impact of project production management on fgp-wpmp · 2021. 3. 24. · •fgp-wpmp is designed to...

15
© 2018 Chevron Impact of Project Production Management on FGP-WPMP Craig Evans Project Production Performance Manager December 2018

Upload: others

Post on 07-Aug-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

© 2018 Chevron

Impact of Project Production

Managementon FGP-WPMP

Craig EvansProject Production Performance Manager

December 2018

Page 2: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

2© 2018 Chevron

An opening thought

“Science is the art of looking at the evidence and removing your prejudice.”

Professor Brian Cox OBE, FRS

Page 3: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

3© 2018 Chevron

Future Growth Project and Well Head Pressure Maintenance Project

• FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and maximize the ultimate recovery of resources.

• Construction methodology is to use large, fabricated equipment blocks called modules.

• Modules are being fabricated in South Korea, Kazakhstan and Italy, then transported to Tengiz for final assembly and hook-up.

• Construction stick built man-hours remain very high after module integration.

Page 4: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

4© 2018 Chevron

Why Project Production Management?

• Similar to Industry performance, Chevron Major Capital Project historical performance is unacceptable.

• The project has adopted a holistic approach to productivity management, including Project Production Management.

• The project’s focus areas are Workface Planning, Production Control, Performance Coaching and Lean Sigma to drive improved performance.

Pre Assembled Rack Loadout (PAR)

Page 5: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

5© 2018 Chevron

Project Production Management is an integral part of the overall system

Construction Work

PackageSequence

Production scheduling

Production planning

Work not completed

Project Production Management

Installation Work

Package

Workface Planning

Analytics continuous

improvement

Execute the work

Company/contractor level 3/4 schedules

Project controls

Weekly game plan and performance boards

Performance coaching

Lean

Sig

ma

Page 6: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

6© 2018 Chevron

Implementation of Project Production Control

Project Production Control (PPC) has been implemented as the Project Production Management solution using three business processes:

• Production Scheduling

• Production Planning

• Continuous Improvement

Page 7: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

7© 2018 Chevron

Project Production Control approach

• Build upon robust Workface Planning

• Assess the problem you are trying to solve

• Learn by doing

• Train the trainer

Page 8: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

8© 2018 Chevron

Project Production Control deployment

Using Project Production Control, the principles of Project Production Management are maturing to be fully deployed.

Types of worksCivils (earthworks and concrete)Structural steelUnderground pipingPre assembled rack settingMechanical, electrical and instrumentation Pipeline crossingsPipeline anchor blocksSubstation installationFiber optic installationBuildingsEngineeringModule fabricationSystems completionIn 2019 we plan to expand to 100% in most areas.

Page 9: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

9© 2018 Chevron

Impact of Project Production ControlEngineering*

• Improvements to resource planning

• Standard work processes that were predictable and able to absorb short term variability, resulting in schedule recovery

• Identification workflow interfaces that were not previously identified

* Note: The following engineering deliverables scopes introduced and applied PPC: 1) Loop diagrams, HVAC I&C and Process Safety Layouts

Page 10: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

10© 2018 Chevron

Applying Project Production ManagementConstruction

The application of Workface Planning, Production Control, Performance Coaching and Lean Sigma resulted in improved production efficiency by controlling Work in Process (WIP).

Project A demonstrated the full benefits of creating an inventory of IWPs through Workface Planning to leverage PPC.

Open Installation Work Package (IWP) = Work in Process (WIP)PF = Productivity Factor% of Monthly Progress Achieved = Throughput

July 2018 data Project A Others

Base IWP inventory 100% 100%

% of open IWPs (WIP) 17% 46%

PF – cumulative to date 97% 57%

PF – July incremental 150% 79%

% of planned progress achieved 100% 86%

0%10%20%30%40%50%60%70%80%90%

100%

% of Open IWP's(WIP)

PF - Cumulative % of MonthlyProgress Achieved

(Ju l-18)

Work in Process (WIP) versus performance metrics

Project A All Other Scope

IWPs

Page 11: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

11© 2018 Chevron

Applying Project Production Management Construction

Last 90 days Project A Others

Avg. available IWP size (batch) 1,111hrs 1,590hrs

Avg. estimated IWP duration 13 days 22 days

PF – Cumulative to date 97% 57%

PF – July incremental 150% 79%

% of planned progress achieved 100% 86%

The Project A applied Workface Planning discipline, Project Production Management processes and Performance Coaching to exceed their target cumulative productivity. Project A applied the proven principles of optimizing IWP size (batch) and driving work to completion (WIP).

Project A All Other Scopes

Throughput of planned hours

Project A All Other Scopes

Average IWPs completed

per week Month

Page 12: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

12© 2018 Chevron

Applying Project Production ControlConstruction

Sound Workface Planning enabled effective Project Production Control and Performance Coaching resulting in direct labor capacity being reduced while ensuring throughput remains stable.

Jun Jul Aug Sep

Actual linear meters (lm) of Pipe Installed

Jun Jul Aug Sep

Direct Hours Expended (Capacity)

20%

Page 13: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

13© 2018 Chevron

Applying Project Production ControlConstruction

Coupled with Workface Planning and performance coaching, throughput increased, for HDPE pipe welding (fusion bonding).

-

2.0

4.0

6.0

8.0

10.0

12.0

14.0

-

100.0

200.0

300.0

400.0

500.0

600.0

Jun Jul Aug Sep

lm P

ipe

Inst

alle

d Pe

r wel

d

Num

ber o

f Wel

ds

Welding Production (# of welds)

No. of Welds lm Pipe per weld

8.0

9.0

10.0

11.0

12.0

13.0

14.0

-

4,000

8,000

12,000

16,000

20,000

Jun Jul Aug Sep

Aver

age

Pipe

Dia

met

er (i

nche

s)

Tota

l Inc

h D

iam

eter

Wel

ded

Welding Production (inches)

Inch dia welded Avg Pipe Dia

151% Increase116% Increase

Page 14: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

14© 2018 Chevron

Next steps

• Engineering; Red-lines > As-builts, Design Changes and Field Changes

• Project System Optimization

• Expansion to Mechanical, Electrical and Instrumentation installation Contracts

• Systems Completion and Handover

• Supply Flow Control

Page 15: Impact of Project Production Management on FGP-WPMP · 2021. 3. 24. · •FGP-WPMP is designed to increase daily production from the Tengiz reservoir by 260,000 barrels per day and

15© 2018 Chevron

Closing

• Implementing Project Production Management solution is not an insurmountable challenge

• Project Production Management integrates and works with other performance tools

• FGP-WPMP has proven the feasibility of Project Production Management as part of a total solution to close a significant performance gap in the industry

• Q&A Session

Craig EvansProduction Performance Manager+44 7887 687 [email protected]