!I&lll ,ft, AGREEMENT N'O. CEI38/95 IMPROVEMENT TO Kk\1 TIN nOAD, STAGE 1 ENVIRONMENTAL IMPACT ASSESSMENT AND DRAINAGE IMP ACT ASSESSMENT STUDIES ENVIRONMENTAL IMP ACT ASSESSMENT FINAL REPORr (VOLUME 2 OF 2) ENVIRONMENTAL MONITORING AND AUDIT MANUAL DOC NO. BBL/96010/n07 ISSUENO.2 NOVEMBER 1996 Highways Department New Terr itories Region BlObtie BMT (Hong Kong) Ltd and Ho Tin & Associates Consultir.g Engineers Ltd. 71F., Swire & I\IlrIclaine lIouse 2 nd floor, Ho !\Ian Tin Government Offices 88 Chung Hou Street Ho ManTio Kowloon ... 21. Austin Avenue Tsimshatsui

Upload: phamkhue

Post on 26-May-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

!I&lll ,ft, AGREEMENT N'O. CEI38/95

IMPROVEMENT TO Kk\1 TIN nOAD, STAGE 1 ENVIRONMENTAL IMPACT ASSESSMENT AND

DRAINAGE IMP ACT ASSESSMENT STUDIES

ENVIRONMENTAL IMP ACT ASSESSMENT

FINAL REPORr

(VOLUME 2 OF 2)

ENVIRONMENTAL MONITORING AND AUDIT MANUAL

DOC NO. BBL/96010/n07

ISSUENO.2

NOVEMBER 1996

Highways Department New Territories Region

BlObtie BMT (Hong Kong) Ltd and Ho Tin & Associates Consultir.g Engineers Ltd.

71F., Swire & I\IlrIclaine lIouse 2nd floor, Ho !\Ian Tin Government Offices 88 Chung Hou Street Ho ManTio Kowloon ...

21. Austin Avenue Tsimshatsui

u [f

[

a-[[

0' [T

[[

IT

o:~

[l

IT. [i' .. , .

, ' ,

. I=.ro. Our Ref: 9601 0/EIA/854/KTCNY "\l(-Your Ref:

2 December 1996

To Distribution List

Dear Sirs,

Agreement No. CE 38/95 Improvement to Kam Tin Road, Stage I Environmental Impact Assessment and Drainage Impact Assessment Studies Environmental Impact Assessment Final EIA Report, EM&A Manual and Executive Summary

We enclose one set of the Final EIA Report, EM&A Manual and the Executive Summary for your retention and record.

Yours faithfully, For and on behalf of Babtie BMT (Hong Kong) Ltd. and Ho Tin & Associates Consulting Engineers Ltd.

cc

Cheung ct Director

Ho Tin - Mr. Kelvin Lau (w/o) Enpac - Mr. Derek Lam (w/e) Urbis - Mr. Matthew Pryor (W/e)

in/0415/96010.854

~BmT

Babtie BMT (Hong Kongl Ltd 7th Floor, Swire & Maclaine House 21 Austin Avenue, Kowloon Hong Kong Tel: (852) 2369 0175 Fax: (852) 2739 6648 email: [email protected]

Directors Roger Coiton, David Fawcett, Peter French, David Goodrich, Henry Leung Associate Directors Mark Cheung, Y.w.Yeung.

Incorporating Babtle Oakervee LImited and Peter Fraenkel BMT (Asia) Limited

IJ

0 Your Ref: Our Ref: 9601 0lEIAI8541KTCNY

n Distribution List

Attention Final· Executive ~nmr

[] Report Summary

Omelegco Secretriat 1 1

] Urban Council and 5 5 Regional Council YLDB Ms. Clara Tam 2 45

/ AC for TINT, TO Mr.S.K. Lo 1 1

J / PM/NTN, TOO Mr. P. C. Leung 1 1 '" DLOIYL Mr. Y.M. Ho 1 1

DOIYL Mr. K.K. Mok 2 2

] /DAF Mr. K.W. Cheung 1 1 DRS Ms. Connie Chau 1 1 DLMIYURSD Mr. W.M. Kwan 1 1

- CE/MN,DSD Mr. H.W. Ma 1 1

J / CE/DP, DSD Mr. C.M. Chung 1 1 CE/MNW, WSD Mr. K.K. Lau 1 1 DEP Mr. Stanley Lau 8 8

J /DFS Mr. Y.C. Choi 1 1

C of P (CSP Traffic) Mr. K.L. Wong 1 1 /DPOITM & YL Mr. Richard Siu 1 1

CGE/P, GEO, CEO Mr. R.P. Martin 1 1 KCRC Mr. Sterling Brisbin 1 1 CLSIYL, LD Mr. K.F. Chang 1 1

Highways Department

,- CEIWHL & CPS (R3) Mr. Y.S. Heung 1 1 - CE/Railway Mr. Stephen Ching 1 1

J CHE/R&D Mr. K.T. Li 1 1 CHE/Structure Mr. K.K. Lee 1 1 CHE/NTE Mr. M.Y. Wong 1 1

J CE/MW(NT), MWPMO Mr. H.K. Vim 1 1 SLA Mr. C.T. Ma 1 1 RHE/NT Mr. T.S. Lam 10 10

50 93

inl041519691 0.854

L

[

[

[

[

[

C [

[

[

[

[

[

c [

[

[

Highways Department Improvement to K:lm Tin Road. St:lgl! 1 Environment::t! [mp:lct Assessment

ENVIRONMENTAL IMPACT ASSESSMENT

FINAL REPORT

(Volume 2 of2)

ENVIRONMENTAL MONITORING AND AUDIT .MANUAL

CONTENTS

1. Introduction

2.

3.

4.

5.

1.1 1.2

Background The Proposed Project

Purpose Of Em&A Manual

2.1 EM&A Objectives 2.2 EM&A Requirements

Environmental impact assessment

3.1 Summary of Impact Assessment 3.2 / Recommended Mitigation Measures

Em&A Organization And Management

4.1 Organization and Management Structure 4.2 Responsibilities and Lines of Communication

Construction Em&A Programme

5.1 5.2 5.3

.5.4

Purposes Noise Ecology LandscapeNisual

Babtie BMT (Hong Kong) Ltd. Ho Tin & Associates Co~sulting Engineers Ltd.

1

1 1

3 3

5

5 7

9

9 9

12

12 12 17 19

Doc No : 960101007 Issue: 2

Highways Department

6. Post-Project/Operation Em&A Programme

6.1 Purposes 6.2 Noise 6.3 Ecology 6.4 LandscapeNisual

7. Contingency Plan

8. Environmental Complaints And Responses

9. Records And Reporting

9.1 Data Recording 9.2 Reporting

. Figures

Appendices

Appendix A AppendixB

Abstract on EAD Operation Manual Sample Field Data Record Sheets

Improvement to Karn Tin Road. Scage 1 Environmental Impact Assessment

20

20 20 21 21

22

23

24

24 24

L

[

C [

c c [

[

c [

[

[

[

c [

[

[

[

[

-;:-;-::--;;=::-;----;;--:-:--'-:---------~--=--- [ Babtie BMT (Hong Kong) Ltd. Doc No: 96010/007 Ho Tin & Associates Consulting Engineers Ltd. Issue: 2 [:

Highways Department

Section 1

Introduction

Babti. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

DOC NO: 96010/007 Issue: 2

L [

r [

[

[

C C [

[

[

[

[

o [

[

[

[

[

[

r-

Highways Department

1. INTRODUCTION

1.1 BACKGROUND

Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

The section of Kam Tin Road between Au Tau Roundabout and the proposed Kam Tin . Bypass (western end) is to be improved to increase its capacity in order to cater for the increasing traffic demand arising from the rapid development of the North West New Territories areas, and to relieve the heavy traffic flow on Kam Tin Road upon the planned opening of Route 3 - Country Park Section in 1998 and Kam Tin Bypass in end 200 I.

The stretch of Kam Tin Road for which improvement works are proposed is currently a single 2-lane carriageway with provision of narrow footpaths at discrete locations. The proposed improvement works, including widening/modification of road sections, provision of pedestrian/cyclist facilities and lay-bys, and construction of engineering and traffic management works, will upgrade the road to a dual 2-lane carriageway. Shown in Figure I is the works limit of Improvement to Kam Tin Road, Stage 1 (the Project).

An Environmental Impact Assessment (EIA) has been performed to address and evaluate the potential impacts associated with the implementation of Project. While results of the impact assessment and mitigation requirements for the Project are detailed in the EIA Report, this Environmental Monitoring and Audit (EM&A) Manual will form a separate stand alonedocument as part of the EIA Report, and will also include a practical guide that will be designed to assist the Engineer and the Contractor in fulfilling their requirements for environmental review.

1.2 THE PROPOSED PROJECT

1.2.1 Road Improvement Works

The existing Kam Tin Road is to be improved to provide additional traffic capacity and at the same time to enhance safety through provision of wider continuous footpaths.

The project will upgrade the l.l km long Kam Tin Road between Au Tau Roundabout and Kam Tin River from a single carriageway to a dual 2-lane carriageway. The alignment of the upgraded Kam Tin Road in this section will follow approximately the existing alignment ofKam Tin Road.

In addition, a 2 m wide footpath with 3 m wide cycle track on the north side and 3.5 m wide footpath on the south side will be provided. There will be a 24 m long lay-bys for buses and general loading/unloading activities at appropriate locations (averaging 300 m apart).

Babli. BMT (Hong Kong) LId. Ho Tin & Associates Consulting Engineers Ltd.

Doc No : 96010/007 Issue: 2

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

1.2.2 Construction Activities and Schedule

Road works will consist of construction of flexible pavement comprising subbase, roadbase, basecourse and wearing course. Drainage for the carriageway will be provided by a gravity flow drainage system consisting of gullies, manholes, drain pipes, surface channels and possibly subsoil drains ..

The existing traffic will be maintained during the construction period by adopting an appropriate temporary traffic diversion scheme. The sequence of construction will proceed generally in the following manner: (a) widening of carriageway while maintaining traffic in the existing Kam Tin Road, and (b) reconstruction of the existing Kam Tin Road while diverting the traffic to the widened carriageway.

A preliminary construction programme for the road widening works has been scheduled (also see Figure 2):

Months 1-2 Months 3-12 Months 6-15 Months 12-18 Months 12-15 Months 15-19 Months 17-20 Months 20-26 Months 22-26 Months 23-27 Months 25-30 Months 28-30

Babti. BMT (Hong Kong) Ltd.

Preliminaries, site clearance and mobilization Excavation Back filling and subbase Drainage and utilities Kerbing Road paving on widened portion Breaking of existing road surface Drainage and utilities . Back filling and subbase Kerbing Road paving and road sign Footpath

2 Ho Tin & Associates Consulting Engineers Ltd.

Doc No: 96010/007 Issue: 2

L [

c [

[

[

C [

[

['

[

[

[

[

[

:[

[

[

Highways Department

Section 2

Improvement to Kam Tin Road, Stage I Environmental Impact Assessment

Purpose of EM&A Manual

Babti. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

L [

[

[

[

[

c [

c [

c c c o [

[

[

[

[

[

L

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

2.

2.1

2.2

PURPOSE OF EM&A MANUAL

EM&A OBJECTIVES

As part of the objectives of the EIA Study as stated in Section 3.1.1 of the Brief, an EM&A programme shall be developed to design and specifo the environmental monitoring and audit requirements necessary to ensure the implementation and the effectiveness of the environmental protection and pollution control measures adopted.

Specifically, the EM&A Manual involves:

'Monitoring of the environmental performance of the Project and the effectiveness of mitigation measures.

Verifying the environmental impacts predicted in the EIA.

Determining Project compliance with regulatory requirements and Government policies.

Taking remedial action if unexpected problems or unacceptable impacts arise.

EM&A REQIDREMENTS

The Environmental Protection Department (EPD) requires that monitoring is undertaken for the following stages of the Project:

Baseline Monitoring refers to the measurements of environmental parameters such as existing noise levels and ecological elements, to determine the nature and ranges of n!\tura1 variation and to establish, where appropriate, the nature of change. This information is useful for assessing the short and long term environment impacts of

, the Project activities.

Impact monitoring involves the measurement of environmental parameters during the Project activities, in order to determine the impacts of the activities and the effectiveness of the mitigation measures proposed in the EIA Report, and any further remedial measures which are needed.

Compliance Monitoring involves periodic sampling and/or continuous measurement of environmental parameters and the determination of their compliance with regulatory requirements and standards.

It is a further requirement of th~ EPD that the environmental monitoring programme is subject to environmental audit. The aim is to determine satisfactory compliance with the legislative requirements, ensure that no annoyance is caused to sensitive receivers and initiate the remedial action plan when required. This will require information on the statutory requirements for parameters of concern and monitoring data.

Babti. BMT (Hong Kong) Ltd. 3 Doc No: 96010/007 Issue: 2 Ho Tin & Asso~iates Consulting Engineers Ltd.

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

Each audit will consist of a review of the monitoring data and comparison with the relev,ant legislative requirements and environmental perfonnance standards specified in the Contract Document.

The monitoring and audit requirements for the Project will be as follows:

Pre-Construction Phase Including all baseline monitoring prior to any Project activity occurring on site.

Construction .Phase Including impact/compliance monitoring and audit during all construction activities.

Post-Project/Operational Phase Including impact monitoring and audit after completion of Project and opening of road to traffic.

In addition, requirements stipulated in EAD Operation Manual, Chapter 5, Environmental Monitoring & Audit o/the Major Development Projects (Appendices B and C) shall also be followed. An abstract on the operation manual is provided in Appendix A.

Babtie BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

4 Doc No: 96010/007 Issue: 2

L [

[

[

[

[

c c [

[

[

[

[

c [

[

[

l [

L

l Highways Department

Section 3

Improvement to Kam Tin Road , Stage 1 Environmental Impact Assessment

Environmental Impact Assessment

Babli. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

L.

[

[

r [

C [

c [

[

C [

c [

[

[

[

[

[

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

3. ENVIRONMENTAL IMPACT ASSESSMENT

3.1 SUMMARY OF IMPACT ASSESSMENT

3.1.1 Identified NSRs

NSRs within the Study Area are low-rise developments. Locations of the identified NSRs are shown in Figures 3 and 4.

3.1.2 Construction Phase

3.1.2.1 Noise

With the exception.of the noise sensitive receivers (NSRs) at Kam Tin Shi, most of the NSRs along Kam Tin Road will be subject to significant construction noise impacts. Mitigation measures are therefore required to reduce construction noise. For daytime construction activities, the effectiveness of amelioration measures will be confirmed in practice by the EM&A programme. For activities conducted during restricted hours, statutory requirements under the Noise control Ordinance (NCO) will be adhered to:

3.i.2.2 Ecology

No severe direct ecological impacts are anticipated within the works limit and they can be mitigated. Indirect impacts such as polluted water and dust may affect the species and habitats outside the works boundary, and appropriate mitigation measures should be installed.

3.1.2.3 LandscapeNisual Impact

The works would have a minimal impact on the overall landscape .character of the area. High localised landscape impacts would result from the clearance of mature roadside trees. The potential loss of a number of inscribed stones would result in a high cultural impact.

Severe negative visual impacts are predicted for residents in Ko Po Tsuen during construction. Other residential areas and work places would experience negligible visual impacts. Pedestrians and cyclists along route would experience high negative visual impacts and motorists would experience low negative visual impacts during construction. Mitigation measures have been proposed to reduce landscape, cultural and visual impacts.

Babtie BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

5 Doc No : 96010/007 Issue: 2

Highways Department

3.1.3 Post-Project/Operational Phase

3.1.3.1 Noise

Improvement to Kam Tin Road, stage 1 Environmental Impact Assessment

Operational impacts on the nearby NSRs, in particular those are located in the immediate vicinity of Karn Tin Road, will be significant. Noise mitigation structures will be provided and their effectiveness will be verified through the implementation of the EM&A programme.

3.1.3.2 Ecology

There will not be any permanent loss of fish pond arising from this project, and no rare nor endangered species were discovered within the works boundary. The only direct impact is the removal of some roadside trees which can be compensated by landscape planting.

3.1.3.3 LandscapeNisual Impact

Medium negative visual impacts are predicted at Ko Po Tsuen during the early operational phase and beneficial impacts in the longer term. Other residential areas and work places would experience negligible visual impacts. Pedestrians, cyclists and motorists would experience low negative impacts during the early operational phase. In the longer term the proposed environmental improvement measures would result in beneficial impacts for cyclists, pedestrians and motorists.

Mitigation proposals aim to provide a comprehensive landscape treatment for the road, which would be a significant environmental improvement for the whole area. Mitigation· measures would reduce landscape, cultural and visual impacts to acceptable levels and negligible residual impacts are predicted as a result of the scheme.

Bab!i. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

6 Doc No: 96010/007 Issue: 2

L [

[

[

[

[

C [

c [

[

[

[

[

[

[

[

l L L

L [

[

[

[

[

c [

c [

[

G [

[J

r [

[

[

[

[

Highways D~partment Improvement to Kam Tin Road. Stage 1 Environmental Impact Assessment

3.2 RECOMMENDED MITIGATION MEASURES

3.2.1 Construction Phase

A summary of the mitigation measures recommended to be installed during the construction phase is indicated in Table 3.1. .

Table 3.1 Construction Mitigation Measures

Aspect Mitigation Measures

Install temporary noise barriers. Locate noisy equipment and activities as far from NSRs as is practical. Replace noisy plant or processes by quieter alternatives where possible. Schedule noisy activities to minimize exposure of nearby NSRs to high levels of construction noise.

Noise Turn off or throttie down idle equipment, and operate noisy equipment only when necessary. Provide vibration isolation and/or acoustic enclosures to the power units of non-electric stationary plant and earth-moving plant. Plan to avoid parallel conduction of noisy activities close to a given

. receiver. Properly maintain and operate construction plant and the associated silencing measures.

Plant suitable native tree species along the widened Karn Tin Road.

Ecology Implement proper house-keeping procedures to prevent the discharge of polluted water into water bodies outside the works boundary and to minimize the emission of dust.

. Take precautions not to alter the hydrology of the area.

Detailed alignment of road to reduce visual impacts and loss of existing Landscape trees and cultural artefacts. Nisual Construction work areas to be restricted to a minimum and protective

fencing used. Erect hoarding to a safe minimum height at Ko Po Tsuen.

Minimise night-time working and lighting

Bab!i. BMT (Hong Kong) Ltd. 7 Doc No: 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

3.2.2 Post-Project/Operational Phase

A swnmary of the mitigation measures recommended to be implemented during the post­project/operational phase is shown in Table 3.2.

Table 3.2 Post-Project/Operation Mitigation Measures

Aspect Mitigation Measures

Provision of 3m high noise barriers and S.7m high inverted-L barriers to Noise protect NSRs at "Kam Fung Terrace" and Ko Po Tsuen.

Consideration for indirect technical measures to redress the residual impact.

Planting of suitable tree species along the widened Kam Tin Road.

Ecology Reinstatement and return of the affected fish pond to the owner after completion of the works.

New replacement tree planting.

. Dense tree and shrub planting to screen views to the road from sensitive

Landscape receivers.

Nisual Raised amenity areas to provide visual and physical separation of pedestrians, cyclists and vehicular traffic.

Noise barriers to be sensitively designed and planting used to help ameliorate their appearance.

. Environmental improvements to the roadside including a paved area in front ofKo Po Tsuen .. -

Babtie BMT (Hong Kong) Ltd. 8 Ho Tin & Associates Consulting Engineers Ltd.

Doc No: 96010/007 Issue: 2

L [

[

[

[

[

c [

[

[

[

[

[

[

[

[

[

[

[

[

Highways Department

Section 4

Improvement to Kam Tin Road, Stage I Environmental Impact Assessment

EM&A Organisation and Management

Babtie BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

L,

[

[

r [

[

c

Highways Department Improvement to Kam Tin Road.,Stage 1 Environmental Impact Assessment

4. EM&A ORGANIZATION AND MANAGEMENT

4.1 ORGANIZATION AND MANAGEMENT STRUCTURE

4.2

A number of parties will take part in the implementation of the EM&A programme, namely (a) Client Department, i.e. Highways Department (HyD) and its representatives, (b) EM&A Section of EPD, (c) Engineer, (d) Independent Environmental Auditor, (e) Contractor, and (f) Environmental Sub-Contractor. The organization and management structure for the EM&A programme is illustrated in Figure 5.

RESPONSIBILITIES AND LINES OF COMMUNICATION

The principal responsibilities of each project team member are outlined in the followings:

C 4.2.1 Client Department

c c [

[

c [

[

[

l [

[

Overall management of the Project including EM&A programme. Communication with EPD over decisions/actions on non-compliances.

4.2.2 EM&A Section ofEPD

Overall review and approval of the EM&A programme. Advice on regulatory policies and environmental requirements.

4.2.3 Engineer

Ensuring the Contractor has implemented the mitigation measures recommended in the EIA. Approving the appointment of the Environmental Sub-Contractor. Ensuring the Contractor carries out the environmental monitoring programme .

. Ensuring the Contractor undertakes any remedial measures necessary to address unanticipated or unacceptable impacts arising during construction of the Project. Liaising with the Independent Environmental Auditor. Ensuring smooth circulation of all project-related environmental information to all concerned parties. Reviewing monitoring and audit reports. Notifying EPD of exceedances of environmental quality performance limits. Initiating the action plans in the event of non-compliances.

Babli. BMT (Hong Kong) Ltd. Ho Tin & Associates Cons~lting Engineers Ltd.

9 Doc No : 96010/007 Issue: 2

Highways Department Improvement to Kam Tin Road, Stage 1 . Environmental Impact Assessment

4.2.4 Independent Environmental Auditor

Undertaking analysis of the monitoring results. Performing audits of the EM&A activities. Preparing audit reports. Undertaking site inspections on issues related to EM&A. Making recommendations and suggestions to. the Engineer for improving environmental performance at the site. Liaising and consulting with all relevant parties during the implementation of the Event! Action Plans. Modifying, if necessary, the EM&A progranune in consultation with the Engineer, EPD and other concerned parties. Producing reports on implementation of action plans and responses to public complaints.

4.2.5 Contractor

Undertaking construction in compliance with the EM&A requirements. Implementing mitigation and improvement measures as necessary and as instructed by the Engineer. Appointing the Independent Environmental Auditor (the Auditor). Appointing and supervising the Environmental Sub-Contractor for conduction of monitoring works. Preparing and submitting monitoring reports to the Engineer. Reporting to the Engineer on any abnormalities, difficulties and extraneous activities (unrelated to the construction of the Project) observed/recorded during the monitoring process.

4.2.6 Environmental Sub-Contractor

Performing all monitoring and sampling tasks as specified or directed. Recording all necessary field data during monitoring and sampling. Undertaking maintenance and calibration of monitoring and sampling equipment. Compiling and submitting monitoring results and reports to the Contractor. Reporting to the Contractor on any abnormalities, difficulties and extraneous activities (unrelated to the construction of the Project) observed/recorded during the monitoring process.

Babli. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

10 Doc No: 96010/007 Issue: 2

L

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

[

u n

[I

o [:

[J

[j

[I

[J [j

L!

U U

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

Shown in Figures 5 and 6 are the lines of communication between the concerned parties, and EM&A procedures respectively.

Prior to commencement of construction, the Contractor should submit to the Engineer a detailed monitoring and audit progranune for construction and operation. The progranune must be approved by EPD before work commencing on site. The Contractor should undertake the monitoring and recording of environmental issues in order to assess the impacts of the Project activities and compliance against agreed environmental quality performance limits. Details of the specific monitoring parameters and the required frequency of sampling are provided in the following sections.

Babti. BMT (Hong Kong) Ltd. 11 Doc No: 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

yo'" /

Highways Department

Section 5

Improvement to Kam Tin Road , Stage 1 Environmental Impact Assessment

Construction EM&A Programme

Bab!i. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

l.

l. c

[

c [

c [

[

[

[

c [

[

[

L L [

L

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

5.

5.1

CONSTRUCTION EM&A PROGRAMME

PURPOSES

The construction monitoring and audit programme will be used to verifY the predictions of environmental impact developed during the design stage and to ensure that unforeseen impacts are detected during the construction stage. This will allow corrective measures to be implemented before irrecoverable damages occur. The objectives of the programme are as follows:

To provide a database of environmental data against which to determine any short 'term or long term environmental impacts as a result of the construction activities.

To confirm the assumptions made in the design of the Project and particularly the effectiveness of the mitigation measures.

To provide an indication whether the environmental control measures are effective in maintaining the required standards.

To provide data to enable the environmental audits to be carried out.

To achieve these aims the, environmental monitoring will be carried out in two stages, namely pre-project (baseline monitoring) and during construction (impact/compliance monitoring).

5.2 NOISE

5.2.1 Monitoring Methodology and Equipment

5.2.1.1 Monitoring Methodology ,

Noise measurements shall be undertaken in accordance with the procedures and methodologies specified, in the order of precedence, in the Noise Control Ordinance (NCO), EPD's requirements, the Engineer's instructions, and this EM&A Manual. Standard acoustical principles and practices shall be followed in the measurement and analysis of the noise being monitored.

Noise monitoring shall be undertaken at the designated and/or agreed locations. Unless otherwise accepted by the Engineer and EPD, the measurement point for noise monitoring conducted outside a building shall be at I m from the exterior of the sensitive facade. Where a measurement is to be made of noise being received at a place other than a building, the measurement shall be at a position 1.2 m above the ground in the free-field.

Babti. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

12 Doc No: 96010/007 Issue: 2

Highways Department Improvement to Kam Tin Road, St~ge 1 Environmental Impact Assessment

Noise monitoring shall be carried out at a time appropriate for the activities on site or as directed by the Engineer. Where construction is to be carried out during restricted hours, noise monitoring shall follow the conditions and terms specified in the Construction Noise Permit. Noise measurements shall not be made: (a) when other intrusive noise sources other than Influencing Factors are apparent at the measurement point, or (b) in the presence of fog, rain, or excessive steady/gusty winds.

All noise measurements shall be rounded to the nearest whole dB (A), with values of 0.5 or more being rounded upwards.

5.2.1.2 Monitoring Equipment

Sound level meters used for noise monitoring shall comply with International Electrotechnical Commission Publications (lECP) 651:1979 (Type 1) and 804:1985 (Type 1), and other noise measuring and analysis instrumentation shall be of comparable professional quality.

All monitoring equipment shall be maintained in calibration at all times. Recalibration shall be carried out in accordance with the requirements stated in. this Manual or those

• recommended by the manufacturer, whichever is more stringent. Noise monitoring equipment shall be calibrated at least annually by the manUfacturer or an accredited laboratory.

Calibration shall be made prior to and after each set of measurements, and the resclts of the calibration recorded on the appropriate field data sheet. Measurements will be considered as valid only if.the calibration levels before and after the noise measurement agree to within 1 dB(A). Routine calibration equipment and procedures shall comply with IECP 942.

All noise measurement equipment and accessories shall be used with great care and maintained in accordance with the manufacturer's recommendations.

5.2.2 Monitoring Locations and Schedule

5.2.2.1 Monitoring Locations

Noise monitoring is suggested to be undertaken at the following locations:

MS-A Village house adjacent to access road to the electrical sub-station. MS-B Village house at Ko Po San Tsuen MS-C Village house at Ko Po Tsuen MS-D Kam Tin Mung Yuen Public School

. Babli. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

13

'.

Doc No: 96010/007 Issue: 2

L

[

[

[

[

c [

c [

[

[

[

[

[

[

[

[

l [

[

[

r [

c [

[

[

[

c

o [

[

[

[

[

l [0

Highways Department Improvement to Kam Tin Road, Stage 1 Environment!ll Impact Assessment

For baseline monitoring, noise measurements will be made at MS-B, C and D. Impact and/or compliance noise monitoring shall be conducted, on a routine basis and when required, at the 3 closest monitoring stations (chosen from MS-A to D) within 200 rn of the active portion of site. Monitoring at other locations may be required by the Engineer in case of non-compliances or upon receipt of complaints. Additional noise monitoring locations shall. be agreed with EPD and the Engineer if works carried out during restricted hours are necessary.

Figure 7 shows the locations of the suggested noise monitoring stations.

5.2.2.2 Baseline Monitoring

Noise monitoring shall be carried out prior to the commissioning of the construction work for a period of at least 2 weeks, with measurement to be taken on a daily basis. There should not be any construction activities in the vicinity of the stations during the baseline monitoring.

5.2.2.3 Impact/Compliance Monitoring

Noise monitoring shall be carried out at the chosen monitoring station(s) every 6 days during normal construction hours. Noise measurements shall be conducted over a 30-minute period to give 6 consecutive L,q(5 min) readings. The Leq(30 min) reading shall be determined from the L,q(5 min) readings within the noise meter.

The frequency of monitoring shall be increased: (a) in case of non-compliances, (b) upon receipt of complaints, or ( c) when works are carried out during restricted hours. Furthermore, the effectiveness of mitigation measures should be ensured by checking that any silenced construction equipment is properly used and maintained, any mitigation measures such as noise barriers are properly positioned and maintained, and good site practice is observed. .

Babti. BMT (Hong Kong) Ltd. 14 Ho Tin & Associates Consulting Engineers Ltd.

Doc No : 96010/007 "Issue: 2

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

A summary of the construction noise monitoring programme is provided in Table 5.1.

Table 5.1 Summary of Construction Noise Monitoring Programme

Item Baseline Monitoring ImpactlComplhince Monitoring

3 closest monitoring stations of Monitoring Stations MS-B, CandD MS-A to D within 200 m of the

active portion of site

Daily basis for a 2~week period Every 6 days during normal FrequencylDuration prior to construction works construction hours

Parameters L 10, L,q and L90 L,q(30 min) reading derived

- from 6 consecutive L,q(5 min) readings

· In case of non-compliances Additional Monitoring Nil · Upon receipt of complaints

· During restricted hours · Test ofrnitigation measures

5.2.3 Environmental Quality Performance Limits

Three environmental quality performance limits will be used for the environmental audit, as described in Table S.2.

The trigger, action and target (TAT) levels for construction noise pollution are shown in Table 5.3.

Babli. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

15 Doc No: 960101007 Issue: 2

L [

[

[

[

[

[

c

[

[

[

[

[

C l [

[

L L

c [

[

[

c [

[

[

[

[

[

[

[

[

[

Highways Department

Table 5.2

Level

Trigger Level

Action Level

T arger level

Table 5.3

Level

Trigger Level

Action Level

Target level

Improvement to Kam Tin Road. Stage 1 Environmental Impact Assessment

Environmental Quality Performance Limits

Indication and Response

The level beyond which there is an indication of a deteriorating ambient environmental quality for which a typical response could be more frequent monitoring.

The level beyond which appropriate remedial actions may be necessary to prevent the environmental quality from going beyond the Target Limit, which would be unacceptable.

The level stipulated in relevant pollution control ordinances, the HKPSG, or other appropriate criteria established by EPD for a particular project, beyond which the works should not proceed without appropriate remedial action, including a critical review of plant and work methods.

Trigger, Action and Target Levels for Construction Noise Monitoring

Indication and Response

This level acts as an "early warning" of deterioration, so that closer monitoring of noise levels may be initiated, possible sources of the noise may be identified, and early mitigation measures enacted to prevent further deterioration. This level may be defined as receipt of one independent complaint (directed either to EPD or the Engineer).

Achievement of this level indicates that noise levels have increased from the Trigger Level, and that corrective action is required before conditions further deteriorate and relevant standards are not met. This level may be defined as receipt of more than one independent complaint in a two-week period.

This is the upper limit, or maximum permissible level that will still comply with the appropriate regulation. In the absence of statutory controls to limit daytime (07:00-19:00 hours) construction noise, a limit of75 dB(A) shall be used, with a limit of70 dB(A) and 65 dB(A) for schools during normal school days and during examination respectively, as the Target Level. Exceedance of the Target Level is generally not permitted.

Babli. BMT (Hong Kong) Ltd. 16 Doc No: 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

Highways Department

5.2.4 Event! Action Plan

Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

Whenever monitoring indicates that a particular parameter has exceed its trigger, action or target level, the Engineer shall initiate a programme of action, i.e. the Event!Action Plan. The Event! Action Plan for noise exceedance are detailed in Table 5.4 and included as flow diagram in Figure 8.

5.3 ECOLOGY

5.3.1 Baseline

A baseline ecological study of flora and fauna was completed during the environmental impact assessment stage and the results are presented in the EIA report.

5.3.2 Construction

L [

[

[

[

C [

It is recommended that the following monitoring and aud. it programme to be carried out during the construction phase: [

Monitoring and auditing the use of Ko Po Tsuen Egretry and/or other active [ egretries adjacent to the works areas along the road corridor by egrets and herons monthly during the nesting season, in view of its proximity to the works site.

Monitoring and auditing the success of the landscape planting, in terms of health, [ survival and growth of vegetation, by landscape contractor every 6 months.

Babtie BMT (Hong Kong)Ltd. Ho Tin & Associates Consulting Engineers Ltd.

17 Doc No : 96010/007 Issue: 2

[

[

[

[

[

l l l [

r-: r; r-: r-: r-: r-l c:J rJr-l LJ LJ r---J r-: c::-:J :----l r-: r---J C""'l i~ ~ Highways Department lmllrovcment to Knill Tin Road, Stnge 1

Table S.4 Action Plan for Construction Noise Exceedance

--- --- -

Event Action by Engineer

One independent com- Investigate complaint. plaint received NotifY Contractor.

Investigate complaint. More than one indepen- NotifY Contractor. -dent complaint received in -Require Contractor to propose a 2-week period measures to reduce noise.

\

Investigate noise problems. NotifY Contractor.

Target Level exceeded Require Contractor to propose measures to reduce noise.

Bablie BMT (Hong Kong) Ltd. 18 110 Tin & Associntcs Consulting Engineers Ltd.

Environmental Impact Assessment

----- ----- - --------

Action by Contractor

Investigate noisy operations.

Review noise source and working method. Increase frequency of monitoring. Submit noise mitigation proposals to the Engineer. Implement noise mitigation measures. Perform noise monitoring after implementation of noise mitigation measures.

Review noise source and working method~ Increase frequency of monitoring. Submit noise mitigation proposals to the Engineer. Implement noise mitigation measures. Perform noise monitoring after implementation of noise mitigation measures.

Doc No : 96Q I 0/007 Issue: 2'

Highways Department

5.4 LANDSCAPENISUAL

5.4.1 Baseline

Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

A study of the eXIstmg landscape and sensltlve receivers was completed during the environmental assessment stage and the results are presented in the EIA report. A detailed tree survey is recommended prior to the detailed design of the works, as part of the necessary tree felling application.

5.4.2 Construction

The contractor will be responsible for implementing the EM&A programme during the

L [

b [

[

[ construction, and the organisation and management will be as described in Section 4. C The following monitoring and audit programmes are to be carried out during the construction phase : . [

Monitoring and auditing the effectiveness of the proposed mitigation measures in reducing visual impacts on Ko Po Tsuen, cyclists, pedestrians and motorists. . L Monitoring and auditing the effectiveness of the proposed mitigation measures in [ retaining existing vegetation and cultural artefacts. ~

Babtie BMT (Hong Kong) Ltd. 19 Ho Tin & Associates ConSUlting Engineers Ltd.

Doc No: 96010/007 Issue: 2

[

[

[

[

[

[

l l [

[

[

Highways Department

Section 6

Improvement to Kam Tin Road , Stage 1 Environmental Impact Assessment

Post-Project/Operation EM&A Programme

Babti. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

L [

c [

[

[

c [

c []

[

[]

C [J [

[]

[

L [

[

[

Highways Department Improvement to Kam Tin Road. Stage 1 Environmental Impact Assessment

6.

6.1

6.2

POST-PROJECT/OPERATION EM&A PROGRAMME

PURPOSES

The post-project/operation monitoring and audit programme will be used to verify the predictions of environmental impact developed during the design stage and to ensure that unforeseen impacts are detected during the early post-project/operational stage. This will allow corrective measures to be implemented before irrecoverable damages occur. The objectives of programme are as follows: .

To provide a database of environmental data against which to determine any short or long term environmental impacts as a result of the post-project/operational activities.

To confirm the assumptions made in the design of the Project, and particularly the effectiveness of the permanent mitigation measures.

To provide data to enable the environmental audits to be carried out and to review the requirements for anyon-going monitoring programme . . ,.

To achieve these aims the environmental monitoring will be carried out on project completion and early operational stages.

NOISE

The Contractor should be responsible for implementing the post-project/operation EM&A programme for noise on project completion. The EM&A organization and management structure will be as that described in Section 4, and the monitoring methodology and equipment used shall generally follow that detailed in Section 5.2.1.

The noise monitoring will be undertaken to verify the performance ,in terms of noise reduction achieved, of the proposed noise screening structures. The monitoring locations, schedule and parameter are shown in Table 6.1.

Babtie BMT (Hong Kong) Ltd. 20 Doc No : 96010/007 Issue: 2 Ho Tin & Associates Consliiting Engineers Ltd.

(

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

Table 6.1 Summary ofPost-ProjectJOperation Noise Monitoring Programme

Item Description

Monitoring Stations MS-B,CandD

FrequencylDuration · Upon completion of each set of noise mitigation structures. ·6 and 12 months after full opening of the road to traffic.

Parameters LlO(Peak hour)

· When any of the noise screening structures do not achieve the

Additional Monitoring required noise reduction. · After remedial works are taken.

63 ECOLOGY

The Contractor should be responsible for implementing the post-project/operation EM&A programme for ecology, and the organization and management will be as that described in Section 4.

The post-project/operation monitoring and audit programme for ecology will run for one year after' the completion of the Project and will cover the followings:

Monitoring and auditing the use of Ko Po Tsuen Egretry and/or other active egretries adjacent to .the works areas along the road corridor by egrets and herons monthly during the nesting season, in view of its proximity to the works site.

Monitoring and auditing the success of the landscape planting, in terms of health, survival and growth of vegetation, by landscape contractor every 6 months.

6.4 LANDSCAPEIVISUAL

The contractor will be responsible for implementing the post project EM&A programme, and the organisation and management will be as described in Section 4.

L [

[

[

[

c c [

[

[

[

[

[

[ The post-project/operation monitoring and audit programme will last for 1 year after the [. completion of the project and will cover the following:

Monitoring and auditing the success of the landscape planting, in terms of health, [ survival and growth of vegetation every 6 months.

Monitoring and auditing the success of the mitigation planting as above, in reducing [ visual impacts on Ko Po Tsuen, cyclists, pedestrians and motorists.

Babtie BMT (Hong Kong) Ltd. 21 Ho Tin & Associates ConSUlting Engineers Ltd.

Doc No : 96010/007 Issue: 2

[

[

Highways Department

Section 7

Improvement to Kam Tin Road , Stage I Environmental Impact Assessment

Contingency Plan

Babli. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

u n

[1

[I

[l

o o []

[:

[i

o

[:

U u u u

['

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

7. CONTINGENCY PLAN

Contingency plan should be proposed and submitted by the Contractor to cater for the eventualities described in Table 7.1. Any changes in the monitoring schedule due to unforeseen circumstances should be reported to EPD and the Engineer immediately. The originally agreed monitoring should be resumed as soon as practicable.

Table 7.1 Requirements of Contingency Plan

Issue Requirements ,

Make ail efforts to acquire, prepare and install the monitoring equipment before the start of the monitoring

Delay in equipment deliv- programme. ery of set-up Inform EPD and the Engineer on the revised start date for

the particular environmental parameter in case of delay in equipment installation.

, Proceed the monitoring programme for those parameters , not affected by the delay.

-Fill in the position within 1 week of the commencement of

Prolonged non-availability the period of non-availability of any key monitoring of key personnel personnel for longer than 2 weeks.

Assign other equally qualified personnel to take up the responsibilities of the individual in question in the interim period.

Failure or theft of equip- Obtain the back-up monitoring equipment or have the ment equipment repaired within 1 week of equipment failure or

theft.

Adverse weather condi- Propose and implement make-up monitoring schedule as tions soon as weather conditions permit.

Bab!i. BMT (Hong Kong) Ltd. 22 Doc No: 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

.~

Highways Department

Section 8

Improvement to Kam Tin Road , Stage 1 Environmental Impact Assessment

Environmental Complaints & Responses

Babli. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

u n

n [j

[

[

I L L l'

L l

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

8. ENVIRONMENTAL COMPLAINTS AND RESPONSES

In the event of any complaints, EPD will liaise with HyD and the Engineer and the latter would be responsible for ensuring the implementation of necessary remedial measures and actions, in accordance with the complaints handling procedures outlined in Figure 9.

In particular, the followings procedures and actions shall be observed:

Record all complaints including complainants, details and dates of receipt onto the complaint database.

Investigate the complaint to determine its validity, and to assess whether the source of the problem is due to recurring works/activities.

Identify the problem, and determine and implement suitable mitigation measures if compliant is valid.

Undertake additional monitoring and audit to verify the situation as necessary, and address the issue in the progress report.

Record the monitoring data, results of the investigation and remedial actions taken onto the database.

Notify the complainants on the results of compliant investigation and, where applicable, remedial measures implemented.

Bahti. BMT (Hong Kong) Ltd. 23 Doc No : 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

Highways Department

Section 9

Improvement to Kam T in Road , Stage 1 Environmental Impact Assessment

Records and Reporting

Babtie BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd.

DOC NO: 96010/007 Issue: 2

L [

[

[

r [

c [

[

[

[

[

[

[

[

[

[

l [

l

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

9.

9.1

9.2

RECORDS AND REPORTING

DATA RECORDING

The Contractor should record the results of the monitoring on standard field data sheets and report to the Engineer on a monthly basis (also see Section 9.2 below). The data will then be input into a computer database which serves as a systematic method of recording, storing and retrieving data. The database will be so designed such that the data can easily be referenced in the event of complaints or non-compliances.

The Contractor's monitoring personnel should, whenever applicable, register the following minimUin information on a field record sheet:

Details on project name, monitoring staff, monitoring location/station, date of measurement and monitoring period.

Details on equipment used, including 'type and made of equipment, model/serial number, equipment settings and calibration status ..

Monitoring results for each environmental parameters.

Other relevant non-quantitative information/observations relevant to the interpretation of the monitoring results, including weather conditions, site conditions. and activities, and presence of abnormalities and extraneous activities.

The field records shall be reviewed by a competent personnel of the Contractor within 24 hours. '

A set of sample field data record sheets for noise monitoring is attached in f\ppendix B.

REPORTING

The Contractor shall prepare monthly SUll)IIlary records of monitoring data. At monthly intervals, and not more than 6 calendar days after the end of the month to which the date refer, the Contractor should submit duplicate' copies of a summary monitoring report in both printed and electronic form to the Engineer. '

The Engineer, upon receiver of the monthly monitoring report prepared by the Contractor, shall forward the report to the Auditor for review and audit. A monthly Environmental Monitoring and Audit Report (EM&A Report) will be prepared by the Auditor within 14 calendar days of the end of each month, with the first report due in the month after construction commences.

Babtie BMT (Hong Kong) Ltd. 24 Doc No: 96010/007 Issue: 2 Ho Tin & Associates ConSUlting Engineers Ltd.

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

The EM&A Report, together with a disk containing all the monitored data, will be submitted to both EPD (EM&A Section) and the Engineer. The format of the database will be agreed with EPD prior to the issuance of the first report.

Each EM&A Report will contain the information as shown in Table 9.1. While under normal situations, non-compliances and remedial actions will be addressed in the EM&A Reports, they would also need to be dealt with on a day to day basis through the issue of action plans and site instructions.

Babli. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

25 Doc No: 96010/007 Issue: 2

L [

C t:

[

[

c [

[

[

[

[

[

[

[

[

[

l [

l L

.~ , r: r: r: r: r: r: [""""J rJ rl Ll r-l r-:J Ll r:-J rJ r: rJ C"""l rJ Improvement to Kllm Tin Ro:ul, ,stllge I HighwflYS Department

Environmental Impact Assessment

Table 9.1 Contents of Monthly EM&A Reports

- --- --- --

Issue No. Item

1 An executive summary. General

2 Briefproject background information including project programme, organization and management structure.

A summary ofEM&A requirements including: (a) all monitoring parameters: (b) environmental quality performance limits (trigger/action/target I levels), (c) Event/Action Plans, (d) recommended environmental mitigation measures, and (e) environmental requirements in Contract Documents.

2 Drawings showing environmental sensitive receivers/elements and locations of the monitoring stations.

All monitoring results (in both hard and diskette copies) and other relevant information including: (3) nionitoring methodologies, (b) equipment used 3 and calibration details, (c) parameters monitored, (d) monitoring locations/positions, (e) monitoring time, frequency, duration and period, (t) weather

conditions during monitoring, (g) site activities during monitoring, and (h) other factors that might affect the monitoring results.

4 A summary of non-compliances (exceedances) orthe environmental quality performance limits (trigger/action/target levels). Monitoring

5 A review of the reasons for the non-compliances including review of pollution sources and works procedures/methodologies.

6 A description of the actions taken in the event of non-compliances and any follow-up procedures related to earlier non-compliances.

7 A record of all complaints (written or verbal) received including nature and location of complaint, liaison and consultation undertaken, actions and follow-up procedures taken.

g A forecast of the works programme anCi monitoring schedule for the coming month.

9 Comments and conclusions for the month.

Dabtie DMT (ilong ](ollg) LId. 26 Doc No : 960 I 0/007 Issue: 2 liD Tin & Associates Consulting Engineers Ltd.

I

~

.--, , r--;

Highways Department Improvement to Kam Tin Road, Stage t Environmental Impact Assessment

Table 9.1 (Con't)

Issue

Audit

No.

I

2

3

4

5

6

7,

S

9

10

II

Item

A summary on the checking and validating the monitoring results.

An analysis and interpretation ofthe monitoring results to establish an environmental profile at the time ofaudi!.

A summary of on-site inspections and investigations to identify sources and cause of non-compliances and unacceptable impacts.

A review on whether the Contractor fulfills the contractual and statutory requirements, licensing conditions, etc. relating to protection of environment.

A review on whether all mitigation measures are properly and effectively implemented, and the anticipated protection/mitigation achieved.

An assessment ofthe accuracy of environmental impact predictions by comparing the predicted impacts with the actual impacts measured.

An assessment of the effectiveness ofthe environmental management system, practices and procedures.

An identification orany remedial measures in case or non-compliances and improvements in management, control and operations if environmental objectives are not achieved.

An identification of any environmental problems/impacts which may be encountered in the near future and the associated resolutions.

An investigation of complaints received and the actions taken.

A review of the overall monitoring philosophy, in terms of procedures, location of monitoring stations, monitoring frequencies, parameters measured, test methods, acceptance criteria, etc.

D.btie DMT (Hong Kong) LId. 27 Doc No : 96010/007 Issue: 2 1-10 Tin & Associates Consulting Engineers Ltd.

r; r: r-1 r--: rJ rJ r-:-l r-J r-l rJ Cl r-J Ll c-1 rJ lJ C"I rJ ;--

Highways Department

Babti. BMT (Hong Kong) Ltd Ho Tin & Associates Consulting Engineers Ltd .

Figures

Improvement to Kam Tin Road , Stage 1 Environmental Impact Assessment

DOC NO: 96010/007 Issue: 2

[

[

D

[

[

c o c [

[

[

c c o [

[

[

[

[

[

Highways Department Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

List of Figures

Figure I Works Limit of Proposed Road Improvement Works

Figure 2 Preliminary Construction Programme

Figure 3 Noise Sensitive Receivers and Representative Sensitive Facades (Sheet I of2)

Figure 4 Noise Sensitive Receivers and Representative Sensitive Facades (Sheet 2 of2)

Figure 5 EM&A Organization and Management Structure

Figure 6 EM&A Procedures

Figure 7 Noise Monitoring Stations

Figure 8 Event/Action Plan for Noise Exceedance

Figure 9 Complaints Handling Procedures

Babtie BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

Doc No: 96010/007 Issue: 2

r; ~, r-l ~--L_,,_' __ I""}-_L_,._." . .J __ r-J __ ~_ .",. __ .i __ ~ __ ~ __ ~ __ ~"" '-~--~-.~--;-~--:---;--~--L. __ .. .J-~--,--.--..,

~ :-'-'-(' 1\ "'to ,.... .,/ I 0 - -i. .... ("'" \ II'" '" ·····J\1 ~ .",-.~.~. .... .' . • 0 ~ ..... _.~....,. ... , 1_... .'. . "_ . .1.. \ J ,"'" ,. -

~n r~ ""Ii> ;I,l.~ ~ ,,0 I ] .. -I"'-·-;:::::::::...···········:~-···I~ • .1" .. : ... ..;,' ~~f-";' ",.' C· ,. ~: f Jr-h'::::';'''' I....... ..- r)'f:r-I\ .. ..J ~ , J)- i.·:8 , 1[::.-.. ···,.· ...... _ ..... "',0'-'. ,\II)4,,;,\t,'3Jlli 11U I I"" \ . .'Q ','- ,'tl' ~Q' ".1"11,1\ 0 '. ~'" 1m .... (~. I"" ::1.. I.. /.,,~ .. I;"; I..' { . ..,. ! l • ..';'1 <U ...... ... - ...... ",\ rt ....... , I',,· ~'\ •. :0.,:: •• •• •• ..Iii ....... : .... /

.\ll ~/ \\ ;;(""1""'0'''-'::''/' '\- "', "oc·Jp·_···;·" \ .. 11;; \")1.):((; (' .'Ut.I'i!,1l-·lV~·' I. .. ~j :;; .. " \:' i" I '. \ r II ..d.~,1; · ..• i •... ·... IIi u \ , •. L ... ··) I'~ .' .-.... " .... ~,. I .. -:: ...... , rJ \\ I 0 D I ,,,C, o'~.~"":.<>-.'.. , ... __ ",;:: ')1-""" _.' 3_' 1 ..... -.. -.. :> Il, , (, ,I' V-\ ,,0 . N I I·"

.-/ '.:.::: ~~f.""'·l- . '!::::l"" II) l' ,.,-- ..... ,Q \. /." . "4' \ ." ,\ 'n' !... '\.-''''-''. ,.:;" / i~' r (J _,., . ',"-"'.( \ ',.J;,,". { )."1 ,,;( '. -'" ;:00"'\« ,;' ,-" 'I ! . /' " \\~ i ,I;. "'?s'" \tr '\ ir"'Q.-),;j., /'·· ... u/ 1r·""'··· "j lin"'\."f:U~:>!·\!ii·"Ap.! . / /

! a.,.~J,,~~oLi"·"ao· ~ ~'" (. ,PR'dpOS~D 'STlJ6Y "AREA'V,H 1\P.iJk.JW(J;,~t'U;,,,,,.,"'t~.;J\:.· -.(-----L._.. 1'/ / .-::~ ; '/i ',\. \. "\\. ...... ".. .. .. J( '., ) ,/;,..[--.1 T C1 \-r5~~. ~ -l~

I) i;-..... -I U .i . ,i,l i .' .,'1: /'\~ \ .} 1 '" "-.~ __ ~"~'::!.'~.:J ...... , ....... /. ... /:(' .. 1 .• '/'1 ~J ~~t~ en ~ ' .. u~~ • ~~t'l~\1L1../" : --r-'-:\ Q I, ': \ • ".. ~ . ., •...••.••• ~ --"---' .• , .•...• '-:.1 }.,: • r • , '. ~.~ !i,iiAJC::';1 ~"'''''-':'''' •

g '. • Qg; . "'fe ". •••• I ............. ____ ... - ... _ ••••• ~ 7 .. I, ... ,'.' I; '. \ I ... !:' .... df'. ,~: ~" ............ 0 I. :) 01 !-.?ll' 0 Au" "Shin.::.! Uel .i/" ~ , .. ./ PROPOSED WORKS LIMIT ' .. : 1 .-.... ( \ ~,!\( '\[I"O"~l1" ·f·1·/~··'$;.,)· ? "! ,. 0';" ~II y... {,\ I"~\' • ~'\\i ·I,~\;I:·:I"·I/· )'''~' .. ''"> • 834

_",.,...--_ -..... ~ .... -i-.,I,',.,.--..... - ..... \ .... 'n......... . ... _~....-... _ .... __ .~ .. L.""'_"i{ ...... ..:I,. ___ l. __ ~J:r_'-";"'iL-"\lF.',';;::':::l:-f--"~'c..:"-;'" .. -L.~----. " ..-'i! Tau ... I///n \ J ".! .. , . "I '\' .. ~ :a.i;r.:.·.. l( if ;Ii.. 1·····( (' ....... ,,' '.or I .. H.I ·!,n··· "., -'r \"q,1J .... I'· :) ~F .. ' on." , •.• ··r (! ~.~,. .....: .. ,. Ir. .. !~.."... / ......... J !, .(/-. ..... :::, ;.:. .. -: ....... ::, ...... ~y~., ... ,(~?:;i::·''>', l ~,:.o·· I ""0 ';

L n - i .' . -; , ,., .' '"., .. , .. ' ... ]>,,: .. :. I i I \ I;! .... ,.".. '. ,;:.,,{, "': ;'/' ',i n '[~o" ,', '

~~~r-~' t:::~(;;ll¢ }~~,::}:{<;~}:'(l(>l~~ ! j!!(~tt~~:;2ir!t/~,,!!f'·,<:>~\ · t·} ,::gil nIl,' r- i i . .:..~~ .. \_1'; ;-. n::'ci'·i~·. I "\ ".f t )····.1 . I} ·.!,~i,{J,::f' ~","q n K A M ,\.\. T I ~II .~~ r "~;;3JL .~ I :.:._ -~"'. ....·.4..· ,'..... . ... , ,o.' .. ". ~ .. ·;~:·i .' : ':. .. \ f\l1 I.' , Irl b . :: ':.:... ~~ if.··· ~ I ./ "' I~ . .... , .:: ....... _ ....... ! .. ~. .,', ;'~ .... ~.~..... I i \\g !ao "t"I

\\9'1 f;~ ~ I .... :."!j. ~~··'oIJ:' i· .. · .. ···,' /: ······ .. ··:)r .. i! . ~'.... .:~:"~ .. (jr" !. ~ ·:.~::;::·E·~-;;--· ... i'.',' II liii 21 ~ :. '. "'.' " ii.. . w·.,· \ .' ~; Kam, Hlng \; "'.J\ .})/O"1 1~ .. II il ....... '\' .... :'!i.\ ·\'r··\ ... : .. "1 ~ (II!, ";, , ~ ~..... ._.. II ~ -.. ' v • . . " c I{ ll§e;,?!, !i 1 I ',,,' >- :Ko Po .:. '.;1 \ ,. " '" .' WO, " , • \~ , q ~::. , n '/ . '" . \' ,", \ . . I r:" c {1eo I... \ ::£: :... L;'U . ~'I L I.\c:.0 // : ',. T .! . t\u· I \ ~". ,"\: '1 r.lo(f' L~" \\ \ .... s:;;h)! \; .. ) 'i.' F'~ ~ suen .. ' t'" ,,~,\\ ·::·'···JK r \~ ,,!!, ,; r~';, :"; >,\:1". ."'. : .. ~. ';:,'JDi ¥~~~~ ~'--'-''':--'':~--f-- ........ ---.. -:-.... -......... .;;;:. ...... f:-:~· .. .:J::~··i ,j.~ :&~./.;;;:~;::/)~· ... _ .. ·W,·.m..··_ .. 9m · .... ·~0..~ft ';")~;"-"-4 ~,I. ~!'i.!.:'~,f:i(-.. : .0 sSt

. ': .. ;0..... (\ .... j ' .. , :i'! {iif i, " ........... ~ .. "'" I \\!I SR, '.; 'I)"~ f;l':""~"il, ·?'·V,~'lih,.'~d/f!)l!~ f. ." • ..;; .... ~... ~ -l • • :.t ••• : • , ". I . ,1\ [·· .. 1 .. 'Ir. I.: ,. 1"1 ·t'.... . ~ ....... '1/: • "'{'}.'t':'{· •

I)' .... , .... '\ •• ,) .. I . .. I . .... ··l.. \:\1 ..... : •. :/111. 1/:. ;/9,,' ~rj le"J. ..•. a·V8· ::11 ,:/\':~J. ;;;(i~;"'\ ! "'. !' ! "I/i" ,.... I ) ~,~;~:= :.:.:.:::::~~:::;~~.:.ll~:~:·. :: .. --ii·····;·;~::·:1Ik11.i,i=:i;~jb~!~;~I{-:.~" 0 ~\. 0; ~ i~\ "\\ \ i '. ..~. 0i :: I( j :. ... : I: ( . .l". )~. . ..... ' :_ .. 'V ) .... :.x:.:: .... :.,'l~!. ::;;/ . :~~:M ':)~~~f7~-*~b -~

.: \'0 Q ''''j~t_.~J i .1 jl ' .. i! :,.1" ':1 ~~ j'('] '1::"'":::\.\ ·.!lI" ('r'1~~j,~ i'" r4::.~nt":\llrJ,' i /I :. (\ : 'V \\0 \':-. l r/ :','''. ··i' .... , ... '-_ .. ~ ... ! "',Ii'. '~I Mt . . .' r.:-, ;,tI .,.

t." PROPOSEQ CENTRE !L I NE, . ;, i;·!<q; Po ".:;, .... , ..... ~?' .... '.' ! .. ,:.;: .• :.:li.t.Wai"g!{, '1~1 iSR.9g:;;.~H ~~jQ~."ng /, " OF. KAM I I N ROAD! '. I .In ' ::\ Son, T suen ',' !.:! .: '. Ii il .. ···:··".······::·:···· .. _~::!::2!Jen "f· $1l=':1--:· .. ·y

u \Y':~· ~ " .. ! \ / .. --t.. / :/1 ~ ,..' ,. ,\, 1 . . .... ".: .~- .••• ::::: .. - •. ~.:..-: .. I) C :/ ~l. i~·· .D " •• ~),.~ ~,:". I 'l 1 .: ~,,,,··rJ ... :~~ii • .' '.J .: " ".::: ......... /' : .......... -.-•. :: ... n... ;:'.fo":~~

c '!i4.J ·/:.~ \J. \ ./ . ,1,.1. '.... ......1,........ ....• ':: ;/ ~", ." ..... r";'·:::·;(.\·a,.,:\'Ij~.

:~;::;-Tf.~t ;;~:£2'jf-:-~:~:-::-~--;~~;,l,,:;.z~---~;f:!~1:~r,~-:t:~;~~!,f?~\;:-,I:t;~§ Scale 1: 1 0000

FIGURE 1 WORKS LIMIT OF PROPOSED ROAD IMPROVEMENT WORKS

BABTIE BMT (HONG KONG)L ID. HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD.

----, r-: r-: r-: r.J .Lj Lj CJ LJ r::J r-J LJ r:-J c-J c:J CJ LJ rJ r::J LJ 'I

Activities/Month 1 1 1 2 1 3 41516171819110111112113114115116117118119120121122123124125126127128129130

1. Preliminaries, Site Clearance and Mobilization

2. Excavation

3. Back Filling and Subbase

4. Drainage and Utilities

5. Kerbing

6. Road Paving on Widened Portion

7. Breaking of Existing Road Surface

8. Drainage and Utilities

9. Back Filling and Subbase

10. Kerbing

11. Road Paving and Road Sign

12. Footpath

FIGURE 2 PRELIMINARY CONSTRUCTION PROGRAMME BAnTlE BMT (HONG KONG) LTD.

HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD.

o o o n fl !

:0 i

10. I

io.

0.

0.

0.

10

o o o o 0.

o 0.

C.

I'

Legends

• Noise Sensitive Receiver

~ Representative Sensitive Facade No. AT-l

CD Industrial Development/Godown/Open Storage

§ Other Non-sensitive Development

(e.g. Community Centre, Grocery, Farm. Storage Shed, etc.)

@ Ruin/Abandoned Building

@ Building Removed

@ Building Substantially Protected by Topographic Features

@ Building Resumed by Route 3 (CPS) Project

@ Building Resumed by Western Corridor Railway Project

NOISE SENSITIVE RECEIVERS AND REPRESENTATIVE SENSITIVE FACADES

(SHEET 1 OF 2)

",,-'

-.

. '.

:t" • ..

1 .

. i,,>0,1~;]', . .. /).,/1/.;,.:, " ,. '. ',~' ,~ ....... "" ,:< . ". ../ / reter;ll'l. .. .,.. ';" ~·~·~m-::,:--:=::!::"",~~':'=::3-==::;

FIGU~ 3

. BABTIE BMT (HONG KONG) LTD. HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD.

u o o

o o o o o o o o o o o o o o o [1

-H AT-l

CD 8

§ ~

Noise Sensitive Receiver

Representative Sensitive Facade No,' AT-l

Industrial Development/Godown/Open Storage

Other Non-sensitive Development

(e.g. Community Centre, Grocery. Farm, Storage Shed, etc.)

Ruin/Abandoned Building

Building Removed

Bu1dingSubstantially Protected by Topographic Features

NOISE SENSITIVE RECEIVERS AND REPRESENTATIVE SENSITIVE FACADES

(SHEET 2 OF 2)

_.-

'" __ .. J.I'~ ,;£-. ,.... "

\ , ~l'" Meter 20 0

;PO ••. ,

20

/

f ,

, \' " 40

. :1': ," -'U'/' ':;; .. ,

.:.::/

"-, .. ~

.. _.J;;. ::';:;::::::':-';'-,'::::_'':: ; ..... ,.,

.' :/

.. ,

\, 'j I

60

~. ~. \

8(l , .. :-" 100 120 140 160

FIGURE 4

'"

•....

.~ "

-'-'-~~' :' , '.\"

200 ..

BABTIE BMT (HONG KONG) LTD.

..... -,

.•..

:~.

HO TIN & ASSOCIATES CONSULTING ENGINEERS'LTD.

----"J , . " '"- . " . " '--" ,-, .. ~ ........... --' L _ ___ ..J .... -----' '-_. _ ._ • .J c. ., '~ _ .... J l., ,_ j l...-_.,~, J '--- , , , , , , r---"!

, liaison ___ Client Department EPD EM&A Section '----,-_.-(Highways Department)

I I I I

audit 'monitoring reports L _liaison __ I

I~-, reports Engineer

I audit reports, recommendations &

Independent improvements

I Environmental monitoring supervision Auditor reports I

~ _____ liaison ______ I I

I I liaison

'. Contractor

w~ I

'-'\ -.' -~.

I monitoring I supervision

I resultsl I reports

I I liaison L ___________ --..

Environmental .-_-.l Sub-Contrator

FIGURE 5 EM&A ORGANISATION AND MANAGEMENT STRUCTURE

BABTIE BMT (HONG KONG)L TD. --.--.------~----,-.- --------_. -------

HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD.

~ r-: r-: r--: r-J r--: r--: c:J C"J C"J r--: C"'"'J r-J C"J Cl C""l .:-:-:J Cl co r-J l~ . i 1------

Implementation ofEM&A Requirements L ___ 1_ - - ~j-oII"I--------,

Responsibilities

Engineer r, ~..J

Contractor! 0 Sub-Contractor

Auditor D 1- - - ~

EPD , , 1 ___ ,

Prepare reports for Engineer

r----J - -, Review reports and send to Auditor 1

• Monitor noise/ecological elements

• Prepare recond sheets for Engineer

is No ./' there

exceedance of trigger I action/target

levels?

Yes

r-- - -, I Implement parameter-specific 1

event/action plans L_] __ ..J

• Implement mitigation/remedial measures as requested by Engineer and to meet environmental requirements

• Include details of remedial actions in monthly report

Recommend changes to improve environmental perfonnance

Increase site". monitoring inspections

r------------~-----I ,. , I Make recommendations and I

: decisions on non-compliance : • ____________ ~ _____ J

j

L ____ ]_..J Are

. - Y Prepare audit reports from • high/regular >-____ e_s ___ .,-__ -.-1 Contractor's reports and Auditor's site Exceedances? inspections

No , I Report to H~~ and EPD JI--------------'

FIGURE 6 EM&A PROCEDURES

BABTIE BMT (HONG KONG)L TO. HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD.

--,

~

'\ ~ \:-~ '----"":'\j:H~ ili :"~'9';::HO HOK SHAN

\ ',- .. ,;, . ; ~ ".,,1 :; / " / /

... '}- \ 1 !'! /

'~" I"

:' ,..--', \' : '-../ ; /: '-' ,

~~~--~> ioJ

1, ~\loe.~ I :. ,

• (\' en i:>' .0 '(1) 'I\>g\ 1/; ~> ''\ c::> r":" 'II) \. ; , , -.., '< "V'" \ I ' __

(i.. 'L ~-,"TTl I )1 ""'r-' ,! ~',' I - --ll.I --.......... r-... ':',.1 ~ ... :: ,~ -;=! " ! ~

-'-.\ [~, ; -" - ~l\ ,I' __ • tV • ..- 4 l.l 0-.",

, , _., ...... t\ ~ (1,( "", :, ...- \ I' --~,.-' ... \'" :-./" \) \.11; ·.~L_ JL, '. :.::L~,,_(';,~()(

-- r J ' ('.'--"!;,, U, ,--- ,'~ I ~i.> " •... :.)

! ' ~ • ti \ I \ •• ~ 0 '\' , , ~ II~' ,.

' '. ',/1' :'J' ' '" ," f~r=:-I \'t, "L:>., 01.., I., : I? ' ; r:: I C"'-, It , '\ J . ...r ,...... ; •

NOISE MONITORING STA nONS

C"J r:J C":l

, !

U· WOlltS on progress

i

!

1 :5000

C"J C"J c-l ::-J

\LJ Legend C"J - CD ':--1 -,

Noise Monitoring Station MS-A

FIGURE 7

BABTIE BMT (HONG KONG)LTD: HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD,

-'

L

Monitor noise level

Complaint received or target

level exceeded?

Yes

No

Is target level No exceeded?

Yes

• Review noise source and working method • Implement noise mitigation measures • Peform noise monitoring after

implementation of mitigation measures

, --- , I No action

L --- -.J

More than one

complaint received in a4 weeks

period?

Yes

No

,-- ---, Investigate complaint, instruct I Contractor to increase frequency of I I monitoring I '--------'

,---, Investigate complaint

L ___ -.J

Responsibilities

Engineer ,--, L_...I

Contratorl 0 Sub-.Contractor

[l------------.--:------========='-l FIGURE 8

L EVENT/ACTION PLAN

FOR NOISE EXCEEDANCE BABTIE BMT (HONG KONG)LTD. HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD.

I [

[

[

r c c c c

,

[

c o

o o c [

c C-

[

[

1

I L

---- 1 1 ---- 1

I Indirect Complaints I L ---- ~

Direct Complaints I ---- ~

1 --I - - 1

I Notify Engineer I L ---- - ~

1 -, - - - - -'- -'I

I • Carry out initial investigation I I

• Identify source/review working method I • Request subsequent investigation

I work by Independent Auditor I L ________ ~

1----1 r---------------~~

Implement mitigation measures

Environmental monitoring

1 --1--. -, exceedances 1

~------------.----I Compliance Check I L ~

= = Iceptable= 1 1 I Report in progress report I L _____ ~

I Reply to the complaints I L ____ ~

Responsibilities

. Engineer

Contrator/ Sub-Contractor

FIGURE 9

,-, L_.J

o

COMPLAINTS HANDLING PROCEDURES BABTIE BMT (HONG KONG)LTD.

HO TIN & ASSOCIATES CONSULTING ENGINEERS LTD.

Highways Department

Appendix A Abstract on EAD Operation Manual

Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

Appendix A is an aostract on EAD Operation Manual, Chapter 5, Environmental Monitoring & Audit of the Major Development Projects (Appendices B and C) prepared by tbe Environmental Protection Department. This appendix contains tbe following relevant sections of the operation manual:

Appendix B Engineer's Guidelines for Implementation ofEM&A Programmes

Appendix C A Selection from tbe EM&A Protocols

B.b,i. BMT (Hong Kong) Ltd. H~in & Associates Consulting Engineers Ltd.

Doc No : 96010/007 Issue: 2

L [

[

[

[

c [

c [

c c c c [

[

L [

[

[

[

HIghways Department Improvement to Kam Tin Road. Stage I Environmental Impact Assessment

I.

2.

3.

Engineer's Guidelines for Implementation of Environmental Monitoring and Audit (EM&A) Programmes

Prior to commencement of works the Engineer shall review the Environmental Impact Assessment study final report for the project in question and ensure that he and his environmental monitoring and audit (EM&A) team review and perform in accordance with the requirements set out in the EM&A Manual, agreed with the EPD.

The Engineer shall incorporate agreed pollution control contract clauses into tender and contract documents.

EM&A Manual: The Manual shall be a stand-alone document and shall be reviewed and revised as necessary during the EM&A programme. The Manual should include the following:

(a)

(b)

(c)

(d)

(e)

(t)

(g)

(h)

(i)

project background including organisation and programme;

purpose of the manual;

an implementation schedule, surnmanzmg all recommended environmental mitigation measures with reference to the programme for their implementation. The measures should include those identified at detailed design, contract preparation, construction, and operation stages of the project;

drawings showing all environmentally sensitive receivers;

an EM&A programme for the construction of the project including:

responsibility for EM&A work; EM&A organisation and management structure; EM&A methodology; equipment to be used and calibration required; locations, parameters, frequency and duration for baseline, impact and compliance monitoring; environmental quality performance limits (Trigger, Action and Target levels); Event-Action plans and decision audit flow charts; procedures for reviewing the monitoring results; compliance audit procedures and follow-up;

implementation programme and impact prediction review procedures;

site inspection, deficiency and action reporting procedures;

complaint/consultation procedures, and

baseline, monthly, quarterly and any other reporting format and procedures;

Babti. BMT (Hong Kong) Ltd. Doc No : 960101007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

Highways Department Improvement to Kam Tin Road. Stage 1 Environmt;!ntal Impact Assessment

4. Prior to contract commencement, the Engineer shall establish an independent EM&A team which shall be responsible for the implementation and execution of the agreed EM&A programme. The EM&A team may form part of the resident site staff, but should be independent of the contractor for the construction phase of the project. Consideration should be given to setup an EM&A team for the post-project and operational stages, if such monitoring works are required.

5.

6.

7.

The Engineer (his EM&A team) should acquire the stipulated environmental monitoring equipment through an appropriate means.

[Note: In many cases the Engineer would rely on the contractor responsible for the construction works to provide the morutoring equipment. This approach often has the drawback of delaying the commencement of the EM&A programme and making it very difficult" to acquire sufficient background information before work begins. Therefore, as far as possible, equipment shaH be ready for use about 6 weeks before contract commencement by the Proponent, the Engineer, an independent laboratory or any other means acceptable to the Proponent]

The Engineer shall recover, if not already available, the baseline environmental profile of the works area through baseline monitoring as specified in the agreed EM&A Manual.

Baseline Monitoring Report: The baseline monitoring report should include at least the following:

(a) up to half a page executive summary;

(b)

(c)

(d)

(e)

(f)

brief project background information;

drawings showing locations of the baseline monitoring stations;

monitoring results (in both hard and diskette copies) together with the following information:

monitoring methodology; equipment used and calibration details; parameters monitored; monitoring locations (and depth); monitoring data, time, frequency and duration;

details on influencing factors, including:

major actiYities, if any, being carried out on the site during the period; weather conditions during the period; other factors which might affect the results;

determination of the Trigger, Action and Target Levels for each monitoring parameter;

Babtie BMT (Hong Kong) Ltd. 2 Doc No: 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

L [

[

[

[

[

c [

c [

[

[

[

c [

[

l [

[

[

[

L [

o [

r [

c [

C

[

[

[

o [

[

[

[

L [

Highways Department Improvement to Kam Tin Road. Stage I Environmental Impact Assessment

8.

9.

(g) revisions for inclusion in the EM&A Manual; and

(h) comments and conclusions.

The Engineer (his EM&A team) shall carry out or supervise his laboratory or Contractor to carry out regular monitoring as stipulated in the agreed EM&A Manual, and shall audit the monitoring results. The Engineer shall also inspect the work sites regularly and initiate appropriate actions as per the agreed Event! Action Plan contained in the EM&A Manual.

Compliance Audit: Compliance audits shall be conducted in conjunction with the environmental monitoring programme as specified in the EM&A Manual. Compliance audits shall include:

(a)

(b)

(c)

(d)

(e)

(t)

(g)

(h)

(i)

(j)

inspection and validation of the monitoring procedures and results;

organisation and presentation of the monitoring data;

analysis and interpretation of the monitoring results to establish an environmental profile at the time of audit;

verification that the monitoring results are in compliance with established environmental quality limits (trigger/action/target levels andlor any regulatory requirements) and documentation of any exceedances;

on-site inspections and investigations to identify sources and causes of non­compliance and unacceptable impacts;

Inspections to ensure the Contractor fulfils the contractual and statutory requirements, licensing conditions etc., relating to protection of environment. Such inspections mayor may not involve sampling for analysis which is not covered by the regular monitoring. [Note: Should noncompliance associated with the works be proven through sampling and testing, the Contractor shall be liable for all such expenses incurred.]

inspection to ensure that all environmental mitigation measures are properly and effectively implemented, and review the adequacy of the implemented measures;

comparison of impact predictions with the actual impacts measured to assess the accuracy of predictions;

assessment of the environmental management systems, practices and procedures;

identification management, achieved;

. , of remedial measures if noncompliance and improvements in control and operations of environmental objectives are not

Babti. BMT (Hong Kong) Ltd. 3 Doc No: 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

Highways Department Improvement to Kam Tin Road. Stage 1 Environmental Impact Assessment

(k) identification of potential enviroI1IIlental problems or impacts associated with the programme works and the works method statement and identify solutions to avert or minimise these impacts;

(I) investigation of complaints from residents/sensitive receivers and actions taken when the complaints are received; and

(m) a review of the overall monitoring philosophy, in terms of procedure, location of monitoring stations, frequency, parameters measured, test methods, acceptable criteria, etc.

10. Monthly EM&A Reports: The results· and findings of each audit should be documented in monthly EM&A reports prepared by the Engineer (his EM&A team). Monthly EM&A reports shall include at least the following:

(*: Where applicable, items which have already been included in the EM&A Manual need not be repeated in each monthly EM&A report unless there are substantial amendments.)

(a) 1-2 pages executive summary;

(b)* basic project information inc!uging a synopsis of the project organisation, programme and management structure, and the work undertaken during the month; .

(c)* a brief summary ofEM&A requirements including:

all monitoring parameters; environmental quality per(ormance limits (Trigger, Action and Target levels); Event-Action Plans; environmental mitigation measures, as recommended in the project EIA study final report; environmental requirements in contract documents.

(d) advice on the implementation status of environmental protection and pollution control [mitigation] measures, as recommended in the project ErA study report, summarised in the updated implementation schedule;

(e)* drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

(f) monitoring results (in both hard and diskette copies) together with the following information:

monitoring methodology equipment used and calibration details parameters monitored monitoring locations (and depth)

Babti. BMT (Hong Kong) Ltd. 4 Ho Tin & Associates Consulting Engineers Ltd.

Doc No : 960)0/007 Issue :-2

L [

[

[

[

[

c [

C c c c [

o [

C c c l [

r

L [

C [

[

[

c [

c [

[

o o [

C

l l [

[

Highways Department Improvement to Kam Tin Road. St:lge 1 Environmental Impact Assessment

11.

monitoring date, time, frequency, and duration;

(g) graphical plots of trends of monitored parameters over the past four reporting periods for representative monitoring stations annotated against the following:

(h)

(i)

major activities being carried out on site during the period; weather conditions during the period; and any other factors which might affect the monitoring results;

advice on the solid and liquid waste management status;

a summary of noncompliance (exceedances) of the environmental quality performance limits (Trigger/ActionlTarget levels) [see e.g. in Table 1];

(j) a review of the reasons for and the implications of noncompliance including review of pollution sources and working procedures;

(k) a description of the actions taken in the event of noncompliance and deficiency reporting and any follow-up procedures related to earlier noncompliance;

(I) a summary record of all complaints received (written and verbal) for each media, including the locations and nature of complaints, liaison and consultation undertaken, actions and follow-up procedures taken and summary of complaints [see e.g. in Table 2];

(m) a forecast of the works programme, impact predictions and monitoring schedule for the next three months; and

(n) comments, recommendations and conclusions for the month.

Quarterly EM&A Reports: The quarterly EM&A summary report which should generally be around 5 pages (including about 3 of text and tables and 2 of figures) should contain at least the following information:

(a)

(b)

(c)

up to half a page executive summary;

basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of work undertaken during the quarter;

a brief summary of EM&A requirements including:

monitoring parameters; environmental quality performance limits (Trigger, Action and Target levels); and environmental mitigation measures, as recommended in the project EIA study report;

Babtie BMT (Hong Kong) Ltd. 5 Doc No: 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

Highways Department Improvement to Kam Tin Road. Stage 1 Environmental Impact Assessment

12.

13.

(d) advice on the implementation status of environmental protection and pollution control [mitigation] measures, as recommended in the project EIA study report, summarised in the updated implementation schedule;

(e)

(f)

(g)

(h)

drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;

graphical plots of trends of monitored parameters over the past 4 months (the last month of the previous quarter and the present quarter) for representative monitoring stations annotated against the following:

the major activities being carried out on site during the period; weather conditions during the period; and any other factors which might affect the monitoring results;

advice on the solid and liquid waste management status;

a summary of noncompliance (exceedances) of the environmental quality performance limits (Trigger/Actionrrarget levels) [see e.g. in Table 1];

(i) a brief review of the reasons for and the implications of no.ncompliance including review of pollution sources and working procedures;

G) a summary description of the actions taken in the event of noncompliance and any follow-up procedures related to earlier noncompliance;

(k) a summary record of all complaints received (written and verbal) for eachmedia, including the locations and nature of complaints, liaison and consultation undertaken, actions and follow-up procedures taken and summary of complaints [see e.g. in Table 2];

(1) comments, recommendations and conclusions for the quarter; and

(m) proponents' contacts and any hotline telephone number for the public to make enquiries.

The Engineer shall liaise with respective organisations and parties in the case that complaints are received, and to investigate the complaints and initiate appropriate actions as deemed necessary.

The Engineer shall continue the monitoring and auditing programme to the end of the agreed period. Meanwhile, there may be a need for ad hoc liaison meetings between the Proponent, the Engineer, the EM&A team, and the EPD. There may also be a need for briefings and presentations to the Advisory Council on the Environment, District Boards and other interested parties.

Babli. BMT (Hong Kong) Ltd. 6 Doc No : 96010/007 Issue: 2 Ho Tin & Associates Consulting Engineers Ltd.

L [

C [

[

[

c

[

[

[

[

[

c [

[

[

[

[

[

L

r-lr-lr-Jr-lr-ll"Jr-lc::""""JrJr:-lr-lr:Jr:::JL""""Jc:::-:J Highways Department

Table 1 Summary of Compliance/Exceedances of Criteria Levels

Environmental Jul94 Aug 94 Parameter

Total Action Target Total Action

Air 13 0 0 5 0

Noise 248 0 0 253 0

DO Surface 320 0 0 448 0

DO Bottom 160 0 0 224 0

Turbidity 747 105 26 702 112

Total = Number of monitoring events undertaken Action = Number of monitoring events exceeding the Action Level Target = Number of monitoring events exceeding the Target Level

Ilabtie IlMT (I long Kong) Ltd. 7

110 Tin & Associlltcs Consulting Engineers Ltd.

Target

0

0

0

0

33

Sept 94

Total Action Target

IS 0 0

243 0 0

408 0 0

206 0 0

614 83 15

r-l l"J .:-J_ .. J r-l r-Improvement to Kam Tin RO:ld, Stage I

Environmental Impact Assessment

Doc No : 960 J 0/007 Issue: 2

Ilighways Department

Table 2 Summary of Complaints

Environmental Cumulative No. Parameter Brought Forward

Air 0

Noise 3

Water 0

Waste 0

Total 3

Babtie BMT (Hong Kong) Ltd. 110 Tin & Associntes ConsuUing Engineers Ltd.

No. of Complaint

Jul94 Aug 94

0 0

0 0

0 0

0 0

0 0

8

Sept 94

0

0

0

0

0

Cumulative No.

0

3

0

0

3

Improvement to Kam Tin Road. Stage 1 Environmental Impact Assessment

Doc No : 96010/007 Issue: 2

l"lr-lr-lr-lr-lr-Jr-Jr=Jc-:JC'"JrlL":lC'Jr-lc:::-:Jc-Jr-Jr-Jr-Jr-Jr-

L

[

Q

['

[

[

c c c c [

[

[

C ['

[

[

[

[

[

Highways Department lmprU"t!IlIl:la lU l'I.:.UII 1111 I'\.uau ... .H.,::;e l

Environmental Impact Assessment

A Selection from the EM&A Protocols

BmU Standard Air. Water and Noise Monitoring Requirements

(1) Introduction

(i) The objective of the following notes is to provide guidance to staff on typical monitoring requirements for air, water and noise and respective specifications Vlith respect to the following:

- monitoring equipment - selection of monitoring site - positiOning of samples - calibration requirements - data collection - laboratory measurement/analysis - monitoring requirements - Trigger! Action!f arget levels

(ii) These requirements and specifications are prepared primarily based on the needs of the EM&A programme for construction. Nevertheless, these requirements represent good practices (e.g. the equipment requirements) which may also be considered for general monitoring works.

(iii) It should be noted that these kind of monitoring requirements and specifications should in fact come from the respective environmental consultants for various EIA studies and should form part of the EIA recommendations. In another word, these notes are to facilitate our staff in (a) guiding the consultants to draft up EIA recommendations and thus an EM&A Manual; and (b) checking if the consultants' recommendations and proposals are up to our requirements.

(iv) Therefore, these guidance notes should be read in conjunction with relevant EIA recommendations and other environmental specifications for the particular project, which stipulate the responsibilities of various parties in relation to EM&A and environmental protection works.

(v) These EM&A requirements and specifications are intended to be incorporated into the EM&A Manual, which is to be agreed between the project proponent and EPD.

(vi) The project proponent should assign an environmental team and supervisor to assume the overall responsibility for the EM&A programme. It is much preferable for the project proponent to employ an environmental consultant, independent from the Engineer and particularly the Contractor for that partiCUlar contract, to carry out the EM&A programme.

Bab!i. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

9 Doc No: 96010/007 Issue :2

. .

U'6" nay;:, ut:parrment Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment

(vii) However in may cases, the project proponent would prefer to delegate his EM&A responsibility to the Engineer responsible for the tender preparation and contract management. In that case, the EM&A requirements described in these guidelines should be specified in respective consultancy agreements between the Engineer and the project proponent. The Engineer should employ an environmental team and supervisor who should not be directly involved in supervision of construction works throughout the contract period.

(2)

(3)

(4)

4.1

4.2

(i)

(ii)

Air Quality Monitorin~

{This section is not applicable to this Project and is thus omitted]

Water Quality Monitorin~

{This section is not applicable to this Project and is thus omitted]

Noise Monitorin~

Monitoring equipment

The sound level meter shall comply with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications, as referred to in the Technical Memoranda to the Noise Control Ordinance.

Selection of the monitoring site 1

Locations of monitoring stations should be defined according to the recommendation in the EIA study, Final Report and EM&A Manual and any other locations considered necessary, in agreement with the EPD. .

The monitoring locations should be chosen based on the following criteria:

(a) at locations close to the major site activities which are likely to have noise impacts;

(b) close to the sensitive receptors (N.B. For the purpose of this section, any domestic premises, hotel, hostel, temporary housing accommodation, hospital, medical clinic, educational institution, place of public worship, library, court of law, performing art centre should be considered as noise sensitive receiver);

(c) for monitoring locations located in the vicinity of the sensitive receptors, care should be taken to cause minimal disturbance to the inhabitant during monitoring.

4.3 Positioning of sampler

(i) Where a measurement is to be carried out at a building, the monitoring station should normally be at a point I m from the exterior of the building facade but may also be at any point considered to be appropriate by EPD.

Babtie BMT (Hong Kong) Ltd. 10 Doc No: 96010/007 Issue :2 Ho Tin & Associates Consulting Engineers Ltd.

L [

[

[

[

C [

c [

c c [

C c c [

[

L

c

o [

[

c o c o c [

C

.C

[1

[

[

[

l [

[

Highways Department Improvement to Kum Tin Road. Stage 1 Environmental Impact Assessment

(ii)

4.4

4.5

(i)

(ii)

(iii)

4.6

Where a measurement is to be made of noise being received at a place other than a building, the monitoring station should be 'at a position 1.2 m above the ground, at a particular point considered appropriate by EPD.

(Note: I EPD should have the right to impose additional requirements or change the monitoring station, where necessary.)

Calibration requirements

The sound level meter should be calibrated in accordance with the International Electronical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications, as referred to in the Technical Memoranda to the Noise Control Ordinance. The measurement.should be discarded if the calibrations before and after do not agree to within 1 dB(A), then repeated until the calibrations before and after agree to within 1 d8(A).

Data collection

The following data should be provided in the monitoring record sheet:

, (a) measured noise level (b) background noise level

The following provides and initial guide on regular monitoring frequency for each representative receiver on per week basis when noise generating activities are underway:

(a) (b) (c) (d)

one measurement between 0700-1900 hours on normal weekdays; one measurement between 1900-2300 hours; one measurement between 2300-0700 hours of next day; and one measurement between 0700-1900 hours on holidays.

The following requirements should be complied in carrying out the noise measurements:

(a) The noise level shall be measured at 1m from the most affected external facade of the nearby noise sensitive receivers during any 30 minute period.

(b) During school examination periods, the noise level shall be measured at 1m from the most affected facade of the nearby schools over any 30 minute period. Liaison with the schools and the Examination Authority should be maintained (by the project proponent or his engineer) to ascertain the exact dates and times of all examination periods during the course of the contract.

Laboratory measurement/analysis

No laboratory measurement/analysis is needed for noise monitoring.

B.btie BMT (Hong Kong) Ltd. 11 Doc No: 96010/007 Issue :2 Ho Tin & Associates Consulting Engineers Ltd.

Highways Departmen·t Improvement to Kam Tin Road, Stuge 1 Environmental Impact Assessment

4.7

(i)

Monitoring requirements

Baseline Monitoring

(a) The baseline monitoring should be carried out prior to the commissioning of the construction work for a period of at least 2 weeks, with measurement to be taken on a daily basis.

(b) There should not be any construction activities in the vicinity of the stations during the baseline monitoring.

(c) Reference should be made to a set of baseline monitoring data which should have been available in the EIA study at one or more of the most representative location(s), for the concerned project.

(d) In case no monitoring data or reliable results ate available, the EPD using its knowledge of the ambient noise condition in the project area have the right to assign a new set of data to be used as the baseline reference condition.

(ii) . Impact monitoring

For impact monitoring, the measurement frequency at least once per week should be strictly observed at all monitoring stations.

(iii) Compliance monitoring

In case of non-compliance with the recommended noise level, more frequent noise monitoring as specified in the Event and Action Plan should be carried out. This additional monitoring should be continued until the recorded noise. levels are rectified.

Babti. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

12 Doc No: 96010/007 Issue :2

[

[

o [

[

C

o c D

c [

c o o c [

[

[

[

[

-~. ___ J r---Jlligl~'\VllY~) DCjl~fl.(hIJII( rJ r-J r:l c:::J L ...... _I L ....... .1 r"""""l C""l c:-:::J r::l C::-J Ln, .. j'·cmL. .... J"anc ... J~o:"I._ .... Jc I \_ ... 1 C--Environmcnhil Impact Assessment

Table 1 Typical Event and Action Plan for Air, Water and Noise Monitoring (During Construction)

ACTIONS EVENT

ENVIRONMENTAL ENGINEER'S TEAM LEADER REPRESENTATIVE (RE)

TRIGGER LIMIT

Noise When a complaint is received I. Notify Contractor 2. Conduct Measurement 3. Investigate noisy operations

ACTION LIMIT

Noise When more than one complaint I. Notify Contractor arc received within 2 weeks on lhe 2. Analyze investigation same event or at the same location 3. Require Contractor to propose measures for the analyzed noise

4. Increase monitoring frequency to check mitigation effectiveness

TARGET LIMIT

Noise Non·statutory - 75' dB(A) I. Notify Contractor exceeded between 0700·1900 hrs 2. Notify EPDY on normal weekdays 3. Require contractor to implement mitigation measures increase

on effectiveness

Slatulory - 60/65170" dB(A) ex-ceeded between 0700-2300 Ius on

I

holidays and 1900-2300 hrs on all Slalulory olher days; 45/50/55" dB(A) exceeded belween 2300-0700 Ius of the next day

, reduce to 70 d13(A) lor schools and 55 d13(A) during school examination periods . .. to be selected based on Area Sensitivity Rating. /I only applicable 10 projecls of Significant scale.

lIablic IlMT (llong Kong) Ltd. 13 110 Tin & Associllics Consulting Rngiuccrs Ltd.

CONTRACTOR

I. Submit noise mitigation proposals to Environmenlal Team Leader/Engineer's Representalive 2.

I. 2.

Implement noise mitigation proposals

Implement miligation measures Prove to Environmental Team Leader/·

Doc No : 96010/007 Issue: 2

I

I

Highways Department

4.8 Trigger, Action and Target Levels

Improvement to Kam Tin Road, Stage 1 Environmental Impact Assessment.

The Trigger/ActionfIarget levels are defined as follows:

Trigger Action Target

0700-1900 hrs on When a complaint is When more than one 75' dB (A)

normal weekdays received complaints are received within 2 weeks' time on the same eventllocation

0700c2300 hrs on When a complaint is When more than one 60/65/70" dB (A) holidays; and 1900- received complaints are 2300 hrs on all other received within 2 days weeks' time on the

same eventllocation

2300-0700 hrs of When a complaint is When more than one 45/50/55" dB(A) next day received complaints are

received within 2 weeks' time on the same eventllocation

• reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods . .. to be selected based on Area Sensitivity Rating. .

Babti. BMT (Hong Kong) Ltd. Ho Tin & Associates Consulting Engineers Ltd.

14 Doc No: 96010/007 Issue: 2

[

[

E [

[

C

o c []

[]

[

c [

[

[

[

[

[

[

Highways Department

Appendix B Sample field Data Record Sheets

Babtie BMT (Hong Kong) Ltd. """'0 Tin & Associates Consulting Engineers Ltd.

Improvement to Kam Tin Road, Stage I Environmental Impact Assessment

Doc No : 960 I 0/007 Issue: 2

[

o [1

C [

[

[

[I

l_

[

L [:

[,

[!

DATA SHEET FOR NOISE MONITORING

Project No. Date of measurement

Performed by Location

Type ofSLM

Serial No. Weather Conditions

Measurement Period

Calibration Record:

Type of Calibrator

Serial No.

Noise Level (dBA) Before After

Results:

Time L,. L,. 4- L,. Lm,,, Remarks

.

Checked by

Date

II U

o o o o o o [J

o [I

[I

o [J

[J

o o o

DATA SHEET FOR NOISE MONITORING

Project No. Date of measurement

Performed by Location

Type ofSLM

Serial No. Weather Conditions

Measurement Period

Calibration Record:

Type of Calibrator

Serial No.

Noise Level (dBA) Before After

Results:

Time Leo (5 min) Lmax Remarks

Logarithmic Average

Checked by

Date

\