impacts of reserve and fixed costs on greece’s day-ahead scheduling problem panagiotis andrianesis...
Post on 20-Dec-2015
220 views
TRANSCRIPT
Impacts of Reserve and Fixed Costs on Greece’s Day-Ahead Scheduling
Problem
Panagiotis Andrianesis a, George Liberopoulos a Kostis Sakellaris b,c, Andreas Vlachos b
a Department of Mechanical and Industrial Engineering, University of Thessaly, Volos, Greece
b Regulatory Authority for Energy, Athens, Greecec Athens University of Economics and Business
PROMITHEAS-2 International Black Sea Energy Policy Conference"Energy Investments and Trade Opportunities"
8,9 October 2008, Athens, Greece
1. IntroductionEuropean Directive 96/92/EC: liberalization and integration of the national electricity markets
GREECE: Regulatory Authority for Energy (RAE)Hellenic Transmission System Operator (HTSO)
Grid Control and Power Exchange Code for Electricity (2005): Day-Ahead Market Real Time Dispatch Imbalances Settlement Capacity Assurance Mechanism
1. Introduction
Day-Ahead Scheduling (DAS) Problem:basis for the wholesale electricity market
DAS: aims at minimizing overall cost of serving energy load, under conditions of reliable system operation, ensuring adequate reserves, i.e., a security-constrained unit commitment program, co-optimizing energy and reserves
2. Greece’s Electricity System
Type Number of units Capacity (MW)
Lignite 22 4808.10
Oil 4 718.00
Combined Cycle 5 1962.10
Natural Gas 3 486.80
Small Thermal 2 116.10
Hydro 39 3016.50
Renewables/Cogeneration >100 889.94
Total Capacity: 11997.54
Total Capacity (thermal plants): 8091.10
Generation mix
2. Greece’s Electricity SystemYearly load profile for 2007
2. Greece’s Electricity System
Frequency-related ancillary services (“reserves”):
Primary reserve requirement : 80 MW
Secondary reserve requirement : 150-300 MW
Tertiary reserve requirement: 300-600 MW
2. Greece’s Electricity SystemNorth: 2/3 of installed capacity
South: 2/3 of load
Transmission Constraint
2. Greece’s Electricity System
2-zone model : North – South
Producers face different Marginal Generating Prices, when the transmission constraint is activated
Suppliers always face a uniform System Marginal Price (SMP)
Incentives: installation of new generation near consumption
3. Day-Ahead Scheduling ProblemINPUTS: - Energy offers - Reserve offers- Fixed costs (start-up, shut-down, minimum-load)- System load- Reserve requirements- Transmission constraints- Units’ technical characteristics (technical minimum, technical maximum, maximum reserve availability, minimum up/down times, ramp up/down limits)
OUTPUTS:- Unit commitment- Energy and reserve scheduling for each hour of the next day
3. Day-Ahead Scheduling ProblemDAS problem formulation (MILP):
Variable cost coefficients
Continuous variables (energy, reserve)
Fixed cost coefficients
Integer variables (status, start-up,
shut-down)
overall variable costs
overall fixed costs+minimize
,u h x 0 , integeru hz
, ,
T T, , ,,
, ,
min { }u h u h
DAS u h u h u u hu h u h
f x z
c x d z
3. Day-Ahead Scheduling Problemsubject to:
, ,u h u h hu u
1 2A x A z a
, , , , ,u h u h u h u h u h 1 2B x B z b
h
,u h
0,0u ux x 0
,0u uz z u
• Market clearing constraints:
• Individual constraints:
• Initial conditions:
and
3. Day-Ahead Scheduling ProblemDAS problem formulation :
overall reserve cost
overall fixed costs
+minimize overall energy cost
+
start- up shut-down minimum-loadsubject to:
energy balancereserve requirements
market-clearing constraints
technical minimumtechnical maximummaximum reserve availabilityminimum up/down timesramp up/down limits
individual constraints
3. Day-Ahead Scheduling ProblemDAS problem formulation :
overall reserve cost
overall fixed costs
+minimize overall energy cost
+
start- up shut-down minimum-loadsubject to:
energy balancereserve requirements
market-clearing constraints
technical minimumtechnical maximummaximum reserve availabilityminimum up/down timesramp up/down limits
individual constraints
3. Day-Ahead Scheduling Problem 3.1 Impact of Reserve Offers
Questions: Pricing reserve as separate commodity ?
Priced reserve offers ?
Offers included in the objective function ?
Pricing scheme?
Impact on scheduling ?
Rules (price caps…) ?
3. Day-Ahead Scheduling Problem 3.1 Impact of Reserve Offers
Pricing schemes for reserve:1.Scheme based on shadow price:
a. Non-priced bids (sorting rule based on energy bids)b. Priced bids included in the objective function
2. Scheme based on highest bid accepted:a. Bids not included in the objective function (sorting rule
based on reserve bids)b. Bids included in the objective function
3.Pay-as-bid scheme:a. Bids not included in the objective function (sorting rule
based on reserve bids)b. Bids included in the objective function
3. Day-Ahead Scheduling Problem 3.2 Impact of Fixed Costs
Fixed costs introduce non-convexities Non existence of equilibrium prices in a Walrasian auction Relevant literature: O’Neill et al. (2002, 2005)
Hogan and Ring (2003) Bjørndal and Jörnsten (2004)
DAS problem: - Should fixed costs be included in the objective function or not? - Should producers be paid for their fixed costs? - If not paid, they must internalize fixed costs in their energy offers, distorting the SMP.
4. Illustrative Example8-unit example:
Type Unit Capacity(Technical maximum)
Technical minimum
Energy bid
Lignite u1 4000 2500 35
Oil u2 450 250 80
Gas u3 476 144 72
Gas u4 300 150 110
Gas u5 550 155 75
Gas u6 389 240 70
Gas u7 389 240 85
GT u8 141 0 150
Energy offers
4. Illustrative Example8-unit example:
Type Unit Reserve availability Reserve bid
Lignite u1 300 10
Oil u2 50 5
Gas u3 150 4
Gas u4 80 4.5
Gas u5 150 6
Gas u6 149 3.5
Gas u7 149 3
GT u8 141 2
Reserve offers
4. Illustrative Example8-unit example:
Unit Start-up/shut-down cost
Minimum-load cost
Minimum up/down time
Initial condition
u1 1 000 000 - 24 ON
u2 40 000 800 8 OFF
u3 16 000 550 8 ON
u4 30 000 1 000 16 OFF
u5 24 000 700 5 ON
u6 14 000 500 3 ON
u7 14 000 600 3 OFF
u8 5 000 200 0 OFF
Units’ data
4. Illustrative ExampleAdjusted demand (load curve)
Reserve requirement: 600 MW
4. Illustrative Example
DAS problem: modeled with mathematical programming language AMPL
solved with ILOG CPLEX 9.0 optimization software package
4. Illustrative ExampleEnergy prices (SMP) and Reserve Prices (RP) for different pricing schemes
4. Illustrative ExampleEnergy prices (SMP) and Reserve Prices (RP) for different pricing schemes
SMPs
RPs
4. Illustrative ExampleEnergy prices (SMP) and Reserve Prices (RP) for different pricing schemes
SMPs
RPs: shadow price scheme
RPs: highest bid accepted scheme
4. Illustrative Example
Unit Case 1a Case 1b Case 2a Case 2b Case 3a Case 3b
u1 2 636 000 2 662 820 2 647 990 2 650 650 2 636 660 2 650 650
u2 - 30 150 - 26 175 - 28 300 - 27 125 - 28 750 - 27 875
u3 - 3 002 19 935 -32 145 - 12 912 -12 135
u4 - - - - - -
u5 - 21 280 905 - 19 210 - 19 045 - 24 244 - 24 446
u6 20 155 28 475 20 074 20 880 15 340 16 431
u7 - 7 812 - 5 428 - 6 024 - 6 024 - 7 812 - 7 812
u8 22 701 44 133 15 910 25 380 6 768 6 768
Units’ net profits in €
4. Illustrative Example
Unit Case 1a Case 1b Case 2a Case 2b Case 3a Case 3b
u1 2 636 000 2 662 820 2 647 990 2 650 650 2 636 660 2 650 650
u2 - 30 150 - 26 175 - 28 300 - 27 125 - 28 750 - 27 875
u3 - 3 002 19 935 -32 145 - 12 912 -12 135
u4 - - - - - -
u5 - 21 280 905 - 19 210 - 19 045 - 24 244 - 24 446
u6 20 155 28 475 20 074 20 880 15 340 16 431
u7 - 7 812 - 5 428 - 6 024 - 6 024 - 7 812 - 7 812
u8 22 701 44 133 15 910 25 380 6 768 6 768
Units’ net profits in €
4. Illustrative Example
Unit Case 1a Case 1b Case 2a Case 2b Case 3a Case 3b
u1 28.562 28.583 28.692 28.721 28.570 28.721
u2 - 7.947 - 6.899 - 7.459 - 7.149 - 7.578 - 7.347
u3 - 0.486 3.163 - 0.005 0.023 - 2.090 - 1.925
u4 - - - - - -
u5 - 4.369 0.186 - 3.944 - 3.910 - 4.977 - 5.019
u6 4.193 6.080 4.176 4.459 3.191 3.509
u7 - 8.138 - 5.654 - 6.275 - 6.275 - 8.138 - 8.138
u8 N/A N/A N/A N/A N/A N/A
Units’ net profits in €/MWh
4. Illustrative Example
Units may incur losses even if they get paid for their fixed costs
WHY?
Need for a bid/cost recovery mechanism
4. Illustrative Example
CaseOverall Energy
Payments
Overall Reserve
Payments
Overall Fixed Costs Payments
1a 7 281 950 96 600 158 200
1b 7 299 050 187 800 (as 1a)
2a (as 1a) 110 400 (as 1a)
2b (as 1b) 108 000 (as 1a)
3a (as 1a) 65 032 (as 1a)
3b (as 1b) 64 722 (as 1a)
Overall Payments
Reserve Payments: range from 0.9 – 2.6 % of energy paymentsFixed Costs Payments: about 2.2 % of energy payments
4. Illustrative Example
Type Unit Fixed costs includedfor all cases
Fixed costs excluded for all cases except for 3a
Lignite u1 1-24 1-24
Oil u2 10-24 10-22
Gas u3 1-24 1-24
Gas u4 - -
Gas u5 1-24 1-24
Gas u6 9-24 9-24
Gas u7 11-14 11-14
GT u8 1-24 1-24
Unit Commitment
5. Summary and Conclusions
Sketch of Greece’s electricity system
Simple model of the Day-Ahead Scheduling problem
Emphasis on: frequency-related ancillary services (“reserves”) fixed costs (start-up, shut-down, minimum-load)
Various reserve pricing schemes: shadow price highest bid accepted pay-as bid
Illustrative 8-unit example
5. Summary and Conclusions
Units may incur losses through DAS participation
Bid/cost recovery mechanism is needed
Reserve payments contribute to the same direction
DAS: very complicated problem
due to energy – reserve interaction, and
non-convexities introduced by fixed costs
careful and incentive-compatible design is needed
Questions ?