Growth focused company producing customized blow-molded plastic containers
Approximately 3,900 employees
2002 Sales of $906.7 million
55 plants in 11 countries
Graham Packaging Company LP
Our situation in 1998
Excessive Spreadsheet Use Custom Core Application
Lack of Timely Information Cumbersome Core Applications
Data Integrity Concerns Year 2000 Issues
Lack of Technology Sharing Network Infrastructure
Limited End-User Access to Data
Linkage of Strategy to Budget
Policy and Procedure Discipline
Deployment of Best Practices
Reliance on Specific Personnel Centralization vs. Decentralization
Limited Detailed Production Information
Performance Management
Aging Hardware Platform
Why SAP?
CustomerFaster and more effective response to external customer needsProvide a competitive advantage
People / EnvironmentGreater response to internal customer needsEmployees become more valuable as they gain a greater understanding of ourbusiness through effective access to reliable information Less time reporting results and more time analyzing information to drive performance
Management Operate in a best practice environmentGreater flexibility in accessing and formatting information
GrowthAccommodate acquisitions efficientlyAccommodate organic growth with new plants and products produced globally
SAP R/3 Implementation
• Very Successful implementation– 10 months to build, test, and train– Rolled out to 31 plants in US and Canada all in 1 weekend in April
1999!– Not just one module but 8 (AM, HRPAY, PS, FI, MM, PP, SD, COPA)
• Implementations continue– 8 Countries (US, Canada, Mexico, France, Spain, Belgium, Brazil,
Argentina)– 51 Plants– 10 Modules (AM, HRPAY, PS, FI, MM, PP, SD, COPA, QM, AR)
• ONE Global Instance
SAP R/3 4.6B
Dell Servers running Windows NT 4.0
EMC SAN, approximately 500gig
DEV, QAS, PRD, EBP systems
SAP R/3 Landscape
Decentralized Procurement function
Hand written requisitions
PO Approval, Receipt, Invoice on same day
30 plants / 30 suppliers
Same supplier providing different discounts
No record of spend by material
Procurement before the e
Questions
Why do we have all these vendors?
Can’t we use an automated system?
How many checks under $1,000 do we cut?
Can’t the IT department help?
Why do we manually do requisitions?
Why aren’t we getting better discounts?
What is SAP doing for us?
A New VP of Global Sourcing
Procurement without the e
Decentralized to centralized purchasing
Limited spend data – surveys and countlesshours of research
Outsourcing to procurement firms
Consolidation and reduction of vendors
Consistent pricing/discounts at all plants
Hard dollar savings - $6 million in 2 years
Adding the e to Procurement
Implemented with an ASP provider in February 2001.
• No capital cost
• Low monthly fee vs high software costs
• Quick implementation
• Limited use of internal resources
• Gain process and compliance experience
Implementing an ASP
Implementation Process - 6 Weeks
Reviewed “as is” and created “to be”
processes
Handling of direct vs indirect materials
Data files from SAP
Integration – POs, POAs and ASNs using
IDOCs, conversion tables, eAdapter
Scenario testing
User training
Implementing an ASP
Problems
Multiple purchasing organization structures
Handling of account assignment data
Insufficient test environment
Limited control - sharing system with otherclients
Automate the payment process
Payment via Evaluated Receipt Settlement (ERS)
Firm and accurate catalog prices
Data provided by supplier on the ASN
POA and ASN is required before postingreceipt in SAP
Payment references invoice number
Why switch from ASP to SAP
ASP financial problems
ASP system problems
Language capabilities
Currency capabilities
Closer integration with SAP
Lower cost
Internal control
Implementing 3.5
Implementation Process - 6 Months
Hardware/Software SetupIntegration
• BugsEye with EBP• EBP with R/3
Loading of CatalogsSupplier Order & Response Center (ORC) SiteScenario Testing – EBP & ORCDocumentation – User & SupplierUser TrainingSupplier Training
Implementing 3.5
Challenges
Organization Structure
4-Level Approval
Override Product Category and GL Account
E-Mail Alerts
Interfacing with Vendors
Catalog Setup
Monitoring and approving catalog changes• eMerge• Access
Special request orders
PO, POA, COA and ASN process Order & Response Center site
Documentation and training
Order & Response CenterSupplier is a user of our SAP system.
Order & Response CenterCan view PO history in addition to sending POAs and ASNs. Also has access to SAP reports.
Order & Response CenterCan select multiple POs to POA or ASN without jumping back and forth between screens.
Order & Response CenterPOA and ASN screens look similar for easy use.
Graham Procurement after e
93 suppliers on-line
$310 million of spend on-line
87% of on-line spend paid via ERS
Substantial reduction in maverick spending
One shopping cart, one approval, multiple POs
No more paper requisitions
Complete and accurate spend data
Questions