In Pursuit of Quality Access Lake Victoria South Water Services Board 10 YEARS ACHIEVEMENT REPORT 2007-2017 Photo: Completed Kisumu water supply in kajulu

Upload: others

Post on 29-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

In Pursuit of Quality Access

Lake Victoria South Water Services Board

10 YEARS ACHIEVEMENT REPORT

2007-2017

Photo: Completed Kisumu water supply in kajulu

Page 2: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 ii

ABBREVIATIONS

AFD : French Development Agency

AfDB : African Development Bank

ASK : Agricultural Society of Kenya

CEO : Chief Executive Officer

CoK : Constitution of Kenya

EACC : Ethics and Anti-Corruption Commission

EIB : European Investment Bank

GoK : Government of Kenya

ISCs : Inspectorate of State Corporations

KFW : German Development Bank

KICC : Kenyatta International Convention Centre

KIDDP : Kenya-Italy Debt for Development Programme

KOICA : Korea International Cooperation Agency

LTIs : Long Term Interventions

LVSWSB : Lake Victoria South Water Services Board

LVWATSAN : Lake Victoria Region Water and Sanitation Initiative

MWI : Ministry of Water and Irrigation

NRW : Non-Revenue Water

ORIO : Facility for Infrastructure Development of Netherlands

PS : Principal Secretary

PWDs : People with Disabilities

SPA : Service Provision Agreement

STRWSSP : Small Towns Rural Water Supply and Sanitation Projects

UNICEF : United Nations Children Education Fund

WSBs : Water Services Boards

WSPs : Water Service Providers

Page 3: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 iii

TABLE CONTENT

ABBREVIATIONS ........................................................................................................................ ii

INSTITUTIONAL BACKGROUND .......................................................................................... 1

CORPORATE MISSION ............................................................................................................. 1

CORPORATE VISION ................................................................................................................ 1

CORE VALUES ............................................................................................................................ 1

CORE FUNCTIONS ..................................................................................................................... 2

STRATEGIC OBJECTIVES .......................................................................................................... 2

BOARD OF DIRECTORS ............................................................................................................ 4

CORPORATE GOVERNANCE STATEMENT ........................................................................ 7

MANAGEMENT STAFF ............................................................................................................. 7

QUALITY POLICY STATEMENT ............................................................................................. 9

CHAIRMAN’S STATEMENT .................................................................................................. 10

CHIEF EXECUTIVE OFFICER’S STATEMENT .................................................................... 12

PROJECTS’ REPORT ................................................................ Error! Bookmark not defined.

PHOTO GALLERY .................................................................................................................... 28

ACHIEVEMENTS ..................................................................................................................... 30

CHALLENGES ........................................................................................................................... 31

WAY FORWARD ....................................................................................................................... 31

Page 4: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 1

INSTITUTIONAL BACKGROUND

Lake Victoria South Water Services Board (LVSWSB) is a non-commercial State

Corporation under the Ministry of Water and Irrigation (MWI). The Board was

established under Section 51 of the Water Act (2002) vide Gazette Notice No. 1714 of

12th March 2004 with the mandate of “ensuring efficient and economic provision of

Water and Sanitation Services in its area of jurisdiction”. Geographically, it covers

21,720 Sq. Km in the host Counties of Kisumu, Siaya, Migori, Homa Bay, Bomet,

Kericho, Nyamira, Kisii and parts of Nandi and Narok Counties. The aggregate

jurisdictional population is estimated at 8.75 million with a distribution of 21% in urban

and 79% in rural areas.

In the last 10 years, LVSWSB has since signed Service Provision Agreements (SPAs)

with eight (8) urban and over eighty six (86) rural Water Services Providers (WSPs) to

operate and maintain its service provision assets. During the inception of the Board,

much of the time was devoted to the development of governance and institutional

structures which included strategic plan, organizational structure, stakeholder

mapping, planning and designing and of various projects, formation and contracting of

water service providers.

Strategically the Board has mobilized financial resources from both the Government of

Kenya and Development partners amounting to approximately Kshs. 13 Billion in

capital infrastructure investments in water and sanitation which has benefited 2,590,000

people.

CORPORATE MISSION

The Board’s Mission is “to provide adequate water and sanitation infrastructure and

related services in a sustainable manner”.

CORPORATE VISION

The Board’s vision is “to be the most efficient and effective Water Services Board in

Kenya”.

CORE VALUES

The Board upholds these fundamental beliefs which define our expected standards of

behaviour and culture:

Professionalism

Page 5: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 2

Transparency

Accountability

Equity

Involvement

Consistency

CORE FUNCTIONS

The core functions of the Board are as follows:

Developing national public water and sanitation works.

Formulating water services development and investment plan for rural and urban

areas.

Mobilizing resources for infrastructure development and improvement of water

services delivery.

Facilitating establishment and efficient operations of cross-county and other water

services providers.

Providing technical assistance in water infrastructural development.

Ensure proper co-ordination of stakeholders for enhanced synergy and increased

impact in water services.

STRATEGIC OBJECTIVES

The Constitution of Kenya [CoK] (2010) bestows on every individual the right to clean

and safe water in adequate quantities. The attainment of economic and social rights in

the framework of our mandate demands a clear roadmap that is aligned to Kenya’s

Vision 2030. The Board’s first Strategic Plan 2005-2010 was revised and extended to

cover 2011/2012. The first strategic plan was driven by pursuit of excellence in

institutional strengthening, capacity building, rehabilitation and augmentation of water

and sanitation infrastructure. The current Strategic Plan 2013-2017 is anchored on the

constitution of Kenya 2010 and Vision 2030. It aims to achieve progressive realization of

universal access to quality access to water and sanitation as enshrined in the

Constitution of Kenya and Sustainable Development Goal No. 6.

Page 6: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 3

Our strategic objectives include:

Strategic objective 1: To develop and manage national public water and

sanitation, infrastructure to increase water services

coverage from 53% to 63% (water) from 30% to 50%

(sanitation) by 2017.

Strategic objective 2: To develop, contract and regulate viable and

sustainable water service providers (WSPs).

Strategic objective 3: To provide technical support in water services

provision for sustainability and operational

efficiencies.

Strategic objective 4: To mobilize resources and facilitate funding for

infrastructure development to enhance service

delivery.

Strategic objective 5:

Strategic objective 6:

Strategic objective 7:

To enhance collaborations and synergies with actors

and stakeholders both within and outside water

sector.

To update development and investment plans for

water and sanitation services.

To strengthen internal processes and human

resource capacity to enhance equity and efficiency

in service delivery.

Page 7: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 4

BOARD OF DIRECTORS

The LVSWSB is governed by the Board of Directors in accordance with Section 51 of the

Water Act (2002) and Section 6 of the State Corporations Act (2015). The GoK through

the Ministry of Water and Irrigation has appointed Board of Directors to provide

leadership and policy guidance.

The Board of Directors have been inducted on the Code of Governance for State

Corporations, Mwongozo (2015) to build their capacity on corporate governance and

leadership skills.

The current Board of Directors was constituted vide the Kenya Gazette Notice 2914 of

27th April 2015 (Directors), No. 2919 of 27th April 2015 (Chairman), and No. 4468 of 17th

June 2016. In addition, there are two (2) Alternate Directors to Principal Secretary (PS)

Ministry of Water and Irrigation (MWI), Cabinet Secretary National Treasury. The

Inspector of State Corporations (ISCs) attends the Board meetings as part of their

inspectorate role.

Page 8: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 5

BOARD OF DIRECTORS

Hon. Amb. John Arap Koech EGH, Chairman

Dir. Rose Aroko Gonda Independent Director

Dir. Victor Omanwa Independent Director

Dir. Hellen Makone Independent Director

Dir. Prof. Barack Okeyo Independent Director

Dir. Consolata Onguto Independent Director

Page 9: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 6

Dir. Hudson Mugodo Alternate to PS, Treasury

Dir. Joshua Ouma Alternate to PS, MWI

Dir. Dr. Betty Korir Independent Director

Dir. David Gichuhi Alternate to Director, ISCs

Dir. Rosemary Rumo Independent Director

Dir. George Ayugi Independent Director

Dir. Hilary Alila Independent Director

Dir. Andrew Sunkuli Independent Director

Dir. Violet Omwamba Independent Director

Page 10: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 7

CORPORATE GOVERNANCE STATEMENT

The Board of Directors of LVSWSB is committed to the values and principles of good

corporate governance. Good corporate governance emphasizes that the Board governs

the organization with integrity in accordance with its mandate under Section 53 of the

Water Act (2002). This mandate embraces the Corporation’s collaboration with

Government agencies and other stakeholders such as sector regulators, County

Governments, development partners, business community, Water Service Providers,

consumers of water services, media, pressure groups and the general public.

The Chairman Board of Directors, Board members and Management of LVSWSB regard

corporate governance as pivotal to the successes of the Board and are unreservedly

committed to ensuring that good corporate governance is practiced. This guarantees the

Board as a sustainable and viable vehicle towards realization of sector development.

As a public service organization, LVSWSB’s decisions are guided by the core tenets

prescribed in the Public Officers Ethics Act, and internal codes of conduct. We are

committed to effectively and efficiently deliver service to the public entrusted to the

organization by the Government.

The Board and its Committees embraces good governance and prudent management of

public resources to ensure consistency in delivery on its mandate.

MANAGEMENT STAFF

The LVSWSB Management is responsible for day-to-day institutional operations. The

Chief Executive Officer (CEO) is the Board’s Accounting Officer and communicates

policy matters to other employees. There are four departments headed by Chief

Managers: Technical Services, Finance, Corporate Planning, and Human Resource and

Administration. The heads of Procurement and Legal Services report directly to the

CEO, while the Internal Auditor functionally reports to the Board of Directors but

administratively to the CEO. The departments are subdivided into divisions which are

headed by Managers.

Page 11: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 8

Eng. Petronilla Ogut, OGW Chief Executive Officer.

Eng. Petronilla Ogut is currently the LVSWSB’s Chief Executive

Officer. She is a graduate of the University of Nairobi with BSc

(Science and Civil Engineering) and has MSc (Hydro informatics) from the International Institute for Infrastructural, Hydraulic and Environmental Engineering Netherlands. Eng. Ogut also holds MBA from Strathmore University, Diploma in Corporate Finance and management in Sourbonne University Paris France. She is a Registered Engineer with Engineers Registration Board of Kenya

Eng. Sammy Mburu - Chief Manager Technical Services

Eng. Sammy Mwangi Mburu is a graduate of University of Nairobi

with BSC in Civil Engineering. He is a full member of the Engineers’

Registration Board (ERB) and an elected member of the Institution of

Engineers of Kenya (IEK). Eng. Mburu also holds Master of Business

Administration in Strategic Management from the University of

Nairobi.

Mr. Sammy. K. Kigen - Chief Manager Human Resources and

Administration

Mr. Sammy Kigen is a holder of BA in Anthropology and

Governance from the University of Nairobi. He is also a holder of

higher Diploma in Human Resources Management and full member

of the Institute of Human Resource Management (IHRM). Mr. Kigen

has a vast work experience in Human Resource Management

spanning a period of over 30 years.

Ms. Phyllis Chepkemboi - Manager Legal and Compliance

Ms. Phyllis Chepkemboi is an Advocate of the High Court of Kenya

and a member of the Law Society of Kenya. She also holds Master of

Business Administration in Human Resource Management from

Maseno University. She is a Certified Mediator and currently a

Certified Public Secretary candidate.

Page 12: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 9

Ms. Rosemary Chelangat – Ag. Chief Manager Finance

Rosemary Chelagat is a graduate from Moi University Bachelor of

Business Management (Finance Option) she holds CPA (K) and a

member of the Institute of Certified Public Accountants of Kenya

(ICPAK). She has 10 years experience in accounting and finance.

QUALITY POLICY STATEMENT

Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy

statement provides a framework for establishing and sustaining quality objectives.

“Lake Victoria South Water Services Board is committed to providing quality customer

service by developing and effectively managing water and sanitation facilities as well as

establishing viable Water Service Providers for efficient supply of safe, adequate and

reliable water and sewerage services at an affordable tariff.

The Board, management and staff of Lake Victoria South Water Services Board are

committed to establishing and maintaining an effective Quality Management System in

line with ISO 9001:2008 requirements and measuring all aspects of the Quality

Management System as a basis for continual improvement.

Page 13: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 10

CHAIRMAN’S STATEMENT

Hon. Amb. John Arap Koech

Chairman Board of Directors – LVSWSB

It is with great pleasure that I report our 10 years achievement since Lake Victoria South

Water Services Board was licensed to efficiently and economically provide water

services. During this period we have realised tremendous progress in development of

water and sanitation infrastructure, institutional structures and human resource capital.

Engaging the public provides an opportunity to celebrate our achievements and share

our future prospects.

The National Values as enshrined in Article 10 of the Constitution gives us

responsibility as a public institution to uphold and promote them. These values are

fundamental in guiding our corporate and individual actions. The Board in realising its

mandate has embraced the need to promote equity and sustainable development of

water and sanitation projects. We have also demonstrated commitment to uphold

integrity in the use of public resources.

Under good corporate governance, the Directors have expressed their commitment by

signing the code of ethics and Mwongozo code of conduct. The Board encourages public

participation in all project activities to enhance inclusivity, ownership and sense of

responsibility.

We look forward to your valuable feedback which we will use to improve future service

delivery. We support the devolution of water and sanitation services provision to the

Page 14: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 11

County Governments and champion strategic partnerships and collaboration towards

economic empowerment and better health of citizens.

The Board is committed to improving service provision in all areas in our jurisdiction

through development of new water and sanitation projects. To achieve this we will

enhance resource mobilization and call upon our stakeholders to participate in project

identification, financing, implementation and management.

We will continue to partner with the County Governments and development partners

to strengthen the water service providers thus enhancing their efficiency in service

provision.

The board is grateful for the support and continuous collaboration by National

Government, County Governments , development partners and other stakeholders.

“Tomorrow is the future of our children and generations to come. What we do today

with water, determines our future survival. “

Thank you.

Hon. Amb. John Arap Koech Chairman Board of Director - LVSWSB

Page 15: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 12

CHIEF EXECUTIVE OFFICER’S STATEMENT

Eng. Petronilla Ogut, OGW

Chief Executive Officer – LVSWSB

The Water Sector Reforms of Kenya going back to the year 2002 set an agenda to

provide efficient and effective Water and sanitation services to the people of Kenya. A

journey that saw the establishment of Lake Victoria South Water Services Board

(LVSWSB) in 2004, an institution that has pursued quality access.

LVSWSB was licensed by the Water Services Regulatory Board on 11th May 2007 in

compliance with section 53(1) of the Water Act 2002. The organization has fulfilled its

mandate of “ensuring efficient and economic provision of water and sanitation services

in our area of jurisdiction”, obligations of the 10 year licence and is due for renewal of

the licence. I consider this a special privilege to welcome all of you, to this all-important

Public Consultation forum where we share our 10 years achievements and provide an

insight into our future investments. The public and their views are very critical to the

continued development of water and sanitation infrastructure by the Water Services

Board and provision of water and sanitation services through the Water Service

providers owned by the County Governments.

Water and sanitation infrastructure development challenges have been experienced in

the last ten years. These have included low water and sanitation coverage, inadequate

investments to meet increasing water demand, wastewater disposal requirements and

high energy costs. Today marks a historic milestone where we celebrate our

achievements and give you commitment that in the next ten years we shall be at your

Page 16: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 13

service. Great to note is that in the last 10 years major investments worth Kshs.13 billion

were undertaken covering all the counties within our area of jurisdiction. These has

benefited 2,090,000.people with portable water and 500,000 people with sanitation.

LVSWSB collaborates and works with all the stakeholders to mobilize resources for

water and sanitation infrastructure development, institutional capacity strengthening

and human resources development. Adequate infrastructure, strong institutions and

skilled and adequate personnel are key to the realization of the constitutional right to

access to water and sanitation.

LVSWSB’s commitments in the last ten years was anchored on the first Strategic Plan

2005-2010 revised and extended to cover 2011/2012, and the second Strategic Plan 2013-

17. Key strategic objective was to increase water coverage and sanitation coverage of

36% and25% respectively in the year 2007 the beginning of our licensing period to

63%water coverage and 50% sanitation coverage in the year 2017. We owe our

achievements to the support from the Government of Kenya through the Ministry of

Water and Irrigation, host County Governments, development partners, Water Service

Providers and our stakeholders.

I am happy to report that as at 2017 we are at 60% and 43% water and sanitation

coverage respectively. We are implementing four Vision 2030 flagship projects Kisii

Water Supply and Sanitation Project (financed by KFW & GoK), Siaya-Bondo Water

Supply and Sanitation Project (financed by AfDB & GoK), Bonyunyu Multipurpose

Dam (finance by ORIO & GoK), and Rehabilitation and Expansion of Kisumu Sewerage

Project (financed by AFD & GoK). At completion, these projects will serve a population

of 967,000 (water) and 150,000 (sewerage) up to the year 2035. Other Priority Projects

include Kericho, Keroka, Isebania, Nyamira and Litein towns under LVWATSAN II

financed by AfDB, KfW and GoK.

I take this opportunity to appreciate

(1) Government of Kenya and development partners for financing various water and

sanitation infrastructure projects

(2) Ministry of Water and Irrigation for policy guidance and sector coordination

Page 17: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 14

(3) Water Services Regulatory Board for regulating the Water Services Provision and

ensuring the Water Services Providers achieve Minimum water level standards.

(4) The County Governments for collaboration which has facilitated seamless

devolution of water and sanitation services provision

(5) The Water service providers for the continued provision of water and sanitation

services in their service areas

(6) The stakeholders for their collaboration and good will to the organization received

over the years.

In the next Licence period we plan to develop water and sanitation infrastructure

through National Public Works to achieve sustainable Development Goal No. 6 and

constitutional threshold on water and sanitation access enshrined in Article 43(1)(d).

Finally, I sincerely thank the LVSWSB Board of Directors and staff for their dedication

in the execution of our mandate for the benefit of the current and future generations.

Thank you and God bless you.

Eng. Petronilla Ogut, OGW Chief Executive Officer

Page 18: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 15

In Pursuit of Quality Access

INVESTMENT PROGRAMS

2007-2017

Page 19: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 16

KISUMU COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status

Year of

Completion

FY of

completion

Kisumu water supply -STAP AfD water supply KIWASCO Urban

426,400

600,000,000 Completed Aug-08 2007-08

Kisumu water supply,

Emergency Works GOK+AFD water Supply KIWASCO Urban

105,860,554 Completed Dec-10 2010-11

Kisumu Water and

Sanitation, Pumps and

P/House GOK water Supply KIWASCO Urban

28,014,222 Completed Dec-10 2010-11

Kisumu water supply, LTAP

1 AFD water supply KIWASCO urban

1,615,644,065 Completed Dec-13 2013-14

Kisumu water supply, LTAP

2 AFD water supply KIWASCO urban

687,013,072 Completed May-14 2013-14

Kisumu Water and

Sanitation-STAP AfD sanitation KIWASCO Urban 16,614

104,684,280 Completed Aug-08 2007-08

Kisumu water supply, LTAP

3 AFD sanitation KIWASCO urban 110,759

1,284,550,145 Completed Nov-15 2015-16

Kisat Sewerage Expansion

Project LVEMP Sanitation KIWASCO urban 53,000

102,000,430 Completed Jul-15 2015-16

Kisumu water supply,

LVWATSAN-Package 1&2

EIB+

AFD+ITF water supply KIWASCO urban 350,000

2,910,000,000 Planning Jan-20 2019-20

Kisumu water supply,

LVWATSAN -Package3

EIB+

AFD+ITF sanitation KIWASCO urban 120,000

3,500,000,000 Planning Jan-21 2020-21

Intergrated Water Resource

Management Program KFW sanitation KIWASCO Urban 80,000

440,000,000 Planning Oct-21 2021-22

TOTAL

11,377,766,768

Page 20: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 17

KERICHO COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries

Budget

(KES) Status

Year of

Completion

FY of

completion

Kericho Water Supply-

LVWATSAN II-STI AfDB sanitation KEWASCO urban 8,772

56,245,000 Completed Dec-15 2015-16

Kericho Water Supply-

LVWATSAN II- LTI AfDB sanitation KEWASCO Urban

204,000,000 Ongoing Jun-18 2017-18

Kericho Solid Waste

Management- Landfil AfDB sanitation KEWASCO Urban 11,250

14,437,643 Ongoing Dec-17 2017-18

Water Sector Development

Program ( Kericho) KFW water supply KEWASCO urban 189,716

1,300,599,424 Ongoing Dec-19 2019-20

Water Sector Development

Program ( Kericho) KFW sanitation KEWASCO Urban 26,375

228,177,690 Ongoing Dec-19 2019-20

Water Sector Development

Program ( Litein) KFW water supply TILWASCO urban 23,500

76,365,287 Ongoing Feb-19 2018-19

Minihydropower Systems for

Water Supply in Litein KFW energy KEWASCO urban 70,000

500,000,000 Planning Oct-21 2021-22

Total 329,613 2,379,825,044

Page 21: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 18

KISII COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries

Budget

(KES) Status

Year of

Completion

FY of

completion

Kegati Water Treatment

Expansion Project GoK Water supply GWASCO Urban 58,250

68,000,000 Ongoing Jun-17 2016-17

Water Sector Development

Program ( Kisii) KFW water supply KEWASCO urban 150,000

1,684,983,906 Ongoing Feb-19 2018-19

Water Sector Development

Program ( Kisii) KFW sanitation GWASCO Urban 161,420

372,045,200 Ongoing Feb-19 2018-19

Kisii Water Storage (

Bonyunyu Dam ) Project - ORIO water storage GWASCO

urban

-rural 230,000

1,838,000,000 Planning Jan-22 2021-22

Minihydropower Systems

for Water Supply in Kisii KFW energy GWASCO urban 0

500,000,000 Planning Oct-21 2021-22

Total 599,670

8,463,029,106

Page 22: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 19

NYAMIRA COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries

Budget

(KES) Status

Year of

Completion

FY of

completion

Keroka Water Supply-

LVWATSAN II- STI AfDB water supply GWASCO urban 59,438

60,350,000 Completed Dec-15 2015-16 Keroka Water Supply-

LVWATSAN II- LTI AfDB Water supply GWASCO Urban 460,000,000 Completed Mar-17 2016-17 Keroka Solid Waste &

Feacal Sludge AfDB sanitation GWASCO Urban 18,400 14,091,720 Ongoing Jun-17 2016-17 Water Sector

Development Program

( Nyamira) KFW water supply GWASCO urban 110,000 372,045,200 Ongoing Feb-19 2018-19 Nyamira -Kisii Water

Supply& Storage (

Bonyunyu Dam )

Project - ORIO water storage GWASCO Rural 230,000 4,030,800,000 Planning Jan-22 2021-22

Total

417,838 4,937,286,920

Page 23: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 20

BOMET COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries

Budget

(KES) Status

Year of

Completion

FY of

completion

Bomet Sewerage Expansion

Project LVEMP Sanitation BOWASCO urban 29,000 131,230,200 Completed Jan-17 2016-17

Bomet -Mulot Water Supply AFDB Water Supply BOWASCO Urban 243,488 1,600,000,000 Planning Oct-20 2020-21

Bomet Water Supply Project NBI water supply BOWASCO Urban 19,500 26,750,500 Completed Sep-12 2011-2012

Chepalungu water supply project EU water supply BOWASCO Rural 27,250 44,052,250 Completed Jun-11 2010-11

Total

319,238 1,802,032,950

Page 24: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 21

SIAYA COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status

Year of

Completion

FY of

completion

Siaya/Bondo Water Supply Project

(ADB)- Lot 1 AfDB water supply SIBOWASCO urban

130,395 1,576,000,000 Completed Mar-17 2016-17

Siaya/Bondo Water Supply Project

(ADB)- Lot 2 AfDB Sanitation SIBOWASCO urban

29,600 629,000,000 Completed Jun-16 2015-16

Boro-Kanyaboli Water Supply Project KOICA water supply SIBOWASCO rural 87,000 400,000,000 Proposed Jun-23 2022-23

Ugunja/Ukwala/Sega Water Supply AFDB Water Supply SIBOWASCO Urban

72,390 1,100,000,000 Planning Oct-21 2021-22

West Uyoma Water Supply JPNCF Water Supply SIBOWASCO Rural 31,600 45,321,426 Completed Dec-15 2015-16 Asembo Ndori Water Supply Project -

Phase I KOICA Water supply SIBOWASCO Rural

83,808

55,000,612 Completed Apr-10 2010-11 Asembo Ndori Water Supply Project -

Phase II KIDP Water suply SIBOWASCO Rural 47,941,616 Completed Feb-11 2011-12 Asembo Nadori Water Supply Project-

Phase III JNPCF Water Supply SIBOWASCO Rural 94,234,256 Completed Jun-11 2011-12

Asembo Ndori Sanitation JNPCF Sanitation SIBOWASCO Rural 1,200 1,530,000 Completed Jun-11 2011-12

East Uyoma Water Supply Project JPNCF Water supply SIBOWASCO Rural 12,000 43,000,000 Completed May-14 2013-14 Bondo Town Water Supply -

LVWATSAN I

UN-

Habitat Water Supply SIBOWASCO Urban 25,203 26,000,000 Completed Feb-12 2011-12

Total 473,196 4,018,027,910

Page 25: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 22

HOMA BAY COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries

Budget

(KES) Status

Year of

Completion

FY of

completion

Suba Rural Water and Sanitation

Project KIDP water supply Community Rural 17500 41,000,000 Completed Mar-10 2009-10

Homa Bay Sewerage Expansion

Project LVEMP Sanitation HOMAWASCO urban 41,000 86,000,000 Completed Mar-17 2016-17

West Karachuonyo Water Project KIDP water supply HOMAWASCO rural 79,410 91,000,000 Ongoing Apr-17 2016-17

Homa Bay Water Supply

Rehabilitation Project

UN

HABITAT water supply HOMAWASCO urban 14,250 46,000,000 Completed Dec-12 2012-13 Mbita Water Supply and

Sanitation Project (LVWATSAN

III) AfDB water supply HOMAWASCO urban 86,000 600,000,000 Proposed Jun-22 2021-22

Oyugis-Kendu Bay Water Supply

Project AfDB water supply HOMAWASCO urban 110,000 600,000,000 Proposed Jun-19 2018-19

Homa Bay Water Supply

Improvement FINEXPO water supply HOMAWASCO urban 83,000 1,000,000,000 Planning Sep-20 2020-21

Homa bay Wastewater (Trilateral

Program) KFW sanitation HOMAWASCO urban 46,000 800,000,000 Planning Sep-21 2021-22

Kendu - Bay -Oyugis AFDB Water Supply HOMAWASCO Urban

138,944 1,800,000,000 Planning Oct-21 2021-22 Rangwe Water Supply Project-

Phase 1 GOK Water supply HOMAWASCO Rural

15,000

52,369,259 Completed Dec-16 2016-17 Rangwe Water Supply Project-

Phase 2 GOK Water supply HOMAWASCO Rural 24,000,000 Ongoing Feb-18 2017-19 Kanyadhiang Water Supply

Project UNICEF Water supply SIBOWASCO Rural 28,949 58,148,648 Completed Jun-14 2013-14

Sindo Water Supply Project KIDP Water Supply HOMAWASCO Rural 12,876 71,256,352 Ongoing Jun-17 2016-17

Total

672,929.00 5,269,774,259

Page 26: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 23

MIGORI COUNTY

Name of Project Financier Intervention WSP Area Beneficiaries

Budget

(KES) Status

Year of

Completion

FY of

completion

Migori water Supply

project (ADB) AfDB water supply MIWASCO urban 124,000 1,257,039,970 Completed Jun-14 2013-14

Migori Sanitation Project AfDB Sanitation MIWASCO Urban 12,000 41,664,856 Completed Oct-13 2013-14

Awendo Water Supply

Project KOICA water supply MIWASCO urban 68,000 255,000,000 Completed Apr-12 2011-12

Isebania Water Supply-

LVWATSAN II- STI AfDB water supply MIWASCO urban 20,728 49,589,506 Ongoing Dec-15 2015-16

Isebania Water Supply-

LVWATSAN II- LTI AfDB water supply MIWASCO Urban 80,329 440,780,700 Completed Mar-17 2016-17

Isebania Solid Waste &

Feacal Sludge AfDB sanitation MIWASCO Urban 12,250 39,589,506 Ongoing Jun-17 2016-17

Rongo Water Supply

Project GoK Water supply MIWASCO Urban 28,500 45,000,000 Ongoing Jun-18 2017-18

Kehancha Water Supply

Project AfDB water supply MIWASCO urban 54,000 300,000,000 Proposed Jul-22 2021-22

Total 399,807 2,428,664,539

Page 27: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 24

NANDI COUNTY AND NAROK COUNTY

NB: LVSWSB only covers one sub-county in each of the two counties

Name of Project Financier Intervention WSP Area Beneficiaries Budget (KES) Status

Year of

Completion

FY of

completion

Nandi Hills Water Supply Project AfDB water supply KAPWASCO urban 90,000 580,000,000 Proposed Jun-19 2018-19

Kilgoris – Lolgorian Water Supply

Project AfDB water supply NAWASCO urban 88,000 300,000,000 Proposed Jun-19 2018-19

Total 178,000 880,000,000

Page 28: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 25

OUR STAKEHOLDERS

Engaging and building relationships with all Board stakeholders is key to realization of

our strategic objectives. Our stakeholders include individuals, groups of individuals

and organizations that directly or indirectly affect or are affected by our activities,

services and associated performance.

The stakeholder base is broad, including Government of Kenya (through Ministry of

Water and Irrigation), regulatory authorities, County Governments, development

partners, business community, employees, media, WSPs, water consumers and general

public. This means that there are many different views and expectations that LVSWSB

needs to respond to and manage to ensure operational sustainability.

Our approach is to have frank conversations on issues that concern our stakeholders as

tabulated:

Stakeholder Why we engage Stakeholder expectations

How we engage

Ministry of Water and Irrigation

The MWI is our primary development partner through which the Board obtains development counterpart funds. It sets policy framework that guides asset development in the sector.

Sector regulation; improved sector performance; and realization of policy objectives.

Quarterly performance reports; financial reports; circular feedbacks, consultative fora; and official visits.

Regulatory Authorities (WASREB, NEMA, WARMA and others)

The water sector is highly regulated and the Board has committed to comply with all legal provisions and guidelines.

Compliance with regulations; environmental protection; cascading policy; and sector information.

Approvals; regular reports; audits and surveillance.

County Governments

We engage with the host County Governments to ensure a coordinated approach in project formulation and

Transfer of devolved functions, improved coverage and sector

Project formulation, partnering on key programmes, representation and Class A ownership in

Page 29: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 26

implementation through resource mobilization and asset management.

performance, collaboration and synergy.

WSPs.

WSPs One of the most important ways we interact with our customers is through our SPA partnership with WSPs. As custodians of our mandate, we engage with WSPs to ensure excellent customer service across all the areas of jurisdiction.

User-friendly SPAs; infrastructure improvements; institutional capacity building; sector information; friendly regulations.

Public participations; project formulation; consultative fora; operational reports; performance audits

Development Partners

As the providers of capital necessary to support our growth, we engage with our development partners to keep them up to date on the financial need, performance and overall project sustainability.

Prudent management of resources; transparency, accountability and good governance; effective project implementation.

Annual and interim reports; quarterly operational reviews; consultative fora; and approvals.

Employees Our employees are the heart and soul of our existence. Their skills and involvement determine our ability to realize our vision, best value and best service, and to fulfil our purpose of empowering Kenya.

Career development; improved knowledge sharing; simplicity and agility; engagement; building skills in line with the future business growth; and fair remuneration

Performance contracting and appraisals, team meetings, intranet, newsletters, social media.

Business Contractors/Consultants and suppliers impact on

Timely payment and fair terms;

Supplier forums; ongoing site visits;

Page 30: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 27

Community our ability to provide services. They are required to comply with our health, safety and ethical procurement standards. Engaging with them contributes to business continuity, viability and operational efficiency.

improving health and safety standards; and partnering on environmental solutions.

audits; and regular direct engagements

Media As a stakeholder, the media plays a role in keeping LVSWSB stakeholders informed of operational developments, services and the impact of our activities.

Being informed of key activities; timely payments; and transparency.

Face-to-face and telephone engagement; interviews with the Chairman and key Executives; media releases and publicity; site visits; and project reports.

General Public The general public is central to the sustainability of our operations. To build trust among members of public, engagement also helps us to better manage operational risk.

Improved service delivery; and investments that reflect value for money.

Websites; public participations; mainstream and social media; public fora; and CSR.

Page 31: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 28

PHOTO GALLERY

Completed Kajulu Water Supply CS. Hon. Eugene Wamalwa inspecting the

completed Migori Water Supply

ECOSAN toilet donated to Akado youth Polytechnic CS. Hon Eugene Wamalwa during Commissioning

of Mecheo Water Project in Nyamira County

Page 32: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 29

Siaya-Bondo Water LVSWSB Team inspecting pump house in Migori

Page 33: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 30

ACHIEVEMENTS

In the years under review,

1. LVSWSB has constructed water and sanitation infrastructure worth Kshs. 13 Billion

providing portable water to 2.1 Million people and Sanitation to 500,000 people.

2. The Board Contracted 10 Urban Water Service Providers (WSPs) and 86 Community

Water service providers as its agents for provision of water and sanitation services and

improved their institutional capacities.

3. LVSWSB attained ISO 9001:2008 in September 2013 and is committed to the provision

of quality services and continual improvement as per the standards set by Kenya Bureau

of Standards and International standards by World Health Organization.

4. The Board embraced Smart Metering by acquiring and installing auto-transmission bulk-

meters for accurate and real-time monitoring of water flow to reduce human error and

Non-Revenue Water (NRW) in Kisii and Litein towns;

5. The Board acquired the most advanced Terrameter for hydrogeological survey. The

equipment is available for hire by qualified hydro-geologists from the region.

6. The Board promotes National Cohesion and National Values through equitable

distribution of development projects, public participation, and review of Board policies in

line with the requirements of Article 10 (2) of the CoK;

7. The board has collaborated with EACC to sensitize Directors and Management on

integrity and corruption prevention.

8. The Board has involved and empowered Youth, Women and PWDs in national

development by ensuring uptake of 30% tenders reservation.

9. Under CSR, the Board has distributed over 200 storage tanks to various schools in the

jurisdiction.

10. The Board has provided attachment and internship opportunities to over 500 students

from various colleges and universities.

11. The Board has continuously participated in Agricultural Society of Kenya activities to

sensitize the public on its activities.

12. The Board, 8 Water Service Providers and 8 County Governments have embarked on a

technical assistance and capacity building framework that will be used towards achieving

the constitutional right to access to water and sanitation.

Page 34: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 31

CHALLENGES

The Board and WSPs encountered the following challenges during the years under review:

1. Inadequate investment to meet the demand of water and sanitation services.

2. Low revenue mobilization from WSPs due to operational challenges.

3. Delay in land and way-leave acquisition for various projects.

4. High operational costs and water-supply disruptions due to power disconnections at

WSPs level

WAY FORWARD

In the next Licence period, the Board of Directors and Management will seek to address

identified challenges by:

1. Actively mobilise resources for Water and Sanitation Infrastructure development.

2. Continue to partner with County Governments and other stakeholders to ensure the

constitutional right to access to water is realized

3. Timely acquisition of land and way-leaves through collaborative engagements with both

the National and County Governments;

4. Continue to embrace water supply infrastructure that uses gravity designs and renewable

energy options to lower operational costs.

`

Page 35: In Pursuit of Quality Access Lake Victoria South Water ......Lake Victoria South Water Services Board is ISO 9001:2008 Certified. Its quality policy statement provides a framework

Lake Victoria South Water Services Board

10 years achievement Report 2007/17 32

In Pursuit of Quality Access

LAKE VICTORIA SOUTH WATER SERVICES BOARD

P.O BOX 3325-40100

TEL: 57-2025128

FAX: 57-2025127

HOTLINE: 020-2157233

EMAIL: [email protected]

Website: www.lvswaterboard.go.ke