ild requirement for assembly space and time 2015/11/3 yasuhiro sugimoto @lcws2015 1

37
ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Upload: emma-lee-chase

Post on 21-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

ILD requirement for assembly space and time

2015/11/3

Yasuhiro Sugimoto

@LCWS2015

1

Page 2: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Introduction

• Recent status– Limitation on the transportable weight has become clear

(usually ~20t, >20t with special permission) Impact on iron yoke / HCAL assembly

– Assembly scenario of sub-detectors is getting clear– ILC Infrastructure & Planning Working Group requires us to

clarify the requirements for infrastructure

• General assembly plan of ILD has to be updated to cope with these changes

• Sub-detector assembly scenario has to be clarified more to make a detailed design of ILC campuses (Central campus and IP campus)

2

Page 3: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

IRON RETURN YOKE ASSEMBLY

3

Page 4: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Assembly scenario

• Yoke assembly scenario has to be changed– Originally, it was assumed that ~200t blocks

(1/12 of a ring) are made at a factory and shipped to the interaction point (IP)

– It was turned out that transportation of yoke blocks of ~200t is almost unrealistic

– It seems we have to assemble the yoke blocks from iron slabs on site

• New space for yoke block assembly is necessary on or near IP campus

4

Page 5: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Assembly scenario

• There are three options

5

Iron slabs Iron slabs Block

Block Yoke ring

Iron slabstorage

Iron slabs Block

Block Yoke ring

Iron slabs Block

Block Yoke ring

Iron slabs

Iron slabs

Factory Remote campus IP campus

Pre-assembly hall Assembly hall

• Special trailer• Reinforced road

Kitakami area

Page 6: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Assembly scenario• 1st option

– Size of the pre-assembly hall depends on necessary storage space– If fabrication company can ship iron slabs in “Just-in-time” (JIT)

manner, minimum storage space for pre-assembly of one or two blocks is needed on IP campus cost effective

• 2nd option– If fabrication company cannot ship iron slabs “just-in-time”, we need

quite large storage space, which requires some storage space on or outside IP campus

– Minimum space for pre-assembly of one block on IP campus

• 3rd option– No need for additional building on IP campus– Relatively large assembly hall with 250t crane on remote campus– Requires a special trailer and reinforced road to IP campus– Highest cost

6

Page 7: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Yoke pre-assembly hall• A possible conceptual design in option 1 or 2

– Relatively small crane to lift up iron slabs (capacity<20t, TBD)– Yoke block is assembled on a pallet which moves by air pads– Completed block is slid to AH– We need 2 or 3 pallets (1 for block assembly, 1 or 2 for stand-by for installation

in main AH)– Also used as loading area for sub-detector (Endcap CAL, Muon) modules

(another pallet would be necessary)

7

Garage

Path for He pipes

Yoke blockpre-assembly hall

Entrance

Entrance

Vertical shaft

Platform for ILDPlatform for SiD

Page 8: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

ASSEMBLY OF OTHER SUB-DETECTORS

8

Page 9: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Discussion at ALCW2015

• In ALCW2015 at KEK in April, we had a meeting to discuss sub-detector assembly scenario

• There were presentations on VTX/Si tracker, TPC, ECAL, AHCAL, and SDHCAL

• The discussion continued in ILD Topical Integration Meeting in Oct.

9

Space requirement for assembly and test Trailer

Si trackers

~150m2 clean room on IP campus and/or Central campus

TPC ~200m2 / 0m2 clean room on Central campus~100m2 / 200m2 clean room on IP campus

ECAL ~1000m2 space with crane on Central campus or on/near IP campus

15 t

HCAL AHCAL option

~200m2 air-conditioned space on Central campus or IP campus

20 t

SDHCAL option

~1200m2 space on/near IP campus 11 t or 125 t

Page 10: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Some consideration• Space for muon detector is not considered yet

• ECAL and SDHCAL groups assume parallel assembly of the barrel part and the endcap part

– Barrel part and endcap part can be assembled in series to reduce the space requirement (?)

– But still large space is needed even with series assembly

• Transportation of 125t ring of SDHCAL is a big challenge• Additional assembly hall for HCAL is necessary on or near IP campus (<1km)

• Required assembly space for trackers (Si trackers and TPC) are relatively small, and can be located in the research office building

10~15t ECAL stave ~125t SDHCAL ring

Page 11: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Research Office Building at IP

• Requirements for the research office building– Control rooms of experiments– Meeting rooms– Clean rooms for Si (and TPC)– Office rooms– Laboratory space equipped with a

crane and flammable gas ventilation (TPC)

• An example design was presented at SiD workshop at SLAC in January, but there were strong criticisms – Too gorgeous (too many office rooms) – Assembly space for sub-detectors is

too small

11

Page 12: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Example of ROB at KEK

• 3rd building (Sangokan)– 7F– Many office/meeting rooms– Large conference room– No lab space– No crane– High cost

• Advance Instrumentation Lab– 2F/1F– Large lab space

• 5t crane• Gas can be used (CO2, Liq. Ar, Liq.

Xe)

– Some office space– Meeting room 12

Page 13: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Advance Instrumentation Lab at KEK

13

20m

13.5m

Work shop

More office rooms in 2F

Page 14: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Advance Instrumentation Lab at KEK

14

Page 15: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

A possible design of ROB on IP campus

15

1F

2F

Lab Lab

Workshop WorkshopControl room Control room

Cle

an r

oom

Cle

an r

oom

Ent

ran

ce h

all

70m

25m

18m

14m

Office rooms for Si/TPC/DAQ (Office spacefor CAL groups in HCAL assembly hall)

Page 16: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

IP campus layout

16

Research Office bldg.25m x 60m 1500m2

Cooling Towers20 units

Cooling Towersfor CGP 5 units

He Gas tanks 1,600m3

Integrated Utility bldg.40 m x 100m

Cryogenic plant40m x 30m

Utility plant40m x 40m

Electric facility20m x 20m

Shaft entrance space40m x 30m

Parking space

Parking space

Assembly bldg.27m x 181m

Emergency Generator

20m x 20m

Based on Nishimoto-san’s slides

Very limited free space

Track of trailer

Page 17: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

IP campus with 600m2 HCAL-AH

17

Research Office bldg.

Cooling Towers20 units

Cooling Towersfor CGP 5 units

He Gas tanks 1,600m3

Integrated Utility bldg.40 m x 100m

Cryogenic plant40m x 30m

Utility plant40m x 40m

Electric facility20m x 20m

Shaft entrance space40m x 30m

Parking space

Assembly bldg.27m x 181m

Emergency Generator

20m x 20m

Yoke pre-assembly building

HCAL assembly hall

Space here is necessaryfor coil transportation (trailer)

Based on Nishimoto-san’s slides

Page 18: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Open questions• Yoke

– JIT possible ?– Size of yoke pre-assembly building: 20mx20m?– Capacity of the crane: 20t ?

• Muon detector– Location of module storage/test space: Central campus or IP campus?

(Probably Central campus)– Size of the storage/test space (size for one sector (1/12) of a yoke ring would be

enough)

• ECAL– Location of module storage/test space: Central campus or on/near IP campus? – Reduction of the size (1000m2) possible? (Endcap and barrel in series)

• SDHCAL– Location of module storage/test space: on or near IP campus – Reduction of the size (1200m2) possible? (Endcap and barrel in series)

• AHCAL– Location of module storage/test space: Central campus or IP campus? (probably

IP campus) 18

Page 19: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

ILD ASSEMBLY TIMELINE AND PROCEDURE

19

Page 20: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Update of ILD assembly timeline

• Assumption– New timeline for CFS

• Ground breaking (GB) 4 years after project approval • AH becomes ready ~2.5 years after GB• DH becomes ready ~6.5 yeas after GB

– Yoke module assembly and ring assembly in parallel– CMS style solenoid assembly

• 1/3 coil modules are delivered to AH, and assembled into one coil• Outer vacuum tank and inner vacuum tank are also fabricated in AH from smaller

pieces

– Magnetic field measurement on surface after barrel ECAL installation– TPC and silicon inner trackers are installed after lowering the detector to

DH– AH is used only for iron yoke assembly, solenoid assembly, and

installation of ECAL, HCAL, solenoid, and muon detector– AH has a 250t crane and an 80t crane for ILD– Installation period of each sub-detector is based on TDR

20

Page 21: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Gantt chart

21

1 2 3 4 5 6 7 8 9 10

Page 22: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Simplified table

• Definition of T0 here is the beginning of the land development = Ground Breaking (consistent with CFS group)

22

Land develop.AHDHYokeMuonSolenoidEndcap HCALEndcap ECALBarrel HCALBarrel ECALTrackerQD0CommissioningBeam tuning

2015/ 9/ 16

Low

erin

g

Ins.Ins.

Ins.

FM

Ins.

Assembly on site Ins.Ins.

Phase-1Civil construction

-2Utility

Assembly on siteInstallation

Y9 Y10Q2Q3Q4Q3Q4Q1

Y2 Y3 Y4 Y5 Y6 Y7 Y8Q1Q2Q3Q4Q1Q2Q3Q4Q1Q2Q3Q4

Y1Q1Q2Q3Q4Q1Q2 Q3Q4Q1Q2Q1Q2Q3Q4Q3Q4Q1Q2Q3Q4Q1Q2

Page 23: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Assembly procedure

• Summary of tasks at each step

23

Step-1 Step-2 Step-3 Step-4 Step-5 Step-6 Step-7 Step-8YB0 Yoke OVT Muon Coil/ IVT Coil/ IVT CAL CALYE+ Yoke Muon CAL CALYE- Yoke Yoke Muon CAL CALYB+ Yoke Yoke MuonYB- Yoke Muon

YB0: Central barrel yokeYB+: Barrel yoke on + sideYB-: Barrel ypke on – sideYE+: Endcap yoke on + sideYE-: Endcap yole on – sideOVT: Outer Vacuum TankIVT: Inner Vacuum Tank

Page 24: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Magnet high field test

• We assume full current test with all iron yoke rings and the magnetic field measurement can be done after barrel CAL installation, because assembly of yokes YB+ and YB- can be completed quite late

• This procedure has a risk of uninstalling barrel CALs if something wrong is found in solenoid

• If iron yoke assembly can be done in much shorter time (~4y ~3y), we can avoid this risk by installing barrel CALs after full current test of the magnet  

Discussion with manufacturer would be indispensable for more reliable scheduling and cost estimate

24

Page 25: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

SUMMARY

25

Page 26: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Summary

• Yoke pre-assembly hall attached to main AH is necessary• Iron slab storage building might be necessary on or off IP campus if “just-in-

time” delivery of iron slabs cannot be done• HCAL assembly building is necessary on (or near) IP campus• Assembly and test of Si trackers and TPC can be done in Research Office

Building on IP campus• More detailed study and discussion are necessary to fix the size of these

buildings• (There is a possibility of new IP campus site with larger area)

• ILD timeline has been re-considered to cope with the change of iron yoke assembly scenario

• Still possible to complete detector integration in 9 years• Each sub-detector group will study the assembly timeline more in detail, and

the timeline will evolve• Discussion with iron yoke manufacturing company is indispensable to establish

both space requirement and schedule26

Page 27: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

BACKUP SLIDES

27

Page 28: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 1

• Platform construction• YB0 Yoke assembly• Coil assembly preparation

28

YB0

Yoke pre-assemblybuilding

Page 29: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 2

• YE+ Yoke assembly• YB0 outer vacuum tank

(OVT) assembly• Coil assembly

29

YB0

YE+

Page 30: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 3

• YE- Yoke assembly• YE+ Muon detector

installation• Inner vacuum tank (IVT),

Coil assembly

30

YB0

YE+

YE-

Page 31: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 4

• YE- Yoke assembly• YB0 Muon detector

installation• YE+ Calorimeter

installation• IVT, Coil assembly

31

YB0

YE+

YE-

Page 32: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 5

• YB+ Yoke assembly• YE- Muon detector

installation• YE+ Calorimeter cabling• Coil, IVT installation

32

YE+YE-

YB+

YB0

Page 33: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 6

• YB+ Yoke assembly• YE- Calorimeter

installation• Coil, IVT installation

33

YE+YE-

YB+

YB0

Page 34: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 7

• YB- Yoke assembly• YB+ Muon detector

installation• YE- Calorimeter cabling• YB0 Calorimeter

installation

34

YE+

YE-

YB+

YB0

YB-

Page 35: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 8

• YB- Muon detector installation

• YB0 Calorimeter installation

35

YB0

YE+

YE-

YB+

YB-

Page 36: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 9

• YE-, YB-, YB0, YB+, YE+ shuffle the position

36

YB0

YE+

YE-

YB+

YB-

Page 37: ILD requirement for assembly space and time 2015/11/3 Yasuhiro Sugimoto @LCWS2015 1

Step 10

• Close the detector• Field mapping

37

YB0

YE+

YE-

YB+

YB-