IMPORTANT NOTES FOR SOR PART A IMPORTANT NOTES – PART A The PART A of the tender is the lump sum quotation, which shall include all works needed to complete the building from scratch to complete skeleton, including sub-structure,( barricading if required), clearing jungle,excavation, filling with CNS soil, backfilling, subgrade, disposal etc, superstructure including PCC, RCC, formwork, steel reinforcement, wall and partitions,, water-proofing & terracing including tank, mumty, piping, etc, internal and external partitioning, plastering of all internal and external surfaces, painting of all external and internal surfaces,flooring,dado, woodwork, door and windows,pelmet grilles, staircase, lift well, lobby, stilt, and common areas, plumbing and sanitary works, internal electrical works and fixtures,, counters, cupboards, cabinet etc.within the battery limit as described below and as detailed in the drawings enclosed alongwith the tender.. Lump sum quotation includes all works like civil , plumbing ,electrical , sanitary ,etc. all with in the boundary of 2m from the outer line of building in all directions. Drive way Includes way from road to parking area. all civil works including mumty, lift car and machine, lift well, lift machine room, roof tank etc are in Lump sum including supply and installation of lift. The bidder shall include all labour, materials, tools, plant, equipment, infrastructure, transport etc. which may be required in preparation for the full and entire execution and completion of the work as shown in architectural, structural, plumbing and as described in the enclosed schedule of items and specifications. Each type of Building will be considered as unit means B-type,ground floor parking +two floors contains 8 residential blocks with lift as one unit , C-type ground floor parking + four floors(Side by side) contains 4 residential blocks as one unit , D-type G+1(side by side ) which contains 4 residential blocks as one unit(if the unit contains 2 residential blocks only it will be considered as half unit) , OIC ground floor only contains one residential block as one unit and guest house + Hostel (G+1) as one unit BATTERY LIMIT - For sanitary - connection to the first main manhole outside the periphery/plinth protection of each unit, for plumbing- connection of water supply line of each block/unit with the main trunk line , for electrical, the main LT cable bringing supply to each unit will be in item rate and all electrical works beyond and including panel/distribution switch board of each unit/block will be in Lump Sum Before quoting the lump sum and item rates, contractor shall be deemed to have carefully examined and to have full knowledge of the special conditions, general conditions, specifications, schedule of items, drawings and other documents forming the part of the contract and also to have satisfied to himself as to the nature and character of the work to be executed and of the site, local facilities of access and all other relevant matters and details affecting the execution and completion of the works in accordance with the terms and conditions of the contracts. No extra charges consequent of any misunderstanding or otherwise will be allowed. Please note that no extra payment shall be made for any shape of work, pattern, circular design, curvature etc, unless specially stated so. The amount quoted shall remain firm and not to be subject to exchanged variations, labour conditions, fluctuations in any/ all sorts of freights, railway freights or conditions whatsoever. Bidder must include in their amount, sales tax(both CST & LST) excise duty, octroi, turnover tax or other levied by central government, any state government or local authority, if applicable. No claim shall be entertained in this regards. The contractor on his own cost shall barricade the area of operations/construction including the area required for contractor’s stores, site office, fabrication yards etc. as safety measure. The area to be barricaded shall be as per the drawing attached in volume-V of tender documents. After the completion of the work, the contractor shall clear site and all the rubbish barricading, malba, any surplus material brought by him to the site and restore the site to the level, to the original ground before the work can be treated as complete. Page 1

Upload: trinhtram

Post on 17-Mar-2018

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

IMPORTANT NOTES – PART A

The PART A of the tender is the lump sum quotation, which shall include all works needed to complete thebuilding from scratch to complete skeleton, including sub-structure,( barricading if required), clearingjungle,excavation, filling with CNS soil, backfilling, subgrade, disposal etc, superstructure including PCC,RCC, formwork, steel reinforcement, wall and partitions,, water-proofing & terracing including tank, mumty,piping, etc, internal and external partitioning, plastering of all internal and external surfaces, painting of allexternal and internal surfaces,flooring,dado, woodwork, door and windows,pelmet grilles, staircase, lift well, lobby, stilt, and common areas, plumbing and sanitary works, internal electrical works and fixtures,,counters, cupboards, cabinet etc.within the battery limit as described below and as detailed in the drawingsenclosed alongwith the tender.. Lump sum quotation includes all works like civil , plumbing ,electrical ,sanitary ,etc. all with in the boundary of 2m from the outer line of building in all directions.

Drive way Includes way from road to parking area. all civil works including mumty, lift car and machine, liftwell, lift machine room, roof tank etc are in Lump sum including supply and installation of lift.

The bidder shall include all labour, materials, tools, plant, equipment, infrastructure, transport etc. whichmay be required in preparation for the full and entire execution and completion of the work as shown inarchitectural, structural, plumbing and as described in the enclosed schedule of items and specifications.

Each type of Building will be considered as unit means B-type,ground floor parking +two floors contains 8residential blocks with lift as one unit , C-type ground floor parking + four floors(Side by side) contains 4residential blocks as one unit , D-type G+1(side by side ) which contains 4 residential blocks as one unit(ifthe unit contains 2 residential blocks only it will be considered as half unit) , OIC ground floor only containsone residential block as one unit and guest house + Hostel (G+1) as one unit

BATTERY LIMIT - For sanitary - connection to the first main manhole outside the periphery/plinthprotection of each unit, for plumbing- connection of water supply line of each block/unit with themain trunk line , for electrical, the main LT cable bringing supply to each unit will be in item rateand all electrical works beyond and including panel/distribution switch board of each unit/block willbe in Lump Sum

Before quoting the lump sum and item rates, contractor shall be deemed to have carefully examined and tohave full knowledge of the special conditions, general conditions, specifications, schedule of items,drawings and other documents forming the part of the contract and also to have satisfied to himself as tothe nature and character of the work to be executed and of the site, local facilities of access and all otherrelevant matters and details affecting the execution and completion of the works in accordance with theterms and conditions of the contracts. No extra charges consequent of any misunderstanding or otherwisewill be allowed.

Please note that no extra payment shall be made for any shape of work, pattern, circular design, curvatureetc, unless specially stated so. The amount quoted shall remain firm and not to be subject to exchangedvariations, labour conditions, fluctuations in any/ all sorts of freights, railway freights or conditionswhatsoever. Bidder must include in their amount, sales tax(both CST & LST) excise duty, octroi, turnovertax or other levied by central government, any state government or local authority, if applicable. No claimshall be entertained in this regards.

The contractor on his own cost shall barricade the area of operations/construction including the arearequired for contractor’s stores, site office, fabrication yards etc. as safety measure. The area to bebarricaded shall be as per the drawing attached in volume-V of tender documents.

After the completion of the work, the contractor shall clear site and all the rubbish barricading, malba, anysurplus material brought by him to the site and restore the site to the level, to the original ground before thework can be treated as complete.

Page 1

Page 2: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

BRIEF SCOPE OF WORK FOR LUMP SUM PORTION OF CONTRACT

1 CLEARING WORKS

1 Clearing Jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings andremoval of rubbish and disposal of unserviceable material out side the site premises

2 Barricading the area of operations/construction including the area required for contractor’s stores, siteoffice, fabrication yards etc. as safety measure.

2 ANTI - TERMITE TREATMENT :

1 Supply, diluting and injecting approved quality chemical emulsion for PRE-CONSTRUCTIONAL anti-termite treatment and creating a continuous chemical barrier .The work shall be carried - out byspecialised agency and as per IS 6313 (Part II 2001). The anti - termite treatment shall be guaranteed for aperiod of 10 (Ten) Years ,all specified as per drawing and directed by Engineer in Charge

2 BIFLEX ANTI - TERMITE TREATMENT of FMC Professional Solutions. Address: FMC India PrivateLimited, S. Venkat, 35/77, AAJI Flats, V.O.C Street, Bharathi Colony , Kaikankuppan, Alwarthirunagar,Chennai - 600087 Tel: 044-23642733

3 EARTH WORK EXCAVATION :

1 Earth work in excavation in all types of soil including sot and hard rock(hard rock excavation shall becarried out by Control Blasting / Chiseling and Benching method ) at all levels and locations , usingnecessary excavators /manually , including dressing of sides and ramming of bottom, getting out, stacking the excavated soil, filling the same in trenches, plinths, sides of foundations, basement and under floors inlayers not exceeding 200 mm in thickness, consolidating each deposited layer by ramming and watering ( the excavated soil shall be tested for meeting the CNS PROPERTIES and shall be got approved fromconsultant before back filling in plinth areas , and foundations ) Including bailing or pumping out all waterwhich may accumulate in the excavation during the progress of further works due to seepage, springs, rainor any other cause and disposal of surplus/ Unserviceable excavated soil out side the site premises asdirected and disposed soil to be neatly leveled and dressed etc.all specified as per drawing and directedby Engineer in Charge

2 Supply and Banking / filling with CNS SOIL / Moorum, and spreading in layers not exceeding 200 mm indepth, breaking clods, watering, (rolling each deposited layer with 8-10 tonne mechanical Vibro roller toachieve required gradient and camber ) Ramming by hand rammer (where ever area is not available forcompaction by Mechanical Vibro roller) , including necessary soil test /core test, sample taken at the rate ofone sample minimum in an area of 500Sqm under optimum moisture condition to achieve atleast 95% ofthe maximum dry density ( proctor density),complete all specified as per drawing and directed byEngineer in Charge

3 Supply and Filling With River sand , including all lead and lift,in layers not exceeding 300mm thick(compacted) including watering , ramming , consolidating and dressing etc., complete all specified as perdrawing and directed by Engineer in Charge

4 PLAIN AND REINFORECD CEMENT CONCRETE :

1 Providing and laying plain cement concrete 1:3:6 (1 cement : 3 coarse sand :6 graded stone aggregate20mm nominal size) including necessary shuttering in leveling courses under foundations, pipelines, pits,under floors etc., complete at all levels and locations,all specified as per drawing and directed by Engineerin Charge

Page 2

Page 3: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

2 Providing and laying plain cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 crushed graded stoneaggregate 20 mm nominal size) in string or lacing courses, copings, bed blocks, anchor blocks,window cills , Ramps , hard Standings and like including necessary shuttering and centering at all levelsand locations etc., complete all specified as per drawing and directed by Engineer in Charge

3 Providing and laying in position M-25 grade reinforced cement concrete for all concrete works machinebatched, machine mixed, and machine vibrated design mix cement concrete of specified grade withminimum cement content of 300 kg per cum of concrete and water cement ratio not more than 0.5 forreinforced cement concrete structural elements including adding admixtures in recommended proportion (as per IS 9103 ) to accelerate, retard setting of concrete improve workability without impairing strength anddurability, and necessary curing etc.,complete all as directed at all levels and heights .

4 Providing and laying in position M-30 grade reinforced cement concrete machine batched, machinemixed, and machine vibrated design mix cement concrete of specified grade with minimum cementcontent of 320 kg per cum of concrete and water cement ratio not more than 0.45 for reinforced cementconcrete structural elements including adding admixtures in recommended proportion ( as per IS 9103 ) toaccelerate, retard setting of concrete improve workability without impairing strength and durability, andnecessary curing etc.,complete all as directed at all levels and heights .

5 With Ready Mixed Concrete (RMC) procured by the contractor from outside plant of UltraTech,ACC, RDC, IJM, Aparna, India Cements or equivalent.Providing, batching, mixing, transporting through transit mixers, pumping and laying controlled ReinforcedCement Concrete of specified grade at all levels and heights for all concrete works specified ready mixcement concrete from recommended ready mix batching plant ,of specified grade using ordinary Portlandcement of grade 43/53 from approved manufacturer, river sand and crushed sand combination (50:50proportion) 20mm and down size coarse aggregates, necessary admixtures approved by Consultants(elkem and Conplast SP 430SRV from Fosroc or equivalent), including all leads and lifts, pumping usingline pump or boom placer, vibrating/ compaction, scaffolding wherever necessary, curing as directed, Note: Micro silica shall be used for concrete of grade more than M45 at 5% of the weight of cement

6 Supply, Fabricating & fixing in position reinforcement for RCC work with Thermo mechanically (TMT)bar of various diameters and grade of steel as specified in drawigs, conforming to IS specification includingcutting, providing, supplying & bending, hoisting, fabricating and placing in position according to drawingsand binding the reinforcement with GI annealed binding wire in two strands of 18 gauge and providingPVC cover blocks for placing the reinforcements in position and for maintaining the cover specified and/oraccording to relevant IS. Thw work includes providing Spacer bar of any shape & profile ,Cover block, binding wire and to includelead, lift, placing at all levels etc.,complete all specified as per drawing and directed by Engineer inCharge.

7 Providing, fabricating and erecting form work at all levels and places and all shapes whereverneeded/specified as per drawing including striking with 12mm Plastic coated, marine resistant waterproofply/Smooth finished MS plates with adjustable steel props of acceptable Staging system and with sufficientbracing as approved by consultant. Work to include designing of proper form work and staging system tosuit the requirements,Submission of design calculations and shop drawings for approval,sealing the jointswith heavy duty brown self adhesive tape, aligning to line and levels including M.S. Ties, PVC Spacer,Providing openings/ cutouts/ pockets, applying deshuttering chemical, Deshuttering as approved by theconsultant etc., complete complete all directed by Engineer in Charge

Page 3

Page 4: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

8 Providing and laying 50 mm average thick and 1 m wide PCC 1:3:6 (1 cement : 3 coarse sand : 6 gradedstone aggregate 20 mm nominal size) for plinth protection over 75 mm thick dry brick ballast of 40 mmnominal size well rammed, consolidated and grouted with fine sand including finishing the top smooth withextra cement mortar with a floating coat of neat cement finish and making provision for 12mm widegrooves at every 2.0mt interval along the length and at wall junctions including filling the joints with sandand bitumen mix including providing edge retaining wall of half brick work for plinth protection etc.,complete all specified as per drawing and directed by Engineer in Charge

9 Providing and laying Damp proof course, 40 mm thick with PCC 1:2:4 ( 1 cement : 2 coarse sand : 4graded stone aggregate 12 mm nominal size) mixed with approved water proofing compound as permanufacturer's specifications and spreading of two layers of jointless polythene sheet of thickness not lessthan 500 microns fixed with cold bitumen etc., complete all as directed.

10 Providing and filling cinder concrete in sunken slabs with cement mortar 1:15 (1 cement: 15 cinders) at alllevels and locations including ramming, watering etc.,complete all specified as per drawing and directed byEngineer in Charge.

11 Providing Nito bond EP of Fosroc make or approved equivalent for jointing old concrete and newconcrete surfaces.including cleaning of old surface and applying the chemical etc as per manufacturersspecifications .

12 Supplying and mixing integral water proofing admixture of approved brand Fosroc (or approvedequivalent) CONPLASTX 421IC @ 200 ml per 50 kg bag of cement to be mixed with cement concrete tomake it water tight or to reduce the permeability as per manufacturers specifications.

5 STONE AND BRICK MASONRY :

1 Providing and construction of uncoursed stone masonry ,using stones of approved quality includingBond stones at every 2.0meter interval ,using cement mortar 1:6 ( 1cement : 6 Coarse sand ) for allfoundation at all levels and location, including scaffolding, staging ,curing etc and flush pointing to stonemasonry in cement mortar 1:3 (1 cement :3 fine sand) including raking of joints, etc., complete all specifiedas per drawing and directed by Engineer in Charge

2 Providing coursed rubble masonry (second sort) with hard stone including bond stones, above plinth insuper structure in cement mortar 1:6 (1 cement: 6 coarse sand) and flush pointing to stone masonry incement mortar 1:3 (1 cement :3 fine sand) including raking of joints, etc.,at all levels and locations

3 Providing brick work using M-35 grade bricks( with minimum compressive strength of 35kg/sq cm ) incement mortar 1:6 (1 cement : 6 coarse sand) at all levels and heights , locations including scaffolding,staging ,curing etc.complete all specified as per drawing and directed by Engineer in Charge

4 Providing brick work using Modular fly ash lime bricks (FALG Bricks) conforming to IS: 12894-2002,class designation 100 average compressive strength in cement mortar 1:6 (1 cement : 6 coarse sand) at alllevels and heights , locations including scaffolding, staging ,curing etc.complete all specified as perdrawing and directed by Engineer in Charge

5 Providing brick work of half brick thickness using M - 35 grade bricks in Cement Mortar 1:4 (1 cement : 4coarse sand ), proportions in walls/parapets at all heights as per specifications including scaffolding,curing and providing RCC band of size 100 x 80mm with 2 Nos. of 6mm dia MS Bars at every 3rd courseetc., including the cost of MS reinforced steel.complete at levels and locations complete all specified asper drawing and directed by Engineer in Charge

Page 4

Page 5: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

6 STEEL AND WOOD WORK :

1 Providing and fixing second class teak wood frame with double rebate of size specified in drawingfor Windows , including fixing frame with MS hold fast of size 300 long MS flat 50 x 3mm thick 2noson each side of frame Grouted with PCC 1:2:4 ( 1 Cement: 2 Sand: 4 20mm Coarse Aggregate) in wall, ofsize 230x230x300 in length, including embedding of 50mm extra frame length on both sides of top &bottom member , etc , Applying Black Japan Paint to the contact surface of block work / masonry/concrete,including French Spirit Polishing and malamine finish on wooden surface etc., complete allspecified as per drawing and directed by Engineer in Charge.

2 Providing and fixing glazed shutters for windows using second class teak wood shutter of size mentionedin drawing with 4 mm thick float glass panes and with all hardware firttings including black enamelled ISImarked MS friction hinges with necessary screws.inclusive of French Spirit Polishing and melamine finishon wooden surface, teak wood beeding etc., complete all specified as per drawing and directed by Engineerin Charge

3 Providing and fixing second class teak wood 35mm thick wire gauze shutters for doors/windows withhard ware fittings using fly proof galvanised M.S. wire gauze of average width of aperture 1.4mm with wireof dia. 0.63 mm for windows and including ISI marked bright finished or/and black enamelled M.S. butthinges with necessary screws:inclusive of French Spirit Polishing and melamine finish on wooden surface,teak wood beeding etc., complete all specified as per drawing and directed by Engineer in Charge

4 Providing and fixing M.S. grills/Gratings of required pattern in frames of windows/ventilators with25mmX6mm thick M.S. flats, 12mm square or round bars etc. all complete. fixed to openings /woodenframes with rawl plugs, screws ,complete all specified as per drawing and directed by Engineer in Charge.

5 Providing and fixing second class teak wood frame for doors , in frame single/Double rebate of sizeas specified in drawing , including cost of fixing frame with MS hold fast of size 300 long ms flat 50 x3mm thick 3nos on each side of frame Grouted with PCC 1:2:4 ( 1 Cement: 2 Sand: 4 20mm CoarseAggregate) in wall, of size 230x230x300 in length, including embedding of 50mm extra frame length onboth sides of top member into wall & vertical member at bottom into the floor, including the cost ofrequired edge rounding,teak wood beading etc , Applying Black Japan Paint to the contact surface of blockwork / masonry/ concrete,including French Spirit Polishing and malamine finish on wooden surface etc.,complete all specified as per drawing and directed by Engineer in Charge.

6 Providing and fixing 35mm thick second class teak wood panelled shutters for doors, of approvedpattern including ISI marked black enamelled M.S butt hinges with necessary screws including ofpolishing with french Spirit and melamine finish and all hardware fittings . complete as per the Drawingsand Instructions of the Engineer - in – Charge.

7 Providing and fixing PVC rigid foam sheet 1mm thick on existing door shutters (bathroom and W.C.doors) using synthetic rubber based adhesive.

8 Providing Platering on sides of window opening to keep the frame aligned to 90 degrees and fixingactual window with 2 to 3 mm gap alround and filling with silicon sealent etc ., complete all as directed bythe Engineer - in - charge

Page 5

Page 6: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

9 Providing and fixing the following brass hardware fittings of approved make as per relevant IS wherever necessary for above wood work items

bright finished brass butt hinges with necessary screws etc.complete:bright finished brass towerbolts (barrel type) with necessary screws etc. complete:Bright finished Aldrop 200 mm long 12 mm dia rodBright finished brass handles with screws etc. complete :Bright finished brass hanging type floor door stopper with necessary screws, etc. complete.PVC Door BuffersBright finished brass door latch with necessary screws etc.complete:Magnetic door catchersHydraulic door closer (for mosquito proof external doors only)Bright finished brass 100 mm mortice latch with one dead bolt and a pair of lever handles with necessaryscrews etc. complete (best make of approved quality).Special quality bright finished brass cupboard or ward robe locks with four levers including necessaryscrews etc. complete (best make of approved quality)50 mm bright finished brass cup board or wardrobe knob with necessary screws (best make of approvedquality)

10 Providing and fixing the following brass hardware fittings of approved make as per relevant IS wherever necessary for above wood work items

Heavy duty aluminum hinges with necessary screws etc.complete:Heavy duty aluminum towerbolts (barrel type) with necessary screws etc. complete:Heavy duty aluminum Aldrop 200 mm long 12 mm dia rodHeavy duty aluminum handles with screws etc. complete :Heavy duty aluminum hanging type floor door stopper with necessary screws, etc. complete.PVC Door BuffersHeavy duty aluminum door latch with necessary screws etc.complete:Magnetic door catchersHydraulic door closer (for mosquito proof external doors only)

Note : All external doors and cupboard shutters will be fitted with brass fittings ,all other doors and windowswill be fitted with heavy duty aluminum hardware fittings

11 Providing and fixing second class teak wood frame specified in drawing for ventilators , includingfixing frame with MS hold fast of size 300 long MS flat 50 x 3mm thick 1no on each side of frameGrouted with PCC 1:2:4 ( 1 Cement: 2 Sand: 4 20mm Coarse Aggregate) in wall, of size 230x230x300 inlength, including embedding of 50mm extra frame length on both sides of top & bottom member , etc ,Applying Black Japan Paint to the contact surface of block work / masonry/ concrete,including French SpiritPolishing and malamine finish on wooden surface and making grooves in frame for fixing 4mm thicklouvered glass panes etc., complete all specified as per drawing and directed by Engineer in Charge.

7 PLASTERING AND SURFACE TREATMENT :

1 6 mm thick plastering in cement mortar 1:4 (1 cement: 4 fine sand) including necessary scaffolding andcuring etc., complete for all concrete surfaces finished smooth and even at all levels and locations.complete all specified as per drawing and directed by Engineer in Charge

2 12 mm thick plastering in cement mortar 1:4 (1 cement :4 fine sand) on internal surfaces of walls finishedsmooth with trowel including scaffolding, curing etc., at all heights and locations. complete all specified asper drawing and directed by Engineer in Charge

Page 6

Page 7: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

3 18 mm thick cement plastering on external surfaces of brick or concrete surfaces in two layersconsisting of 6 mm thick cement mortar 1:4 (1 cement :4 fine sand) top coat mixed with integral waterproofing compound over a base coat 12 mm thick cement mortar 1:6 (1 cement :6 coarse sand), finishedsemi-rough including necessary scaffolding and curing etc., complete all specified as per drawing anddirected by Engineer in Charge

4 Providing 20mm thick waterproof plastering in cement mortar 1:4 (1 cement : 4 fine sand) on internalsurfaces of lift pits , water tanks finished smooth and even including necessary staging and scaffoldingand adding waterproofing admixture of Fosroc chemical etc ,at all levels and locations. complete allspecified as per drawing and directed by Engineer in Charge

5 Providing and applying two coats of Plastic acrylic emulsion Paint of approved brand and shade forinternal walls and ceiling over a coat of cement primer ,including surface preparation with two coats ofwall care putty of approved brand etc ., complete all specified as per drawing and directed by Engineer inCharge

6 Providing and applying External weather shield paint of BERGER or approved equivalent includingsurface preparation with base coat of primer and two coats of the painting etc complete at all heights andlocations etc,.complete all specified as per drawing and directed by Engineer in Charge

7 Forming Groove of Uniform size at all levels , locations 12x12mm in plastered surface as per approvedpattern using wooden battens, nailed to the under layer including removal of wooden battens, repairs to theedges of plaster panel and finishing the groove complete as per drawing , specifications and directed by theEnginner - in charge.

8 Supplying and mixing of Synthtic fibre tissues of 12 mm size or approved brand mixed as permanufacturers specifications in cement mortars at all levels and locations as directed.

9 Providing and fixing chicken wire mesh in between RCC and brick work.etc. Complete all specified as perdrawing and directed by Engineer in Charge

8 FLOORING

1 Supplying, stacking and laying of soling under floors Using granite stone boulders of 230mm includingspreading to required gradiant and camber and consolidating with mechanical earth rammer includingfilling voids with approved quality of stone screening and binding material obtained from approved quarry..etc. Complete all specified as per drawing and directed by Engineer in Charge

2 Providing and laying polished vitrified tiles and approved brand and shade of thickness upto 10mm andsize maximum of 600 x 600 mm without warpage, laid on 20 mm thick cement mortar 1:4 (1 cement:4coarse sand) including grouting the joints with white cement and matching colour pigment etc. Complete allspecified as per drawing and directed by Engineer in Charge

3 Providing and fixing approved shade and brand vitrified tiles for skirting and Daddo, over 12mm thickbase cement mortar 1:4 (1 cement :4 coarse sand), joints filled with white cement mixed with matchingpigment etc. Complete all specified as per drawing and directed by Engineer in Charge

Page 7

Page 8: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

4 Providing and laying polished Non Slip vitrified tiles and approved brand and shade of thickness upto10mm and size maximum of 600 x 600 mm without warpage, laid on 20 mm thick cement mortar 1:4 (1cement:4 coarse sand) including grouting the joints with white cement and matching colour pigmentetc. Complete all specified as per drawing and directed by Engineer in Charge

5 Providing and fixing in Dadoing vitrified tiles of approved brand and shade of thickness upto 10mmand size maximum of 600 x 600 mm without warpage,laid over 12mm thick base cement mortar 1:4 (1cement :4 coarse sand), joints filled with white cement mixed with matching pigment etc. Complete allspecified as per drawing and directed by Engineer in Charge

6 Providing and laying of 18 mm thick pre polished granite counter for wash basin ,platforms and like ofapproved shade laid over base cement mortar 20 mm thick 1:4 (1 cement : 4 coarse sand) includingnecessary cutting and RCC (1:2:4) slab and 230mm thick brick wall with Plastering for support of RCCSlab etc., complete all as per drawing and specification.

7 Providing and laying pre polished 18 mm thick marble stone in flooring of approved shade & colour /design and pattern, for risers of steps and skirting etc., including under layer of 20 mm thick, cementmortar 1:4 (1 cement : 4 coarse sand) jointed with white cement slurry mixed with pigment to match theshade of granite stone including rubbing and polishing making floor free from scratches etc. Complete allspecified as per drawing and directed by Engineer in Charge

8 Providing and fixing pre polished 18 mm thick granite stone of approved colour / design, for flooring,treads and risers of steps and skirting and cladding etc., including under layer of 20 mm thick, cementmortar 1:4 (1 cement : 4 coarse sand) jointed with white cement slurry mixed with pigment to match theshade of granite stone including rubbing and polishing making floor free from scratchesetc. Complete allspecified as per drawing and directed by Engineer in Charge

9 Providing and laying paver blocks of 75mm thk of M25 grade. from approved manufacturer overprepared well compacted sub grade with classic type blocks of approved colour in the pattern specified byArchitects over 50mm thick sand cushion laid to the required levels and slopes including vibrocompaction,all leads and lifts etc. Complete all specified as per drawing and directed by Engineer in Charge.(Samples of different lots of pavered blocks shall be tested for compressive strength before usingin the works)

10 Supplying and laying of Manglore /Pressed clay tiles of approved make and type including all sizesand shapes , (as per approved pattern 20mm nominal thickness and of approved size) on roofs jointedwith cement mortar 1:4 , (1 cement : 4 coarse sand) mixed with 2% integral water proofing compound laidover a bed of 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand) ,with required cement mortarbattens wherever necessary and finished neatly etc. Complete all specified as per drawing and directed byEngineer in Charge

11 Supplying and laying decorative Pressed cement tile flooring of Eurocon/Duracrete or equivalent approved make, colour, shade and size over and including 20mm thick base layer of CM 1:4 (1 cement : 4 Coarsesand) jointed with white cement slurry mixed with the pigment to match the shade of the tile etc. Completeall specified as per drawing and directed by Engineer in Charge

Page 8

Page 9: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

12 Supply, installation & finishing of Air-Cush wooden sports flooring system consisting of:The Surface Board: Kiln Seasoned imported Hard Maple (Sycamore) wood surface boardfinished with 21mm thick, 60 to 70 mm width and in random length in tongue and grooveshape. The edges of the boardswill have a finger lock grove and the bottom side with air passgroove and applied with polyurethanelacquer.The Under Frame: Made of commercial quality Fir/Spruce/Pine wood runners of 70 mm X45 mm treatedwith anti-termite solution and fixed on the bottom side with 10 mm thick aircushioningpads by staplethrough the two wings at 300 mm clc.

13 Providing and Laying Solid /Natural wood Timber skirting of LOTUS or of approved equivalent ofthickness 18mm and size 910x150mm with PU Coated factory finish and Kiln Dried and shall be installedby stick (and nail as directed by the Engineer) onto Marine Ply wood including the cost of Adhesives ,Wastages, Tools and Tackels etc., complete all as per Manufacturers Specifications and directed by theengineer - in charge.

9 STRUCTURAL STEEL WORKS :

1 Supplying, fabricating, hoisting and erecting in position Mild steel structural steel works ( in windcolumns, jack trusses, canopies, lattice girders, trusses, sub trusses, monitor roof, braces, ties ,claddingposts,purlins ,cladding runners, sag and anti sag rods, access ladders , staire cases ,support for utilitypiping and support structure for electrical items of works.,) at all elevations, levels and heights includingaligning, levelling, providing and fixing bolts,foundation bolts, nuts, washers, comprising ms angles,channels,joists, rails, tees, plates,(incl.base plates&insert plates), rounds, squares,lugs etc., of varioussizes and other structural steel sections conforming to latest IS 2062 Grade - A & B including straightening,cutting, welding, bending to shape, bolting, cleaning the rust and scales to the satisfaction of Architect andinclusive of Sand blasting and applying a shop coat of zinc chromate primer and two coats of syntheticenamel paint. etc. Complete all specified as per drawing and directed by Engineer in Charge

The work includes fixing of bolts, nuts, washers, clamps, welding electrodes and connections and shims ,packing pieces.

2 Providing fabrication and erection of MS gutter with FRP linning using standard 3.15mm thick ms sheetof recommended standard make including cutting , welding , drilling holes including a shop coat of zincchromate primer and two coats of Enemal paint externally and internally lined with layer of FRP linning0.5mm thick with provision for spouts for rain water wherever required etc. Complete all specified as perdrawing and directed by Engineer in Charge

3 Supply, fabrication and erection in position structural steel sections using 6 mm thick chequered platesetc., as required for trenches, platforms as per drawing including two coats of epoxy paint over andincluding a coat of zinc coat primer primer at all levels and locations etc. Complete all specified as perdrawing and directed by Engineer in Charge

4 Supply, fabrication and erection of MS pipe supports made out of standard extruded pipes of mediumquality including cutting to sizes , welding, closing of top open end with MS plate ,Embedding in positionusing PCC ( 1 : 2 : 4 ) (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) block ofsize 250 mm wide x 300 mm long x 400 mm deep and applying a coat of zinc coat primer with two coatsof epoxy paint etc. Complete all specified as per drawing and directed by Engineer in Charge

Page 9

Page 10: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

10 ROOFING WORKS :

1 Providing and fixing BARE GALVALUME SHEET for Roofing of 1000/1020mm cover width, 28 to 30mm high crests at 250/255mm centres in lengths upto 12m to suit site requirements,in hot dip metallic coated steel.Sheet to have wide pans with three stiffening ribs forefficient water shedding and speacial male female sides with full return leg on side lap forsupports from purlins at Ends and anticapillarity flute in side lap.The material shall be cold rolledsteel,550Mpa yield stress ( ASTM A446 Grade E ) With hot dipped mettalic coating of aluminium Zinkalloy ( 150gms/sqm total of both sides, AZ 150 as per ASTM A792 or AS per IS 1397),0.5mm totalcoated thickness.The work should be inclusive of laps,wastages, preparation of shopdrawings,scaffoldings,screws,fasteners etc. Complete all specified as per drawing and directed by Engineerin Charge

2 Providing and fixing COLOUR COATED GALVALUME SHEET for Cladding of 1000/1020mm cover width, 28 to 30mm high crests at 250/255mm centres in lengths upto 12m to suit site requirements,in hot dip metallic coated steel.Sheet to have wide pans with three stiffening ribs for efficient water shedding and speacial male female sides with full return leg on side lap for supports from purlins at Ends and anticapillarity flute in side lap.The material shall be cold rolled steel,550Mpa yield stress ( ASTM A446 Grade E ) With hot dipped mettalic coating ofaluminium Zink alloy ( 150gms/sqm total of both sides, AZ 150 as per ASTM A792 or AS per IS1397),0.5mm total coated thickness.The work should be inclusive of laps,wastages, preparation of shopdrawings,scaffoldings,screws,fasteners etc complete. all specified as per drawing and directed byEngineer in Charge

3 Providing and fixing BARE Coated GALVALUME SHEET for Flashing .The material shall be coldrolled steel,550Mpa yield stress ( ASTM A446 Grade E ) With hot dipped mettalic coating of aluminiumZink alloy (150gms/sqm total of both sides, AZ 150 as per ASTM A792 or AS per IS 1397),0.5mm total coated thickness.The work should be inclusive of laps, wastages, preparation of shopdrawings, scaffoldings, screws, fasteners etc complete.( Laps either with same or with other roofingmaterials will not be considerd for payment )

4 Providing and fixing BARE Coated GALVALUME SHEET for Bargeboard .The material shall be coldrolled steel, 550Mpa yield stress ( ASTM A446 Grade E ) With hot dipped mettalic coating of aluminiumZink alloy ( 150gms/sqm total of both sides, AZ 150 as per ASTM A792 or AS per IS 1397), 0.5mmtotal coated thickness.The work should be inclusive of laps, wastages, preparation of shop drawings,scaffoldings, screws, fasteners etc complete.( Laps either with same or with other Galvalume sheet will notbe considerd for payment )

5 Providing and fixing BARE Coated GALVALUME SHEET for Ridge .The material shall be cold rolledsteel, 550Mpa yield stress ( ASTM A446 Grade E ) With hot dipped mettalic coating of aluminium Zinkalloy ( 150gms/sqm total of both sides, AZ 150 as per ASTM A792 or AS per IS 1397), 0.5mm totalcoated thickness.The work should be inclusive of laps, wastages, preparation of shop drawings,scaffoldings, screws, fasteners etc. Complete all specified as per drawing and directed by Engineer inCharge

6 Providing and fixing 2mm thick Polycarbonate sheets of " GE- Plastics India Ltd " in the roofing in onelayer or any other approved equivalent make with necessary aluminium alloy bolts, washers, nuts etc.Theprofile of the polycarbonate sheet to match with the profile of roofing sheet unless otherwise specified.Theside laps will be 1.5 corrugation and end laps 150mm. At all height and locations etc. Complete allspecified as per drawing and directed by Engineer in Charge

Page 10

Page 11: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

7 Providing,fabricating and fixing MS Weld Mesh of size 25x25mm & 10G thick fixed over MS frameworkmade of angles, tees, flats etc for gate. The work to be inclusive of providing and applying two coats ofenamel paint over a coat of primer etc. Complete all specified as per drawing and directed by Engineer inCharge

8 Supplying and grouting of pockets inside the concrete structures using Conbextra GP2 of M/s Fosrocchemicals or approved equivalent including making arrangements to fix the MS framework , MS bolts ,inserts, etc to required line ,level and position & cleaning the pockets & surface using water to make itfree from dirt and dust ,pouring the ready mixed grout in the locations as per manufacturers detailspecifications including curing at all levels and locations etc. Complete all specified as per drawing anddirected by Engineer in Charge

11 INTERIOR WORKS :

1 Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI marked IS : 14842 -2000, including top cover of 6 mm coir veneer board, nickel plated M.S. Pipe 20 mm dia (heavy type)curtain rod with nickel plated brackets including fixing with 25x3 mm M.S. Flat 10 cm long and rawl plug50 mm long (designation 10 No.) etc. Complete all specified as per drawing and directed by Engineer inCharge

2 Providing and fixing 12mm thick plywood shutter for all cupboards ang kitchen drawers, one sidedecorative veneer and commercial veneer on other face (Type 1) conforming to IS 1328 BWR Type withnecessary screws, priming coat/fixing of veneer tape of same colour on unexposed surface etc. Completeall specified as per drawing and directed by Engineer in Charge

3 Supplying and fixing of stainless steel Storage Units, 300mm /450mm depth drawers for the full widht ofkitchen platform to strore the utencells below the kitchen platform to the full length of the kitchen platformdifferent provisions are to be provided to store dining plates,Glasses , spoons , grossory storage includinggas cylinder easy carrier dust bin holder etc. all front face should be covered with 12mm thick plywoodwith all hardware fittings etc. Complete all specified as per drawing and directed by Engineer in Charge

4 Providing and fixing Precast cement mortor(1:3) shelves of all shapes with weld mesh of 25mmX25mm , including hoisting and setting in position with cement mortar1:3 (1 Cement: 3 coarse sand), cost of required centring, shuttering and finishing smooth with 6mm thick cement plaster 1:3 (1 Cement: 3 fine sand) etc. Complete all specified as per drawing and directed by Engineer in Charge

12 MISCELLANEOUS WORKS :

1 Providing and fixing PVC rain water down take pipes of Class 4, conforming to IS 4985-2000 of110mm/160mm diameters including necessary fittings like clamps, bends, shoes etc.,at all heights andlevels with necessary scafolding, etc. Complete all specified as per drawing and directed by Engineer inCharge

2 Providing and fixing CI gratings of weight not less than 440 gms to rain water pipes on terrace includingfinishing smooth all round with neat cement etc. Complete all specified as per drawing and directed byEngineer in Charge

Page 11

Page 12: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

3 Providing , fabrication and erection of MS hand railing made out of standard quality ms pipes as per thedrawings ,including cutting,welding and erection hoisting , and applying a shop coat of zinc chromiteprimer and two coats of Enamel paint at all levels and locations etc. Complete all specified as per drawingand directed by Engineer in Charge

4 Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete1:2:4 (1 cement: 2coarse sand : 4 graded stone aggregate of 20 mm nominal size)over P.V.C. sheet 1 mx 1 mx 400 micron,finished with 12mm cement plaster 1:3 (1cement: 3 coarse sand) and a coat of neat cement rounding theedge and makingand finishing the outlet etc. Complete all specified as per drawing and directed byEngineer in Charge

5 Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement: 2 coarse sand : 4stone aggregate 10mmand down gauge) including finishing with cement mortar1:3 (1 cement: 3 fine sand) as per standarddesignetc. Complete all specified as per drawing and directed by Engineer in Charge

13 WATER PROOFING WORKS :

1 Providing and Applying Acrylic Reinforced Cementitious water proofing over Terrace with coating ofMasterseal 550 EL, in two coats to achieve 2mm thickness, Fibre reinforcement shall be provided betweenthe two coats, the material shall be mixed and applied fully in accordance with specialised agency, Theproduct shall exibit at least 40% elongation at ambient and 30% elongation in under water condition withtensile strength greater than 20 kg/cm2, The material shall be in compliant to BS 1881 - part 5 1983 andDIN 1048, etc complete a) The surface shall be pressure grouted using 40 PST injection grouting pump with cement slurry mixedwith non shrink injection grout with admixture Flowcable 50 at 250gms/bag of cement. including cutting thePVC grouted pipe and finishing the surface to the level of actual slab surface. if leakages found in slab andgrouting shall be done after pre-approval of Engineer in Charge b) The surface shall be Pre-wetted and provided with coving in cement mortar mixed with Rheomix 141 orequivalent as per manufacturers specification.c) Providing and laying over the treated surface baby chips concrete to an average thickness of 50mm tothe required slope, over the screed finished smooth 15mm thick cement mortar 1:3 (1 cement : 3 sand)mixed with integral water proofing compound Rheomac 707 or equivalent as per manufacturersspecification

2 Sunken SlabSurface PreparationAttention to full and proper preparation of the substrate is essential for complete adhesion.All surfacesshould be dry and free from contamination such as oil, grease, loose particles, decayed matter, moss,algal growth, laitance, and all traces of mould release oils and curing compounds. This is best achieved byrigorous wire brushing. Make sure that all joints are finished flush and blowholes filled with cement sandslurry. All surfaces to be treated with Brushbond RFX coating MUST be pre-soaked with clean water.Ensure that there is no free standing water on the surface

Pressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Renderoc Plug. Pressure grouting usinghand operated pressure grouting pump with a pressure of 2 to 3 kg/sq.mt through the nozzles by startingfrom one nozzle and and stopping when the grout starts coming out from adjacent nozzle and similarlycarrying out grouting operation in all the nozzles as per Fosroc specifications in all the points including thecost of material, labour for carrying grouting operations etc complete

Page 12

Page 13: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

Waterproofing membrane coatingSystem: Brushbond RFX at 1.0mm thickProviding and applying two coats of acrylic polymer modified cementitious waterproof coating BrushbondRFX at 1 mm thickness for sunken slab. The material should consist of a liquid polymer component and acementitious powder component, which shall be mixed as per manufacturer’s instructions and applied overprepared concrete surface strictly maintaining the coverage specified by the manufacturer. The appliedmaterial of Brushbond RFX should have a weight loss of less than 1gm when tested for abrasion resistanceaccording to ASTM-D4060, Pull off adhesion of greater than 1N/mm2 as per ASTM-D4541 and static crackaccommodation of 1mm according to ASTM-C836.The performance of the coating should remainunaffected when tested for continuous exposure to UV rays in QUV weatherometer. Cost inclusive ofmaterial, labor for necessary surface preparation,pressure grouting where ever necessary and applicationetc complete including the cost of cement plaster

CovingAll right angle bends must have a cant strip or coving detail installed. Providing and applying 1 coat ofBrushbond RFX to the prepared surface and Providing and applying coving using CM 1:4 with Conplast X421 IC to the size of 100mm X 100 mm at the slab – wall junction.Providing a final coat of brushbondRFX taken over the coving.Bore PackingApply bonding agent Nitobond SBR slurry coat prepared by 1 volume Nitbond SBR to 1 volume water to 3volumes fresh cement. the pipes to be fixed should be filed in order to provided a proper bond and thesame to be allingned by the respective agency. Minimum of 15mm allround gap to be provided between thepipe and the core.Provide shuttering below the core and providing and applying nonshrink cementitiousgrout Conbextra GPI to the complete depth of the slab

PlasteringProviding and applying CM 1:3 mixed with Conplast X421IC at the dosage of 125ml/bag of cement overcoating to a minimum thickness of minimum 12mm as per site requirement Note : Measurement will be paid for the Inner Surface Area Only

3 Waterproofing with Brushbond RFX comproising of : Surface Preparation:Attention to full and proper preparation of the substrate is essential for complete adhesion.All surfacesshould be dry and free from contamination such as oil, grease, loose particles, decayed matter, moss,algal growth, laitance, and all traces of mould release oils and curing compounds. This is best achieved byrigorous wire brushing. Make sure that all joints are finished flush and blowholes filled with cement sandslurry. All surfaces to be treated with Brushbond RFX coating MUST be pre-soaked with clean water.Ensure that there is no free standing water on the surfacePressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Renderoc Plug. Pressure grouting using handoperated pressure grouting pump with a pressure of 2 to 3 kg/sq.mt through the nozzles by starting fromone nozzle and and stopping when the grout starts coming out from adjacent nozzle and similarly carryingout grouting operation in all the nozzles as per Fosroc specifications in all the points including the cost ofmaterial, labour for carrying grouting operations etc complete

Bore PackingApply bonding agent Nitobond SBR slurry coat prepared by 1 volume Nitbond SBR to 1 volume water to 3volumes fresh cement. the pipes to be fixed should be filed in order to provided a proper bond and thesame to be allingned by the respective agency. Minimum of 15mm allround gap to be provided between thepipe and the core.Provide shuttering below the core and providing and applying nonshrink cementitiousgrout Conbextra GPI to the complete depth of the slab

Page 13

Page 14: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

Waterproofing membrane coatingSystem: Brushbond RFX at 1.0mm thickProviding and applying two coats of acrylic polymer modified cementitious waterproof coating BrushbondRFX at 1 mm thickness for sunken slab. The material should consist of a liquid polymer component and acementitious powder component, which shall be mixed as per manufacturer’s instructions and applied overprepared concrete surface strictly maintaining the coverage specified by the manufacturer. The appliedmaterial of Brushbond RFX should have a weight loss of less than 1gm when tested for abrasion resistanceaccording to ASTM-D4060, Pull off adhesion of greater than 1N/mm2 as per ASTM-D4541 and static crackaccommodation of 1mm according to ASTM-C836.The performance of the coating should remainunaffected when tested for continuous exposure to UV rays in QUV weatherometer. Cost inclusive ofmaterial, labor for necessary surface preparation,pressure grouting where ever necessary and applicationetc complete including the cost of cement plaster

PlasteringProviding and applying CM 1:3 mixed with Conplast X421IC at the dosage of 125ml/bag of cement overcoating to a minimum thickness of minimum 12mm as per site requirement

4 LIFT PIT (OUTSIDE)Surface PreparationAttention to full and proper preparation of the substrate is essential for complete adhesion.All surfacesshould be dry and free from contamination such as oil, grease, loose particles, decayed matter, moss,algal growth, laitance, and all traces of mould release oils and curing compounds. This is best achieved byrigorous wire brushing. Make sure that all joints are finished flush and blowholes filled with cement sandslurry. All surfaces to be treated with Masterseal 550 EL of BASF or equivalent coating MUST be pre-soaked with clean water. Ensure that there is no free standing water on the surface

Pressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern ) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Masterseal 505 or or equivalent. Pressuregrouting with Concressive 1315 or equivalent using hand operated pressure grouting pump with apressure of 2 to 3 kg/sq.mt through the nozzles by starting from one nozzle and and stopping when thegrout starts coming out from adjacent nozzle and similarly carrying out grouting operation in all thenozzles as per manufacturers specifications in all the points including the cost of material, labour forcarrying grouting operations etc completeWaterproofing membrane coatingSystem:Acrylic polymer modified cementitious waterproof coatingat 1.0mm thickProviding and applying two coats of acrylic polymer modified cementitious waterproof coating Masterseal 550 EL at 1 mm thickness for sunken slab. The material should consist of a liquid polymer component anda cementitious powder component, which shall be mixed as per manufacturer’s instructions and appliedover prepared concrete surface strictly maintaining the coverage specified by the manufacturer.CoverageEach square metre will require minimum of 0.9 Kg of mixed material per layer. The coverage rate for eachlayer will be strongly influenced by the roughness of the substrate.1.8 kg / m² in two coats to achieve 1 mm thickness. BS 1881 Part 5 1983 - I.S.A.T.DIN 1048 Water Penetration Test. Cost inclusive of material, labor for necessary surfacepreparation,pressure grouting where ever necessary and application etc complete including the cost ofcement plaster .

PlasteringProviding and applying CM 1:3 mixed with Rheomac 707 or equivalent at the dosage range from 150 mlto 250 ml per100kg of cementitious material is recommended over coating to a minimum thickness of minimum 12mmas per site requirement

Page 14

Page 15: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

Surface PreparationLIFT PIT BASE (INSIDE)

Providing and Applying external surface treatment with Liquid, cold-applied one-component, moisture-curing, Bitumen Free P.U. (polyurethane) elastomeric waterproofing membrane system Masterseal HLM5000R on the concrete surface To be applied in as a coating to built a thickness of 1.2mm on surfaceprepared, fair faced concrete surface, later to be protected as per manufacturers specifications with EPSBoard or Screed Plaste or Acrylic coatings etc depending on the application and utility.

Pressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern ) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Masterseal 505 or or equivalent. Pressuregrouting with Concressive 1315 or equivalent using hand operated pressure grouting pump with apressure of 2 to 3 kg/sq.mt through the nozzles by starting from one nozzle and and stopping when thegrout starts coming out from adjacent nozzle and similarly carrying out grouting operation in all thenozzles as per manufacturers specifications in all the points including the cost of material, labour forcarrying grouting operations etc completeCovingAll right angle bends must have a cant strip or coving detail installed. Providing and applying 1 coat ofMasterseal 550 EL or equivalent to the prepared surface and Providing and applying coving using CM 1:4with or Rheomac 707 to the size of 100mm X 100 mm at the slab – wall junction.Providing a final coat ofMasterseal 550 EL taken over the coving.

Masterpren 1000 is a , bituminousmembrane lined with cross laminated, high densitypolyethylene film, oriented to give optimum strength to the membrane, will be applied with Masterpren 2000 adhesive. The membrane is designed for application onto surfaces, both above and below ground, to keepwater and water borne aggressive salts from penetrating into substrates.

5 SUMP-BASE (INSIDE)Surface PreparationAttention to full and proper preparation of the substrate is essential for complete adhesion.All surfacesshould be dry and free from contamination such as oil, grease, loose particles, decayed matter, moss,algal growth, laitance, and all traces of mould release oils and curing compounds. This is best achieved byrigorous wire brushing. Make sure that all joints are finished flush and blowholes filled with cement sandslurry. All surfaces to be treated with Masterseal 550 ELor equivalent coating MUST be pre-soaked withclean water. Ensure that there is no free standing water on the surface.Coating with Masterseal 180 orMastertop 1110 T or equivalent

Pressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Masterseal 505 or equivalent. Pressuregrouting with Concressive 1315 or equivalent using hand operated pressure grouting pump with apressure of 2 to 3 kg/sq.mt through the nozzles by starting from one nozzle and and stopping when thegrout starts coming out from adjacent nozzle and similarly carrying out grouting operation in all thenozzles as per Manufacturers specifications in all the points including the cost of material, labour forcarrying grouting operations etc completeBore PackingApply bonding agent Rheomix 141 of BASF (as per Manufacturers specifications)or equivalent slurry coatprepared by 1 volume Rheomix 141 to 1 volume water to 3 volumes fresh cement. the pipes to be fixedshould be filed in order to provided a proper bond and the same to be allingned by the respective agency.Minimum of 15mm allround gap to be provided between the pipe and the core.Provide shuttering below thecore and providing and applying nonshrink cementitious grout Masterflow 915 and Masterflex612(Hydroswellable gasket in paste form) at the center of the core.or equivalent to the complete depth ofthe slab

Page 15

Page 16: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

Waterproofing membrane coatingSystem: Elastomeric, cementitious, waterproof coating at 1.0mm thickProviding and applying two coats of acrylic polymer modified cementitious waterproof coating Masterseal 550 EL at 1 mm thickness for sunken slab. The material should consist of a liquid polymer component anda cementitious powder component, which shall be mixed as per manufacturer’s instructions and appliedover prepared concrete surface strictly maintaining the coverage specified by the manufacturer.CoverageEach square metre will require minimum of 0.9 Kg of mixed material per layer. The coverage rate for eachlayer will be strongly influenced by the roughness of the substrate.1.8 kg / m² in two coats to achieve 1 mm thickness. BS 1881 Part 5 1983 - I.S.A.T.DIN 1048 Water Penetration Test. Cost inclusive of material, labor for necessary surfacepreparation,pressure grouting where ever necessary and application etc complete including the cost ofcement plaster .

PlasteringProviding and applying CM 1:3 mixed with Rheomac 707 or equivalent at the dosage range from 150 mlto 250 ml per100kg of cementitious material is recommended over coating to a minimum thickness of minimum 12mmas per site requirement

Waterproofing with Masterseal HLM 5000 for SUMP OUTSIDE

Surface PreparationProviding and Applying external surface treatment with Liquid, cold-applied one-component, moisture-curing, Bitumen Free P.U. (polyurethane) elastomeric waterproofing membrane system Masterseal HLM5000R on the concrete surface To be applied in as a coating to built a thickness of 1.2mm on surfaceprepared, fair faced concrete surface, later to be protected as per manufacturers specifications with EPSBoard or Screed Plaste or Acrylic coatings etc depending on the application and utility.

Pressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Masterseal 505 or equivalent. Pressuregrouting with Concressive 1315 or equivalent using hand operated pressure grouting pump with apressure of 2 to 3 kg/sq.mt through the nozzles by starting from one nozzle and and stopping when thegrout starts coming out from adjacent nozzle and similarly carrying out grouting operation in all thenozzles as per Manufacturers specifications in all the points including the cost of material, labour forcarrying grouting operations etc complete

6 Waterproofing with elastomeric, cementitious, waterproof coating at 1.0mm thickOver head Tank -BaseSurface PreparationAttention to full and proper preparation of the substrate is essential for complete adhesion.All surfacesshould be dry and free from contamination such as oil, grease, loose particles, decayed matter, moss,algal growth, laitance, and all traces of mould release oils and curing compounds. This is best achieved byrigorous wire brushing. Make sure that all joints are finished flush and blowholes filled with cement sandslurry. All surfaces to be treated with Masterseal 550 EL or equivalent, coating MUST be pre-soaked withclean water. Ensure that there is no free standing water on the surface

Page 16

Page 17: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

Pressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Masterseal 505 or equivalent. Pressuregrouting with Concressive 1315 or equivalent using hand operated pressure grouting pump with apressure of 2 to 3 kg/sq.mt through the nozzles by starting from one nozzle and and stopping when thegrout starts coming out from adjacent nozzle and similarly carrying out grouting operation in all thenozzles as per Manufacturers specifications in all the points including the cost of material, labour forcarrying grouting operations etc complete

Bore PackingApply bonding agent Rheomix 141 of BASF (as per Manufacturers specifications)or equivalent slurry coatprepared by 1 volume Rheomix 141 to 1 volume water to 3 volumes fresh cement. the pipes to be fixedshould be filed in order to provided a proper bond and the same to be allingned by the respective agency.Minimum of 15mm allround gap to be provided between the pipe and the core.Provide shuttering below thecore and providing and applying nonshrink cementitious grout Masterflow 915 and Masterflex612(Hydroswellable gasket in paste form) at the center of the core.or equivalent to the complete depth ofthe slab

Waterproofing membrane coatingSystem: An elastomeric, cementitious, waterproof coating at 1.0mm thickProviding and applying two coats of acrylic polymer modified cementitious waterproof coating Masterseal 550 EL at 1 mm thickness for sunken slab. The material should consist of a liquid polymer component anda cementitious powder component, which shall be mixed as per manufacturer’s instructions and appliedover prepared concrete surface strictly maintaining the coverage specified by the manufacturer.CoverageEach square metre will require minimum of 0.9 Kg of mixed material per layer. The coverage rate for eachlayer will be strongly influenced by the roughness of the substrate.1.8 kg / m² in two coats to achieve 1 mm thickness. BS 1881 Part 5 1983 - I.S.A.T.DIN 1048 Water Penetration Test. Cost inclusive of material, labor for necessary surfacepreparation,pressure grouting where ever necessary and application etc complete including the cost ofcement plaster .

PlasteringProviding and applying CM 1:3 mixed with Rheomac 707 or equivalent at the dosage range from 150 mlto 250 ml per100kg of cementitious material is recommended over coating to a minimum thickness of minimum 12mmas per site requirement

Over head Tank –Side Wall Surface PreparationAttention to full and proper preparation of the substrate is essential for complete adhesion.All surfacesshould be dry and free from contamination such as oil, grease, loose particles, decayed matter, moss,algal growth, laitance, and all traces of mould release oils and curing compounds. This is best achieved byrigorous wire brushing. Make sure that all joints are finished flush and blowholes filled with cement sandslurry. All surfaces to be treated with Masterseal 550 EL or equivalent, coating MUST be pre-soaked withclean water. Ensure that there is no free standing water on the surface

Pressure GroutingDrilling 12mm dia holes with electrical drilling machine along the construction joints or honeycomb areas(at every 500mm c/c along construction joints in staggered pattern) to a depth of 25mm and fixing PVCnozzle of 10mm dia in place using quick setting compound Masterseal 505 or equivalent. Pressuregrouting with Concressive 1315 or equivalent using hand operated pressure grouting pump with apressure of 2 to 3 kg/sq.mt through the nozzles by starting from one nozzle and and stopping when thegrout starts coming out from adjacent nozzle and similarly carrying out grouting operation in all thenozzles as per Manufacturers specifications in all the points including the cost of material, labour forcarrying grouting operations etc complete

Page 17

Page 18: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

Bore PackingApply bonding agent Rheomix 141 or equivalent, slurry coat prepared by 1 volume Rheomix 141 to 1volume water to 3 volumes fresh cement. the pipes to be fixed should be filed in order to provided a properbond and the same to be allingned by the respective agency. Minimum of 15mm allround gap to beprovided between the pipe and the core.Provide shuttering below the core and providing and applyingnonshrink cementitious grout Masterflow 915 or equivalent to the complete depth of the slab

PlasteringProviding and applying CM 1:3 mixed with Rheomac 707 or equivalent at the dosage range from 150 mlto 250 ml per100kg of cementitious material is recommended over coating to a minimum thickness of minimum 12mmas per site requirement Waterproofing membrane coatingSystem: An elastomeric, cementitious, waterproof coating at 1.0mm thickProviding and applying two coats of acrylic polymer modified cementitious waterproof coating Masterseal 550 EL at 1 mm thickness for sunken slab. The material should consist of a liquid polymer component anda cementitious powder component, which shall be mixed as per manufacturer’s instructions and appliedover prepared concrete surface strictly maintaining the coverage specified by the manufacturer.CoverageEach square metre will require minimum of 0.9 Kg of mixed material per layer. The coverage rate for eachlayer will be strongly influenced by the roughness of the substrate.1.8 kg / m² in two coats to achieve 1 mm thickness. BS 1881 Part 5 1983 - I.S.A.T.DIN 1048 Water Penetration Test. Cost inclusive of material, labor for necessary surfacepreparation,pressure grouting where ever necessary and application etc complete including the cost ofcement plaster .

PlasteringProviding and applying CM 1:3 mixed with Rheomac 707 or or equivalent. at the dosage of as per thetechnical data sheet of cement over coating to a minimum thickness of minimum 12mm as per siterequirement

14 SANITARY FIXTURES AND ACCESSORIES

1 Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan) with seatand lid, 10 litre low level white P.V.C. flushing cistern with manually controlled device (handle lever),conforming to IS : 7231, with all fittings and fixtures complete including cutting and making good the wallsand floors wherever required :W.C. pan with ISI marked black solid plastic seat and lid

a) C.P. brass angle valve approved quality conforming to IS:893115 mm nominal bore

b) 450 mm long PVC flexible pipe with brass nuts as inlet c) best quality 15mm CP brass Two way Bib Cock with wall flange and health faucet with 8mm dia, 1 meter

long PVC tube and wall Hook.

2 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32mm C.P. brass waste, C.P bottle trap of standard pattern, including painting of fittings and brackets,cutting and making good the walls wherever require :a). White Vitreous China Wash basin size 630x450 mm with a single 15 mm C.P. brass pillar tap.

a) C.P. brass angle valve approved quality conforming to IS:893115 mm nominal bore

b) 450 mm long PVC flexible pipe with brass nuts as inlet

Page 18

Page 19: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

3 SHOWER UNITa Providing and fixing C.P. brass shower rose with 15 or 20 mm inlet:

100 mm diameterb Providing and fixing C.P. brass stop cock (concealed) of standard design and of approved make

conforming to IS:8931.2No.s of 15mm nominal bore stop cocks

c Providing and fixing C.P. brass long body bib cock of approved quality conforming to IS standards andweighing not less than 690 gms.2 No.s of 15 mm nominal bore.Complete set of Shower Unit

4 Supply and fixing of electric storage type vertical/horizontal water heater(geyser) of approved make andcolour having an inner tank manufactured from 99% pure copper which is suitable for both hard and softwater with all other internal fittings, internal insulation, inside non-return valve at inlet pipe all as per IS-2082 with three core heavy duty copper cable with 3 pin plug, CP brass screwd inlet pipe, automaticpressure relief valve, adjustable thermostat assembly 1 No. 15mm CP brass concealed stop cock with wallflange for cold water supply and 2 No.s 600mm long CP copper inlet connecting pipe with end nuts for hotand cold water supply connections etc., complete with mounting frame and bolts. including cutting andmaking good the walls , wherever requireda) 25 L (In all Bath rooms )

5 Providing and fixing Stainless Steel AISI 304 (18/8) kitchen sink as per IS 13983 with C.I. brackets and stainless steel plug 40 mm including painting of fittings and brackets, cutting and making good the walls wherever required :a). Kitchen sink without drain boardb). 610x510 mm bowl depth 200 mm.

a) Providing and fixing C.P. brass stop cock (concealed) of standard design and of approved makeconforming to IS:8931.15mm nominal bore stop cocks

b) Providing and fixing C.P. brass long body bib cock of approved quality conforming to IS standards andweighing not less than 690 gms.a). 15 mm nominal bore.

6 Providing and fixing C.P. brass long body bib cock of approved quality conforming to IS standards andweighing not less than 690 gms.a). 15 mm nominal bore.

7 Providing and fixing C.P towel ring with a minimum distances of 37mm from wall face with concealedfittings arrangement of approved quality and colours etc, complete

8 Providing and fixing C.P towel rail complete with brackets fixed to wooden cleats with CP brass screwswith concealed fitting arrangement of approved quality and colour etc, completea).600mm long towel rail.

9 Providing and fixing CP brass double robe hook and fixed by using CP brass counter sunk screws etc.,complete. (At EWC room door)

10 Providing and fixing 600x450 mm bevelled edge mirror of superior glass (of approved quality) completewith 6 mm thick hard board ground fixed to wooden cleats with C.P. brass screws and washers complete.(At each wash basin)

Page 19

Page 20: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

15 WATER SUPPLY (INTERNAL)1 Providing, fixing, testing and commissioning approved make chlorinated poly vinyl chloride pipes(CPVC),

having thermal stability for hot and clod water supply including all CPVC plain and brass treaded fittingsi.e. fitting the pipes with clamps at 1 meter spacing. This includes jointing of pipes & fittings with one stepCPVC solvent cement & the cost of cutting chases and making good the same including testing of jointscomplete as per direction of engineer in- charge. (Concealed work including cutting chases and mixinggood the walls etc,.)a) 15mm NBb) 20mm NBc) 25mm NB

2 Providing, fixing, testing and commissioning approved make chlorinated poly vinyl chloride pipes(CPVC),having thermal stability for hot and clod water supply including all CPVC plain and brass treaded fittingsi.e. fitting the pipes with clamps at 1 meter spacing. This includes jointing of pipes & fittings with one stepCPVC solvent cement & the cost of cutting chases and making good the same including testing of jointscomplete as per direction of engineer in- charge. (Internal work exposed on wall.)

a) 32mm NBb) 40mm NBc) 50mm NB

3 Supply and fixing of Gun metal gate Valve, material specification Size - 15 to 50mm NB screwed end to BSPT femail.Material:Body cover - Gun metal IS:318, Gr.2Trim - Gun metal IS:318, Gr.2

Size - 65 to 150mm NB flanged end , BS 10 table-DMaterial:Body cover - Cast iron IS:210, Gr-Fg200Trim - C.I disk, Spindle of gun metal IS:318, Gr.2

Hand wheel operated rising stem inside screw union bonnet, removal disk, seat & back seat for rebackingunder working pressure..etc, and complete.

a) 25mm dia (Screwed ends)b) 32mm dia (Screwed ends)c) 40mm dia (Screwed ends)d) 50mm dia (Flanged ends)

4 Providing,fixing,testing and commissionining of lever operated bronze ball valve of approved make andprovided with stainless steel ball (AISI 304) and spindle (AISI 410), glass filled Teflon seating and glandpacking etc., complete. The valve shall be fixed after the union. The quoted rate shall include the cost ofthe union, nipples etc., complete.a) 20mm dia (Screwed ends)b) 25mm dia (Screwed ends)c) 32mm dia (Screwed ends)

5 Supply and fixing 15mm dia air release valve

6 Supply, Installation & Commissioning of Brass float valve with copper ball etc in building overhead tanks(ISI marked)a). 50mm dia

Page 20

Page 21: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

16 SEWERAGE (INTERNAL)

1 Providing, fixing, testing and commissioning of SWR PVC Plain/multi floor trap of `P' or `S' type withframed stainless steel grating (heavy quality hopper type) and 75mm outlet with necessary cementconcrete chamber, water proofing the internal surfaces of chamber etc., complete.

2 Supply and fixing Cockroach free floor trap, SS grating 125mm dia with rim including setting in floor withSilicon Sealent. (chilly make) for kicthen only

3 Providing, fixing, testing and commissioning of class III (6 kg/cm2) SWR PVC (IS:13592) with latestamendment soil waste and vent pipes jointed with solvent cement inclusive of all necessary specials likebends, tees, offsets, junctions, pan connector, cowls etc., laid under floor/under ceiling/on walls withsuitable clamps including making bores in masonry / RCC slabs etc., and rendering the bores in cementmortar after laying the pipes and specials curing etc., complete.a) 110mm SWR PVCb) 75mm SWR PVCc) 50mm SWR PVCd) 40mm SWR PVC

4 Supplying and fixing of PVC cowl a) 75mm dia.b) 100mm dia.

5 Providing and fixing in position best quality salt glazed stoneware gully trap of size 300mm square with100mm outlet confirming to IS:651 construct as per technical specification & drawing

6 Providing & Fixing of inspection chamber of size 600x600x600mm depth construct as per technicalspecification and drawing.Cover of 600 x 450mm size, medium duty (weight of frame and cover not less than 58 kgs).

7 Providing & Fixing of inspection chamber of size 450x450x600mm depth construct as per technicalspecification and drawing.Cover of 450 x 450mm size, medium duty (weight of frame and cover not less than 38 kgs).

17 STORM WATER (Rain water downtakes)

1 Providing, fixing, testing and commissioning of class III (6 kg/cm2) SWR PVC (IS:4985 with latestamendment) Rain Water pipes jointed with solvent cement inclusive of all necessary specials like bends,tees, offsets, junctions, pan connector etc., laid under floor/under ceiling/on walls with suitable clampsincluding making bores in masonry / RCC slabs etc., and rendering the bores in cement mortar after layingthe pipes and specials curing etc., complete.a) 50mm diab) 75mm diac) 110mm dia.

2 Making rain water khurra's/grating with PVC solvent welded type moulded bends, etc. (For 110mm Dia)

3 Providing & Fixing uPVC 6 Kg/sq cm 110mm dia self cleaning special Balcony floor trap with 75 mm outletpasted to the trap complete including SS grating setting in 1:2:4 cement concrete including cutting andmaking good the same including sealing the area using water proofing compund .

Page 21

Page 22: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

18 MISCELLANEOUS WORKS :

1 Providing core cutting of required diameter by using core cutting machine for taking out the soil , waste,rain water pipe and balcony drain pipe line in RCC slab/beam etc,. At all heights and depths and waterproofing the surfaces after the installation & testing the pipes, floor traps etc,. complete.a) 75 mm ODb) 110 mm OD

2 Providing MS angle iron brackets using 40 x 40 x 6mm thick for supporting soil and waste pipes onwalls/ceiling by using hanger rods welded/ grouted and the bracket shall be given two coats of anticorrosive paint over a coat primer etc., complete as per drawing or as per site requirements.

19 ELECTRICAL FITTINGSFACTORY-BUILT /FABRICATED MCB DISTRIBUTION BOARDS:Supply Installation Testing and commissioning of SPN / TPN / VTPN Double Door Distribution boards ofdust and vermin protected and rated for 230 / 415V, Single phase / Three Phase AC supply operationeither surface / recess mounted as per drawings including incoming and out going MCBs / ELCB as perspecifications and required capacity Neutral bar and Earth terminal complete as required . MCB's shall beC-curve for LDB'S, and D-curve for PDB & UPSDB, conform to IS : 8828 and ELCB /RCCB shall conformto IS : 12640. (MAKE-LEGRAND / L&T / HAVELLS)

19.01 12Way SPN Double Door MCB DB With with 40A DP (30mA) ELCB -1 No as incomer , and 6- 25 A(10KA) SP MCBs-10 Nos as outgoings. (Legrand Cat No-607712 )

19.02 6 Way TPN Double Door MCB DB with 32 A FP MCB +RCCB (10KA)-1 No as incomer, and 6- 25 A(10KA) SP MCBs-12 Nos as outgoings. (LEGRAND CAT NO : 6077-16)

19.03 4 Way SPN MCB DB with 200A DP ELCB(30mA) -1 No as incomer, 6- 25 A (10kA) SP MCBs-2 Nosas outgoings + Blanking plats. (LEG RAND CAT NO : 6077-10)

20 DUMMY CONDUIT

Supply and laying of 2 mm thick heavy duty PVC conduit in concealed/surface in wall/ ceiling/floorincluding all accessories such as junction boxes, conduit bends, pulling wire, wall cutting and roughplastering of wall using wire mesh, completed as required.) Conduit;- (AVONPLAST/ VIP/ PRECISION)

20.0 40 mm dia PVC. conduit with all accessories.

20.1 25 mm dia PVC. conduit with all accessories.

20.2 20 mm dia PVC. conduit with all accessories.

21 SUB MAINS/CIRCUIT MAINS/POWER WIRING :Supply, Wiring, testing and commissioning of following size 1100V grade FRLS PVC insulated multi strandcopper conductor wires in and including specified size 2 mm thick PVC conduit laid on wall/ Ceiling withincluding all accessories such as junction boxes, bends, elbows and end termination with suitable copperlugs, Ferrules etc. (Make- Finolex/ L&T/ Havells / Polycab )Conduit;- AVONPLAST/ VIP/ PRECISION.

21.01 2 runs of 1.5 Sq.mm FRLS PVC insulated multi strand Copper conductor wires & 1 run of 1.0 SqmmFRLS PVC insulated multi strand Copper conductor earth wire in and including of 20 mm dia PVCconduit with including all conduit accessories.

Page 22

Page 23: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

2 runs of 1.5 Sq.mm FRLS PVC insulated multi strand Copper conductor wires & 1 run of 1.0 SqmmFRLS PVC insulated multi strand Copper conductor earth wire without 20 mm dia PVC conduit withincluding all conduit accessories.

21.02 2 runs of 2.5 Sq.mm FRLS PVC insulated multi strand Copper conductor wires & with 1 run of 1.5Sqmm FRLS PVC insulated multi strand Copper conductor earth wire in and including of 20 mm diaPVC conduit with including all conduit accessories(For lighting main circuit)

21.03 2 runs of 2.5 Sq.mm FRLS PVC insulated multi strand Copper conductor wires & with 1 run of 1.5Sqmm FRLS PVC insulated multi strand Copper conductor earth wire with excluding of 20 mm dia PVCconduit.

2 runs of 4 Sq.mm FRLS PVC insulated multi strand Copper conductor wires & with 1 run of 2.5 SqmmFRLS PVC insulated multi strand Copper conductor earth wire in and including of 25 mm dia PVCconduit with including all conduit accessories(For lighting main circuit)

2 runs of 4 Sq.mm FRLS PVC insulated multi strand Copper conductor wires & with 1 run of 2.5 SqmmFRLS PVC insulated multi strand Copper conductor earth wire with excluding PVC conduit.

2 Pair 0.5 Sqmm PVC( 2 Pair telephone cable) insulated multi strand Copper conductor wires andincluding of 20 mm dia PVC conduit with including all conduit accessories

RJ 6 ( TV Coaxial cable) Coaxial cable with proper slighter and junction & connectors in and including of 20mm dia PVC conduit with including all conduit accessories

22 POINT WIRING :Supply, wiring, testing and commissioning of Point Wiring for ( Light/ ceiling Fan/ exhaust fan & 6Aindependent socket) with 2 runs of 1.5 Sqmm + 1 run of 1.5 Sqmm FRLS PVC insulated 1100V grademultistrand Copper conductor wires, run in and including 25 mm dia,2mm thick PVC conduitsconcealed in wall / ceiling (wiring should conforming to IS 732 ) including all accessories such as junctionboxes, conduit bends elbows and ceiling rose, with MK make metal boxes, modular switch/socket, fan regulators and the box covered with MK wraparound plus front plate. along with all necessary fixingaccessories like mounting screws etc. (excluding circuit main) Make- Finolex )Conduit;- AVONPLAST/ VIP/ PRECISION..

NOTE: The wiring for point wiring under this item shall be measured from the switch box up to the light /fan / socket only in utility areas other than those with MCB controlled lights. The wiring from the respectiveLDBs to first switch box shall be measured under the heading circuit mains. (Switch & Sockets-ANCHORNOA)(White)

22.01 Single light point controlled by a 6A SP switch or bell push

22.02 Extended light point from the existing light point

22.03 Two way light point controlled by 2no's 6 A Two way switches.at Individual location.

22.04Ceiling Fan points controlled by 6 Amp switch with including M.S fan hook Box, Ceiling Rose and 100watts step type electronic regulator ( CAT NO:29670).

22.05Wall fan point with wall mounted 5A, 5 pin socket near to wall fan location and 6A single pole controllingswitch located independently..

Page 23

Page 24: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

22.06Exhaust fan point with wall mounted ceiling Rose near exhaust fan location and 6A single pole controllingswitch located independently.

22.07Supply and fixing of 6A, 5 Pin switched Socket outlet in Lighting switch boards dependent.

22.08 Supply and fixing of 6A, 5Pin switched Socket outlet independent location.

23 INDOOR LIGHTING FIXTURES WITH LAMPS / CEILING & EXHAUST FANS.

Supply, installation, testing & Commissioning of the following types of light & fan fittings complete withlow loss Electronic ballast , starters,controlgear, connecting wire with Lamps, pf improvement capacitorsfor Lamps,all prewired up to the terminal block As per catalog OR All lamps should be pure white coloronly .

NOTE: All fittings shall be with energy efficient copper / Electronic ballast. All the CFL fixtures shall beprovided with PF improvement condenser compulsorily. Tubes shall be of color 84 (cool day light). Also therates quoted shall include all other accessories complete as required for suspending the lights, fans to therequired level as shown in the respective drawings.(Philips/ Bajaj/ CG/ GE/ Wipro)

23.01 Supply, installation, testing and commissioning of 1 x 36 W FTL light fitting along with all accessoriessuch as control gear, power factor improvement capacitor, Philips T5 lamps etc as required with all fixingaccessories.(PHILIPS CAT NO: TCH 207 1 X TL 5-28W HF)

Supply, installation, testing and commissioning of 1 X 11 Watts, CFL Angle Holder with CFL lamps, Lampholders, Electronic Blast, connectors and all other fixing accessories as required ( Philips Cat. No.-11W CFL ).

23.02 Supply, installation, testing and commissioning of 1 X 20 Watts, CFL wall bracket light with CFL lamps,Lamp holders, Electronic Blast, connectors and all other fixing accessories as required ( Philips Cat. No.-FMS 800/320 ).

Supply, installation, testing and commissioning of 1 X 11 Watts, CFL Angle Holder with CFL lamps, Lampholders, Electronic Blast, connectors and all other fixing accessories as required ( Philips Cat. No.-11W CFL ).

23.03 Supply, installation, testing and commissioning of 1 X 18 Watts, CFL Ceiling mounted light with CFLlamps, Lamp holders, Electronic Blast, connectors and all other fixing accessories as required ( Philips Cat. No.-FMS 343/118 ).

23.04 Supply, installation, testing and commissioning of LED Skirting light 3 module with LEDs, Metal Box andall other fixing accessories as required ( Legrand Cat. No.-674523 ).

23.05 Supply, installation, testing and commissioning of 1 X 11 Watts, CFL Merror light with CFL lamps, Lampholders, connectors and all other fixing accessories as required ( Philips Cat. No.-FMS 300/111 ).

Page 24

Page 25: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

23.06 Supply, installation, testing and commissioning of 1 X 60 Watts, Bulkhead light with 60W lamps, Lampholders, connectors and all other fixing accessories as required ( Philips Cat. No.-FXC 101 ).

23.07 Supply, installation, testing and commissioning of 1 X 50 Watts, Halogen Spot light with 50w12VDClamps, Requaired Gear Box, Lamp holders, connectors and all other fixing accessories as required. ( Philips Cat. No.-).

23.08 Supply, installation, testing and commissioning of 1 x 25Watts, Deco Twist Circular CFL Light with CFLlamps, Lamp holders, connectors and all other fixing accessories as required (Philips Cat. No. DECOTWIST LUX CLD BCS 1902 ).

23.09 Supply, installation, testing and commissioning of 2 x 36 Watts, In door Decorative Light with FTL lamps,Lamp holders, Electronic Blast, connectors and all other fixing accessories as required (Philips Cat. No.TCS 306/ 236 HFE)

23.10 Supply, installation, testing and commissioning of 2 x 28 Watts, Light fixture with FTL lamps,ElectronicBlast, Lamp holders, connectors and all other fixing accessories as required (Philips Cat. No. tcs350/228 c5 HF ).

23.11 Supply, installation, testing and commissioning of 4 x 28 Watts, Light Fixture with FTL lamps,ElectronicBlast, Lamp holders, connectors and all other fixing accessories as required (Philips Cat. No. TPS 325/428 HF ).

Supply & Installation of electronic Calling Bell With Continues Duty.

24 CEILING FANS:Supply, erection, testing and commissioning of ceiling fan with 300mm length down rod ,double ballbearings, accessories, connecting wire and other standard accessories as required but excluding regulator. (CG cat No:- High Speed Decora).

24.01 1200mm Sweep, 3 blade ceiling fan .

24.02 400 Sweep Wall mount Air circulator with full set complete With fixing hardwares (CG Cat No- High FlowWall Mount Fan ).

EXHAUST FANS:

Supply and Erection of exhaust fans with sheet metal blades, necessary brackets, anti corrosive epoxypainting, rubber cushions etc. (CG cat No:- ).

24.03 305 mm dia, 900 Rpm industrial exhaust fan

24.04 Supply, installation, testing and commissioning of 250W MH Flood light fitting along with all accessoriessuch as Gear box, lamps etc as required with all fixing accessories (PHILIPS CAT NO: MWF 300AK/250(ASYM).

Page 25

Page 26: IMPORTANT NOTES – PART Agailtenders.in/writereaddata/corrigendum/rajahmundry part c sor2... · IMPORTANT NOTES – PART A ... lobby, stilt, and common areas ... 1 Supply, diluting

IMPORTANT NOTES FOR SOR PART A

25 LOAD BREAK SWITCHES / SOCKETS/

Supply, erection, testing and commissioning of factory made metal clad Plug and top totally enclosed withmetal housing with industrial socket/interlocked combined rotary switch and socket with scrapping earthconnection and plug top. In case of interlocked socket, the interlocking should ensure that the plug cannotbe inserted or withdrawn while the switch is in 'ON' position. (all switches & sockets shall be housed inpainted MSboxes). The erection rate shall include supply of angle iron frame work and fixing accessoriessuch as grip bolts/grouting/ welding to steel structures etc.

25.01 20Amps, Single phase metal clad industrial socket with plug top with in and including 20 Amps SP(10KA)MCB.(Legrand Cat Log No : )

32Amps, Three phase metal clad industrial socket with plug top with in and including 32 Amps TPN(10KA)MCB.(Legrand Cat Log No : 607872)

26 DOMESTIC TYPE --MODULAR

Supply, erection, testing and commissioning of power points of ANCHOR NOVA make switches/socketsmounted on suitable size metal boxes covered by Wraparound plus white color front plate fixedflush/surface on the wall with all fixing, wiring accessories , box Earthing etc

26.01 BANK OF 3 Nos. 13 Amps, Multipin (230 Volts) single phase Flat Pin socket controlled by 1no - 16 Ampssingle pole switch with box and front plate (UPS OUTLETS) ( MK cat no:- S26110HO FW)

26.02 Bank of 3 Nos.6 Amps, 5-pin (230 Volts) single phase socket (Combination of Multipin) controlled by 16Amps single pole switch with 1 No ( MK cat no:- socket -)

26.03 1 No .6/16 Amps, 6--pin (230 Volts) single phase universal socket (Combination of Multipin) with 16 Ampssingle pole switch with box and front plate(RAW POWER OUTLETS) ( MK cat no:- socket -W 26424 ,switch- W 26411A)

26.04 Bank of 2 Nos.6 Amps, 5-pin (230 Volts) single phase socket (Combination of Multipin) controlled by 6Amps single pole switch with 2 No ( MK cat no:- socket -W 26420 , switch- W 26401A)

26.05 1 no of TV Coaxial sockets with box ,front plate and fixing hardware's as required . (MK CAT NO:)

Supply ,Termination and fixing of Information outlet shuttered, ( RJ11 jack) with 2 Pair Power Cat DataGate Jack shuttered with including Face Plate, with level holders including Metal box ( MK Cat No:- )

16 Amps single pole switch in a Single box and front plate. (GEYSER SWITCH) ( MK cat no:- socket -)

1 Nos.6/16 Amps, 6-pin (230 Volts) single phase universal socket only (Combination of Multi-pin) withmetal box and front plate.(GEYSER SOCKET ) ( MK Cat no:- Socket -W 26424)

Supply and Installation of testing & Commissioning of 6 Person Carrying capacity suitable to lift up toG+4 level building with all necessary equipment, motor, gear box and supporting railing in side the liftrunning area. complete as required and installed in flush with wall including all fixing materials asrequired. It should meet all technical specification requirement and test reports.