impacts of deferred in estment on impacts of deferred ...cost escalation $36 9 2 4 year delay in...

27
Impacts of Deferred In estment on Impacts of Deferred Investment on Capital and Operating Budgets Executive Summary Executive Summary Dr. Robert Paaswell Distinguished Professor of Civil Engineering CCNY Distinguished Professor of Civil Engineering, CCNY Director, University Transportation Research Center Dr. Todd Goldman Assistant Director, University Transportation Research Center December 13, 2004 1

Upload: others

Post on 11-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Impacts of Deferred In estment on Impacts of Deferred Investment on Capital and Operating Budgets

Executive SummaryExecutive Summary

Dr. Robert PaaswellDistinguished Professor of Civil Engineering CCNYDistinguished Professor of Civil Engineering, CCNYDirector, University Transportation Research Center

Dr. Todd GoldmanAssistant Director, University Transportation Research Center

December 13, 2004

1

Page 2: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Purpose and Method

Purpose• To illustrate how deferred capital investments impact the MTA’s capital and

operating budgets.Methodology

• Met with agency capital planning staff to discuss purpose of the study and identify potential case studies.

• Analyzed proposed case studies to examine feasibility and data availability; t f th d t tsent further data requests.

• Discussed with maintenance, operations, and/or capital planning staff at each agency draft assumptions and conclusions for the case studies.R fi d ti t d d l t f l i• Refined estimates and development of conclusions.

2

Page 3: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Deferred Capital Investment Impacts on Operating and Capital CostsImpacts on Operating and Capital Costs

• “Reliability tax” – Routine and emergency repairs become increasingly f t it l i t t i d f d ( b id d k h bilit ti )frequent as capital reinvestment is deferred (e.g. bridge deck rehabilitation).

• “Efficiency tax” – Work is needlessly complicated or resources wasted by obsolete facilities, equipment, and spatial constraints (e.g. bus and rail car maintenance facilities and substation replacement)maintenance facilities and substation replacement).

• “Redundancy tax” – Extra requirements for reserve capacity (larger fleet spare ratios, additional crews) are needed to keep the system operating at a given performance level (e.g. rail car lifecycle maintenance).p ( g y )

• “Capital tax” – The degree of disrepair accelerates over time, or repeated capital investments that otherwise might be avoided remain necessary (e.g. bridge deck rehabilitation and concrete tie replacement).

• Cost escalation – Inflationary pressures increase the cost of a project over time, even if there is no change in its scope. These costs typically grow slightly faster than the CPI. MTA’s revenues do not necessarily grow as fast as CPI inflation so even modest increases in “real” cost can impact the agency

3

inflation, so even modest increases in real cost can impact the agency.

Page 4: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Deferred Capital Investment Long-Term ImpactsLong-Term Impacts

OperationsMaintenanceCapital: System Improvement

Leve

ls

Capital: System ImprovementCapital: Normal ReplacementCapital: State of Good Repair

Premium paid for not being in good repair

Fund

ing

L

Optimum level of capital and operating spending

Max. Sustain-able Level of Capital Spending

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40

Years

Rising costs squeeze budgets for normal replacement andCuts in NR funding create

SGR AchievedReduced expenses enable system

improvements to

4

for normal replacement and system improvement

Cuts in NR funding create need for SGR investments

pbegin

Page 5: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Case StudiesCase StudiesR lt f C t B fit A lResults of Cost-Benefit Analyses

Useful Budget

Project NameLife

(Years)Capital

Cost ($M)Scenario Tested

Impact vs. Capital Cost

Railcar Lifecycle Maintenance Investments 25 $167.6 No Build 252%Jamaica Bus Depot Replacement 100 $130.0 5-Yr Delay 23%yCross Bay Bridge Deck Rehabilitation 50 $48.8 9-Yr Delay 547%Verrazano Bridge Deck Replacement 50 $165.0 2-Yr Delay 57%Commuter Rail Power Distribution 35 $207.9 5-Yr Delay 31%Commuter Rail Concrete Tie Installation 50 $116 2 No Build 214%Commuter Rail Concrete Tie Installation 50 $116.2 No Build 214%These cases are not directly comparable, but illustrate that SGR and NR investments bring long-term savings across a variety of capital systems.

5

Page 6: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Railcar Lifecycle Maintenance Key assumptionsKey assumptions

Scenario Tested: Modify and outfit new and existing facilities to enable the transition to full a Lifecycle Maintenance Program vs maintain existing practicetransition to full a Lifecycle Maintenance Program vs. maintain existing practice

Key Assumptions:• Business-as-usual (BAU) assumes periodic inspection and maintenance costs are 80%

of those under LCM; without LCM major costs increase 6% annually; other costs grow ; j y; gwith inflation.

– These BAU assumptions produce a net cost escalation of 3.9%. Historic LIRR cost escalation has been 5%, so these assumptions are conservative.A sensitivity analysis was conducted on the assumed cost of major repairs– A sensitivity analysis was conducted on the assumed cost of major repairs.

• LCM scenario uses LIRR’s detailed cost projections over 25 years.• Worker availability and fringe benefits add 62% to the nominal cost of labor.• LCM enables spare ratio to be reduced from 13.7% to 11.1%, resulting in a future fleetLCM enables spare ratio to be reduced from 13.7% to 11.1%, resulting in a future fleet

reduction of 32 cars for this study (a.k.a. the “redundancy tax”).• Not included: benefits from safer and better working conditions, more reliable service,

and reduced need for train-moving crews.

6

Page 7: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Railcar Lifecycle Maintenance Cost benefit analysis resultsCost-benefit analysis results

Impact Net Year-of-Expenditure Costs ($M) Description

“Reliability Tax” $317.5 Difference between higher unscheduled major repairs and lower scheduled maintenance.

“Efficiency Tax” $0.0

“R d d T ” $249 0 C it l d ti t f l fl t“Redundancy Tax” $249.0 Capital and operating costs from larger fleet.

“Capital Tax” -$144.2 Capital savings from not building new maintenance facility.

Cost Escalation $0.0

• Although periodic inspection and maintenance costs are 20% higher LCM saves on

$

Net Budgetary Impact $422.2 Net cost of business-as-usual scenario

• Although periodic inspection and maintenance costs are 20% higher, LCM saves on unscheduled major repairs and a lower spare ratio.

• The LCM capital investments yield savings of 252% of the capital cost.• Including inflation and borrowing costs, investing now has a $35.6 million present value

b fit (i 2005 d ll )

7

benefit (in 2005 dollars).

Page 8: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Railcar Lifecycle Maintenance Cost benefit analysis results

Cumulative Nominal Costs$11 000

Cost-benefit analysis results

(Capital and Maintenance Costs)

$8,000

$9,000

$10,000

$11,000

Lifecycle Maintenance Program

Business As Usual Maintenance Program

Net cost of delay $422M by 2030.

( p )

$5,000

$6,000

$7,000

$8,000

Cos

ts ($

M)

By 2030, over $95 million savings annually (15.3% over current practices)

$2,000

$3,000

$4,000

Tota

l

By 2025, all capital costs are recovered.

$0

$1,000

2005 2010 2015 2020 2025 2030

Year B 2016 ann al

8

Year By 2016, annual savings exceed expenditures.

Page 9: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Jamaica Bus DepotKey assumptionsKey assumptions

Scenario Tested: Project is deferred 5 years to the next capital plan.

K A tiKey Assumptions:• The new Jamaica Depot would match the system’s highest-performing depots in

terms of shifting costs and labor costs for bus maintenance.

• The new facility would serve 250 vehicles drawing 191 from the existing Jamaica• The new facility would serve 250 vehicles, drawing 191 from the existing Jamaica Depot, 29 from Queens Village, and 30 from Casey Stengel.

• In the absence of this investment, there would be no deterioration of existing conditions at Jamaica Depot

• Useful life of the facility is 100 years

Not included in this analysis:• Improved working conditions for MTA employeesImproved working conditions for MTA employees

• Reduced maintenance costs for deteriorating Jamaica facility

• Avoided costs of handling hybrid-engine vehicles.

• Potential that improved maintenance and vehicle storage will reduce lifecycle costs

9

• Potential that improved maintenance and vehicle storage will reduce lifecycle costs

Page 10: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Jamaica Bus DepotCost benefit analysis resultsCost-benefit analysis results

Impact Net Year-of-Expenditure Costs ($M) Description

“Reliability Tax” $0.0

“Efficiency Tax” $9.3 Reduced bus shifting needs, and reduced time per maintenance task.

“R d d T ” $0 0“Redundancy Tax” $0.0

“Capital Tax” $0.0

Cost Escalation $20.7 Five-year delay in construction and land acquisition.

• Building the depot now saves $30 million (in current-year dollars) compared with

y y q

Net Budgetary Impact $30.0 Net cost of five-year delay

Building the depot now saves $30 million (in current year dollars) compared with delaying the investment for five years.

• A 5-year delay effectively adds 23% to the capital cost of pursuing the project now.

10

Page 11: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Jamaica Bus DepotCost benefit analysis results

Cumulative Nominal Costs$350

Cost-benefit analysis results

(Capital and Maintenance Costs)

$300

$350

Proposed Project

Five-Year DelayNet cost of delay $30 0M

( p )

$200

$250

osts

($M

)

$30.0M5-year delay

$100

$150

Tota

l Co

$0

$50

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

11

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Year

Page 12: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Cross Bay Bridge Deck Rehab Key AssumptionsKey Assumptions

Scenario Tested: Current proposal vs. beginning project 9 years earlier ( t ti j t i 2006 i tl b i id d i 1997(constructing project in 2006 as is currently being considered vs. in 1997 as originally proposed).

Key Assumptions:f f• Timely completion of the original repaving and waterproofing project would

have prevented the subsequent expansion in the scope of work needed.

• All maintenance costs in excess of the average maintenance costs for a bridge this size are due to the deferred maintenancebridge this size are due to the deferred maintenance.

• No social costs from the increased potholes and duration of construction are included in the cost-benefit analysis.

12

Page 13: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Cross Bay Bridge Deck Rehab Cost benefit analysis resultsCost-benefit analysis results

Impact Net Year-of-Expenditure Costs ($M) Description

“Reliability Tax” $1.1 Increased maintenance and emergency repairs.

“Efficiency Tax” $0.0

“R d d T ” $0 0“Redundancy Tax” $0.0

“Capital Tax” $38.7 Increased project scope.

Cost Escalation $2.3 Nine year delay in construction.

f f

y y

Net Budgetary Impact $42.2 Net cost of nine-year delay.

• Accounting for inflation and borrowing costs, investing in this project in 1997 would have had a $34.1M present value benefit (in 2005 dollars).

• The 9-year delay effectively added 548% to the original capital cost of the project.

13

Page 14: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Cross Bay Bridge Deck Rehab Cost benefit analysis results

Cumulative Nominal Costs

Cost-benefit analysis results

(Capital and Incremental Maintenance Costs)

$50

$60

Originally Proposed

9 Year Deferral

(Capital and Incremental Maintenance Costs)

$30

$40

osts

($M

)

9-Year Deferral

Net cost of delay

$10

$20

$

Tota

l Co y

$42.2M

$0

$10

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

14

Year

Page 15: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Verrazano Deck ReplacementKey assumptionsKey assumptions

Scenario Tested: Project is deferred 2 years (begin construction in 2010 instead of 2008).

Key Assumptions:• Postponing this project will delay four other projects by 2-4 years.• This delay will require the scope of another project – rehabilitation of the

Lower Level deck (VN-80B) – to be expanded into a full deck replacement project. This will roughly double its cost.

• Annual maintenance costs for Upper Level deck are $6 million per year• Annual maintenance costs for Upper Level deck are $6 million per year higher than they would be for a facility in a state of good repair.

15

Page 16: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Verrazano Deck Replacement Cost benefit analysis resultsCost-benefit analysis results

Impact Net Year-of-Expenditure Costs ($M) Description

“Reliability Tax” $12.0 Additional maintenance and emergency repairs.

“Efficiency Tax” $0.0

“Redundancy Tax” $0.0

“Capital Tax” $45.0 Increase in project scope for VN-80B.

Cost Escalation $36 9 2 4 year delay in construction

f $

Cost Escalation $36.9 2-4 year delay in construction.

Net Budgetary Impact $93.9 Net costs of two-year delay.

• Including inflation and borrowing costs, investing now has a $18 million present value benefit (in 2005 dollars).

• 2-year delay effectively adds 57% to the capital cost of the project.

16

Page 17: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Verrazano Deck ReplacementCost benefit analysis resultsCost-benefit analysis results

Cumulative Nominal Costs(Capital and Incremental Maintenance Costs)

$600

$700

Implementation as Proposed

Two-Year Deferral

Net cost of delay $94M

( p )

$400

$500

Cos

ts ($

M)

$200

$300

Tota

l C

$0

$100

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

17

Year

Page 18: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Commuter Rail Power DistributionKey assumptionsKey assumptions

Scenario Tested:.Project deferred by five years.Key Assumptions:Key Assumptions:

• Capital funds expended at constant rate, and benefits phased in proportionally to expenditure of funds.

• Modernization of substations allowed the elimination of 56 substation operator positions, saving $2.65 million per year.

• Energy savings assumptions:• Substations are spaced evenly over the 56 miles of the project• Third rail resistance dropped from 0.0125 to 0.0038 ohms/1000 ft• Power requirements per car range from 250 kW when idle to 640 kW at

full speed.• Acceleration and deceleration each take 40 seconds; dwell time at

stations is 45 seconds.• Delay of project assumed not to affect quantity of service provided.

18

Page 19: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Commuter Rail Power Distribution Cost benefit analysis resultsCost-benefit analysis results

Impact Net Year-of-Expenditure Costs ($M) Description

“Reliability Tax” $0.0

“Efficiency Tax” $30.8 Higher personnel and energy costs.

“Redundancy Tax” $0.0

“Capital Tax” $0.0

Cost Escalation $33 1 5 year delay in constructionCost Escalation $33.1 5-year delay in construction.

Net Budgetary Impact $63.9 Net costs of 5-year delay.

• Including inflation and borrowing costs, investing in the project when MTA did had a $10.8 million present value benefit (in 2005 dollars), compared with a 5-year delay.

• Five-year delay effectively adds 30.7% to the capital cost of the project.

19

Page 20: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Commuter Rail Power DistributionEffects of Deferral

Cumulative Nominal Costs$300

Effects of Deferral

(Capital and Incremental Operating Costs)

$250

$300

Net cost of delay $63.9M

$150

$200

Cos

ts ($

M)

$50

$100

Tota

l C

Built as Planned

$0

$50

1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997

Y

5-Year Delay

20

Year

Page 21: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Concrete Tie Installation Key assumptionsKey assumptions

Scenario tested: Continue with wood tie replacement cycle vs. install concrete ties.Key Assumptions:

• Analyzed generic 1-mile project, based on average system-wide installation costs

• In wood tie replacement case, rails are replaced in Year 1. Concrete ties replacement has a positive NPV as long as the rails on wood ties need replacement by Year 20.

• Costs and benefits not included:– Replacing broken or flawed rails– Track outages for maintenance– Schedule changes and busing programs– Purchasing, maintaining, or leasing equipment – Improved track quality

Hi h t f d ti l t i hi h l

21

– Higher average costs of wood tie replacement in high-volume areas

Page 22: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Concrete Tie Installation Cost benefit analysis resultsCost-benefit analysis results

Impact Net Year-of-Expenditure Costs ($M) Description

“Reliability Tax” $0.0

“Efficiency Tax” $19.9 Greater frequencies for unscheduled tasks (rail, weld, surfacing for wood ties; surfacing for concrete ties).

$“Redundancy Tax” $0.0

“Capital Tax” $41.5 Lower costs for scheduled tasks (just ties for wood ties; ties, rail, and welds for concrete ties).

Cost Escalation $178.2 Rising costs over 50 years of ongoing capital and i t kCost Escalation $178.2 maintenance work.

Net Budgetary Impact $239.7 Average cost of using wood ties instead of concrete

• Including inflation and borrowing costs, conversion of 56 miles to concrete ties has a net present benefit of $10.2 million.

• This savings represents 214% of the capital costs of the proposed investment..

22

Page 23: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

Concrete Tie Installation Cost benefit analysis results

Cumulative Nominal Costs$8 0

Cost-benefit analysis results

(Capital and Maintenance Costs)

$6.0

$7.0

$8.0

Concrete Ties + Rails, Welds, Surfacing

Wood Ties + Rails Welds Surfacing

( p )

$4.0

$5.0

Cos

ts ($

M) Wood Ties + Rails, Welds, Surfacing

Net cost of delay $4.3M

$1 0

$2.0

$3.0

Tota

l C

$0.0

$1.0

2004 2009 2014 2019 2024 2029 2034 2039 2044 2049 2054Y

23

Year

Page 24: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

ConclusionsFocusing only on internal budgetary benefits, the case studies illustrated how timely capital investments:

• Improve support facilities like shops and depots enabling more efficientImprove support facilities like shops and depots enabling more efficient operations and lower maintenance costs.

• Arrest structural deterioration thereby lowering maintenance costs and averting more expensive replacement projects.g p p p j

• Upgrade infrastructure such as power and track improving service, reducing operating and maintenance costs, preventing costly disruptions in service.

I i h i l ill hInvestment in the core capital program now will ensure that…• MTA will have even more capital funds for future discretionary investments.• MTA’s operating units can continue their efforts to improve productivity.• MTA will have the basic infrastructure in place to take advantage of the full

benefits of “system improvement” investments.• The public will see continuous improvement in the quality of MTA’s services.

24

p p q y

Page 25: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

ConclusionsThe estimates in this study are conservative. They do not include:

• Key internal benefits that could not be quantified due to data limitations.• Benefits to MTA customers.• Benefits to region more generally.• Secondary effects of customer and social benefits on MTA revenues.y

Despite these conservative assumptions, the study found that good repair delivers higher performance at a lower price. g p p

• Failing to reinvest in the system costs more in the long run. • Minimizing long-run capital and operating costs requires analysis of the

optimal reinvestment schedules for each asset categoryoptimal reinvestment schedules for each asset category.• Reinvesting below these levels damages the system’s quality, efficiency, and

reliability, raising costs for both the agency and its customers.

25

Page 26: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

ConclusionsMTA and the operating agencies will have a continuing need for strategic analysis of capital planning proposals.• In 1981, Richard Ravitch said “operating budgets are inexorably intertwined with

the requirements of capital replenishment.” This remains is as true as ever. • Ties between operating and capital programming need strengthening.• This requires the tracking of key operating data across the full range of asset

categories, tied to key policy variables to facilitate analysis.• But it is critical to recognize that many projects cannot be analyzed in isolation –

they often have strategic interrelationships that must be analyzed on a programmatic basis:

• A group of subprojects may all need to be completed to fulfill a single f fcommon strategic objective and provide significant benefits.

• But individually, some may not appear beneficial if the analysis is drawn too narrowly.

26

Page 27: Impacts of Deferred In estment on Impacts of Deferred ...Cost Escalation $36 9 2 4 year delay in construction f$ Cost Escalation $36.9-4 year delay in construction. Net Budgetary Impact

RecommendationsMTA should incorporate into its capital planning and its daily operations a more strategic approach to asset management.

• Asset management systems provide a framework that seeks optimum benefits at minimum cost.

• They help prioritize investments, reduce risk, communicate value, and ensure th t i t t d i i ti d t th i ti ' i ithat investment decisions are tied to the organization's mission.

• The quality and effectiveness of asset management efforts depends on the quality of information available on direct and indirect costs, benefits, and risks.

MTA capital planning should assess a wide range of project benefits:• Operating and budget impacts

• Risk reduction

• User benefits

For these analyses to be useful in the capital planning process, operating agencies need to track costs and performance more systematically and creatively

27

agencies need to track costs and performance more systematically and creatively.