implementation of life-cycle assessment in the...

29
Pavement Life-Cycle Assessment Symposium 2017 Champaign IL | April 12-13 2017 Implementation of Life-Cycle Assessment in the optimization of road pavement choice: comparative analysis based on a real case study Marco Pasetto Emiliano Pasquini Giovanni Giacomello and Andrea Baliello University of Padua, Padua, Italy Department of Civil Environmental and Architectural Engineering Andrea Baliello

Upload: others

Post on 17-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Pavement Life-Cycle Assessment Symposium 2017Champaign IL | April 12-13 2017

Implementation of Life-Cycle Assessment in the optimization of road pavement

choice: comparative analysis based on a real case study

Marco Pasetto Emiliano Pasquini Giovanni Giacomello and Andrea Baliello

University of Padua, Padua, ItalyDepartment of Civil Environmental and Architectural Engineering

Andrea Baliello

Page 2: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Introduction

LCA in road engineering

Research objectives

LCA methodology

Case Study

Life Cycle Inventory

Scenario hypothesis

Results and discussions

Conclusions

Contents1

2

3

4

6

a

b

c

5

Page 3: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Life CycleAssessmentEvaluation of the potential product/service impacts, considering

all the life cycle stages (design, construction, utilization,

maintenance and final disposal).

Valid support to the decision-making processes conditioning

the public policies and the industrial competitiveness.

Its main objectives are addressed to the:

� reduction of energy and resource consumptions;

� health improvements;

� environment saving.

Although without specific prescriptions (about methodology and

procedures), LCA is defined in ISO 14040 and ISO 14044 (ISO

2006a, b) standards.

1

Introduction 1

Page 4: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Life CycleAssessmentISO standards describe in detail principles, framework,

requirements and guidelines for the LCA, mainly including:

a) the goal and scope definition;

b) the Life Cycle Inventory (LCI) analysis phase;

c) the Life Cycle Impact Assessment (LCIA) phase;

d) the life cycle interpretation phase;

e) reporting and critical review of the LCA;

f ) limitations of the LCA; relationship between the LCA phases;

g) relationship between the LCA phases 2

Introduction 1

1 - Goal and scopedefinition

2 - Life Cycle Inventory analysis(LCI)

3 - Life Cycle Impact Assessment(LCIA)

4 - Life Cycle Interpretation

Goal and scopedefinition

Life Cycle Inventory(LCI)

Life Cycle Impact Assessment(LCIA)

Life cycle interpretation

Page 5: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

LCA in road engineering 2

3

Road constructionLCA in road engineering tries to evaluate the environmental impacts connected to transport

infrastructures, facing the most important problems related to the material type and its

transport, that strongly represent onerous items in road construction and maintenance.

LCA is utilized in decision procedures to control final impacts (costs and environmental

emissions) of road construction, management, maintenance and rehabilitation, as

example considering:

▪ alternative design hypothesis; ▪ marginal materials reutilization;

▪ construction equipment and techniques; ▪ effect of transportations;

▪ energy consumption levels; ▪ importance of maintenance activities;

▪ request of virgin materials; ▪ etc.

Page 6: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

4

The overall road life

cycle could be divided

in 5 main phases:

1. material production ;

2. construction ;

3. road use;

4. maintenance and

rehabilitation (disposal of old material,

production of new material,

transportation and laying

processes);

5. end-of-life (pavement demolition and

material disposal).

Virgin/recycled

material

Transport

Processing plant

(asphalt/concrete)

Transport

Material production phase

Road

construction

Construction phase

Virgin/recycled

materialTransport

Processing plant

(asphalt/concrete)

Transport Survey

Rehabilitation

works

Road

utilization

Utilization phase

Managment / maintenance phase

Demolition

works

End-of-life phase

Energy

Fuel

Energy

Fuel

Emissions

Emissions

Rec

ycle

d m

ater

ial

Emissions

Traffic

Workers

Machinery

Workers

Machinery

Energy

Fuel

Energy

Fuel

Wastes EmissionsWastes

EmissionsWastes

LCA in road engineering2

Page 7: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Road construction� Santero, Masanet & Horvath, 2011. Life-cycle assessment of pavements. Part I: Critical re-

view. Resources, Conservation and Recycling. 55: 801-809.

� Amini, Mashayekhi, Ziari & Nobakht, 2012. Life cycle cost comparison of highways with

perpetual and conventional pavements. Int. J. Pav. Engineering. 13(6): 553-568.

� Bryce, Katicha, Flintsch, Sivaneswaran & Santos, 2014. Probabilistic Life-Cycle Assessment as

Network-Level Evaluation Tool for Use and Maintenance Phases of Pavements. TRR. 2455.

� Butt, Mirzadeh, Toller & Birgisson, 2014. LCA for asphalt pavements: methods to calculate and

allocate energy of binder and additives. Int. J. of Pav. Engineering. 15(4): 290-302.

� Santos, Ferreira & Flintsch, 2015. A life cycle assessment for pavement management: road

pavement construction and management in Portugal. Int. J. Pav. Engineering. 16(4): 315-336.

� AzariJafari, Yahia & Amor, 2016. Life cycle assessment of pavements: reviewing research

challenges and opportunities. J. Cleaner Production. 112: 2187-2197.

LCA in road engineering 2

5

Page 8: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Study aims� Evaluating the validity of LCA in order to mitigate environmental

impacts, decrease costs and control energy consumption (fuel,

electrical energy, etc.).

� Determining the importance of maintenance policies and future

investments (definitely affecting costs and environmental

impacts).

� Contribute to enlarge the worldwide database about the

implementation of LCA for pavements.

Based on a real designed motorway in Italy, LCA analysis was

applied in order to compare alternative asphalt pavements (with

marginal materials) with respect to traditional (high-quality,

expensive) ones.

Research objective 3

6

Page 9: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

PaLATEPavement Life cycle Assessment Tool for Environmental and Economic Effects

LCA applicator (Excel tool) useful to assess the pavement and road life cycle

considering extraction, production, construction, maintenance and end-of-life.

Input structure

Divided into different sheets, each one able to collect input data/information

(engineering, environmental and economic-based) and return a wide range of output:

Design ► Initial construction ► Maintenance ► Equipment ► Unitary costs

Output structure

► Costs [material production, transportations, processes, equipment].

► Impacts

7LCA methodology 4

[energy (E), water consumption (WC), carbon dioxide (CO2), nitric oxide (NOx),

particulate matter (PM10), sulfur dioxide (SO2), carbon mono-oxide (CO), heavy metals

(Hg and Pb), hazardous waste generated (HWG), human toxicity potential cancer(HTPC) and human toxicity potential non-cancer (HTPNC)].

Page 10: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Case study 5

8

Case study is based on a real Italian road construction project, the A3 motorway from Salerno to

Reggio Calabria. Life Cycle Assessment was applied to a unitary motorway stretch (1000 m long) for a

total period of 20 years (from construction to end-of-life).

A semi-rigid pavement was designed calculating the

Equivalent Single Axle Load (ESAL) number during the

infrastructure life-time according with AASHTO method.

All data were collected from:

▪ Italian motorways company – “Autostrade per l’Italia”;

▪ asphalt concrete producers and transport companies;

▪ typical Italian price lists and specifications.

▪ 50 mm: porous wearing course M

▪ 70 mm: asphalt binder course T

▪ 150 mm: asphalt base course T

▪ 200 mm: cement sub-base course

▪ 200 mm: Unbound sub-basecourse

T With traditional binder M With polymer-modified binder

* Subgrades, drainages, tack coat, road markings and other

particular street furniture were not considered.

A3 motorway

Page 11: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Case study 5

Cross sectionStretch length: 1000 m

Two lanes per each direction

Paved emergency lane

Single lane width: 3.75 m

Emergency lane width: 3.00 m

Semi-width: 12.50 m

Total width: 25.00 m

Double New-Jersey separation

Border guard-rails3.75 m 3.00 m3.75 m0.70 m1.30 m

11.20 m

Lane Emergency lane

LaneLeft shoulder

0 1 2 3 4 5

New-Jersey device

* Embankments were not included in LCA analysis.

** The left shoulder was considered not paved.

9

Retainingdevice

Page 12: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

MaterialsTypical Italian road materials with verified properties

were considered to match the local specifications.

Data derived from quarries and plants close to the

construction site, asphalt concrete producers and

typical Italian price lists were obtained for:

▪ virgin aggregates;

▪ bitumen (traditional or polymer-modified);

▪ recycled materials (RAP);

▪ industrial by-products (steel slags).

ImpactsInput of data concerning transportations (by road only),

consumptions and emissions, regarding:

machinery performance ▪

fuel, water and energy consumptions ▪

truck capacities ▪

material densities ▪

emissions to air ▪

leachate ▪

Life cycle inventory a

10* Feedstock energy was not examined.

** Negligible emissions from paver machine were not accounted.

Page 13: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

CostsTypical Italian price lists gave single

prices of raw materials (for production,

construction and maintenance) and

processes. As examples:

▪ pavement laying cost;

▪ full depth reclamation cost;

▪ asphalt plant cost;

▪ machinery use cost.

Discount rate:actualization index of the overall costs of road

infrastructure (2 tested scene):

▪ BASE SCENE: 1.0 %

▪ ALTERNATIVE SCENE: 4.0 %

Company profit:

On the total cost of infrastructure: 23%

Life cycle inventory a11

Page 14: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

MaintenanceScheduled maintenance during pavement life-time (20 years from construction).

During the binder layer maintenance phase (milling and reconstruction), 30 % of RAP coming

from the milling of the same layer is expected to be used. RAP re-use can be carried out with a

hot recycling procedure: RAP is sent to plant and mixed with virgin aggregates and bitumen.

Scenario hypothesis b

* Calculation of approximate ESAL number (AASHTO method)Milling and re-construction of the layer

Years 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

* ESAL

0 27 993 000 60 445 000 98 066 000 141 679 000

12

Page 15: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Test

ed s

cena

rios

Scenario AThe use of virgin

aggregates only was supposed.

Transportation distance for supply was assumed up to

100 km.

A100 km

Virgin

Scenario BSteel slag and RAPwas used in partial

substitution of virgin aggregates.

Transportation distance for supply was assumed up to

100 km.

B100 km

Recycled

Scenario CThe use of virgin

aggregates only was supposed.

Transportation distance was assumed

up to 10 km (available in situ).

C10 km

Virgin

Scenario DSteel slag and RAPwas used in partial

substitution of virgin aggregates.

Transportation distance was assumed

up to 10 km (available in situ).

D10 km

Recycled

Scenario hypothesis b13

Page 16: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Scenario A | Virgin | 100 km

Production Transportation Process Total

E [MJ] 824 766 458 43 568 017 3 904 838 872 239 312

WC [kg] 275 762 7 421 367 283 550

CO2 [Mg] 45 118 3 257 29 48 404

NOx [kg] 289 093 173 527 6 750 469 370

PM10 [kg] 170 190 33 560 710 204 460

SO2 [kg] 6 293 294 10 412 446 6 304 152

CO [kg] 159 794 14 461 1 455 175 710

Hg [g] 1 065 32 2 1 099

Pb [g] 53 168 1 478 82 54 728

HWG [kg] 10 596 575 314 074 17 540 10 928 190

HTPC 174 183 222 1 569 208 0 175 752 430

HTPNC 150 792 239 042 1 954 641 048 0 152 746 880 089

Results and discussions c

Environmental impact results

Scenario B | Recycled | 100 km

Production Transportation Process Total

784 998 830 46 761 742 3 904 838 835 665 409

261 100 7 965 367 269 432

42 465 3 496 294 46 255

277 573 186 248 6 750 470 570

155 479 35 857 710 192 046

6 283 626 11 175 446 6 295 247

151 244 15 521 1 455 168 219

1 010 34 2 1 046

50 364 1 586 82 52 031

10 037 005 337 097 17 540 10 391 642

165 784 422 1 677 640 0 167 462 062

138 441 537 092 2 089 706 829 0 140 531 243 921

14

Page 17: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Scenario A | Virgin | 100 km

Production Transportation Process Total

E [MJ] 824 766 458 43 568 017 3 904 838 872 239 312

WC [kg] 275 762 7 421 367 283 550

CO2 [Mg] 45 118 3 257 29 48 404

NOx [kg] 289 093 173 527 6 750 469 370

PM10 [kg] 170 190 33 560 710 204 460

SO2 [kg] 6 293 294 10 412 446 6 304 152

CO [kg] 159 794 14 461 1 455 175 710

Hg [g] 1 065 32 2 1 099

Pb [g] 53 168 1 478 82 54 728

HWG [kg] 10 596 575 314 074 17 540 10 928 190

HTPC 174 183 222 1 569 208 0 175 752 430

HTPNC 150 792 239 042 1 954 641 048 0 152 746 880 089

Results and discussions c

Scenario B | Recycled | 100 km

Production Transportation Process Total

784 998 830 46 761 742 3 904 838 835 665 409

261 100 7 965 367 269 432

42 465 3 496 294 46 255

277 573 186 248 6 750 470 570

155 479 35 857 710 192 046

6 283 626 11 175 446 6 295 247

151 244 15 521 1 455 168 219

1 010 34 2 1 046

50 364 1 586 82 52 031

10 037 005 337 097 17 540 10 391 642

165 784 422 1 677 640 0 167 462 062

138 441 537 092 2 089 706 829 0 140 531 243 921

14

Environmental impact results� As expected, impacts generally decreased with the substitution of virgin aggregates with recycled materials.

� Since innovative production techniques of asphalt concrete were not used, slightly lower impact reductions in

comparison to those found in other bibliography demonstrated the cruciality of process in final impact results.

Page 18: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Scenario A | Virgin | 100 km

Production Transportation Process Total

E [MJ] 824 766 458 43 568 017 3 904 838 872 239 312

WC [kg] 275 762 7 421 367 283 550

CO2 [Mg] 45 118 3 257 29 48 404

NOx [kg] 289 093 173 527 6 750 469 370

PM10 [kg] 170 190 33 560 710 204 460

SO2 [kg] 6 293 294 10 412 446 6 304 152

CO [kg] 159 794 14 461 1 455 175 710

Hg [g] 1 065 32 2 1 099

Pb [g] 53 168 1 478 82 54 728

HWG [kg] 10 596 575 314 074 17 540 10 928 190

HTPC 174 183 222 1 569 208 0 175 752 430

HTPNC 150 792 239 042 1 954 641 048 0 152 746 880 089

Results and discussions c

Environmental impact results

Scenario B | Recycled | 100 km

Production Transportation Process Total

784 998 830 46 761 742 3 904 838 835 665 409

261 100 7 965 367 269 432

42 465 3 496 294 46 255

277 573 186 248 6 750 470 570

155 479 35 857 710 192 046

6 283 626 11 175 446 6 295 247

151 244 15 521 1 455 168 219

1 010 34 2 1 046

50 364 1 586 82 52 031

10 037 005 337 097 17 540 10 391 642

165 784 422 1 677 640 0 167 462 062

138 441 537 092 2 089 706 829 0 140 531 243 921

14

� As example, RAP use during maintenance and by-products (steel slags) reutilization reduced total requested

energy and water consumptions (less material disposals to landfill were needed).

� As expected, impacts generally decreased with the substitution of virgin aggregates with recycled materials.

� Since innovative production techniques of asphalt concrete were not used, slightly lower impact reductions in

comparison to those found in other bibliography demonstrated the cruciality of process in final impact results.

Page 19: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Scenario C | Virgin | 10 km

Production Transportation Process Total

E [MJ] 824 766 458 4 451 723 3 904 83 833 123 018

WC [kg] 275 76 758 367 276 887

CO2 [Mg] 45 118 333 294 45 745

NOx [kg] 289 093 17 731 6 750 313 573

PM10 [kg] 170 190 3 574 710 174 474

SO2 [kg] 6 293 294 1 064 446 6 294 804

CO [kg] 159 794 1 478 1 455 162 727

Hg [g] 1 065 3 2 1 070

Pb [g] 53 168 151 82 53 401

HWG [kg] 10 596 575 32 092 17 540 10 646 207

HTPC 174 183 222 241 144 0 174 424 366

HTPNC 150 792 239 042 300 374 143 0 152 092 613 184

Results and discussions c

Similar findings for Scenario C and Scenario D (transportation distance up to 10 km – material available in situ):

Scenario D | Recycled | 10 km

Production Transportation Process Total

781 227 517 4 006 379 3 904 838 789 138 734

261 100 734 367 262 200

42 564 322 294 43 180

280 836 17 152 6 750 304 737

155 510 3 400 710 159 620

6 544 939 1 029 446 6 546 414

151 338 1 429 1 484 154 251

1 011 3 2 1 016

50 372 146 84 50 602

10 038 761 31 044 18 109 10 087 914

166 126 114 236 209 0 166 362 32

139 049 945 940 294 227 423 0 139 344 173 364

15

Environmental impact results

Page 20: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Scenario C | Virgin | 10 km

Production Transportation Process Total

E [MJ] 824 766 458 4 451 723 3 904 83 833 123 018

WC [kg] 275 76 758 367 276 887

CO2 [Mg] 45 118 333 294 45 745

NOx [kg] 289 093 17 731 6 750 313 573

PM10 [kg] 170 190 3 574 710 174 474

SO2 [kg] 6 293 294 1 064 446 6 294 804

CO [kg] 159 794 1 478 1 455 162 727

Hg [g] 1 065 3 2 1 070

Pb [g] 53 168 151 82 53 401

HWG [kg] 10 596 575 32 092 17 540 10 646 207

HTPC 174 183 222 241 144 0 174 424 366

HTPNC 150 792 239 042 300 374 143 0 152 092 613 184

Results and discussions c

Similar findings for Scenario C and Scenario D (transportation distance up to 10 km – material available in situ):

Scenario D | Recycled | 10 km

Production Transportation Process Total

781 227 517 4 006 379 3 904 838 789 138 734

261 100 734 367 262 200

42 564 322 294 43 180

280 836 17 152 6 750 304 737

155 510 3 400 710 159 620

6 544 939 1 029 446 6 546 414

151 338 1 429 1 484 154 251

1 011 3 2 1 016

50 372 146 84 50 602

10 038 761 31 044 18 109 10 087 914

166 126 114 236 209 0 166 362 32

139 049 945 940 294 227 423 0 139 344 173 364

15

Environmental impact results

� about general impacts;

Page 21: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Scenario C | Virgin | 10 km

Production Transportation Process Total

E [MJ] 824 766 458 4 451 723 3 904 83 833 123 018

WC [kg] 275 76 758 367 276 887

CO2 [Mg] 45 118 333 294 45 745

NOx [kg] 289 093 17 731 6 750 313 573

PM10 [kg] 170 190 3 574 710 174 474

SO2 [kg] 6 293 294 1 064 446 6 294 804

CO [kg] 159 794 1 478 1 455 162 727

Hg [g] 1 065 3 2 1 070

Pb [g] 53 168 151 82 53 401

HWG [kg] 10 596 575 32 092 17 540 10 646 207

HTPC 174 183 222 241 144 0 174 424 366

HTPNC 150 792 239 042 300 374 143 0 152 092 613 184

Results and discussions c

Scenario D | Recycled | 10 km

Production Transportation Process Total

781 227 517 4 006 379 3 904 838 789 138 734

261 100 734 367 262 200

42 564 322 294 43 180

280 836 17 152 6 750 304 737

155 510 3 400 710 159 620

6 544 939 1 029 446 6 546 414

151 338 1 429 1 484 154 251

1 011 3 2 1 016

50 372 146 84 50 602

10 038 761 31 044 18 109 10 087 914

166 126 114 236 209 0 166 362 32

139 049 945 940 294 227 423 0 139 344 173 364

15

Similar findings for Scenario C and Scenario D (transportation distance up to 10 km – material available in situ):

Environmental impact results

� about general impacts;

� about energy and water consumptions.

Page 22: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

With regard to the use of

materials, initial

construction, maintenance

and end-of-life dismissions

phases presented

significant differences in

terms of environmental

impacts.

Environmental impact results

Results and discussions c16

Phasesof pavement

life

25 %

5 %

75%

Initial construction impact

Maintenance impact

End-of-life dismission impact

* According with other study:

� Processes and equipment involved in construction and

maintenance phases constituted the smallest contributions.

Page 23: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Transportation impacts

Distance: 100 km Distance: 10 km

Scenario A Scenario B Scenario C Scenario D

E [MJ] 43 568 017 46 761 742 4 451 723 4 006 379

WC [kg] 7 421 7 965 758 734

CO2 [Mg] 3 257 3 496 333 322

NOx [kg] 173 527 186 248 17 731 17 152

PM10 [kg] 33 560 35 857 3 574 3 400

SO2 [kg] 10 412 11 175 1 064 1 029

CO [kg] 14 461 15 521 1 478 1 429

Hg [g] 32 34 3 3

Pb [g] 1 478 1 586 151 146

HWG [kg] 314 074 337 097 32 092 31 044

HTPC 1 569 208 1 677 640 241 144 236 209

HTPNC 1 954 641 048 2 089 706 829 300 374 143 294 227 423

Material production

owned a marginal weight

in life cycle of road

pavement with respect to

the transportation

processes.

Environmental impact results

Results and discussions c17

Page 24: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

\ Transportation impacts

Distance: 100 km Distance: 10 km

Scenario A Scenario B Scenario C Scenario D

E [MJ] 43 568 017 46 761 742 4 451 723 4 006 379

WC [kg] 7 421 7 965 758 734

CO2 [Mg] 3 257 3 496 333 322

NOx [kg] 173 527 186 248 17 731 17 152

PM10 [kg] 33 560 35 857 3 574 3 400

SO2 [kg] 10 412 11 175 1 064 1 029

CO [kg] 14 461 15 521 1 478 1 429

Hg [g] 32 34 3 3

Pb [g] 1 478 1 586 151 146

HWG [kg] 314 074 337 097 32 092 31 044

HTPC 1 569 208 1 677 640 241 144 236 209

HTPNC 1 954 641 048 2 089 706 829 300 374 143 294 227 423

Material production

owned a marginal weight

in life cycle of road

pavement with respect to

the transportation

processes.

Environmental impact results

Higher specific gravity of steel slags burdens on the transportation costs;

for this reason, project implied only the use 30% of slags by the total

aggregate weight (to prevent the increasing of total impact).

� Significant concern of transportation process: great

impact reduction with available in situ materials.

� Transportation processes give a contribution close tothe 20% of the total impact.

Results and discussions c17

Page 25: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Scenario Acosts� During initial construction

phase, material costs were

greater with respect to the

equipment and worker ones.

� Vice versa, during

maintenance phase,

equipment and worker costs

prevailed.

� Since initial costs were the

same, alternative scene,

with a discount rate of 4.0 %,

obviously gave a significant

reduction in total costs due

to lower maintenance

expensiveness.

Construction costs: 21 511 453 €

Maintenance costs: 19 599 351 €

Total costs: 41 110 805 €

BASE SCENE

Discount rate: 1.0 %

41 mlnTotal cost

20 years

52%

48%

Initial construction cost

Maintenance cost

41 mln.Total cost

20 years

41 mlnTotal cost

20 years

61%

39%

35 mln.Total cost

20 years

Due to the exclusive use of natural aggregates, Scenario A costs were higher

because of the onerous activities connected to waste materials disposal

towards landfills.

Construction costs: 21 511 453 €

Maintenance costs: 13 488 463 €

Total costs: 34 999 917 €

ALTERNATIVE SCENE

Discount rate: 4.0 %

Results and discussions c

18

Page 26: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

B and D scenarios request lightly

reduced investments (with

respect to the scenario A) due to

slightly lower costs for marginal

material rehabilitation operations

in comparison with the use of

virgin aggregates

Difference are also related to the

contribution of onerous material

disposals during maintenance

activity.

Greater cost reductions were

otherwise connected to the

shorter distances for material

availabilities (C and D scenarios).

Percentages with respect to costs of scenario A.

Construction costs

Scenario B:

Scenario C:

Scenario D:

94%

90%

84%

Maintenance costs

Scenario B:

Scenario C:

Scenario D:

98%

95%

91%

Total costs

Scenario B:

Scenario C:

Scenario D:

97%

92%

87%

Results and discussions cBASE SCENE – Discount rate: 1.0 %

B, C, D costs

19

Page 27: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Construction costs

Scenario B:

Scenario C:

Scenario D:

94%

90%

84%

Maintenance costs

Scenario B:

Scenario C:

Scenario D:

97%

96%

93%

Total costs

Scenario B:

Scenario C:

Scenario D:

96%

92%

88%

Percentages with respect to costs of scenario A.

ALTERNATIVE SCENE – Discount rate: 4.0 %

20

Results and discussionsc

B, C, D costs

In analogy, effectiveness of

marginal material

rehabilitation (with lower

disposal costs) and reduction

of supply distance were also

identified in ALTERNATIVE

SCENE (with a discount rate

of 4.0 %)

Between BASE (1% discount

rate) and ALTERNATIVE

scenes (4 % discount rate), a

light decrease in

maintenance costs (thus in

total investments) with the

highest discount rate was

evinced.

Page 28: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Conclusions 621

� The LCA appeared to be a useful tool to check the suitability of projects, and, in

general, a successful way to support decision-making processes considering

environmental impact assessment and costs evaluation.

� An advanced LCA analysis, performed during design phases of infrastructures, is

definitely able to objectively and univocally state the best design and construction

alternative, evaluating the most (social and environmental) sustainable construction

and maintenance technologies for the correct integration of the work.

Conclusions

Page 29: Implementation of Life-Cycle Assessment in the ...publish.illinois.edu/lcaconference/files/2016/06/LCA_Presentation_AB_Baliello.pdfImplementation of Life-Cycle Assessment in the optimization

Thank for you attention

Questions?

University of Padua Padua ItalyDepartment of Civil Environmental and Architectural Engineering

Andrea [email protected]