In-Line Anode Installation Guide for TN-IL and TN-IL-20 1. Nut 2. Anode Wire Lug 3. Vent Thumb Screw 4. Small O-Ring 5. Flanged Nut 6. Medium O-Ring 7a. Technode Cap (use with TN-IL) 7b. Technode Cap (use with TN-IL-20) 8. Large O-Ring 9. Medium O-Ring 10. Flanged Nut 11. Washer 12. Zinc Anode 13. Female PVC Adapter (use with TN-IL) 14a. Clear Anode Housing (use with TN-IL) 14b. Clear Anode Housing (use with TN-IL-20) 15. PVC Bushing 16a. PVC Tee (use with TN-IL) 16b. PVC Tee (use with TN-IL-20) 17. Split Bolt 18. Anode Connection Wire (Green) 17 18 Replacement Zinc: Part # TN-100 TN-IL 1 2 3 4 5 6 7a 8 9 10 11 12 13 14a 15 16a Replacement Zinc: Part # TN-200 TN-IL-20 1 2 3 4 5 6 7b 8 9 10 11 12 14b 15 16b Remove TechNode components from package and separate the clear pipe from all PVC slip joints. The clear anode tube is fabricated from PVC material. Using PVC primer and cement, glue the clear anode housing (14) as illustrated. TechNode In-line fits both 1-1/2” and 2” plumbing. Step 1) Components Step 2) Where to Install Step 3) Installation Orientation Step 5) Connect the Anode Decide where to install the In-Line anode in the pool plumbing. For proper anode function, the anode must be installed up-stream of the pool heater and salt system generator. Clearance: Make sure to provide adequate clearance for removing the zinc from the plumbing. The anode can be installed vertical up, vertical down or in a horizontal position. Trapped air in the anode chamber will reduce the effective action of the anode. Air can be bled out using the anode vent (3). Mounting the anode vertical down or horizontal will insure that air will never be trapped in the anode tube (recommended). Glue the anode tee (16) into the pool plumbing using PVC primer and cements. Reducer bushings (15) are supplied for 1-1/2” pipe. How to use In-Line Anodes • Anode “A” - General corrosion protection. Help prevent plaster discoloration, black wall stains and metal deterioration in pool lights and rails. • Anode “B” - Helps prevent corrosion failures. Connect the anode directly to heater or stainless steel filter. Always install separate anodes for metal filter and heater. If metal filter has no bonding lug, connector wire must be soldered or clamped to the metal filter. Multiple anodes can be installed on any pool installation. Anode A - Installation General corrosion protection - Connect the anode connector wire (18) to the anode wire lug (2). Connect the other end of the wire to the pool bonding grid using the split bolt connector (2) supplied. This method of anode connection will help prevent plaster discoloration, black wall stains and metal deterioration in pool lights and rails. Anode B - Installation Heaters and Metal Filters - Connect the anode connector wire (18) to the anode wire lug (2). Connect the other end of the wire to the heater or filter bonding lug. Apply O-ring lubricant (not supplied) to the large O-ring (8) on the TechNode Cap (7a or 7b). Thread the Anode Cap into the threaded end of the Female PVC Adapter (13) 1 or the 2” Clear Anode Housing (14b) 2 and tighten approximately 1/6 turn after the O-ring contacts the housing. IMPORTANT Apply Installation Date Sticker to Anode Replace the anode every 2 years Licensed Product US. Patent 7655116B1 REVISION 07/2013 Glue These Joints Vertical Up Vertical Down Horizontal Perma-Cast Co. Pueblo, CO www.permacastonline.com Call 800-748-2770 Utility Anode TN-SK Ladder Anode TN-LD Light Anode TN-LT TechNode Component Anodes Step 4) Cap Installation Anode A Anode B Pump Suction from Pool Filter Heater Salt System Return to Pool Anode Connection Wire Anode Connection Wire Bonding Grid Anode Flow Filter Heater Salt System 8” Clearance 7a 8 8 13 14b 7b DON’T FORGET ABOUT

Upload: others

Post on 13-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: In-Line Anode Installation Guide for TN-IL and TN-IL …...In-Line Anode Installation Guide for TN-IL and TN-IL-20 1. Nut 2. Anode Wire Lug 3. Vent Thumb Screw 4. Small O-Ring 5. Flanged

In-Line Anode Installation Guidefor TN-IL and TN-IL-20

1. Nut 2. Anode Wire Lug 3. Vent Thumb Screw 4. Small O-Ring 5. Flanged Nut 6. Medium O-Ring 7a. Technode Cap (use with TN-IL)

7b. Technode Cap (use with TN-IL-20)

8. Large O-Ring 9. Medium O-Ring10. Flanged Nut11. Washer12. Zinc Anode13. Female PVC Adapter (use with TN-IL)

14a. Clear Anode Housing (use with TN-IL) 14b. Clear Anode Housing (use with TN-IL-20) 15. PVC Bushing16a. PVC Tee (use with TN-IL) 16b. PVC Tee (use with TN-IL-20)

17. Split Bolt18. Anode Connection Wire (Green)

17 18

Replacement Zinc: Part # TN-100

TN-IL12

3

456

7a

8

91011

12

13

14a

15

16a

Replacement Zinc: Part # TN-200

TN-IL-2012 3

456

7b

8

910

11

12

14b

15

16b

Remove TechNode components from package and separate the clear pipe from all PVC slip joints. The clear anode tube is fabricated from PVC material. Using PVC primer and cement, glue the clear anode housing (14) as illustrated. TechNode In-line fits both 1-1/2” and 2” plumbing.

Step 1) Components Step 2) Where to Install Step 3) Installation Orientation

Step 5) Connect the Anode

Decide where to install the In-Line anode in the pool plumbing. For proper anode function, the anode must be installed up-stream of the pool heater and salt system generator. Clearance: Make sure to provide adequate clearance for removing the zinc from the plumbing.

The anode can be installed vertical up, vertical down or in a horizontal position. Trapped air in the anode chamber will reduce the effective action of the anode. Air can be bled out using the anode vent (3). Mounting the anode vertical down or horizontal will insure that air will never be trapped in the anode tube (recommended). Glue the anode tee (16) into the pool plumbing using PVC primer and cements. Reducer bushings (15) are supplied for 1-1/2” pipe.

How to use In-Line Anodes• Anode “A” - General corrosion protection. Help prevent plaster discoloration, black wall stains and metal deterioration in pool lights and rails.• Anode “B” - Helps prevent corrosion failures. Connect the anode directly to heater or stainless steel filter. Always install separate anodes formetal filter and heater. If metal filter has no bonding lug, connector wire must be soldered or clamped to the metal filter.Multiple anodes can be installed on any pool installation.

Anode A - InstallationGeneral corrosion protection - Connectthe anode connector wire (18) to theanode wire lug (2). Connect the otherend of the wire to the pool bonding gridusing the split bolt connector (2) supplied.This method of anode connection willhelp prevent plaster discoloration, blackwall stains and metal deterioration inpool lights and rails.

Anode B - InstallationHeaters and Metal Filters - Connect theanode connector wire (18) to the anodewire lug (2). Connect the other end ofthe wire to the heater or filter bondinglug.Apply O-ring lubricant (not supplied) to the large O-ring (8)

on the TechNode Cap (7a or 7b). Thread the Anode Cap into the threaded end of the Female PVC Adapter (13)1 or the 2” Clear Anode Housing (14b)2 and tighten approximately 1/6 turn after the O-ring contacts the housing.

IMPORTANTApply Installation Date Sticker to AnodeReplace the anode every 2 years

Licensed Product US. Patent 7655116B1 REVISION 07/2013

GlueTheseJoints

VerticalUp

VerticalDown

Horizontal

Perma-Cast Co. Pueblo, COwww.permacastonline.com

Call 800-748-2770

Utility AnodeTN-SK

Ladder AnodeTN-LD

Light AnodeTN-LT

TechNode Component Anodes

Step 4) Cap Installation

Anode A

AnodeB

Pump

Suctionfrom Pool

Filter

Heater

SaltSystem

Returnto Pool

AnodeConnection Wire

AnodeConnection Wire

Bonding Grid

AnodeFlow FilterHeater

SaltSystem8”

Clearance

7a8

8

13

14b

7b

DON’T FORGET ABOUT