ’s on the critical path
![Page 12: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/12.jpg)
PERT analysis• Draw the network.• Analyze the paths through the network and find the
critical path.• The length of the critical path is the mean of the project
duration probability distribution which is assumed to be normal
• The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum
• Probability computations can now be made using the normal distribution table.
12
![Page 13: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/13.jpg)
Probability computation
13
• Determine probability that project is completed within specified time
Z =
x -
where = tp = project mean time
= standard deviationx = (proposed ) specified time
![Page 14: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/14.jpg)
Normal Distribution of Project Time
14
= tp Timex
Z
Probability
![Page 15: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/15.jpg)
15
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8B -- 1 4.5 5C A 3 3 3
D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7
![Page 16: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/16.jpg)
16
![Page 17: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/17.jpg)
PERT Example
17
Activity Expected Time (μ) Variance (σ2) (a + 4m + b)/6 [(b – a)/6]2
A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9
![Page 18: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/18.jpg)
18
![Page 19: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/19.jpg)
19
σ2path = σ2
A + σ2C + σ2
F + σ2I + σ2
K
= 4/9 + 0 + 1/9 + 1 + 4/9 = 2σpath = 1.414Mean project completion time = 23Proposed completion time = 24
z = (24 - 23)/(24-23)/1.414 = .71
From the Standard Normal Distribution table:
P(z < .71) = .5 + .2612 = .7612
![Page 20: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/20.jpg)
Using the PERT-CPM Template for Probabilistic Models
• Instead of calculating µ and by hand, the Excel template may be used.
• Instead of entering data in the µ and columns, input the estimates for a, m, and b into columns C, D, and E.– The template does all the required
calculations– After the problem has been solved, probability
analyses may be performed.
![Page 21: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/21.jpg)
Enter a, m, b instead of
Call SolverClick SolveGo to PERT OUTPUT worksheet
![Page 22: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/22.jpg)
Call SolverClick Solve
![Page 23: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/23.jpg)
To get a cumulativeprobability, entera number here
![Page 24: In the name of Allah the Most Gracious the Most Merciful](https://reader035.vdocuments.us/reader035/viewer/2022062815/56816910550346895de02ab0/html5/thumbnails/24.jpg)
P(Project is completed in less than 180 days)