Preparatory phase (3 months)
Aim : focused on top manager to :
1. Understand 5S- KAIZEN-TQM
concepts
2. Establish structure of 5 S
implementation
-
Steps Preparatory phase
1. Dissemination of 5 concepts
2. Training of management staff
3. Formulation of quality improvement team
4. Situation analysis of 5 activity
5. Selection of 3-5 areas
-
1-Dissemination of 5 concepts
Education true meaning of the 5 S
Wrong concept??????
True concept?????
Practiced daily to be a culture of health facility
-
2-Training of management staff
Basic concepts of 5 S-kaizen-TQM
Action plan development
Self monitoring and evaluation
-
3-Formulation of Quality Improvement Team (QIT)
Responsibilities of the QIT:
1. Conduct situation analysis
2. Train staff
3. Implement 5 S activities
4. Solving problem by KAIZEN approach
5. Provide technical advice to WIT
6. Review action plan according to situation analysis
7. Write progress report every 3 months
-
4-Situation analysis before 5 S activity
1. Taking pictures to all departments as a base line
for useful comparison and measure the progress
2. Observation and interview the staff are another
tool s in situation analysis
-
5-Selection of 3-5 areas
Criteria of selection:
1. Presence of Personal commitment
2. Situation need to be improved for better care
3. Section facing few problems to be easily managed
-
Introductory phase (6 months)
Training of staff
Work improvement team
Implementation of 5 S
Continuous improvement and standardize
-
Getting Started
Planning launches your 5S activity
Evaluating tells you what you need to do
Preparing gets you ready for
implementation
-
Planning Assemble a 5S Lead team (WIT)
Define the work area 5S boundaries
Assign work group members to their 5S areas
Install a 5S communication board
Determine 5S targets, activities, and schedule
Review/finalize plans with work group and site
leadership
-
6-Training all staff Everyone participation (successful key)
1. 5S KAIZEN-TQM concepts and tools
2. Situation analysis for each department
3. Work Improvement Team (WIT)
4. Development of an action plan with self monitoring
-
7-Work Improvement Team (WIT) Cooperation & Commitment (successful key)
1. Regular meeting (weekly)
2. Prepared agenda
3. Focused discussion
4. Encourage and support all the team
-
Evaluating Your Initial Situation
Prepare to take work area photos
Take work area photos
Evaluate current 5S Level of Achievement
-
Implementation phase (2 years)
Standardize
Sustain
Expansion of 5 S activities
KAIZAN activities
-
8-Practice the first 3 S Challenges (successful key)
1. Sorting by proper use of Red tag tool
2. Set in order by use can see, can takeout and can
return philosophy
3. Shine by preparing a cleaning schedule with
responsible person and exact time for continuous
practice
-
9-Practice the fourth S
Regular and Continuous practice (prevent relapses)
1. Schedule for doing
2. Development of SOPs
3. Use of checklist for each activity
-
10-Making 5 S culture
Good habits (successful key)
1. Good practices for patients care
2. Refreshment training to the staff
3. Awarding of good practice
4. Periodical meeting QIT-WIT
-
Preparing for Implementation
Obtain existing standards for color-coding
Decide on 5S color-coding
Prepare for Sorting
Prepare for Set
Prepare for Shine
Prepare for Standardizing
Prepare for Sustaining
-
Implementation of 5S activities
Conduct situation analysis of your hospital
visit all sections and units, and take photos before 5S
Select 2-3 pilot areas to implement S1-S3
create show that other sections can copy from the pilot
areas)
Develop checklist and monitoring tools
Important to measure changes
Share progress and changes of pilot areas with other
sections and units
-
Contents of progress report from
hospital
1. Composition of QIT members
2. Actual Implementation structure for QIPs with
organogram
3. Training records (type of training, number of trainees)
4. Self-evaluation results
5. Records and Good practice sheet
6. KAIZEN cases (if any)
-
Implementation of 5S activities
Seeing is believing! This will help to reduce
resistance
Expand areas to implement 5S step by step
Conduct regular monitoring and coaching
Keep all records of QIT and WITs activities
Utilize 5S tools effectively to enhance 5S activities
-
Maintenance phase (sustainability)
Continuous 5 S cycle
More KAIZAN activities
Refresher training
Awarding and motivation
-
Preparatory
phase
3 month
Introductory
Phase
6 month
Implementation phase
2 years
Maintenance
phase
On going
Situation analysis
Training of managers
Training of staff
Sorting Setting Shining
Standardizing Sustaining Expansion areas to practice 5S activities
Continue 5S
cycle
5S Phases
24
-
Expansion and sustainability mechanism
in a health facility
Training of
Trainers
Establishment
of QIT
In-hose
training
Practice 5S-KAIZEN
Monitoring
Internal evaluation
Coaching
Consultation visit
by MoHSW
Progress Report
Meeting
Establish Mechanism of generating ideas Learning each other Self evaluation Technical improvement Team work and ownership
development
25
External activities
-
10 steps for 5S implementation
Step 1: Dissemination (Sensitization) of 5S-KAIZEN-TQM concepts
Step 2: Provide 5S training to Hospital Management Team (HMT)
Step 3: Quality Improvement Team (QIT) should be established in a health facility for leadership and commitment for Quality improvement
Step 4: Conduct Situation Analysis (Problem finding + Solutions). Take photos of current situation as baseline data
Step 5: Identify the priority area(s) =Target area(s) to be improved based on the analysis
Step 6: Provide 5S training to staffs in the targeted area(s)
Step 7: Establish Work Improvement Team (WIT) is better be established at targeted area(s) for ownership of quality improvement Program and commitment
Step 8: Conduct Sort/Set/Shine activities at targeted area(s) to be the 5S showcase
Step 9:Proper practice of S1- S3 and develop standards and regulations for both administrative and technical aspects for Standardization of practice
Step 10: Work to improve the condition more & more. Repeat 5S cycles for Sustainability
On
go
ing
M&
E b
y Q
IT an
d W
IT
After TOT, trained personnel need to take this 10 steps
-
Action plan
Activity Objective Strategy Who will do
When will be started
When will be completed
Impact on customer
-
Key words of success There should be continued commitment and
support by top management
5 S implementation start with education and
training of all health workers
There are no observers everyone must participate
Practice 5S daily in order to achieve standard and
be as routine work
-
Thank you