imia · 2019-10-28 · bouygues to design a tbm that can inject the lower part of the tunnel to...
TRANSCRIPT
![Page 1: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/1.jpg)
1
IMIA24/09/2014
1
Miami Tunnel Project
![Page 2: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/2.jpg)
22
Miami Tunnel Project
I GENERAL RISK MANAGEMENT TOOL WITHIN BYTP IN TUNNELING
PROJECTS
MOBYDIC
TELEMAC
BYDAS
![Page 3: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/3.jpg)
33
Miami Tunnel ProjectMobydic : « Monitored Bouygues Disc Cutter »
TMB in board real time view, based on data transmitted by the disc cutter sensors
![Page 4: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/4.jpg)
44
Miami Tunnel ProjectMobydic : « Monitored Bouygues Disc Cutter »
• Mobydic system allows optimizing of the TBM advancement by real time knowledge of :
Front geologyDisc cutter state (temperature, rotation, wearing statut, load)
- Cutter head plugging area (by interpretation of disc cutters temperatur )- Prevents cutter head structure deep damage- This system is especially powerfull in heterogeneous condition, by
avoiding disc cutter overload and brake away- It reduces also hyperbaric intervention
![Page 5: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/5.jpg)
55
Miami Tunnel Project
From instantaneous to final recordings, all data are recorded and can be treated for any type of following
View are specially developped for TBM supervision (instantaneous) in order to help the pilot (here slurry system super vision)
BOUYGUES DATA ACQUISITION SYSTEM FOR TBM SITE
![Page 6: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/6.jpg)
66
Miami Tunnel ProjectBOUYGUES DATA ACQUISITION SYSTEM FOR TBM SITE
GraphShop, CSVShop and TrendsPowerful tools adapted to TBM for real time and historical trends and usable for any tendancy analysis (sampling fro second to days), here TBM pushing force and cutter head speed.
![Page 7: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/7.jpg)
77
Miami Tunnel ProjectBOUYGUES DATA ACQUISITION SYSTEM FOR TBM SITE
Weekly and Monthly Report, for managment reporting, and recording
![Page 8: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/8.jpg)
88
Miami Tunnel ProjectBOUYGUES DATA ACQUISITION SYSTEM FOR TBM SITE
Smartphone ApplicationReal Time and historical pages are available from smartphones
![Page 9: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/9.jpg)
99
Miami Tunnel ProjectII RISK ANALYSIS LAYER 7
• EXAMPLES OF CORAL
CORAL HEAD – LAYER 7
KEY LARGO HIGHLY DISSOLVEDLAYER 7
LAYER 6 “COQUINA”
![Page 10: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/10.jpg)
1010
Miami Tunnel ProjectSURVEY
WATSON
19 CONE PENETRATION TEST (CPT) FOR THE TUNNEL (INCLUDING 6 SHALLOW ONES CLOSE TO BI/BO) 7 CPT FOR LINE ANALYSIS13 SPT CORES10 SONIC CORES2 SHAFTS LARGE DIAMETER TOTAL NUMBER OF DRILLS : 51 (+49)
CHANNEL
5 SONIC CORES18 CPT TOTAL NUMBER OF DRILLS : 23 (+13)
DODGE
23 CPT (INCLUDING 2 SHALLOW ONES CLOSE TO BI/BO)12 SPT CORES5 SONIC CORES1 INVESTIGATION SHAFT TOTAL NUMBER OF DRILLS : 41 (+25)
![Page 11: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/11.jpg)
1111
Miami Tunnel ProjectGEOLOGICAL PROFILE - EAST BOUND
![Page 12: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/12.jpg)
1212
Miami Tunnel ProjectGEOLOGICAL PROFILE – WEST BOUND
Geological Model (Westbound)
Above is the geological profile of layers S1 to S8 as confirmed by the survey
Significant reduction of grains <2mm in layer S7 with respect to “GDR/GBR” confirmation by sonic core, large diameter test shaft and the response of the terrain during the “compaction grouting” test phase
Unstable zones identified inlayer 7 – red hatched area
![Page 13: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/13.jpg)
1313
Miami Tunnel ProjectGEOLOGY – IMPACT ON TUNNELING
CALL FOR TENDER AFTER SURVEY
The granulometry reported in the"gbr" has led Bouygues to use theEPB method (Earth PressureBalance) for excavations
The zones of layer 7 have ledBouygues to design a TBM thatcan inject the lower part of thetunnel to avoid the TBM buryingitself.
The geological survey has shownthere is no sand or fine material inlayer 7
The "cpt" tests have shown thereare unstable zones in layer 7
![Page 14: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/14.jpg)
1414
Miami Tunnel Project
IMPACT ON THE EXCAVATION METHOD
It is not possible to excavate by the EPB method when there is no sand
The instability of the front cannot be compensated without confinement
The EPB method and the production of the paste are not possible [the permeability of the terrain is too high, 10-2 to 10-4 m/s]
The unstable parts of layer 7 must be consolidated 7 and a new systemmust be implemented to excavate and remove high porosity terrains (strongwater inflow to be handled by the TBM)
![Page 15: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/15.jpg)
1515
Miami Tunnel Project
III SOLUTION DESIGN AND IMPLEMENTATION
EXCAVATION - EPB METHODE
Water and terrain pressure
IMPORTANT - the use of the WCP process requires that the excavation face be self-stable.
The Key Largo limestone layer was determined to be meta-stable leading to a significant risk of face instability, over-excavation and the inability to construct and grout the segmental lining in place.
Ground treatment was therefore required to provide stability prior to excavation.
![Page 16: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/16.jpg)
1616
Miami Tunnel ProjectNEW EXCAVATION METHOD: WCP (WATER CONTROL PROCESS)
DEVELOPED TO HANDLE THE NEW GEOLOGICAL CONDITIONS
The solution was the Water Control Process (WCP) which was adopted where the alignment encountered the Key Largo :
• the plenum is maintained full of water at hydrostatic pressure and the excavated rock is evacuated via the screw conveyor, through an inline crusher and into a hydraulic circuit to the surface.
![Page 17: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/17.jpg)
1717
Miami Tunnel ProjectSoil instability – Risk of excessive excavation
![Page 18: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/18.jpg)
1818
Miami Tunnel ProjectGEOLOGICAL LAYERS – EXCAVATION MODES
Layer 7 Layer 7
![Page 19: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/19.jpg)
1919
Miami Tunnel ProjectIMPLEMENTED INJECTIONS SCHEMES
Injections were necessary to consolidate the unstable zones of layer 7 (wcp) and add fine material (Epb+wcp)
Nombre total de forages = 824 ( hors cross passages )
![Page 20: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/20.jpg)
2020
Miami Tunnel Project
Treatment target Layer S7
Objective – to prevent instability ofthe excavation face so enabling theuse of the WCP excavation process
SCHEMATIC OF TREATMENT
![Page 21: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/21.jpg)
2121
Miami Tunnel ProjectIV TOOL DEVELOPPED DURING MIAMI PROJECT
SNAKE IS USED ON MOST OF OUR NEW TUNNELING PROJECTS
Inspection arm for Compressed TBM cutting chamber :
Visual inspection and recordCutting tools Wear measurement & damage detection
Un-plugging of cutter head, prior important damage as :
hard plugging and over heatingmain bearing sealing system damage due to plugging
TBM Jet Inspection arm « SNAKE »
![Page 22: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/22.jpg)
2222
Miami Tunnel ProjectINSPECTION
Cutter head adjusted position on arm 6
![Page 23: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/23.jpg)
2323
Miami Tunnel ProjectINSPECTION ARM 6 - REAR -
10H 18 VIEW OF CUTTER DISC 63.65 (FROM REAR) AND SUPERVISION SCREEN
![Page 24: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/24.jpg)
2424
Miami Tunnel Project
V ORGANISATION DESIGNED TO CONCENTRATE AND SHARE EXPERIENCES
Department of « Tunnel Expertise » Analyse of the past projects problems (use of End of Site Report)BenchmarkIntelligence
R/D CommitteeValidation of products we intend to developPriorisation of the need on short/middle/long timeValidation of budget/time for each product
Innovation ApproachRevisit of the impacting components of bored tunnelUse of a « method of creativity »Goal to improve the execution while decreasing risks factors
One exemple
![Page 25: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/25.jpg)
2525
Miami Tunnel Project
TELE-OPERATED MAINTENANCE OF CUTTER HEAD : « TELEMACH »
Special disc cutter implemented to be changed with robot arm :
Avoid human hyperbaric works
Help human being for heavy lifting
Decrease cutting chamber human intervention time
![Page 26: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/26.jpg)
2626
Miami Tunnel Project
![Page 27: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/27.jpg)
2727
Miami Tunnel Project
DON’T ONLY QUOTE THE RISK
QUOTE WHO IS TAKING IT
![Page 28: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/28.jpg)
2828
INDUSTRIALIZATION OF THE CONSTRUCTION SECTOR
Construction is living a revolution
Construction is mooving to industrializationmore and more components are pre-build outside the construction siteNew productsIncorporated across many projects
This is mooving fast and embracing all type of works
QA/QC improving efficiencyImproving claim experienceMore and more problems are identified very early in the processQuite often well before any damage
![Page 29: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/29.jpg)
2929
GENERATING NEW RISKS
A contractor is now an integrator
Find solutions for these risks generated by new methods of construction
No one else but the Construction / Engineering branch of insurance can manage this
![Page 30: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/30.jpg)
3030
EXISTING SOLUTIONS
Construction / Engineering Insurance Solutions / RiskTransfer Solutions : have not yet evolved
The gap between the need for transfer and transfersolutions is increasing
We still very much need the existing solutions (CAR, TPL, machinery breakdown, DSU, etc…)
But we also need new solutions
![Page 31: IMIA · 2019-10-28 · Bouygues to design a TBM that can inject the lower part of the tunnel to avoid the TBM burying itself. yThe geological survey has shown ... over-excavation](https://reader036.vdocuments.us/reader036/viewer/2022081405/5f098a887e708231d42751ee/html5/thumbnails/31.jpg)
3131
CREATING NEW SOLUTIONS
This is an opportunity for the market to propose new solutions including with very substantial retention
We are looking for a Construction Product Liability type solution
Covering the works prior to handoverPure defect cover