impact of converter-based technologies on power system ... · and a threat to power system...
TRANSCRIPT
![Page 1: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/1.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Impact of Converter-based Technologies on Power System Stability: Challenges, Lessons Learnt and Recommendations.
Dharshana MuthumuniYousef PipelzadehWesley Mueller
![Page 2: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/2.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Abstract: The use of appropriate modelling tools can facilitate insights into the performance of low inertia (weaker) AC systems with high levels of renewable technologies, HVDC links and FACTs devices connected in close proximity. Phenomena’s such as control interactions and sub-synchronous oscillations are a real challenge and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study weak grids with large penetration of renewables and HVDC links, and cannot accurately capture the transient interactions and events that could potentially lead to demand disconnection as recently experienced in the GB and Australian power system. As part of lessons learnt from recent events in Australia, the electricity market operator AEMO, developed new and mandatory modelling requirements and guidelines for using Electromagnetic transient (EMT)-type simulation tools for studying large-scale power systems. Therefore, the entire Australian Power System has been developed in PSCAD to diagnose and reproduce the network response with high fidelity.
Manitoba Hydro International, as the developers of PSCAD™/EMTDC™ have provided consulting services, expert advice and in-depth training on electromagnetic transient (EMT) studies for over 40 years to utilities and manufacturers. This technical seminar highlights the importance of EMT modelling and demonstrates through real case studies the benefits of using EMT studies to address the challenges, lessons learnt and opportunities for accommodation of higher penetration and share of renewable energy in electricity grids.
![Page 3: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/3.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Manitoba Hydro International (MHI)
• Head Quarter in Canada and Technical Expert Presence in the UK
• Engineering Consulting
• Software development (PSCAD)
Who we are
![Page 4: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/4.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Outline
General Description of Challenges❖ Inverter based interface to power systems❖ EMT Studies – Background on EMT and RMS❖ Connecting to weak grid locations❖ Impact of transmission network characteristics
Brief Description of Selected Practical Cases (USA, UK and Australia)❖ Control Interaction Issues ❖ Low frequency voltage oscillations❖ Low inertia concerns - South Australian Blackout 2016❖ Resonance issues and inverter response to network voltage and current transients❖ Controls interactions and Torsional interaction (SSTI) concerns
![Page 5: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/5.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Wind Generators and influence of Transmission
System Characteristics
o The characteristics of wind generators are much different from traditional synchronous machine based generation.o Wind and PV generation is interfaced to the grid through power electronic devices
o Fast control of P and Qo Natural ‘Inertia’ – not available from power electronic interfaced devices. Even with Type 3, the fast controls will regulate
(maintain) the power to pre-set values.
o Nature of AC or HVDC transmission used to connect wind to the transmission grid (long ac cables, filters, weak grids, series compensation)
Synchronous generator based
Wind Type 3Wind Type 4
![Page 6: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/6.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Wind and Solar PV generation – Based on Power Electronic converter interface – Impact of Network Characteristics
• Weak grid (Low short circuit current, high system impedance)
• T3 and T4 controls depend on system voltage and current measurements as inputs
• Weak grids : Changes in system quantities are harder to track following a system event.
• Specially the change in voltage phase.
• Series compensated systems
• Network resonance points in the sub synchronous frequency range ( < 50 Hz)
Base Case - Case1
Hz 0.0 0.2k 0.4k 0.6k 0.8k 1.0k 1.2k ...
...
...
0.0
0.2k
0.4k
0.6k
0.8k
1.0k
1.2k
1.4k
Z+(o
hm
s)
case0 case1
Zs
System Impedance Vs Frequency Plots
Zs
![Page 7: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/7.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Wind Generators and Transmission characteristics
• The dynamic characteristics of wind and Solar PV installations are much different from traditional synchronous
machine based generation.
• Nature of AC (or HVDC transmission) used to connect wind to the transmission grid (weak grids, series
compensation, long ac cables, filters) has a significant impact on wind/solar PV response following system events
Inputs to generator controls:RMS and instantaneous inputs to inverters
![Page 8: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/8.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Wind Generators and Transmission characteristics
Vabc abc→dq vq
vd
PI
0
−
ω0
Reset Input to PLL
PLL Output to Inverter
![Page 9: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/9.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Integration of wind power to weak grids –Example
Bus voltage following a fault
This voltage must be tracked and phase angle shifts estimated accurately and fast to ensure stable operation
time
P and Q reference
Pref
Qref
![Page 10: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/10.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Integration of wind to weak grids – Example to highlight importance of system voltage tracking
P controller
d-qTo
ABCQ
controller
Vd*
Vq*
P
P’ref
Q
Q’ref
Voltage angle(PLL)
EMT simulations must be used to accurately represent the response of the PLL and fast controls.This is more of a concern in ‘weak grid interconnections’ and when there is significant penetration of renewables in an area.
![Page 11: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/11.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Characteristics of Synchronous generators - Inertia
The Synchronous generator response
is determined by
• Machine electrical
characteristics
• Exciter characteristics
• Governor / turbine
• Inertia of the rotating
masses
SG
Network
Exciter
Governor/Turbine
The inertial response immediately follows the
event
• The inertial response is due to the inertia of
large synchronous generators
• Primary control - 20 -30 Sec
• Power electronic based generation does not provide the same style of ‘inertia’
![Page 12: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/12.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
EMT and RMS Simulation –Main Differences
![Page 13: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/13.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
PSCAD/EMTDC – The Industry Standard EMT Simulation Tool
![Page 14: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/14.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Transients and Steady State
• Transient solution – influenced by
• Harmonics
• Non-linear effects
• Frequency dependent effects
• Steady state solution
• RMS Value of voltages and currents
• Magnitude and phase
Transients are initiated due to a change to the network topology
• Switching Events
• Faults and fault clearance
• Lightning
• Others
Example: Closing the breakers has initiated an electromagnetic transient. The energy exchange between L-C causes the oscillatory transient. Resistance in the circuit acts to damp the transient.
![Page 15: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/15.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Transients and Steady State
o RMS type simulations • Each solution based on phasor calculations
• 50Hz/60 Hz representation of electric network
• Network dynamics are not considered
o Electro-Magnetic Transient Simulations (EMT)• Direct time domain solution of Differential Equations• Network dynamics are captured in the solution (results
are based on the solution of the differential equations)
)()()()( ILjIRV +=)()()( ti
dt
dLtiRtv +=
2. π. 50
![Page 16: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/16.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.EMT Vs RMS response
Capacitor voltage response
R
CEcap
- Harmonics- DC offset in currents and voltages are represented- Fast controls of inverters can be better represented- Interaction between fast acting power electronic devices
can be studied- However, emt simulations are slow compared to rms type
simulations
![Page 17: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/17.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.EMT Vs RMS response - Example
![Page 18: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/18.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.EMT vs. RMS Simulations
RMS• Assume quasi-steady state• Network transients neglected• Fundamental phasor solution• Positive sequence• Large network possible
EMT• Consider differential equations• Numerical integration substitution• Upper freq. depends on simulation time step (0~MHz)
![Page 19: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/19.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Weak Grids
![Page 20: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/20.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Weak Grids – Low Short Circuit Ratio (SCR)
line_6_7_1
line_6_7_2
Bus_6
P+
jQ0.6
/ph
-0.9
/ph
10
#1 #2
300132 / 275
Bus_9
Bus_7
40
Bus_10
P+
jQ6 /
ph
0 /
ph
PI Section
line_7_11_1
Bus_11
line_7_12_1
Bus_12
#1#2
150132 / 66
P+
jQ10.5
/ph
17.0
/ph
Bus_8
line_POI_8_1V
A
V
A PI Section
Bus_POI
P+
jQ7.6
666 /p
h0.6
/ph
P+
jQ7.6
666 /p
h0.6
/ph
Bus_1
#1#2
7566 / 22
Bus_2
line_1_3_1
Bus_3
line_3_5_1
Bus_4
P+jQ1 /ph
0.5 /ph
Bus_5
P+
jQ30 /p
h2.5
/ph
#1
#21
0066
/
22
#1#2
125132 / 66
60 km
45 km
3 km
30 km
1 km
30 km
80 km
40 km each
15
RRL
RRL
RRL
TimedFaultLogicABC->G
Ia
#1#2
100132 / 26
Synch. Gen. a
V
A
V_2 B2B1
10.8
DBlkV
A
DBlkTIME
10.0
BRK1
BRK1
Vw
Type-IV
Wind turbine
A ‘weak’ Point of connection (POC) (‘weak’ grid)
• Low short-circuit current level at POC
• High system impedance
Injection of P and Q (Current) at a weak POC will
lead to voltage variations at the bus
Zsystem
VPOCVTH
VPOC = Iinj x Zsystem + VTH
![Page 21: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/21.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Weak Grids – Undesirable interactions
Bus_6
P+
jQ0.6
/ph
-0.9
/ph
10
P+
jQ10.5
/ph
17.0
/ph
Bus_8
line_POI_8_1V
A
V
A PI Section
Bus_POI
Bus_1
line_1_3_1
Bus_3
line_3_5_1
Bus_4
P+jQ1 /ph
0.5 /ph
Bus_5
P+
jQ30 /p
h2.5
/ph
#1
#21
0066
/
22
#1#2
125132 / 66
60 km
45 km
3 km
30 km
40 km each
TimedFaultLogicABC->G
Ia
#1#2
100132 / 26
Synch. Gen. a
V
A
V_2 B2B1
10.8
DBlkV
A
DBlkTIME
10.0
BRK1
BRK1
Vw
Type-IV
Wind turbine
Vw
Type-IV
Wind turbine
10.8
Vrms
1pu
Injection of P and Q (Current) at a weak POC
will lead to voltage variations at the bus
Small Q injection ‘large’ Voltage change
![Page 22: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/22.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Practical Examples
![Page 23: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/23.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 1 – Black System South Australia – September 28, 2016
![Page 24: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/24.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 3 – Black System South Australia –September 28, 2016
![Page 25: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/25.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Black System South Australia – September 28,
2016
Event Description▪ Extreme weather conditions resulted in five system faults on the SA transmission system in the 87 seconds between 16:16:46 and
16:18:13, with three transmission lines ultimately brought down
▪ In response to these faults, and the resulting six voltage disturbances, there was a sustained reduction of 456 MW of windgeneration to the north of Adelaide.
▪ Increased flows on the Heywood Interconnector counteracted this loss of local generation by increasing flows from Victoria to SA
▪ This reduction in generation and increase of imports on the Interconnector resulted in the activation of HeywoodInterconnector’s automatic loss of synchronism protection, leading to the ‘tripping’ (disconnection) of both of the transmissioncircuits of the Interconnector. As a result, approximately 900 MW of supply from Victoria over the Interconnector wasimmediately lost.
▪ This sudden and large deficit of supply caused the system frequency to collapse more quickly than the SA Under-Frequency LoadShedding (UFLS) scheme was able to act.
▪ Without any significant load shedding, the large mismatch between the remaining generation and connected load led to thesystem frequency collapse, and consequent Black System.
![Page 26: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/26.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Black System South Australia – September 28, 2016
Fault ride through requirement of wind farms
• All wind farms met the ride through requirement for the number of faults within the short duration
• However, an additional protection that was not known to system operators got activated to trip some of the wind farms (more than 3-4 faults experienced within a pre defined short duration)
![Page 27: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/27.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Black System South Australia – September 28, 2016
Lessons Learned and Recommendations
•Generation Mix and System Inertia:
▪ The system inertia on the SA side was not sufficient to maintain the frequency drop (once theHaywood interconnector tripped) and to make the under frequency load shedding (UFLS)effective.
▪ ‘Must run’ thermal generation may have to be identified.
▪ Synchronous condensers may be investigated as a potential solution if the thermal generationdispatch is expected to be low under specific load conditions.
▪ Load shedding
![Page 28: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/28.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Black System South Australia – September 28, 2016
System Studies – Model validity
Reference:
BLACK SYSTEM SOUTH AUSTRALIA 28 SEPTEMBER 2016 - Report by
AEMO
www.aemo.au
![Page 29: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/29.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Hornsdale wind farm (300 MW) and Battery Energy Storage System – South Australia
December 2017 – “Hornsdale Power Reserve, constructed by Tesla in South Australia, kicked in just 0.14 seconds (5-7 cycles) after a major plant, the Loy Yang station in the neighboring state of Victoria tripped”
![Page 30: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/30.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 2 –300 MW Wind Farm near Series Compensated 345 kV line – SSCI and Interaction with Network Transients
![Page 31: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/31.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Wind farms near series compensated lines
The series compensated line is tapped to facilitate the wind farm connection
![Page 32: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/32.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Wind farms near series compensated lines
Issue No.1: Sub Synchronous Control Interaction - SSCI (more an issues with Type 3 wind)
Network Impedance characteristics
Unstable - SSCI
![Page 33: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/33.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Wind farms near series compensated lines
Issue No.2: Wind Inverter response to system transients
The DC offset in the POI voltage caused the inverter DC link voltage to rise.- Poor network side damping- Excessive energy in DC link chopper
resistance (resulted in a trip)
![Page 34: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/34.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Potential for sub synchronous oscillations between wind farms and series compensated lines in the UK
Series Cap locations
Wind farm locations
-20
-15
-10
-5
0
5
0 10 20 30 40 50 60
Frequency scan of Type 3 wind generator• Dynamic Resistance vs Frequency
![Page 35: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/35.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 3 – Multiple Inverter Based Devices in a Local Area – Control Interactions in a Weak Grid Area
![Page 36: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/36.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
• Fault is applied at 15s for 120ms
• First 10ms duration fault: large rotation in Vd and Vq frame leads to high Iq injection and Low Id injection
• Next 50ms, inverter bring down Id and Iqto allow the PLL to relock to the phase.
• Last 60ms during the fault: inject Iq to support the system
• After fault release, PLL goes unstable and causes large voltage fluctuation
![Page 37: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/37.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 4 – Low Frequency Voltage Oscillations – Weak Grid Issue
![Page 38: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/38.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 2 – Low Frequency Voltage Oscillations (8- 10 Hz range)
Bannerton SF
T[s] 20.0 25.0 30.0 35.0 40.0 ...
...
...
0.0
0.2
0.4
0.6
0.8
1.0
1.2
pu
V_Bannerton SF 66kV
-0.2
0.0
0.2
0.4
0.6
0.8
1.0
1.2
pu
P_Bannerton SF
-0.10
-0.05
0.00
0.05
0.10
pu
Q_Bannerton SF
Low Frequency Voltage Oscillations – Interaction between multiple dynamic devices
![Page 39: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/39.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 5 – Line Series Compensation – Fixed Capacitors Or power electronic inverter based solutions
![Page 40: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/40.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Series compensation – Power electronic based devices
FACTS Devices – Series Compensation
Series compensation of transmission lines - Series Capacitors
System
![Page 41: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/41.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
-1.00E-03
-5.00E-04
0.00E+00
5.00E-04
1.00E-03
1.50E-03
2.00E-03
10 15 20 25 30 35 40 45Dam
pin
g Fa
cto
rFrequency (Hz)
SSTI Impacts on a Gas Power Station
Without SV With SV
System Dynamic Response Study results
![Page 42: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/42.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Transmission System Expansion and Interconnectors in the UK
![Page 43: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/43.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
![Page 44: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/44.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 6: – Control Interaction and SSTI Impacts -South East England
![Page 45: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/45.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Potential Control Interaction and SSTI issues -South East England
• South East England is where several HVDC interconnectors land and is a region that has little synchronous plants and even that is being displaced by offshore wind farms.
• Three STATCOMs commissioned to provide voltage support.
• The short circuit ratio is low and reactive current during a fault is sought.
• Control interactions and sub synchronous oscillations concerns given the ‘weak grid’
To Netherlands (BritNed)
To Belgium (Nemo Link)
To France (ElecLink)
To France (IFA)
![Page 46: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/46.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Potential Control Interaction and SSTI issues -South East England
• Modelling the entire South East England network including all vendor models for all HVDC, STATCOMS, Wind farms in EMT Platforms.
![Page 47: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/47.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Model Validation of South East England between PSCAD and PF
Active Power flow
x 3.0 4.0 5.0 6.0 ...
...
...
-400.00
-350.00
-300.00
-250.00
-200.00
-150.00
-100.00
-50.00
MW
Blyth - Tynemouth (PF) Blyth - Tynemouth (PSCAD)
20.00 40.00 60.00 80.00
100.00 120.00 140.00 160.00 180.00
MW
Fourstone-Stella West (PF) Fourstone-Stella West(PSC...
0.800k
0.850k
0.900k
0.950k
1.000k
1.050k
1.100k
1.150k
MW
Gretna - Harker (PF) Gretna - Harker (PSCAD)
0.850k
0.900k
0.950k
1.000k
1.050k
1.100k
1.150k
1.200k
MW
Harker - Moffat (PF) Harker - Moffat (PSCAD)
60.00 80.00
100.00 120.00
140.00 160.00 180.00 200.00 220.00
MW
Harker - Stella West (PF) Harker - Stella West (PSCAD)
Reactive Power flow
x 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 ...
...
...
-300.00
-250.00
-200.00
-150.00
-100.00
-50.00
0.00
50.00
MVAr
Blyth - Tynemouth (PF) Blyth - Tynemouth (PSCAD)
-50.00 0.00
50.00 100.00 150.00 200.00 250.00 300.00 350.00 400.00
MVAr
Fourstone-Stella W (PF) Fourstone-Stella West (PF)
-160.00 -140.00 -120.00 -100.00 -80.00 -60.00 -40.00 -20.00
0.00 20.00
MVAr
Gretna - Harker (PF) Gretna - Harker (PSCAD)
-20.00 0.00
20.00 40.00 60.00 80.00
100.00 120.00 140.00 160.00
MVAr
Harker - Moffat (PF) Harker - Moffat (PSCAD)
-100.000
0.000
100.000
200.000
300.000
400.000
500.000
MVAr
Harker - Stella West (PF) Harker - Stella West (PSCAD)
Bus Voltage
x 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 ...
...
...
0.00
50.00
100.00
150.00
200.00
250.00
300.00
kV
Blyth - Tynemouth (PF) Blyth - Tynemouth (PSCAD)
140.00 160.00 180.00 200.00
220.00 240.00 260.00 280.00 300.00
kV
Fourstone-Stella West (PF) Fourstone-Stella West (PSCAD)
310.00
420.00
kV
Gretna - Harker (PF) Gretna - Harker (PSCAD)
310.00
420.00
kV
Harker - Moffat (PF) Harker - Moffat (PSCAD)
180.00
290.00
kV
Harker - Stella West (PF) Harker - Stella West (PSCAD)
The full National Grid System model in PowerFactory was validated against PSCAD
![Page 48: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/48.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 7: Hornsea 3 Offshore Wind Power - System Interaction Studies
![Page 49: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/49.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Offshore Wind Power Projects
![Page 50: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/50.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Hornsea 3 Offshore Wind Power Projects: studies
![Page 51: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/51.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Example 8: European Transmission Network Model Development for Transient Studies
![Page 52: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/52.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.Transmission Upgrades - Belgium
Network model development for transient studies
![Page 53: Impact of Converter-based Technologies on Power System ... · and a threat to power system stability and security. Phasor-based RMS simulation programme have key limitations to study](https://reader034.vdocuments.us/reader034/viewer/2022042107/5e861223a9841a05b07affa3/html5/thumbnails/53.jpg)
pscad.comPowered by Manitoba Hydro International Ltd.
Thank You