impact of pv on the gb generation and transmission system · •solar: aggregated from 11 sub-...
TRANSCRIPT
Impact of PV on the GB Generation and Transmission System
Yutian Zhou*, Lingxi Zhang, Pierluigi Mancarella and Joseph Mutale
Power and Energy Division
School of Electrical and Electronic Engineering
The University of Manchester
Contents Impact on the GB Generation System 3
- Generation model - Assessment methodology - Findings and impacts
Impact on the GB Transmission System 11 - Transmission model - Assessment methodology - Findings and impacts
Contribution from PV to the Security of Supply 19 - Adequacy assessment model - Assessment methodology - Findings and impacts
Summary 27
WISE-PV Stakeholder Workshop 20 September 2016, London 2
Impact on the GB Gen. Sys.: Model (1/3)
•Nuclear, coal, gas (CCGT) & biomass •Pumped-hydro plants as system operator dispatched storage for providing generation reserve
•Five different scenarios for the mix of different generation technologies (referred to as S1 to S5 later)
Conventional Generation
WISE-PV Stakeholder Workshop 20 September 2016, London 3
2015: 63.6 GW
Conventional Generation Mix in S1 (in % of total conventional capacity)
2035: 68.3 GW
Impact on the GB Gen. Sys.: Model (2/3)
•Wind: aggregated from 39 representative wind farms (on-/off-shore) with different wind speed profiles
•Solar: aggregated from 11 sub-national regions with different solar irradiance profiles
Renewable Generation
WISE-PV Stakeholder Workshop 20 September 2016, London 4
Impact on the GB Gen. Sys.: Model (3/3)
•The National Demand (ND) from National Grid as primary data source
•EHP profiles created by a detailed technical model for 11 sub-national regions
•EV profiles created based on the EV profile from the Future Energy Scenario, National Grid
•Consumer-owned batteries profiles created by a detailed battery model
Demand
WISE-PV Stakeholder Workshop 20 September 2016, London 5
Half-hourly Index
0 4380 8760 13140 17520
% o
f Ins
talle
d P
V C
apac
ity
-0.4
-0.2
0
0.2
0.4
0.6
Impact on the GB Gen. Sys.: Method A deterministic unit commitment(UC) model is adopted here, which features Mixed Integer Linear Programming (MILP) algorithm.
WISE-PV Stakeholder Workshop 20 September 2016, London 6
Inputs: characteristics of conventional generators and storage, time series profiles of renewable generation, demand (incl. EV & EHP) and consumer-owned batteries, and requirements of generation reserve
Optimisation: centralised generation scheduling using cluster-technique for different generation technologies with half hourly
resolution
Outputs: schedule of the capacities of conventional generation technologies taking account of the economic cost and technical
constraints, energy production of different generation technologies, and curtailments of wind and PV, etc.
Impact on the GB Gen. Sys.: Findings (1/3) Energy production from different generation technologies
WISE-PV Stakeholder Workshop 20 September 2016, London 7
S1 in 2015 S2 – S5 in 2015
S1 in 2035
S2 in 2035 S3 in 2035
S4 in 2035 S5 in 2035
Impact on the GB Gen. Sys.: Findings (2/3) Demand not supplied
2035 S1 S2 S3 S4 S5
Annual Energy Not Supplied
(% of ATEC*) 0.004 0.042 0.004 0.084 0.018
Maximum Demand Not Supplied
(GW) 3.3 8.2 3.9 10.6 6.8
Total Hours with Demand Not
Supplied (hours) 7 32.5 7.5 103 34.5
*ATEC stands for Annual Total Energy Consumption.
WISE-PV Stakeholder Workshop 20 September 2016, London 8
Impact on the GB Gen. Sys.: Findings (3/3) Curtailment of PV generation
2035 S1 S2 S3 S4 S5
Annual Energy Curtailed
(% of AEA) 0.4 0.4 0.7 1.2 1.6
Maximum Power
Curtailed (GW)
6.4 8.4 11.6 14.5 14.8
Total Hours with
Curtailment (hours)
30 62 89 119 158
*AEA stands for Annual Energy Available.
WISE-PV Stakeholder Workshop 20 September 2016, London 9
Impact on the GB Gen. Sys.: Impacts 50 GW PV Integration
•PV would contribute about 9% of the future energy production in the GB power system.
Infrequent Demand Not Supplied •On condition that all conventional power plants are perfectly reliable, the future GB system will face a challenge of encountering generation capacity deficiency infrequently throughout the year. However, no substantial energy shortage would be expected.
Curtailment of PV Generation •The PV curtailment is attributed to either the minimum stable generation of convention generation, or the insufficiency of conventional generation capacity to provide reserve.
WISE-PV Stakeholder Workshop 20 September 2016, London 10
Impact on the GB Trans. Sys.: Model (1/4)
WISE-PV Stakeholder Workshop 20 September 2016, London 11
A reduced 29-Bus representative GB transmission network
Impact on the GB Trans. Sys.: Model (2/4)
WISE-PV Stakeholder Workshop 20 September 2016, London 12 12
A reduced 29-Bus representative GB transmission network
2015 2035
Impact on the GB Trans. Sys.: Model (3/4)
WISE-PV Stakeholder Workshop 20 September 2016, London 13 13
A reduced 29-Bus representative GB
transmission network Representative solar regions
Impact on the GB Trans. Sys.: Model (4/4)
WISE-PV Stakeholder Workshop 20 September 2016, London 14 14
39 representative wind farms:
- 25 offshore - 14 onshore
A reduced 29-Bus representative GB
transmission network
Impact on the GB Trans. Sys.: Method The classic linear optimal power flow (OPF) is applied in the assessment.
WISE-PV Stakeholder Workshop 20 September 2016, London 15 15
Inputs (from the UC model): generation online/offline schedule, locations of different generation technologies across the network, and
time series of system aggregated load/wind/solar curtailment.
Optimisation: classic linear optimal power flow framework.
Outputs: generation dispatch, network power flow distribution, allocation of wind/load/solar curtailment.
Impact on the GB Trans. Sys.: Findings (1/2)
WISE-PV Stakeholder Workshop 20 September 2016, London 16 16
0%
100%
Maxim
um
Pow
er Flow in
% of
the ratin
g of th
e corridor
Longitude
-6 -5 -4 -3 -2 -1 0 1 2
Latit
ude
50
51
52
53
54
55
56
57
582015
Impact on the GB Trans. Sys.: Findings (2/2)
WISE-PV Stakeholder Workshop 20 September 2016, London 17 17
0%
100%
Maxim
um
Pow
er Flow in
% of
the ratin
g of th
e corridor
Longitude
-6 -5 -4 -3 -2 -1 0 1 2
Latit
ude
50
51
52
53
54
55
56
57
582035
Impact on the GB Trans. Sys.: Impacts
No immediate investment needs for transmission network have been identified due to the large-scale integration of PV.
WISE-PV Stakeholder Workshop 20 September 2016, London 18 18
Contribution from PV to the SoS: Model
Conventional Generation Tech. Average
Unit Capacity (MW)
Average Unit Availability
Nuclear 1781 81%
Coal 1368 88%
Gas (CCGT)
734 87%
Biomass 458 88%
Pumped-hydro
809 97%
Renewable Generation
•33 years of wind speeds at the 39 representative wind farms
Wind
•2 years of solar irradiance for the 11 sub-national regions PV
WISE-PV Stakeholder Workshop 20 September 2016, London 19
Contribution from PV to the SoS: Method
Generation Adequacy Assessment Based on Sequential Monte Carlo Simulation
Maintaining the SoS by Conventional Generation
Maintaining the SoS by Combined PV & Storage
Capacity Value of the Combined PV & Storage
WISE-PV Stakeholder Workshop 20 September 2016, London 20
Contr. from PV to the SoS: Findings (1/4)
WISE-PV Stakeholder Workshop 20 September 2016, London 21
* The LOLF in 2015 is 6.2 occurrences per year
S1 S2 S3 S4 S5
Worst case: S4-2035
Contribution from PV to the SoS: Findings (2/4) Maintaining the SoS with Conventional Capacity
WISE-PV Stakeholder Workshop 20 September 2016, London 22
S4-2035
Only 61 GW of dispatchable generation
capacity
Peak demand of 79 GW due to the EHP integration
The additional 16.5 GW of dispatchable generation capacity is due to the projected capacity portfolio of different generation technologies for S4-2035, and cannot be exclusively attributed to the PV integration
Contribution from PV to the SoS: Findings (3/4) Maintaining the SoS with PV & Storage
WISE-PV Stakeholder Workshop 20 September 2016, London 23
Contribution from PV to the SoS: Findings (3/4) Maintaining the SoS with PV & Storage
WISE-PV Stakeholder Workshop 20 September 2016, London 24
Contribution from PV to the SoS: Findings (4/4) The capacity value of combined PV & Storage
WISE-PV Stakeholder Workshop 20 September 2016, London 25
Contribution from PV to the SoS: Impacts
•For the WISE PV scenarios, the security of supply would improve slightly thanks to the peak reduction that is attributed to the replacement of electric boilers with electric heat pumps. However, the security of supply deteriorates significantly due to the substantial increase of peak demand, which is also attributed to the integration of electric heat pumps.
•In order to maintain the level of security of supply in 2035 at the same level as in 2015, in the worst case scenario for the mix of generation technologies (i.e., S4-2035), an additional dispatchable generation capacity of 16.5 GW is needed.
•For S4-2035, the GB system requires approximately 35 GWh storage to maximise the contribution from the combination of PV & storage to the security of supply.
•The maximum capacity value of the combined PV & storage is equivalent to a dispatchable generator with the capacity of 2.5 GW.
WISE-PV Stakeholder Workshop 20 September 2016, London 26
Summary
GenSys 9% in total
energy production
Curtailments due to reserve
issue
TransSys Mostly
consumed locally
No needs for immediate investment
SoS 16.5 GW more dispatchable
capacity
PV & 35 GWh storage = 2.5
GW dispatchable capacity
WISE-PV Stakeholder Workshop 20 September 2016, London 27
WISE-PV Stakeholder Workshop 20 September 2016, London 28
Impact of PV on the GB Generation and Transmission System
Yutian Zhou*, Lingxi Zhang, Pierluigi Mancarella and Joseph Mutale
Power and Energy Division
School of Electrical and Electronic Engineering
The University of Manchester