in the matter of the resource management act 1991 (the act) fileunder the resource management act...
TRANSCRIPT
BEFORE THE HEARING PANEL
UNDER the Resource Management Act 1991
AND
IN THE MATTER A hearing of an application
APP-2016200983.00 from the Palmerston North
City Council for resource consents in relation to
the construction of a pedestrian and cycle bridge
over the Manawatu River
SECTION 42A REPORT OF LUKA LYNN DE JONG
PLANNING
2 FEBRUARY 2017
Section 42A Planning Report
Application No. APP-2016200983.00 Palmerston North City Council Prepared by Luka Lynn de Jong – Consents Planner for Manawatu Wanganui Regional Council 31 January 2017
2
TABLE OF CONTENTS
A. INTRODUCTION ......................................................................................................... 3
B. SCOPE OF THIS REPORT ......................................................................................... 3
C. REPORT OUTLINE ..................................................................................................... 4
D. APPLICATION FOR RESOURCE CONSENT ............................................................. 5
E. LOCATION .................................................................................................................. 7
F. NOTIFICATION AND SUBMISSIONS ......................................................................... 8
G. SECTION 104 ............................................................................................................ 12
H. ACTUAL AND POTENTIAL EFFECTS ON THE ENVIRONMENT ............................. 13
I. STATUTORY CONSIDERATIONS ............................................................................ 22
J. OTHER MATTERS THE CONSENT AUTHORITY CONSIDERS RELEVANT ........... 27
K. ASSESSMENT AGAINST RMA PROVISIONS .......................................................... 28
L. CONCLUSION ........................................................................................................... 32
M. RECOMMENDATION ................................................................................................ 34
Section 42A Planning Report
Application No. APP-2016200983.00 Palmerston North City Council Prepared by Luka Lynn de Jong – Consents Planner for Manawatu Wanganui Regional Council 31 January 2017
3
A. INTRODUCTION
1. My name is Luka Lynn de Jong. I am a Consents Planner at the Manawatu-Wanganui
Regional Council (hereafter referred to as ‘MWRC’). I have held this position since
June 2014. I hold the qualification of a Bachelor of Resource and Environmental
Planning from Massey University. I am a member of the New Zealand Planning
Institute, holding an intermediate class membership.
2. I have 4 years experience in planning and resource management. Following my
graduation in 2013, I was employed at The Surveying Company Ltd (Wellington) as a
Planner. From 2013 to 2017 I have had a range of experiences in planning, including
providing assistance to organisations to process consent applications as well as
preparing consent applications on behalf of clients. As a Consents Planner at MWRC, I
have processed a diverse and complex range of Land Use Consents, Discharge
Permits, Water Permits and Coastal Permits.
3. I have visited the site, most recently being 11 January 2017. The site visit included
both the true right and true left banks of the Manawatu River where the bridge is
proposed to be constructed. I am familiar with the location of the proposed activities.
B. SCOPE OF THIS REPORT
4. This report provides an analysis of the resource management issues relating to the
resource consent application sought by the Palmerston North City Council (hereafter
the ‘Applicant’) associated with the construction of a Pedestrian and Cycleway Bridge
over the Manawatu River.
5. This report considers the potential environmental effects and statutory obligations that
are set out in section 104 of the Resource Management Act (the “Act”) is relevant to
the resource consent application to the MWRC.
6. The assessment and recommendations contained within this report are intended to
help inform the commissioners with their decision.
7. In preparing this report I have considered:
a. The application and Assessment of Environmental Effects (AEE); Resource
consent application and AEE, He Ara Kotahi: Manawatu Pedestrian and Cycle
Bridge, November 2016, prepared by Tonkin & Taylor Ltd;
b. He Ara Kotahi: Manawatu Bridge response to request for further information,
prepared by Tonkin & Taylor Ltd, 13 January 2017;
c. Draft Erosion and Sediment Control Sketches, prepared by Tonkin & Taylor on
24 January 2017;
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
4
d. The submissions that have been made on the above applications; and
e. The Section 42A reports prepared by Dr Alex James (Ecology and Water
Quality Consultant), Mr Hamish Sutherland (Senior Consents Monitoring
Officer) Mr Philip Wallace (Engineering Consultant), and Mr James Lambie
(Senior Environmental Scientist).
8. The recommendations and conclusions within this report may be reconsidered
following the pre-circulation of applicant and submitter evidence and presentations at
the hearing.
9. I confirm that I have read the Code of Conduct for Expert Witnesses in the
Environment Court Practice Note. I agree to comply with the Code of Conduct.
Except where I state that I am relying upon the specified evidence of another person,
my evidence in this statement is within my area of expertise. I have not omitted to
consider any material facts known to me that might alter, or detract from, the opinions
that I express.
C. REPORT OUTLINE
10. My report has been prepared and covers the following matters:
i. a brief outline of the background to the applications;
ii. a description of the proposal;
iii. a brief description of the site and environment;
iv. an outline of the notification process;
v. a summary of the matters raised in submissions made on the consent
application;
vi. an assessment of the environmental effects associated with the activities
proposed application;
vii. an assessment of the proposal against the planning framework including the
relevant National Environmental Standards, National Policy Statements,
Regional Policy Statements and Regional Plans as they relate to the proposal;
viii. an analysis of the Resource Management Act 1991 as it relates to the resource
consent application, including S107 and Part 2 of the Act;
ix. conclusion; and
x. recommendation.
11. In accordance with section 42A (1A) and (1B) of the RMA, I have minimised the
repetition of information included in the application and where I have considered it
appropriate, adopted that information.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
5
D. APPLICATION FOR RESOURCE CONSENT
Background
12. The Applicant has applied for a number of resource consents to both PNCC -
Regulatory and MWRC for the construction a shared pedestrian and cycle bridge over
the Manawatu River.
13. The proposed works are part of a wider project to design and construct a pedestrian
and cycle shared pathway from Fitzherbert Bridge to Linton Army Camp in Palmerston
North. The project is referred to as He Ara Kōtahi. A summary of the wider project is
contained within the application1.
Applications for resource consent
14. On 9 November 2016 MWRC and PNCC received an application prepared by Tonkin
& Taylor Limited on behalf of Applicant. The following resource consents are sought by
the Applicant from MWRC:
ATH-2016201107.00 Land Use Consent (Earthworks)
15. A Land Use Consent is sought to undertake large scale land disturbance and
vegetation clearance associated with the construction of a bridge and movement of a
stopbank and any ancillary discharges of sediment into water resulting from the land
disturbance.
16. The proposal comprises of approximately 5,500m2 of ground clearance and 4000m3 of
fill on the northern embarkment to raise the existing stopbank and construct the bridge
abutment. The southern embankment, bridge abutment and ramps will require a
approximately 3,500m2 of ground clearance and 5000m3 of fill.
17. A detail description of the proposed earthworks and associated vegetation clearance
relating to this application, including the timing of works, reasons for the works, erosion
and sediment control devices and monitoring required, has been provided in Section
3.9 of the application and the amended draft ESCP received on 14 January 2017. In
addition, draft sketches of the proposed river diversions were submitted on 24 January
2017 in response to the further information request under s92A of the RMA.
ATH-2016201172.00 Discharge Permit (Cleanfill)
18. A Discharge Permit is sought to discharge cleanfill material to land which will exceed
2,500m3 per year per property. As mentioned above, fill is required to create bridge
abutments and movement of the existing stopbanks.
1 Application, Section 1.1, Page 1
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
6
ATH-2016201173.00 Water Permit (Diversion)
19. A Water Permit is sought to temporarily divert the Manawatu River using in situ river
bed gravels to provide machinery access to construct two bridge piers in the bed of the
Manawatu River. This is intended to take place between October and April (inclusive)
during lower river levels. It is expected to take 8 weeks for each pile site to be
completed with the true left side pile being completed followed by the true right hand
side.
20. The draft ESCP outlines a brief methodology for the proposed in stream diversion
associated with construction of the piles and the proposed mitigations to address any
potential adverse effects.
ATH-2016201174.00 Land Use Consent (Beds, Rivers & Lakes)
21. Land Use Consent is sought to carry out earthworks, vegetation clearance, alteration
of a stopbank, construction of a new bridge and install rock armouring abutments in a
reach of river and its bed with Schedule B values of Sites of Significance – Cultural
and Flood Control and Drainage. This includes the associated disturbance of the bed
of the river and any ancillary sediment discharges into water or onto land resulting from
the construction works.
22. A 4-span bridge approximately 195m in length and 4.5m wide, which includes two
bridge piles within the Manawatu River and one bridge pile on the true right bank of the
Manawatu River. The proposed bridge elements are described in Section 3.3 of the
application and are illustrated in the Layout Plan, in Appendix D of the application.
23. Section 3.4 of the application2 outlines the proposed alterations to the northern
stopbank to enable the construction of the proposed bridge, parking area and shared
pedestrian and cycle pathway. A change to the existing stopbank over a length of
approximately 100 metres is required. The application notes maintaining the integrity of
these stopbank during construction and operation of the new bridge has been a central
part of their design.
24. There are no other resource consents required from MWRC.
25. A term of 35 years has been sought by the applicant.
26. Further information was requested by both PNCC – Regulatory and MWRC under
section 92A of the RMA on 20 December 2016. A copy of the information requested is
attached as Appendix 10.
2 Application, Section 3.4, Page 10
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
7
27. The applicant responded to the further information request on 13 January 2017 and
24 January 2017.
Rule Assessment and Overall Activity Status
28. The application3 states resource consents sought from MWRC associated with the
proposed construction of the bridge is to be assessed as Discretionary Activity. I agree
with the assessment provided and that the application is assessed as a Discretionary
Activity.
Permitted Activities
29. The application states there will be a surface water take from the Manawatu River to
assist with dust control on the southern bank. The application states the abstraction of
15m3 of surface water per day will not be exceeded. The activity can be a Permitted
Activity, provided the Applicant must ensure all conditions outlined under Rule 16-1 of
the One Plan are being implemented by the contractor to ensure aspects with Rule 16-
1 of the One Plan (2016) are met.
E. LOCATION
30. The site is located south-west of Palmerston North city centre. The proposed bridge
and associated works are located on Crown land, administered by Land Information
New Zealand and on Dittmer Reserve owned by the Palmerston North City Council. An
aerial photo of the site and location of the site are shown in the Layout Plan, in
Appendix D of the application4.
One Plan – Water Management Zones
31. The One Plan 2016 identifies Water Management Zones (WMZs) as a means of
managing water quality. The proposed site is located within the Lower Manawatu
(Mana_11) WMZ and Lower Manawatu (Mana_11a) sub-zone as identified within the
One Plan. The values associated with the zone are identified in Schedule B of the
One Plan and include the following:
Zone wide values
Life supporting capacity
Aesthetics
Contact Recreation
Mauri
Stock water
Existing Infrastructure
3 Application, Section 7.1, page 22
4 Application, Appendix D, Engineering Drawings
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
8
Industrial Abstraction
Irrigation; and
Capacity to assimilate pollution
Reach specific values
Amenity
Site of Significance – Cultural (SOS-C)
Site of Significance – Riparian (SOS-R)
Trout Fishery (Other)
Flood Control and Drainage
Existing Environment and Site Description
32. A description of the environment has been detailed in Section 2 of the application5. I
do not consider it necessary to repeat this information rather I will highlight the key
points below:
(a) The site of the proposed He Ara Kotahi bridge development (the site) spans the
Manawatu River adjacent to the intersection of Ruha Street and Dittmer Drive,
in Palmerston North.
(b) The Manawatu River runs in a southeast direction toward the sea. The
southern side of the river is a floodplain; generally flat pastoral land used for
dairy farming, research and educational purposes. The northern side of the
river (true right bank) is primarily park reserve with residential housing and
roading setback approximately 80 metres from the Manawatu River.
(c) Vegetation in the area includes exotic grasses, poplar, willow, Pohutukawa and
pine.
(d) The Manawatu River, which essential divides the proposed site in two parts
(northern and southern bank), is approximately 100 metres wide at the site and
around 4 metres at its deepest point near on the northern side of the river (true
right bank).
(e) There is an existing stopbank on the true right bank of the Manawatu River at
the proposed bridge location. The Manawatu River has been heavily modified
with in the urban landscape using flood protection structures, particularly rock
protection structures along the true right bank toward Fitzberbert Bridge,
approximately 1.3 kilometres upstream.
F. NOTIFICATION AND SUBMISSIONS
5 Application, Section 2, Pages 4-7
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
9
33. The applications sought from both MWRC and PNCC were jointly, publically notified on
21 November 2016. The notice was served on a number of potentially affected
parties. The submission period closed on 19 December 2016.
34. A total of 27 submissions were received within the submission period.
35. There were 2 late submissions received 1 working day after the submission closing
date. A decision has already been made by the Regional Council with agreement of
the Applicant to extend the submission period pursuant to Section 37A of the RMA. A
copy of the Decisions, both from MWRC and PNCC is attached as Appendix 12 and
Appendix 13. The result of the extension means all submissions are considered to be
received within the statutory timeframe.
36. A complete summary of submissions on the project is attached as Appendix 15. The
key points are as follows:
a. A total of 29 submissions were received. 9 submitters wished to be heard, 18
submitters do not wish to be heard and 2 submitters did not comment on
whether they wish to be heard.
b. The following are what I consider to be the key points raised within the
submissions (in no particular order):
i. Cultural effects;
ii. Location, connectedness and accessibility between the northern and
southern sides of the River and their associated land uses;
iii. Design and materials of bridge, appearance, road user conflict and
safety; and
iv. Increased walker and cyclist safety by not using main roads;
v. Resilience against natural hazards and potential damage to the existing
Fitzherbert Avenue bridge;
vi. Alternative forms of transport;
vii. Recreational potential within the reserve;
viii. The location of the bridge in relation to other features and surrounding
land-uses;
ix. Effects on residential amenity and quietness;
x. Construction effects including timing of year, traffic, dust, vibration,
hours of operation and noise;
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
10
xi. On-street parking and vehicle movements;
xii. Potential for crime;
xiii. Community consultation during options assessment; and
xiv. Vegetation removal and effects on bird and fish habitat including habitat
biodiversity.
37. The above is a summary of all issues raised, however some submissions relate solely
to PNCC matters. Tables 1, 2 and 3 below identify the issues pertaining to the MWRC
that were raised in the submissions. The identified issue is linked to the submission
number.
Table 1: Summary of Submissions in Support
Issues / Concerns raised through submissions
Comment Submission Number(s)
Cultural effects Tanenuiarangi Manawatu Inc (TMI)
who represents Rangitāne as an "iwi
authority" for the purposes of the
RMA, support the application noting
management of cultural elements
have been agreed upon
1
Public access Provision of access to the Manawatu
River and flood protection measures
2, 18
Infrastructure and power Discussed benefits of proposed
installation of power cables
3, 13
Civil defence Benefits of an additional bridge
following a natural hazard event
6, 7
Flood protection Noted flood protection will be retained 10, 20, 21
Table 2: Summary of Submissions in Opposition
Issues / Concerns raised
through submissions
Comment Submission
Number(s)
Cultural effects Iwi involvement in the project unclear 26
Construction effects Concerns relating to public access,
timing of works, dust prevention and
potential property damages as a result
of the construction works
2, 20, 9, 26
Infrastructure and power Opposes inclusion of electricity cables 9, 26, 28
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
11
Issues / Concerns raised
through submissions
Comment Submission
Number(s)
Ecology impacts Potential impact on biodiversity,
herpetofauna, birdlife, native and
game fish species, biodiversity
9, 25
Civil defence and Existing
Infrastructure
Potential damages to Fitzherbert Ave
Road bridge following natural hazard
event
26, 28
Consultation Community consultation not
adequately addressed
9, 26
Table 3: Summary of submissions that neither support nor oppose the application
Issues / Concerns raised
through submissions
Comment Submission
Number(s)
Construction effects Submissions raised concerns relating
to public safety during construction
works, timing of works and dust.
4, 22, 27
Ecology impacts Potential impact on biodiversity,
herpetofauna, birdlife, native and
game fish species, biodiversity.
Conditions required to protect
ecological values.
4, 22, 27
Civil defence matters Potential damages to Fitzherbert Ave
Road bridge following natural hazard
event
27
Legislation requirements RMA, LGA, and community
consultation issues raised
4, 27
Flooding and flood
protection
Flooding during and after works 27
38. Of these submissions above, overall a total of 15 submitters stated that they support
the application, 9 submitters stated they oppose the application and 5 submitters have
been considered neutral as they did not clearly outlined their position or have stated in
their submission whether they support or oppose the application.
39. While I have not listed all submitters, it is considered that their matters raised are
considered a District Council matter and will be addressed by PNCC’s Reporting
Planner; Mr Mark St.Clair, Consultant Planner.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
12
G. SECTION 104
40. The provisions of section 104 of the Act must be considered by the consent authority in
making a decision on the resource consent application. The applicant has identified
some of the relevant provisions under s104 of the Act within the application6. I have
expanded on this analysis where I consider appropriate. In my opinion, the matters
contained in section 104 include:
104(1) Actual and potential environmental effects. An assessment of the
environmental effects has been provided with the application7. The following
assessment of the actual and potential effects of the proposed activities is
given below.
b.(i) National Environmental Standards. The applicant considers there are no
National Environmental Standards (NES) considered to be relevant to the
proposed works. I agree with the assessment that there is no relevant NES
in relation to the application.
b.(ii) Other regulations. There are no other regulations of relevance to this
application.
b.(iii) Relevant National Policy Statements. An assessment against the National
Policy Statement for Freshwater Management (2014) is provided below.
b.(v) Relevant Regional Policy Statements or Proposed Regional Policy
Statements. An analysis of the operative Regional Policy Statement (Part I
of One Plan, 2016) is given below.
b.(vi) Relevant Regional and District Plans. I have undertaken an assessment
of the proposal against the Operative Regional Plan (Part II of the One Plan,
2016) and is given below.
(c) Other Matters the Consent Authority Considers Relevant. In this section,
I address other relevant matters which include term, the Manawatu River
Accord, and the Regional Transport Plan.
6 Application, Section 9, pages 34-40
7 Application, Section 8, Page 27-33
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
13
H. ACTUAL AND POTENTIAL EFFECTS ON THE ENVIRONMENT
41. Section 3 of the Act encompasses a broad definition of what constitutes environmental
effects. The Act requires the consideration of both actual effects and potential future
effects.
42. This assessment includes positive or adverse effects, any temporary or permanent
effect, any past, present of future effects and any cumulative effects on the
environment. In addition, consideration must be given to any potential effect of high
probability and any potential effect of low probability which has a high potential impact.
43. In the following sections I provide an assessment of the actual and potential effects on
the environment.
Actual and Potential Effects
44. In assessing the actual and potential effects of the proposed activities, I have
considered the information from the application, further information provided, and the
evidence provided in the s42A reports of the technical experts for the Regional
Council. In my view there are six principle categories of environmental effects relevant
to the application:
i. Positive Effects;
ii. Construction effects;
iii. Effects on flood risk;
iv. Effects on the water quality, aquatic habitat and species within Manawatu
River;
v. Effects on terrestrial ecology and biodiversity; and
vi. Cultural effects.
Positive Effects
45. The application8 notes the proposal aims to enhance amenity outcomes in the
community. In addition, submissions noted positive effects of the bridge relating better
transport routes in the city and a safer active transport link as oppose to cycling over
the existing bridge on Fitzherbert Avenue to access key areas such as Massey and the
Linton Camp.
8 Application, section 8.2, Page 27
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
14
46. Overall, I consider the anticipated outcomes of the proposal will have positive effects
for the community by providing access to areas of employment and education facilities
on the southern side of the city. The bridge project is likely to have environmental,
social and economic benefits for the community by encouraging the uptake of walking
and cycling as a transport mode and for recreational purposes.
Construction Effects
47. The construction activities associated with the proposed bridge are of a scale and
duration has the potential to cause adverse effects on the River. These effects are
considered temporary in nature with the construction phase anticipated to be
completed within approximately 12 months. However, effects will require careful
management to ensure any significant adverse effects are avoided, remedied, or
mitigated. The following assessment considers the potential affects associated with the
construction.
Effects from dust
48. The project involves a large amount of earthworks which has the potential to create
dust. The applicant has noted that in the event that dust emissions become a problem
during dry, windy conditions, portable water sprayers can be used as necessary to
dampen down problem areas on the site. The application states 15m3 of surface water
per day can be abstracted from the Manawatu River for dust control purposes.
49. The effects from dust are expected to be temporary in nature and the dust effects can
be appropriately managed through conditions of consent (Appendix A). Overall the
effects from dust during construction are expected to be no more than minor if
managed appropriately.
Sediment release
50. Submitter 26 raised concerned that a finalised Erosion and Sediment Control Plan
(hereafter ‘ESCP’) was needed and information was missing from the application, such
as the location of stock piles required on site. The Applicant has since provided an
amended draft ESCP in response to the further information requested.
51. The draft ESCP has been reviewed by Mr Sutherland. Mr Sutherland has assessed the
application against the Greater Wellington Regional Council document titled; “Erosion
and Sediment Control Guidelines for the Wellington Region” (2002, reprint 2006) (the
GW Guidelines).
52. The amended draft ESCP including a brief methodology to minimise the potential
adverse effects during construction of the piles. The Applicant proposes to redistribute
in situ river bed gravels to divert part of the river flow in the Manawatu River to provide
dry working conditions for machinery accessing the two pile sites.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
15
53. The draft ESCP states that cleanfill is expected to be gravel material with limited fines.
This Mr Sutherland states in his evidence that the proposed soil used for fill purposes
is considered ‘low risk’, however the soil type needs to be confirmed by the fill
specification. If the fill specification indicates a finer particle size soil type, a Universal
Soil Loss Equation (USLE) will need to be completed, to determine sediment yield and
clearly define this risk. Based on Mr Sutherland’s recommendation, I have included a
requirement for a USLE to be provided if necessary.
54. Mr Sutherland considers the proposed draft ESCP meets the GW Guidelines, however
a Final ESCP is necessary prior to works commencing to ensure the proposed
methodology is confirmed. The application provides a sequence of works and
construction methodology, however the applicant has requested that there is flexibility
in the consent conditions to allow for changes to the methodology to be made. Mr
Sutherland considers this a reasonable request. Mr Sutherland notes a Management
Plan is appropriate and will need to include a detailed winter works management plan
to ensure the Applicant can minimise the effects and comply with the recommended
conditions of consent.
55. Mr Sutherland’s evidence states the project presents a ‘Medium Risk’ of discharging
into the Manawatu River. Based on Dr James evidence regarding the receiving
environment, Mr Sutherland has assessed the overall site risk for the earthworks
component of the project to be ‘Medium Risk’ on the Site Risk Assessment Matrix.
56. Taking into account the predicted level of risk assessed by Mr Sutherland, I am
satisfied the potential effects from the earthworks resulting in sediment release can be
managed through conditions of consent. Therefore, I have included conditions to
ensure best practice is carried out in terms of erosion and sediment controls that will
minimise potential effects on the Manawatu River during the construction works. A
finalised ESCP is recommended to be required for approval prior to construction
commencing, and is included as a condition of consent in Appendix A of this report.
Potential Effects on Flood Risk
Flooding and drainage – Construction
57. The application outlines the hydraulic design developed for the preferred bridge in the
following reports: Preliminary Hydraulic Report; Detailed Business Case – Hydraulic
Report, Piers & Abutments technical note v2; and Interim advice for DBC.
58. Mr Wallace has assessed the potential effects of the application, specifically the
change in water level in the Manawatu River (including the long-term effect of both the
abutments and piers).
59. The application recognises there is an element of risk during the proposed construction
works as a result of damages from high flows in a flood event which could occur during
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
16
the course of construction. Measures can be put in place for the Applicant to ensure
they are aware of any flood warnings and there is a procedure in place which will be
carried out to ensure that the city’s level of flood protection and infrastructure are not
put at risk during a flood event while the construction phase of the works is still in
progress.
60. Stockpiled material could be washed down stream in a flood event, and depending on
what stage construction is at, partially completed structures could be damaged. An
area on the northern side is allocated for surplus materials, yet it is unclear whether a
stock pile site is required on the true left side of the river. Conditions has been
recommended to ensure this is addressed in the final ESCP, including a requirement
for a Flood Contingency Plan.
Flood risk (Northern side)
61. The proposed works on the true right bank of the river are located on a stopbank
designed to contain a 1 in 500 year return period flood event. The application9 states
the proposed works undertaken on a stopbank has the potential to alter existing flow
paths in the river and operational performance of the stopbank. Figure 2 of the
Preliminary Hydraulic Report shows the potential change in water levels.
62. Mr Wallace has confirmed the modelling approach and the method of estimating the
effects of the bridge is sound. Paragraph 13 of Mr Wallace’s report notes some
elements of the modelling require revision. Mr Wallace recommends the model review
findings outlined in Appendix A of his evidence, be taken into consideration during the
detailed design stage. In addition, he notes the applicant needs to confirm at that stage
that the effects are of similar order of magnitude as documented or better. This can be
taken into account in the final design of the bridge.
63. Despite changes being suggested in Mr Wallace’s evidence, overall he considers the
increase in water level as a result of the bridge is likely be an imperceptible effect on
peak water levels and the flood protection measures.
64. Based on Mr Wallace’s advice, I consider the potential effects can be managed
through conditions of consent, being certification of the final design and methodology
of the proposed bridge and associated construction works. The final design plans and
construction methodology will need to be certified by MWRC against the integrity and
functionality of the existing level of river flood protection structures.
65. Further information provided notes the integrity of the stopbanks will be preserved;
crest level of the stop banks will be preserved, with the slope and crest width locally
improved in some locations. Also, the Applicant’s response noted “proposals for
temporary stopbanks, or other measures required to preserve the performance of the
9 Application, Section 8.4, page 28
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
17
stopbanks will be developed by the contractor”. The evidence prepared by Mr Wallace
confirms that this is reasonable, subject to appropriate conditions to ensure this is
achieved. A condition is recommended to ensure the integrity of the stopbank is
maintained and any damage is rectified by the consent holder.
Flood risk (Southern side)
66. Mr Wallace has considered the effects of flooding on the southern side of the river,
specifically Massey Campus on the northern side of Tennant Drive. Opus assessment
calculates that, in a 1 in 500 year flood event, depths in that area would be up to 800-
900 mm in that area. Mr Wallace recommends that the final design plan confirms that
the predicted increase in that area remains no more than 10 -15 mm to the existing
area. This would mean no additional areas would be flooded.
67. Although uncertainty exists in terms of the final bridge design, I consider that this
uncertainty can be addressed through adequate conditions, as recommended in
Appendix A of this report.
Potential scour and erosion
68. During a flood event, there is potential for scour or erosion to occur. The evidence of
Mr Wallace discusses the potential of local scour, in addition to general river bed
scour, during flood events. Paragraph 16 of Mr Wallace’s evidence notes this needs to
be considered in the final design of the river bridge crossings. He is satisfied that this
can be addressed through adequate conditions. Conditions outlined in Appendix A
require scour and erosion prevention to be incorporated into the final design plans
which will need to be certified by the MWRC prior to works commencing.
Surface Water Quality
69. The proposed works will result in the discharge of sediment to the Manawatu River
while instream works are carried out, specifically during the proposed stream
diversions which are required to construct two piers in the bed of the river. There is
also risk of a change in pH as a result of any concrete wash or wastewater discharge
to the river. This release of sediment and other containments may have adverse
effects on the water quality and consequently has the potential to have adverse effects
on aquatic life.
70. The application proposes two river diversions. Each river diversion aims to create a
bunded area to enable piles to be construction in the dry. Based on Mr Sutherland’s
opinion, the Applicant will need to work within the bed of the river for approximately 3-5
days to create each bund. In addition, the Applicant will need to work within the river to
de-construct each temporary bunded area around the pile. Likewise, Mr Sutherland
estimates approximately 3-5 days to complete this stage.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
18
71. To mitigate potential effects of the temporary plumes of sediment discharge during the
proposed diversions and de-watering works, the applicant suggests the following
monitoring requirement:
- “The establishment of a reference monitoring site upstream of the project, a site at
the end of the zone of reasonable mixing (200 m downstream of the discharge
point) and a third downstream site. Sites should be on the same side of the river
that works are occurring.
- The establishment of appropriate water quality trigger levels for adaptive
management at the end of the zone of reasonable mixing. We understand that a
general standard for such works is <30% change in visual clarity.
- The collection of visual clarity, pH and suspended sediment measurements at the
above sites during sediment generating works or discharges.
- The establishment of a reference monitoring site upstream of the project, at the
end of the zone of reasonable mixing (200m downstream of the discharge point)
and a third downstream site to ensure water quality trigger levels are not breached;
no greater than 30% change in visual clarity within the water body”.10
72. Provided instream works are limited to 3-5 days and in accordance with the
application, the effects of the discharge of sediment on aquatic life are considered no
more than minor.
73. The accidental release of fuel, oils or other chemicals from machinery working in the
riverbed may have adverse effects on water quality. The application11 recommends pH
is monitored. Mr James concurs that pH monitoring should be required. In addition, Mr
James recommends a requirement for some corrective management actions wherever
trigger levels of any monitored parameters are exceeded.
74. I concur with the recommendations provided in Dr James evidence, and have outlined
recommended conditions of resource consent, if granted, that minimise any adverse
effects.
Effects on Aquatic Life
75. The application12 outlines an assessment of the potential effects of the proposal on
aquatic life. Dr James evidence provides a detailed assessment of the potential effects
of the bridge construction on benthic ecology and fish fauna.
10
Application, Appendix C, Section 3.4.2, page 7 11
Application, Appendix C, Section 3.4.2, page 7 12
Application, Appendix C, Section 3.4.2, page 7
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
19
76. Dr James agrees with the Applicant’s conclusion that the Manawatu River has “high”
fishery values in the vicinity of the bridge project. Dr James’s suggests that additional
site specific information is required to determine if the proposal would have any
potential adverse affects on fish. The applicant did not carry out a site-specific
assessment.
77. The application provides a list of fish species known within the Manawatu River
catchment at or upstream of the site derived from New Zealand Freshwater Fish
Database (NZFFD) records. Dr James report provides a list of migratory species likely
to be present in the river and the fish species likely to pass the bridge site at certain
times of the year. Schedule B of the One Plan recognises ‘Other Trout Fishery’ values
for this reach of the Manawatu River.
78. Submission 4 (Fish and Game) outlined proposed conditions to minimise the impact on
trout and the health of the supporting ecosystem. One of these proposed conditions is
that works be limited to the summer low flows. The Applicant has indicated that this
may not be achievable with works possibly required during the winter to meet project
deadlines. Dr James has recommended measures to ensure the instream values are
protected, particularly reach specific values under Schedule B of the One Plan which
includes Trout Fishery (other).
Effects on bank birds, herpetofauna and vegetation
79. The Applicant’s assessment did not include an onsite assessment of riparian
vegetation and herpetofauna (lizards) assessment. Mr Lambie has assessed the
application and provided an opinion on the ecological risks associated with the
proposed bridge with specific regard to the bank vegetation, lizards and birds.
Birds
80. The site is identified as a “Site of Significance-Riparian”. This is associated with gravel
beaches suitable for nesting wader birds (in this instance banded dotterel), Mr Lambie
has recommended measures to ensure the Dotterels are protected. I have recommend
conditions in Appendix A.
81. Mr Lambie considers that the bridge will not adversely affect the flight paths of
indigenous birds, given birds can navigate around the piers and under (or over) the
bridge.
82. Submission 9 noted moreporks nest in the pines on the southern bank of the river
which will be removed as part of the project. The Applicant has since assessed the
potential effects on bird habitat in response to the further information requested. Mr
Lambie’s evidence notes the Applicant’s assessment is reasonable with regard to the
use of trees for prey roosts of falcon and nesting for morepork. Mr Lambie
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
20
recommends tree removal should be done after March and before October to avoid
their nesting time. I have suggested a condition in Appendix A of this report.
Herpetofauna
83. Mr Lambie has confirmed gecko’s may be present in suitable habitat in the Esplanade
and so he can not disregard potential effects on herpetofauna. Pohutukawa trees on
the site (and are subject to removal) are within the construction envelope which may
provide a suitable habitat for geckos (skinks). Given there is potential for geckos to be
present, Mr Lambie has recommended a condition to remedy effects. I have suggested
a condition in Appendix A of this report to take into account his recommendation.
Vegetation
84. Mr Lambie considers the on-site vegetation of both banks does not meet the One Plan
definition of significance (i.e. is not a rare, threatened or at-risk habitat type listed in
Schedule E Table F1). Similarly, none of the species present trigger the species-
specific triggers for significance listed in Table F2a of the One Plan.
85. Mr Lambie notes it is highly unlikely that there are any rare or threatened native
grasses, herbs, or other vulnerable native plant species present in the areas to be
cleared. Based on Mr Lambie’s opinion, I consider that the proposed vegetation
clearance to be no more than minor.
86. Relying on Mr Lambie’s assessment, I have recommend conditions to address the
effects on birds, herpetofauna and vegetation, outlined in in Appendix A and overall,
consider the effects to be no more than minor.
Cultural Effects
87. The application discussed cultural effects in general terms. There are no known waahi
tapu or sites of cultural significance within the works area, however this reach of the
Manawatu River is identified as a “Site of Significance – Cultural” under Schedule B of
the One Plan, signalling the Manawatu River is of great importance to iwi. Accordingly,
the application states that regular consultation with Rangitaane o Manawatu has
occurred as part of the wider project to ensure cultural values have been considered
with respect of the proposal.
88. Written approval from Tanenuiarangi Manawatu Incorporated (TMI) as mandated
authority for Rangitaane o Manawatu has been obtained and provided with the
application.
89. The Applicant has provided the Memorandum of Understanding (MOU)
documentation, dated 11 November 2016, as part of the s92A information request. The
MOU outlines the relationship and responsibilities of the two parties in relation to the
wider He Ara Kōtahi project and the construction of the pedestrian and cycle bridge for
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
21
which consents are sought. Consideration to matters raised in the memorandum of
understanding between TMI and the Applicant have been included in recommended
condition of resource consent.
90. A submission was received from Tanenuiarangi Manawatu Incorporated (TMI) which
did not raise any concerns with regards to effects of the proposed development. TMI
indicated they wish to be heard at the hearing. I consider it may be helpful to hear from
the respective submitter before being satisfied cultural matters have been fully
addressed.
Conclusion
91. The submissions received highlight the benefits associated with the bridge, including
amenity, health and wellbeing benefits for the community.
92. Flood risk can be managed through consent conditions.
93. Based on the evidence presented by the Applicant and MWRC experts, the potential
effects from the construction of the bridge, subject to the recommended conditions, are
likely to give rise to both temporary and long-term effects that overall, I consider to be
no more than minor.
94. There is general agreement that potential adverse effects can be managed through
consent conditions.
95. The proposal is unlikely to result in more than minor adverse effects, however
additional monitoring is recommended to ensure effects on herpetofauna, water quality
and macroinvertebrates are appropriately mitigated.
96. A final ESCP can be provided to ensure the effects of the construction, in particular, in-
stream works, will mitigate potential contaminants entering the Manawatu River.
97. Given a letter of support has been provided from TMI and a Memorandum of
Understanding (MOU) has been provided with the application, I consider the cultural
effects to be no more than minor, provided matters raised in the MOU are adhered to.
98. Potential effects on effects on birds and vegetation will be no more than minor.
99. While recognising the uncertainty that remains with regards to the bridge design, I
consider that the bridge will not adversely impact flood flows and flood protection
structures provided the final design recommended conditions of consent are adhered
to.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
22
I. STATUTORY CONSIDERATIONS
100. When considering an application for a resource consent (as a discretionary activity)
and any submissions received, the consent authority must, subject to Part 2, have
regard to sections 104 and 104B of the Act.
Relevant National Environmental Standards (NES)
Section 104(1)(b)(i)
101. Section 104 requires consideration of any NES’s that are relevant. The applicant has
provided an assessment against the National Environmental Standard for Freshwater
Management 2014 in the application13 and I concur with the assessment provided.
Relevant National Policy Statements (NPS)
Section 104(1)(b)(iii)
102. Section 104 requires consideration of National Policy Statements that are relevant. In
this case the National Policy Statement for Freshwater Management, 2014 (NPSFM
2014) is relevant. The NPSFM outlines a number of national values of freshwater
where fresh waters intrinsic values, such as safeguarding the life-supporting capacity
of water is recognised and considered. I understand that the One Plan aims to give
effect to the NPSFM 2014.
103. In this case, the application has regard to the adverse effects on the life-supporting
capacity of the Manawatu River and its ecosystem. While the discharge of sediment
resulting from the disturbance of the river bed during construction will not be
completely avoided, all practical measures will be taken to minimise sediment release
and any discharge will be temporary in nature.
104. Taking into account the recommended conditions, I consider the proposal is consistent
with the objectives and policies of the NPSFM 2014.
Operative One Plan (2016)
105. The One Plan (2016) contains the relevant Regional Policy Statement and Regional
Plan provisions applicable to the application.
Relevant Regional Policy Statement
106. Section 104(i)(v) of the RMA requires consideration of a Regional Policy Statement
(RPS), in this case part one of the One Plan (2016).
107. The applicant has provided an assessment of the RPS in the application14. Rather
than repeat the objectives and policies, I have provided commentary of the relevant
13
Application, Section 9.1.2.1, Page 35
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
23
objectives and policies below and included additional objectives and policies where I
consider it to applicable.
Chapter 2: Te Ao Māori
108. In addition to the objectives and policies identified in the application, I consider that the
relevant Te Ao Māori Objectives and Policies that apply to the proposal are:
Objective 2-1: Resource management
Policy 2-1: Hapū and iwi involvement in resource management
Policy 2-2: Wāhi tapu, wāhi tūpuna and other sites of significance
Policy 2-3: The mauri of water
Policy 2-4: Other resource management issues
109. The Manawatu River at this location is a “Site of Significance – Cultural” under
Schedule B of the One Plan (2016). Iwi have been involved in the development of the
proposal to ensure matters of social, economic, cultural and environmental importance
are taken into account.
110. The application notes there are no known waahi tapu sites within the works area. The
Applicant and Tanenuiarangi Manawatū Incorporated (TMI) have entered a
Memorandum of Understanding (MOU), which outlines the relationship and
responsibilities of the two parties in relation to the wider project and the construction of
the pedestrian and cycle bridge for which consents are sought. These commitments
are recommended to be conditions of resource consent, if granted (as shown in
Appendix A).
111. Overall, I consider the proposal is consistent with Objective 2-1 and Policies 2-1, 2-2,
2-3 and 2-4 of the One Plan.
Chapter 3: Infrastructure, Energy, Waste, Hazardous Substances and
Contaminated Land
112. I concur with the applicant’s identification of applicable provisions and the assessment
relating to infrastructure in Table 9.2 of the application15. Policy 3-1 recognises benefits
of infrastructure and other physical resources of regional or national importance. Policy
14
Application, Section 9.1.4, Page 36 15
Application, Table 9.2, Page 37
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
24
3-2 highlights the potential adverse effects of other activities on infrastructure and
other physical resources of regional or national importance.
113. The proposed bridge is likely to play an important role in servicing communities,
providing an additional transport link across the Manawatu River. The bridge will
provide value to the community by enhancing public access while not having an
adverse effect on the existing flood protection structures (stopbank). Therefore, I
consider the proposed structures are not inconsistent with the Objective 3-3, Policies
3-1, 3-2, 3-3 and 3-4 of the One Plan (2016).
Chapter 5 Water
114. The applicant has identified the relevant provisions within the application16. Chapter 5
addresses the management of fresh water in the Region. I have provided a brief
summary below of the key objectives and policies I consider relevant to this
application.
115. Objective 5-1 seeks to manage surface water bodies and their beds in a manner which
safeguards their life supporting capacity and recognises and provides for the values
listed in Schedule B of the One Plan. Dr James has assessed the adverse effects on
instream values. Based on Dr James advice, I am of the view that conditions can be
imposed to adequately mitigate adverse effects on Schedule B values, and water
quality is carefully monitored to ensure the One Plan targets are not exceeded to a
level that would adversely effect the Schedule B values relating to life supporting
capacity and Trout Fishery.
116. Policy 5-1 identifies WMZs and the individual values and management objectives
associated with them. Policy 5-2 identifies water quality targets which must be used to
inform surface water quality management.
117. The proposed activities have potential to generate significant sediment release posing
a threat to aquatic life. As discussed in Dr James evidence, water quality targets
should be met in relation to the sediment discharge to protect in-stream values. Based
on Dr James advice, I consider water quality targets are applicable to this application
and therefore I have included conditions to ensure the discharge of sediment does not
breach the relevant One Plan standards thereby protecting in-stream values.
118. The site is within the Lower Manawatu WMZ. The application has correctly identified
the values associated this WMZ, as set out in Schedule B of the One Plan and surface
water quality targets are described in Schedule E of the One Plan.
16
Application, Section 9.1.4, Page 36
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
25
119. Policy 5-22 recognises and provides for the Schedule B Values for the Water
Management Sub-Zone in which the activities takes place, in the manner described in
Policies 5-23, 5-24 and 5-25, all of which are relevant to this proposal.
120. Subject to the conditions being imposed to avoid adverse effects on the Schedule B
values, I consider the proposal consistent with policies 5-22, 5-23, 5-24 and 5-25 of the
One Plan.
Chapter 6 Indigenous biological diversity, landscape and historic heritage
121. Chapter 6 of the Plan deals with Indigenous biological diversity, landscape and historic
heritage. Objective 6-1 is designed so as to protect areas of significant indigenous
vegetation and significant habitats of indigenous fauna and maintain indigenous
biological diversity, including enhancement where appropriate. Policy 6-1 is a process
policy which directs the Council to develop objectives, policies, methods and rules for
the purpose of managing biological diversity in the Region. The Regional Council has
achieved this policy through the relevant objectives, policies and rules contained in
Chapter 13.
122. Policy 6-2 states habitats are determined to be rare or threatened habitats under
Schedule F of the One Plan. Mr Lambie’s evidence confirms on-site vegetation, on
both the true left and true right side of the river, does not meet the One Plan definition
of a threatened or at-risk habitat type listed in Schedule E Table F1.
123. I consider the proposal is consistent with objectives 6-1 and 6-2 and policies 6-1 and 6-
2 of the One Plan, provided, monitoring of herpetofauna is carried out in accordance
with Appendix A of this report.
Regional Plan – One Plan (Part 2)
Objectives and Policies of the Operative Regional Plan
124. The following is an assessment of the proposal against the Objectives and Policies of
the Regional Plan being Part II of the One Plan. The Applicant has identified some of
the relevant Objectives and Policies within the Application17. Rather than repeat the
objectives and policies, I have provided commentary of the relevant objectives and
policies below.
Chapter 13
125. Objective 13-1(b) regulates the vegetation clearance and land disturbance activities
relating to the application, specifically the potential increased sedimentation in water
17
Application, Section 9.1.5, Pages 36 and 37
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
26
bodies as a result of human activity is avoided as far as reasonably practicable, or
otherwise mitigated. Policy 13-1 is relevant to the proposal as it manages those effects
by requiring resource consents for activities adjacent to some water bodies, large-
scale land disturbance, in this case, large scale earthworks within 5 metres of the
Manawatu River.
126. In terms of this proposal, I consider adequate sediment and erosion control measures
are vital to ensure sedimentation effects are mitigated. Mr Sutherland’s evidence has
provided an assessment against the “Erosion and Sediment Control Guidelines for the
Greater Wellington Region”. This document aims to minimise disturbance, protect
waterbodies, stabilise exposed areas quickly, install sediment and erosion controls and
inspect the site. Mr Sutherland has confirmed that the draft ESCP is sufficient in that it
can be assessment against best practice guidelines ensure any adverse effects on
water quality are avoided where possible and otherwise minimised. Therefore, I
consider the application is consistent with Objective 13-1 and Policy 13-1 of the One
Plan.
127. Policy 13-2 outlines matters that need to be considered when making decisions on
resource consent applications for vegetation clearance, large-scale land disturbance
and the ancillary discharges to and diversions of surface water. As noted above, the
ESCP can be used to manage the effects of land disturbance. Policy 13-2 states the
Regional Council must set consent conditions on a case-by-case basis, having regard
to a number of matters, including preparing a ESCP and relevant codes of practice,
standards and guidelines and accepting compliance with them to the extent that they
can be used as conditions on resource consents. Given there is general agreement
that the guidelines can be adopted through a Finalised ESCP, I consider the
application is consistent with Policy 13-2.
128. Under Policy 13-2 (m), matters under Policy 14-9 need to be considered given I the
activities involve an ancillary discharge to surface water. For the reasons discussed in
the assessment against the NPSFM, the application is consistent with Policies 13-2
(m) and 14-9.
129. Objective 13-2 relates to the protection of areas of significant indigenous vegetation
and significant habitats of indigenous fauna and maintenance of indigenous biological
diversity, including enhancement where appropriate. Mr Lambie’s evidence does not
identify any significant indigenous vegetation. Significant habitats of indigenous fauna
have not been fully addressed by the Applicant. Given there may be geckos present,
which have a protected status under the Wildlife Act 1953 in New Zealand, I consider it
appropriate to require further monitoring and consent conditions to imposed, if the
consent is granted.
Chapter 14
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
27
130. Chapter 14 relates to Discharges to Land and Water. Objective 14-1 seeks to manage
discharges and land use activities in a manner which safeguards the life supporting
capacity of water and provides for the Values associated with waterbodies and avoids,
remedies or mitigates adverse effects of discharges to land on surface or groundwater.
131. Policy 14-1 requires consideration of the relevant objectives and policies of Chapter 5
when making a decision or setting consent conditions for the discharge of
contaminants to water. I have dealt with this in paragraphs 29-32 above. I agree with
the Applicant’s identification of relevant Objectives and Policies under Chapter 14.
Therefore, I will not repeat the assessment in my evidence.
Chapter 17
132. Chapter 17 relates to regulation of structures within the bed of a river. Objective 17-1:
Regulation of structures and activities in artificial watercourses and in the beds of
rivers and lakes, and damming, has regard to the effects discussed under Chapter 5
that relate to structures in the beds of rivers. It is my view that Objective 17-1 and
Policy 17-1 are the relevant provisions under Chapter 17.
133. As outlined in Section H of this report, the draft ESCP has been against best
management practices to mitigate adverse effects from deposited sediment into
aquatic environments. Conditions have been recommended in Appendix A of this
report which seek to mitigate any adverse effects on ecological health. For this reason,
I consider the proposed activities are consistent with the relevant provisions.
J. OTHER MATTERS THE CONSENT AUTHORITY CONSIDERS RELEVANT
Manawatu River Accord
134. The Manawatu River Accord is a non-statutory document which records an agreement
between various parties to achieve the goal of improving the health of the Manawatu
River, such that it sustains fish species, and is suitable for contact recreation, in
balance with the social, cultural and economic activities of the catchment community.
PNCC are signatories of the Accord. I consider the construction of a pedestrian and
cycle bridge over the Manawatu River aligns with the direction of the Accord.
Regional Transport Plan
135. The Land Transport Management Act 2003 (LTMA) requires the Horizons Regional
Council Transport Plan (which sets out the strategic direction for land transport in the
region), to include a statement of transport priorities for the first 10 years of the plan.
The identified strategic priorities will guide investment in the land transport network.
136. I consider Strategic Priority 4 of the Regional Transport Plan (Section 2.2.4) broadly
aligns with the He Ara Kotahi bridge project. Strategic Priority 4 recognises the need
for an increased focus on pedestrian and cycling. Over the past 20 years there has
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
28
been a decline in walking and cycling throughout New Zealand. The government has
recognised the important role walking and cycling can have in positive economic,
social and environmental outcomes. The priority highlights walking and cycling in
urban, and between, urban centers can support economic growth and productivity
through the provision of better access to employment areas. It also improves capacity
on existing roads through mode shift and so lessens the amount of maintenance and
construction of new roads.
137. While the He Ara Kotahi bridge is not currently recognised in the Regional Transport
Plan, I consider the wider project to contribute to its overall goal.
K. ASSESSMENT AGAINST RMA PROVISIONS
Section 107
138. Section 107 of the RMA notes the restrictions on the granting of a discharge permit.
A consenting authority shall not grant a discharge if, after reasonable mixing, the
contaminant discharged is likely to give rise to any of the following:
a) The production of conspicuous oil or grease files, scums or foams, or floatable
or suspended materials;
b) Any conspicuous change in the colour or visual clarity;
c) Any emission of objectionable odour;
d) The rendering of freshwater unsuitable for consumption by farm animals;
e) Any significant adverse effects on aquatic life.
139. The discharge of sediment into the Manawatu River associated with the construction
works is anticipated as a result of bed disturbance in the active channel and
earthworks within 5 metres of the bed. The discharge effects may give rise to a
conspicuous change in water clarity, however the discharge is expected to have a
short duration, thus, does not give rise to significant adverse effects on aquatic life.
140. Subject to the recommended conditions I am comfortable that the proposed discharge
would not give rise to the effects listed in Section 107.
Part 2 of the Resource Management Act 1991 – Purpose and Principles
Section 6: Matters of National Importance
141. Section 6 of the Act sets out the matters of national importance which are to be
recognised and provided for when considering applications for resource consent. In
terms of this proposal, I consider that (a), (c) (d), and (e) to be relevant.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
29
142. Part (a) seeks to preserve and protect the natural character of rivers and their margins
from inappropriate use. In terms of 6(a), I consider that the proposal does not impact
on the natural character of the Manawatu River. The Manawatu River is a heavily
modified river, such as construction of stopbanks to control erosion and flooding at the
proposed bridge site.
143. Part (c) being the protection of areas of significant indigenous vegetation and
significant habitats of indigenous fauna, has been assessed within Section H of this
report. 127. The assessment of effects undertaken in Section H of this report has
addressed indigenous vegetation and significant habitats of indigenous fauna effects
and addressed the various mitigation measures. I consider the proposed bridge is
consistent with this matter.
144. Section 6(d) requires recognition of public access to rivers. Currently there is public
access to the reserve area on the northern side. An alternative route around may need
to be considered for recreational purposes. Nevertheless, I consider the proposal does
not restrict public access to the Manawatu River, except where it may be necessary for
public safety reasons. In addition, in the long-term the bridge will enhance public
access.
145. Section 6(e), relates to the relationship between Maori and water and their culture and
traditions associated with the water. The connection between the River and Maori is of
considerable importance being identified as a Site of Significance – Cultural. Section H
highlights the involvement local iwi have had in the development, including prior to the
resource consents being lodged with the MWRC. For the reasons outlined in Section H
of this report relating to water quality, aquatic life and cultural effects, I consider that
matters under Section 6(e) have been addressed.
146. Accordingly, I consider that the proposal has recognised and provided for those
relevant matters of national importance outlined in Section 6 of the Act.
Section 7: Other Matters
147. Section 7 sets out other matters which the decision maker must have had particular
regard to when making a decision on an application for resource consent. Of particular
relevance to this application are sections 7(a), (aa), (b), (c), (d), (f), (h) and (i):
(a) Kaitiakitanga (stewardship);
(aa) The ethic of stewardship;
(b) The efficient use and development of natural and physical resources;
(c) The maintenance and enhancement of amenity values;
(d) Intrinsic values of ecosystems;
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
30
(f) Maintenance and enhancement of the quality of the environment;
(h) The protection of the habitat of trout and salmon; and
(i) The effects of climate change.
148. Regarding section 7(a) and (aa), the RMA requires a decision maker to have particular
regard to kaitiakitanga and the ethic of stewardship. The application outlines that
consultation with TMI was undertaken to ensure tangata whenua interests were
acknowledged and any cultural implications of the bridge were addressed.
149. Section 7(b) requires the efficient use and development of natural and physical
resources. The bridge has been designed taking into account the natural physical
characteristics of the Manawatu River.
150. Sections 7(c) (d) and (f) outline the maintenance and enhancement of amenity values,
the intrinsic value of ecosystems and the maintenance and enhancement of the
environment. I am comfortable that subject to the recommended conditions the
proposal is not contrary to these sections.
151. Part (h) requires regard to be had to the protection of the habitat of trout. The habitat of
trout in the river will not be adversely affected by the proposed works. A number of
conditions have been recommended that will assist with the protection of habitat.
152. Overall, the proposal will has particular regard to matters outlined in Section 7.
Section 8: Treaty of Waitangi
153. Section 8 of the Act requires the consent authority to take into account the principles of
the Treaty of Waitangi. The Court of Appeal (New Zealand Māori Council Case 54/87)
identified four major principles, which are:
a. The Essential Bargain – the exchange of Kāwanatanga (in Article 1) for the
protection of tino rangatiratanga (in Article 2).
b. The Principles of Tino Rangatiratanga and Kāwanatanga – the guarantee to
Iwi and Hapū of full chieftainship or authority over their lands, resources and
taonga, and therefore the control and management of tribal resources
according to Māori cultural preference, as balanced against the Crown’s right to
make law and govern.
c. The Principle of Partnership and Good Faith – the shared obligation of both
Treaty partners to meet their respective commitments and to act reasonably
and in good faith to one another.
d. The Principle of Active Protection – the Crown’s obligation to actively protect
the interests of Māori in their land and resources.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
31
154. The application details consultation was undertaken with Rangitane o Manawatu prior
to the application being lodged. A submission from TMI has been received in support
of the application. I would anticipate that an opinion would be expressed at the hearing
which would be useful to allow for further assessment against Section 8.
155. I am satisfied that the principles of the Treaty have been taken into account given
written approval has been received from TMI.
Section 5: Purpose
156. Section 5 states that the purpose of the Act is to promote sustainable management of
natural and physical resources. Section 5(2) of the Act then proceeds to state that:
“sustainable management” means managing the use, development, and protection of
natural and physical resources in a way, or at a rate, which enables people and
communities to provide for their social, economic, and cultural well-being and for their
health and safety while:-
(a) sustaining the potential of the natural and physical resources (excluding
minerals) to meet the reasonably foreseeable needs of future generations;
(b) safeguarding the life-supporting capacity of the air, water, soil and ecosystems;
and
(c) avoiding, remedying or mitigating any adverse effects of activities on the
environment.
157. I consider the applications are consistent with the purpose of the Act for the following
reasons:
It is anticipated that the life-supporting capacity of the water will be adequately
safeguarded, as highlighted in the assessment of effects undertaken in Section
H of this report.
Any adverse effects on the life-supporting capacity of air, water, soil and
ecosystems are considered temporary in nature.
Short-term effects that may potentially have an adverse effect on the life
supporting capacity of the Manawatu River can be managed through imposing
consent conditions. In addition, any adverse effects on flood risk, bank stability,
water quality, aquatic life, herpetofauna and birds can be mitigated by way of
recommended conditions of consent.
Consideration of Term
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
32
158. In making a recommendation about term I have considered the provisions in Policy 12-
5 of the One Plan. Chapter 12 of the One Plan sets out general objectives and policies,
and Policy 12-5 deals with consent durations. The applicant has sought a term of 35
years.
159. Under policy 12-5, consents are generally granted for the term sought by the Applicant,
other than when considering an application under ss13, 14 and 15 of the Act, set under
Policy 12-5 (b). Accordingly, I give consideration to the matters set out under (b).
160. Under Policy 12-5 (b) consideration must be given to common catchment expiry dates.
Consents should expire or have the ability to be reviewed on these dates and every 10
years thereafter. The common catchment expiry for the Lower Manawatu is 1 July
2013. If granting at next common catchment, matters under 12-5(b)(i)(ii)(iii)(iv) are
relevant.
161. The applicant proposes works with be carried out within 12 months. Provisions under
Rules 17-4 and 17-5 of the One Plan allow the use of an existing structure and
maintenance. Therefore, I consider that only the construction phase needs to be
consented. Taking into account unanticipated delays such as weather constraints, I
consider the next common catchment being 1 July 2023, an appropriate duration.
162. Policy 12-6 details the situations where consent review conditions are considered to be
appropriate. I do not consider a review relevant to this application given the short
duration of construction as well as any adverse effects being avoided, remedied and
mitigated through conditions on consent.
163. It would be helpful if the applicant could clarify its position on this matter in their s41B
report or at the hearing to ensure a shorter duration of consent is appropriate.
L. CONCLUSION
164. I have considered the application, the further information, the submissions and Section
42A reports. In particular I have considered the following:
The actual and potential effects of the activities identified within the AEE;
The matters raised in the written submissions;
The statutory framework being the NPS for Freshwater Management, the
Regional Policy Statement and Regional Plan; and
Part 2 of the RMA.
165. There are long-term positive effects associated with the proposal. The proposed bridge
will provide better pedestrian and cycle access to southern urban areas of the city.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
33
Broadly, the projects focus on enhancing recreational opportunities that encourage
walking and cycling in urban areas.
166. Given TMI have provided written approval, I consider the proposed works will not have
any adverse cultural effects. Consideration to matters raised in the MOU between TMI
and the Applicant have been included in recommended condition of resource consent
(excluding the fencing in Stage 2 of the project) to ensure commitments are
addressed.
167. The proposal will result temporary adverse effects relating to water quality and aquatic
habitats as a result of sediment release during construction of the river diversions.
However, the sediment discharge can be minimised by adopting best practice erosion
and sediment control measures. It is recommended conditions are imposed to ensure
water quality standards under the One Plan are achieved, in accordance with Policy 5-
3 and Schedule E of the One Plan.
168. Policy 13-2 states the Regional Council must set consent conditions on a case-by-case
basis, having regard to relevant codes of practice, standards and guidelines and
accepting compliance with them to the extent that they can be used as conditions on
resource. It is therefore considered appropriate to set conditions to carry out works in
accordance Erosion and Sediment Control Guidelines and allow the draft ESCP to be
certified once the methodology is confirmed.
169. Once the temporary diversions are established the majority of the construction works
associated with the bridge construction will take place in the ‘dry’ river bed and hence
minimises the release of sediment into the river.
170. The proposed bridge will have a no more than minor adverse effect on water quality
and freshwater ecology, provided appropriate consent conditions regarding riverbed-
breeding birds, erosion and sediment control, concrete pouring, fish relocation, and
lighting design are included in the resource consent.
171. The proposed activity is consistent with the relevant objectives and policies in the NPS
for freshwater management, RMA and the objectives and policies of the relevant
Regional Policy Statement and Regional Plan.
172. The potential adverse effects of the proposed development in terms of flood control
and drainage is considered no more than minor.
173. Overall, subject to any additional evidence presented at the hearing, I recommend that
consent should be granted with the recommended conditions imposed.
174. A term of 6 years is appropriate, provided the applicant considers this sufficient time to
complete the proposed works.
Section 42A Technical Hearing Report
Resource Consent Application APP-2016200983.00 Palmerston North City Council Prepared by Luka de Jong – Consents Planner for Manawatu-Wanganui Regional Council 3 February 2017
34
M. RECOMMENDATION
175. Based on the above assessment, I recommend that subject to the conditions included
in Appendix A, resource consents ATH-2016201107.00 (Earthworks), ATH-
2016201172.00 (Discharge of Cleanfill), ATH-2016201173.00 (River Diversion) and
ATH-2016201174.00 (Beds, Rivers & Lakes) can be granted.