in chapter 1 projects are defined as temporary endeavors undertaken to create a unique product or...
TRANSCRIPT
In Chapter 1
Projects are defined as temporary endeavors undertaken to create a unique product or service.
Recent interest in project management is based on a recognition that many organizational tasks do not fit neatly into business-as-usual.
The significant differences between project management and general management are overviewed.
The three interrelated objectives of budget, schedule, and specifications are also introduced.
Two alternative project life cycles are presented and the importance of understanding this distinction is discussed.
Both qualitative (non-numeric) and quantitative (numeric) project selection methods. Are discussed.
The chapter concludes with a discussion of the aggregate project plan and an overview of the organization of the remainder of the text.
04/20/23 Ardavan Asef-Vaziri 1-1
Why the emphasis on project management?
Many tasks do not fit neatly into business-as-usual. A project is temporary (specific start and stop),
unique (a one-of-a-kind output or deliverable aimed at meeting a specific need of the client).
A non-project (a process) refers to the routine, repetitive work of the organization.
Need to assign responsibility and authority for achievement of organizational goals.
04/20/23 Ardavan Asef-Vaziri 1-2
Characteristics of Projects
Main Characteristics Unique Specific Deliverable Specific Due Date
Other Characteristics Multidisciplinary Complex Conflict Part of Programs
04/20/23 Ardavan Asef-Vaziri 1-3
PMI Definition
“A project is a unique temporary endeavor, with a set beginning and end ”
PMI defines project management as “the application of knowledge, skills, tools and techniques to a broad range of activities in order to meet the requirements of a particular project “
Project Management Institute, 2007
04/20/23 Ardavan Asef-Vaziri 1-4
Goals and Trade-offs
The three goals of a project are: On time, On budget, and To specification (i.e., including “quality” and “client
satisfaction”).
The project manager meets the goals by making “trade-offs.” For example, he/she can shorten the project duration by using more resources.
An overdetermined project is one that has a fixed budget, fixed delivery time, and fixed specifications . In the case of an overdetermined project, there is no allowance for any such events.
04/20/23 Ardavan Asef-Vaziri 1-5
Abilities Needed For Effective Project Management
Conflict Resolution Creativity and Flexibility Ability to Adjust to Change Good Planning Negotiation
Win-lose negotiation is like a zero-sum game. Anything one side wins is a loss for the other side. In win-win negotiation, the outcome is such that both parties gain something from the interchange.
Win-lose negotiating is dangerous for project managers who will have to deal with the same parties over and over again. The project manager who forces a functional manager to lose will have created a permanent enemy.
04/20/23 Ardavan Asef-Vaziri 1-6
Project Life Cycle
The main reason one should understand the difference is that resource allocation for the two types is quite different.
04/20/23 Ardavan Asef-Vaziri 1-7
Qualitative Selection Methods
The Sacred Cow A project proposed say by the CEO
The Operating/Competitive Necessity It is required to continue our operations We may loose our market share
Comparative Benefits Q-sort
04/20/23 Ardavan Asef-Vaziri 1-8
The Q-Sort Method
04/20/23 Ardavan Asef-Vaziri 1-9
Quantitative Selection Methods
Financial Assessment Methods payback period discounted cash flow
Scoring Methods unweighted 0-1 factor method weighted factor scoring method
04/20/23 Ardavan Asef-Vaziri 1-10
Payback Period
04/20/23 Ardavan Asef-Vaziri 1-11
InflowsCash Net Annual
Investment Fixed Initial
Discounted Cash Flow
04/20/23 Ardavan Asef-Vaziri 1-12
n
tt
t
k
F
10 )1(
I- (project) NPV
where
I0 = the initial investment
Ft = the net cash flow in period t
k = the required rate of return or hurdle rate
The Weighted Scoring Model
04/20/23 Ardavan Asef-Vaziri 1-13
n
jjiji wsS
1
where
Si = the total score of the ith project
sij = the score of the ith project on the jth criterion
wj = the weight or importance of the jth criterion
Uncertainties encountered in project management
Time required to complete a project Availability of key resources Cost of resources Timing of solutions to technological problems Actions taken by competitors
Uncertainty cannot be eliminated, but if managed properly, it can be minimized.
That is why we need trade-off
04/20/23 Ardavan Asef-Vaziri 1-14
Risk Analysis
Estimate probabilities or distributions associated with key parameters
Develop analytic or simulation model Analyze distribution of outcomes generated by
model
04/20/23 Ardavan Asef-Vaziri 1-15
Project Portfolio Process (PPP)
PPP links projects to the goals and strategy of the organization. In the initiation and planning phases, and throughout the life cycle of the projects.
The PPP is also a means for monitoring and controlling the organization's strategic projects. This may mean shutting down projects prior to their completion because their risks or their costs. Or because another project does a better job of supporting the goals.
04/20/23 Ardavan Asef-Vaziri 1-16
Steps In The Project Portfolio Process
Establish a Project CouncilIdentify Project Categories and CriteriaCollect Project DataAssess Resource AvailabilityReduce the Project and Criteria SetPrioritize the Projects within CategoriesSelect the Projects to be Funded and Held in
ReserveImplement the Process
04/20/23 Ardavan Asef-Vaziri 1-17
Step 1: Establish a Project Council
Establish and articulate strategic direction for projects.
Allocate funds and control the allocation of resources and skills to the projects.
Senior management, project managers of major projects; the head of the Project Management Office, particularly relevant general managers.
04/20/23 Ardavan Asef-Vaziri 1-18
Step2: Identify Project Categories and Criteria
Project categories are identified so the mix of projects will contribute to the organization's goals.
Within each category various criteria are established to rank the projects. The criteria are also weighted.
List the goals of each project and relate then to the organization's goals and strategies.
Identify the categories that are important to achieving the organization's goals.
04/20/23 Ardavan Asef-Vaziri 1-19
Wheelwright and Clark (1992) position - particularly product /service projects
04/20/23 Ardavan Asef-Vaziri 1-20
Wheelwright and Clark (1992) positioning
Derivative projects: With objectives or deliverables that are incrementally different in both product and process from existing offerings. They often replace current offerings or add an extension to them (lower priced version, upscale version).
Platform projects : Major departures from existing offerings in terms of either the product/service itself or the process used to make and deliver it, or both. They become "platforms" for the next generation of organizational offerings, such as a new model of automobile or a new type of insurance plan.
04/20/23 Ardavan Asef-Vaziri 1-21
Wheelwright and Clark (1992) positioning
Breakthrough projects: Involve a newer technology than platform projects. It may be a "disruptive" technology that is known to the industry or something proprietary that the organization has been developing over time. Use of fiber optic cables for data transmission, and hybrid gasoline-electric automobiles.
R&D projects: Visionary endeavors, oriented toward using newly developed technologies, or existing technologies in a new manner. They may also be for acquiring new knowledge, or developing new technologies themselves.
04/20/23 Ardavan Asef-Vaziri 1-22
Wheelwright and Clark (1992) positioning
Graph on page 29 goes here
04/20/23 Ardavan Asef-Vaziri 1-23
Wheelwright and Clark (1992) positioning
The size size/resource needs.
The shape and shade internal/ external, long/medium/short term.
The numbers the order, or time frame, in which the projects are to be implemented, separated by category.
04/20/23 Ardavan Asef-Vaziri 1-24
Benefits of the Aggregate Project Plan
View the mix of projects within each aspect (shape) Analyze and adjust the mix of projects within each
category or aspect Assess the resource demands on the organization,
indicated by the size, timing, and number of projects Identify and adjust the gaps in the categories, aspects,
sizes, and timing of the projects Identify potential career paths for developing project
managers, such as team members of a derivative project, then team member of a platform project, manager of a derivative project, member of a breakthrough project, and so on
Ardavan Asef-Vaziri 1-2504/20/23
26
Analyzing Project Portfolios: Bubble Diagram
Expected NPV
Prob. of Commercial Success
HighZero
Low
High
Bubble diagrams are useful for representing a set of projects and visualizing a project portfolio.
Shapes
Shading
Color
Size
Step 3: Collect Project Data
Collect data on timing, expected benefit and costs using existing/past projects and expert opinion.
Use the scoring models to screen out high cost or lower benefit projects ( because the organization's goals have changed)
Screen in any projects mandated by regulations or laws, competitive or operating necessities, projects required for environmental or personnel reasons.
04/20/23 Ardavan Asef-Vaziri 1-27
Step 4: Assess Resource Availability
Assess the availability of internal /external resources by type/department/ timing.
Balance aggregate project resource needs over future periods. Needing a normally plentiful resource at the same moment by several projects = catastrophe
Scheduling resource usage as closely as possible to system capacity = catastrophe
04/20/23 Ardavan Asef-Vaziri 1-28
Step 5: Reduce the Project and Criteria Set
Reduce the number of projects based on: supporting the organization's goals, existence of competence in the organization, market potentials, profitability, potential partners, availability and timing of resources, technological/knowledge fit with the organization, using the organizations strengths, synergy with other projects, other mutually exclusive projects, slipped in desirability since the last evaluation.
04/20/23 Ardavan Asef-Vaziri 1-29
Step 6: Prioritize the Projects within Categories
Apply the scores and criterion weights to rank the projects within each category.
Hold some hard-to-measure criteria out for subjective evaluation, such as riskiness, or development of new knowledge.
Subjective evaluations can be translated from verbal to numeric terms easily by the Delphi (Dalkey, 1969), pair-wise compari sons, or other methods.
Different projects are offering different packages of benefits that are not comparable. For example, R&D projects will not have the expected mone tary return of derivative projects
04/20/23 Ardavan Asef-Vaziri 1-30
Step 7: Select the Projects to be Funded and Held in Reserve
Determine the mix of projects across the various categories (and aspects, if used) and time periods.
Leave 10-15 percent of the organization's resource capacity free for variability and new opportunities.
Include some speculative projects in each category to allow future options, knowledge improvement, additional experience in new areas..
04/20/23 Ardavan Asef-Vaziri 1-31
Step 8: Implement the Process
04/20/23 Ardavan Asef-Vaziri 1-32