iii ii project

Upload: prasannabtech06

Post on 08-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 III II Project

    1/51

    STUDYOF RELAY TECHNOLOGY AND TESTING

    The Project report submitted in partial fulfillment of therequirements for the Award of the Degree of

    BACHELOR OF TECHNOLOGY

    In

    ELECTRICAL AND ELECTRONICS ENGINEERING

    SUBMITTED

    By

    M.P.PRASANNA KUMAR 06U41A0227

    M.PRASAD KUMAR 07U45A0203

    V.SAGAR 06U41A0237

    S.REVATHI 06U41A0236

    G.J.S.P.R.JYOTHSHNA RANI 06U41A0216

    B.NAVEEN 06U41A0224

    Under The Esteemed Guidance of

    Mr.M.SAI SESHA

    DEPARTMENT OF

    ELECTRICAL AND ELECTRONIC ENGINEERING

    DADI INSTITUTE OF ENGINEERING AND TECHNOLOGY

    ANAKAPALLE, J.N.T.UNIVERSITY, KAKINADA

    1

  • 8/6/2019 III II Project

    2/51

    CERTIFICATE

    This is to certify that the Project entitled

    STUDYOF RELAY TECHNOLOGY AND TESTING

    is a bonifide work done by

    M.P.PRASANNA KUMARpursuing his B.Tech in

    DADI INSTITUTE OF ENGINEERING AND

    TECHNOLOGYANAKAPALLE.

    J.N.T.UNIVERSITY, KAKINADA

    ELECTRICAL AND ELECTRONICS ENGINEERING

    Date: External Guide

    Place: Mr.B.Srinivasa Reddy

    Senior manager (Electrical) Visakhapatnam Steel Plant

    CERTIFICATE

    This is to certify that this project work entitled

    2

  • 8/6/2019 III II Project

    3/51

    STUDYOF RELAY TECHNOLOGY AND TESTING

    is a bonifide work of

    M.P.PRASANNA KUMAR M.PRASAD KUMAR

    V.SAGAR, S.REVATHI, G.J.S.P.R.JYOTHSHNA RANI, B.NAVEEN

    DADI INSTITUTE OF ENGINEERING AND TECHNOLOGY

    ANAKAPALLE.

    ELECTRICAL AND ELECTRONICS ENGINEERING

    UNDER THE GUIDANCE OF

    Mr.M.SAI SESHA

    Associate Prof. (Electrical Dept.)

    DADI INSTITUTE OF ENGINEERING & TECHNOLOGY

    HEAD OF THE DEPARTMENT INTERNAL GUIDE

    Mr.K.V.L.NARAYANA. M.SAI SESHA.

    Date:

    Place:

    3

  • 8/6/2019 III II Project

    4/51

    ACKNOWLEDGEMENT

    We humbly express our sincere profound sense of gratitude for

    Mr.B.JAGAN MOHAN RAO, Principal for giving us an

    opportunity to take up the project work in a prestigious organization

    like Visakhapatnam Steel Plant.

    It is needed a great privilege to express our deep sense of

    gratitude and in debt ness to our distinguished Head of the Dept.

    Mr. K.V.L.NARAYANA, Associate Prof. for his scholarly

    inspiration, valuable guidance and immerse help. Our Sincere thanks

    to Mr. B.SRINIVAS REDDY, Senior Manager (Electrical) that he

    has extended us for the successful completion of this endeavor. It is

    proud to privilege to have the opportunity of guidance from a great

    personality like him.

    Last but not the least; we would like to convey our thanks to

    Mr. M.SAI SESHA, Associate Prof. for the kind guidance to do this

    project in this prestigious organization with his vast knowledge

    Radiance in Electrical Field of Stream.

    CONTENTS

    4

  • 8/6/2019 III II Project

    5/51

    1. Introduction

    6

    2. Introduction to Visakhapatnam Steel Plant

    9

    3. Introduction to Protective Relaying

    12

    4. Important Terms and Fault Characteristics 20

    5. Requirements of Protective Relaying 21

    6. Types of Electromechanical Relay 26

    7. Static Relays 33

    8. Latest Era in Relays -Numerical Relays 37

    9. Testing of Relays and Procedures 39

    10. Suggestions for the forthcoming batches 47

    11. Conclusion 49

    12. References

    50

    5

  • 8/6/2019 III II Project

    6/51

    INTRODUCTION

    In a power system consisting of generator, transformer,

    transmission and distribution circuits, it is inevitable that sooner

    or later some failure will occur somewhere in the system, it must

    be quickly detected and disconnected from the system. There aretwo principal reasons for it. Firstly if the fault is not cleared

    quickly it may cause unnecessary interruption of service to the

    customers secondly rapid disconnection of the faulted apparatus

    limits the amount of damage to it and prevents effects of fault

    from spreading into the system. The capital investment involved

    in a power system for the generation, transmission and

    distribution of electrical power is so great that proper precautions

    must be taken to ensure that the equipment not only operates as

    nearly as possible to peak efficiency but also that it is protected

    from accidents.

    The purpose of protective relays and protective relaying

    system is to operate the correct the circuit breakers so as to

    disconnect only the fault equipment from system as quickly as

    possible, thus minimizing the trouble and damage caused by

    faults when they occur. The modern power system is very

    complex and even though protective equipments from 4% to 5%

    6

  • 8/6/2019 III II Project

    7/51

    of the total cost involved in the System, they play a very

    important role in the system design for good quality of reliable

    supply. The protective relays do not eliminate the possibility of

    faults on the system, rather their action starts only after the fault

    has occurred on the system. It would be ideal if protection could

    anticipate and prevent faults but this is impossible except where

    the original cause of fault creates some effects which can operate

    a protective relay. A protective relay is device that detects the

    fault and initiates the operation of the circuit breaker to isolate

    the defective element from the rest of the system. The relay

    detects the abnormal conditions in the electrical circuits by

    constantly measuring the electrical quantities which are different

    under normal and fault conditions.

    The electrical quantities which may change under faultconditions are voltage, current, frequency and phase angle.

    Through the changes in one or more of these quantities the faults

    signal their presence, type and location to the protective relays.

    Having detected the fault the relay operates to close the trip

    circuit of breaker. This results in the opening of breaker and

    disconnection of faulty circuit. The relay circuit connections can

    be divided into three parts viz..,

    First part is primary winding of a current transformer

    (C.T) which is connected in series with the line to be

    protected.

    7

  • 8/6/2019 III II Project

    8/51

    Second part consists of secondary winding of C.T. and the

    relay operating coil.

    Third part is tripping circuit which may be either A.C or

    D.C. It consists of a source supply, the trip coil of the circuit

    breaker and the relay stationary contacts. When a short circuit

    occurs at a certain point on the transmission line the current

    flowing in line increases to an enormous value. This result in a

    heavy current flow through the relay coil, causing the relay to

    operate by closing its contacts. This in turn closes the trip circuit

    of the breaker, making the circuit breaker open and isolating the

    faulty section from the rest of the system. In this way the relay

    ensures the safety of the circuit equipment from damage and

    normal working of the healthy portion of the system. The

    demand for electrical power is increasing at a very fast rate.This necessitates the installation of transmission lines reaching

    to all the areas of the state. When large bulk of power is to be

    transmitted at very long distances, the efficiency should be

    high. It requires extra high voltage and ultra high voltage

    transmission lines to be erected. These transmission lines are

    required to be protected by comprehensive and quite

    complicated protective schemes. So that the power interruption

    is reduced to minimum, with regard to both the time of

    interruption and the area affected by power interruption. The

    protective scheme must operate fast and selectively before the

    power system becomes unstable.

    8

  • 8/6/2019 III II Project

    9/51

    Our project is dedicated for discussion of different

    protective schemes i.e. by the usage of Relays and mainly on

    distance protection of transmission lines of power system.

    Before going into the details of the Project Theme Line lets

    know about the Overview of Steel Plant.

    OVER VIEW OF VISAKHAPATNAM STEEL PLANT

    BRIEF DESCRIPTION:

    Visakhapatnam Steel plant is located on the coast of Bay of

    Bengal, 16 km to the South West of Visakhapatnam. The

    decision of the Government of India to set up an Integrated

    Steel Plant at Visakhapatnam was announced by the Prime

    Minister Smt. Indira Gandhi in Parliament on 17th April 1970.

    The formal inauguration was done on 20th January 1971 by

    the then Prime Minister. The Government of India and USSR

    signed an agreement in 1979 in setting up the 3.4 million tones

    integrated Steel plant at Vizag.

    The project was estimated to cost Rs.3897.28 corers

    based on 1981 prices but the cost has increased substantially

    over the sanctioned cost and finally the project is estimated to

    cast Rs.5822.17 corers as per 1987. Vizag Steel, also known

    as Visakhapatnam Steel Plant, is a steel company based in the

    outskirts ofVisakhapatnam, India. Its vision - Infrastructuring

    9

    http://en.wikipedia.org/wiki/Steelhttp://en.wikipedia.org/wiki/Visakhapatnamhttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Visakhapatnamhttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Steel
  • 8/6/2019 III II Project

    10/51

    India. Vizag Steel bagged the first prize in Energy

    Conservation constituted by Government, consecutively for

    the last 2 years primarily due to its focus on energy

    conservation, cost reduction and waste utilization. Vizag Steel

    Plant today is among the lowest cost steel producers in the

    world. The Visakhapatnam Steel Plant has been awarded the

    Safety Innovation Award - 2006 by the Institution of

    Engineers for its "outstanding contributions in the field and

    adoption of the best and the most innovative safety practices".

    The plant was awarded the Prime Minister's trophy for the best

    steel plant in the country, for the year 02-03. VSP added

    another feather to its cap by bagging six Government of India,

    Vishwakarma Rashtriya Puraskar (VRP) Awards at national

    level out of total number of 28 awards announced by Ministry

    Of Labour, Government of India.

    PRODUCT MI:

    VSP produces angles, channels, bars, wire rods and billets for

    re-rolling. The Plant produces Pig Iron, 1.44 million tones per

    annum of granulated slag and there are also normal by-

    products from coke-oven and coal chemical plant.

    PLANT FACILITIES:

    VSP has these major production facilities.

    1. Three coke-ovens Batteries.

    2. Two Sinter machines of 312 m square area.

    10

    http://en.wikipedia.org/wiki/Institution_of_Engineers_(India)http://en.wikipedia.org/wiki/Institution_of_Engineers_(India)http://en.wikipedia.org/w/index.php?title=Ministry_Of_Labour_(India)&action=edit&redlink=1http://en.wikipedia.org/w/index.php?title=Ministry_Of_Labour_(India)&action=edit&redlink=1http://en.wikipedia.org/wiki/Government_of_Indiahttp://en.wikipedia.org/wiki/Institution_of_Engineers_(India)http://en.wikipedia.org/wiki/Institution_of_Engineers_(India)http://en.wikipedia.org/w/index.php?title=Ministry_Of_Labour_(India)&action=edit&redlink=1http://en.wikipedia.org/w/index.php?title=Ministry_Of_Labour_(India)&action=edit&redlink=1http://en.wikipedia.org/wiki/Government_of_India
  • 8/6/2019 III II Project

    11/51

    3. Two Blast Furnace of 3200 m cube use full volume.

    4. Steel Melt shop with three L D converters of 150 tons.

    5. Light & Medium Merchant mill of 7, 10,000 tones per year.

    6. Wire Rod Mill of 850000 tons per year.

    7. Medium Merchant & Structural Mill of 850000 tons.

    MODERN TECHNOLOGY:

    VSP is the most sophisticated and modern integrated steelplant it contains selective crushing of coal.

    1. 7metres tall coke-ovens.

    2. Dry quenching of coke.

    3. On ground blending of sinter base mix.

    4. 100% continuous casting of liquid steel.

    5. Hot metal de-sulphurisation.

    6. Computerization for process control. And many more

    Integrated systems are being used in this plant.

    POWER SUPPLY:

    The plant has in plant power generation from a power plant

    having three turbo generators of 60 MW and one 67.5 MW

    generators totally supplying 247.5 MW power supply. And an

    inclusion of Auxiliary Unit constitutes the plant with an Extra

    of 40 MW (2 x 20 MW) resulting the total power supply to

    11

  • 8/6/2019 III II Project

    12/51

    287.5 MW in total. The plant is estimated to cost about Rs.

    8755 crores based on prices as on 1994.

    INTRODUCTION TO PROTECTIVE RELAYING

    About Protective Relaying:

    Protective relaying is necessary with almost every electrical

    plant, and no part of the power system is left unprotected. The

    choice of protection depends upon several aspects such as type

    and rating of the protected equipment, its importance, location,

    probable abnormal conditions, cost etc. Between generators

    and the final load points, there are several electrical equipment

    and the machines of various ratings. Each need is certain

    adequate protection. The protective relaying senses the

    abnormal conditions in a part of the power system and gives an

    alarm or isolates that part from the healthy system. The relays

    are compact, self-contained devices which respond toabnormal condition. The relays distinguish between normal

    and abnormal condition. Whenever an abnormal condition

    develops, the relays close its contacts. There by the trip current

    of the circuit breaker is closed. Current from the battery supply

    flows in the trip coil of the circuit breaker opens and the faulty

    12

  • 8/6/2019 III II Project

    13/51

    part is disconnected from the supply.The last thirty years have

    seen enormous changes in relay technology. The

    electromechanical relay in all of its different forms has been

    replaced successively by static, digital and numerical relays,

    each change bringing with it reductions and size and

    improvements in functionality. At the same time, reliability

    levels have been maintained or even improved and availability

    significantly increased due to techniques not available with

    older relay types. This represents a tremendous achievement

    for all those involved in relay design and manufacture. The

    entire process, occurrence of fault-operation of the relay-

    opening of circuit breaker, removal of faulty part from the

    system is automatic and fast.

    Circuit breakers are switching devices which can interrupt

    normal currents and fault currents. Besides relays and circuit

    breakers, there are several other important components in the

    protective relaying scheme. These include: protective current

    transformers and voltage transformers, protective relays, time

    delay relays, auxiliary relays, secondary circuits, trip circuits,auxiliaries and accessories etc. Each component is important

    protective relaying is a team work of these components.

    The functions of protective relaying include the following:

    13

  • 8/6/2019 III II Project

    14/51

    To sound an alarm or to close the trip circuit of circuit-

    breaker so as to disconnect a component during an abnormal

    condition in the component, which include over-load, under-

    voltage, temperature rise, unbalanced load, reverse power,

    under-frequency, short circuits etc...

    To disconnect the abnormally operating part so as to

    prevent the subsequent faults.

    Example: Over-load protection of a machine protects the

    machine and prevents insulation failure.

    To disconnect the faulty path quickly so as to minimize

    the damage to the faulty part eg: if a machine is

    disconnected immediately after a winding fault, only a

    few coils may need replacement. If the fault is sustained,

    entire winding may get damaged and machine may be

    beyond repairs.

    To localize the effect of fault by disconnecting the

    faulty path, from the healthy part, causing least

    disturbance to the healthy system.

    14

  • 8/6/2019 III II Project

    15/51

    To disconnect the faulty part quickly so as to improve the

    system stability, service continuity and system

    performance. Transient stability can be improved by

    means of improved protective relaying. Faults cant be

    avoided completely .They can be minimized. Protective

    relaying plays an important role in minimizing the faults

    and also minimizing the damage in the event of faults.

    IMPORTANT TERMS:

    It is desirable to define and explain some important terms

    much used in connection with relays.

    1. PICK-UP CURRENT:

    It is the minimum current in the relay coil at which the relay

    starts to operate. So long as the current in the relay is less than

    pick-up value, the relay does not operate and the breaker

    controlled by it remains in the closed position. However, when

    the relay coil current is equal to or greater than the pick-up

    value, the relay operates to energize the trip coil which opensthe circuit breaker.

    2. CURRENT SETTING:

    It is often desirable to adjust the pick-up current to any

    required value. This is known as current setting and is usually

    15

  • 8/6/2019 III II Project

    16/51

    achieved by the use of tappings on the relay operating coil.

    The taps are brought out of a plug bridge as shown in figure.

    The plug bridge permits to alter the number of turns on the

    relay coil. This changes the torque on disc and hence the time

    of operation of the relay. The values assigned to each tap are

    expressed in terms of percentage full-load rating of Current

    Transformer with which the relay is associated and represents

    the value above which the disc commences to rotate and

    finally closes the trip circuit. Therefore, pick-up current=rated

    secondary current of C.T.*current setting.

    3. PLUG-SETTING MULTIPLIER(P.S.M.):

    It is the ratio of fault current in relay coil to the pick-up current

    i.e.., P.S.M= fault current in the relay coil / pick-up current.

    = fault current in the relay coil / rated secondary

    Current of C.T.*100

    4. TIME SETTING MULTIPLIER:

    16

  • 8/6/2019 III II Project

    17/51

    A relay is generally provided with control to adjust the time of

    operation. The time setting dial is calibrated from 0 to 1 in

    steps of 0.05sec as shown in figure. These figures are

    multipliers to be used to convert the time derived from time

    /P.S.M. curve into the actual operating time.

    Thus if the time setting is the 0.1 and the time obtained from

    the time/P.S.M curve is 3 seconds, then actual relay operating

    time is 3*0.1=0.3sec. For instance, in an induction relay the

    time of operation is controlled by adjusting the amount of

    travel of the disc from its reset position to its pick up position.

    This is achieved by the adjustment of the position of a

    movable backstop which controls the travel of the disc and

    thereby varies time in which the relay will close its contacts

    for given values of fault current. A so-called time dial with an

    evenly divided scale provides this adjustment. The time of

    operation is calculated by multiplying the time setting

    17

  • 8/6/2019 III II Project

    18/51

    multiplier with the time obtained from time /P.S.M. curve of

    the relay.

    FAULTS, CAUSES AND EFFECTS:

    A fault in its electrical equipment is defined as a defect in its

    electrical circuit due to which the flow of current is diverted

    from the intended part. Faults are caused by breaking of

    conductors or failure of insulation fault impedance is generally

    low and fault currents are generally high. Fault currents being

    excessive, they can damage not only the faulty equipment but

    also the installation through which the fault current is fed.

    For ex: if a fault occurs in a motor, the motor winding is

    likely to get damaged. Further if the motor is not disconnected

    quickly enough the excessive fault currents can cause damage

    to the starting equipment, supply connections etc.

    Faults in certain important equipment can affect the

    stability of the power system for ex: a fault in bus-zone of a

    power station can cause tripping of all the generator units in

    power station and can affect the stability of interconnected

    systems. These are several causes of faults occurring in a

    particular electrical plant. Faults can be minimized by

    18

  • 8/6/2019 III II Project

    19/51

    improved system design improved quality of components,

    better maintenance etc. however the faults cant be entirely

    eliminated.

    Equipment Cause of fault %of total faults

    1.Overhead lines 1.Lightening strokes, 30-40

    2.storms, earthquakes, icing3. Birds, trees, kites, airplanes etc.

    4.Internal over voltages

    30-40

    2.Under ground

    cables

    1.Damage during digging

    2. Insulation failure due to

    temperature rise.

    3.Failure of joints

    8-10

    3.Alternators 1.Stator faults

    2.Rotor faults

    3.Abnormal conditions

    4.Faults in associated equipment

    5.Faults in protective system

    6-8

    4.Transformers 1.Insulation failure

    2.Faults in tap changer

    3.Faults in protection circuit

    4.Inadequate protection

    5.Faults in bushing

    6.Over loading, overprotection

    10-12

    5.Switchgear

    and protection

    1.Insulation failure

    2.Mechanical defect

    10-12

    19

  • 8/6/2019 III II Project

    20/51

    3.Leakage of air/oil/gas

    4.Inadequate rating

    5.Lack of maintenance

    METHODS OF BACK UP PROTECTION:

    1. Relay Back-up:

    Same breaker is used by both main and back-up protection,but the protective systems are different. Separate trip coils may

    be provided for the same breaker.

    2. Breaker Back-up:

    Different breakers are provided for main and back up

    Protection, both the breakers being in the same station.

    3. Remote Back-up:

    The main and back up protections provided at different

    stations and are completely independent.

    4. Centrally Co-ordinate Back-up:

    The system having central control can be provided with

    centrally controlled back-up. Central control continuous

    supervises load flow and frequency in the system. The

    information about load flow and frequency is assessed

    continuously .If one of the components in any part of system

    fails (ex: a fault on a transformer, in some system) the load

    flow in the system is affected .The central coordinating station

    20

  • 8/6/2019 III II Project

    21/51

    receives info about the abnormal condition through high

    frequency carrier signals. Main protection is at various stations

    and back up protection for all stations is at central control

    center.

    BASIC REQUIREMENTS OF PROTECTIVE

    RELAYING:

    A well design and efficient protective relaying should have

    1. Speed2. Selectivity

    3. Sensitivity

    4. Reliability

    5. Simplicity

    Speed:

    Protective relaying should disconnect a faulty element

    as quickly as possible. This is desirable for many reasons,

    principles among which are:

    a) Improves power system stability

    b) Decreases the amount of damage incurred

    c) Lessens annoyance to electric power consumers and

    decreases total outage time for power consumers

    d) Decreases the likelihood of development of one type of

    fault into other more severe type.

    e) Permits use of rapid re closure of circuit-breakers to restore

    21

  • 8/6/2019 III II Project

    22/51

    service to customers.

    Selectivity:

    It is the basic requirement of relay in which it should

    be possible to select which part of the system is faulty and

    which is not and should isolate the faulty part of the system

    from the healthy one. Selectivity is achieved in two ways:

    (i)Unit system of protection

    (ii)Non-unit system of protection

    Unit system of protection means the one in which if

    the protection responds only to faults with in its own zone and

    does not make any note of the conditions else where, e.g., the

    differential protection of transformers and generators. Here,

    the protection scheme will work only if the fault is in the

    transformer or generator respectively. Non-unit system of

    protection is one in which the selectivity is obtained by

    grading the time or current settings of the relay at differentlocations, all of which may respond to a given fault. Any

    failure occurring within a given zone will cause the opening of

    all breakers within that zone. The various protective zones are

    a) Generators or generator transformer unit

    b) Transformers

    22

  • 8/6/2019 III II Project

    23/51

    c) Bus bars

    d) Transmission lines

    e) Distribution circuits

    Sensitivity:

    It is the capability of the relaying to operate reliably

    under the actual conditions that produce the least operating

    tendency. There may be abnormalities in the normal operating

    conditions or the faults for which the protection has been

    designed. It is desirable to have the protection as sensitive as

    possible in order that it shall operate for low values of

    actuating quantity. However, a protection with high degree of

    sensitivity is more complex and uses more equipment and

    circuitry and therefore is more expensive.

    Reliability:

    Reliability means that the protective relaying must be

    ready to function, reliable and correct in operation at all times

    under any kind of fault and abnormal conditions of the power

    system for which it has been designed.Simplicity:

    Simplicity of construction and good quality of the relay,

    correctness of design and illumination qualified maintenance

    and supervision, etc. are the main factors which influence

    protective relaying. As a rule, the simple the protective scheme

    23

  • 8/6/2019 III II Project

    24/51

    and the lesser the number of relays, circuits and contacts it

    contains, the greater will be its reliability.

    Economy:

    As with all good engineering designs, economics play a

    major role. It is futile to achieve all important general

    requirements together, so compromises become necessary. Too

    much protection is as bad as too little and the relay engineer

    must strike a sensible compromise with due regard to practical

    situation.

    24

  • 8/6/2019 III II Project

    25/51

    Relays and relay settings are not to be changed from what

    is indicated on current issues of relay data sheets unless

    authorized by regional or project personnel with the

    proper responsibility.

    TYPES OF ELECTROMECHANICAL RELAY

    These relays were earliest forms of relay used for the

    protection of power systems, and they date back nearly 100

    years. They work on the principle of a mechanical force

    causing operation of a relay contact in response to a stimulus.

    The mechanical force is generated through current flow in one

    or more windings on a magnetic core or cores, hence the term

    ELECTROMECHANICAL RELAY. The principle

    advantage of such relays is that they provide galvanic isolation

    between the inputs and outputs in a simple, cheap and reliable

    form therefore for simple on/off switching functions where

    the output contacts have to carry substantial currents, they are

    still use. They work on the following two main operating

    principles:

    25

  • 8/6/2019 III II Project

    26/51

    (1)Electromagnetic attraction

    (2)Electromagnetic induction

    ELECTROMAGNETIC ATTRACTION RELAYS:

    Electromagnetic attraction relays operate by virtue of an

    armature being attracted to the poles of an electromagnet or a

    plunger being drawn into a solenoid. Such relays may be

    actuated by d.c or a.c quantities. The principle advantage of

    such relays is that they provide galvanic isolation between the

    inputs and outputs in a simple, cheap and reliable form

    therefore for simple on/off switching functions where the

    output contacts have to carry substantial currents, they are still

    used. The important types of electromagnetic attraction are:

    Attracted armature type relay

    Solenoid type relay

    26

  • 8/6/2019 III II Project

    27/51

    Balanced beam type

    ATTRACTED ARMATURE TYPE RELAY:

    The figure shows the schematic arrangement of an attracted

    armature type relay.

    It consists of a laminated electromagnet M carrying a

    coil C and a pivoted laminated armature. The armature is

    balanced by a counter weight and carries a pair of spring

    contact fingers at its free end. Under normal operating

    conditions, the current through the relay coil increases

    sufficiently and the relay armature is attracted upwards. The

    contacts on the relay armature bridge a pair of stationary

    contacts attached to the relay frame. This completes the trip

    circuit which results in the opening of the circuit breaker and

    therefore in the disconnection of the faulty circuit. The

    27

  • 8/6/2019 III II Project

    28/51

    minimum current at which the relay armature is attracted to

    close the trip circuit is called pickup current. It is a usual

    practice to provide a number of tapings on the relay coil so that

    the number of turns in use and hence the setting value at which

    the relay operates can be varied.

    SOLENOID TYPE RELAY:

    Under normal operating conditions, the current through the

    relay coil C is such that it holds the plunger by gravity or

    spring in the position However, on the occurrence of a fault,

    the current through the relay coil becomes more than the

    pickup value, causing the plunger to be attracted to the

    solenoid. The upward movement of the plunger closes the trip

    circuit, thus opening the circuit breaker and disconnecting thefaulty circuit

    BALANCED BEAM TYPE RELAY:

    28

  • 8/6/2019 III II Project

    29/51

    It consists of an iron armature fastened to a balanced beam.

    Under normal operating conditions, the current through the

    relay coil is such that the beam is held in the horizontal

    position by the spring. However when a fault occurs, the

    current through the relay coil becomes greater than the pickup

    value and the beam is attracted to close the trip circuit. This

    cause the opening of the circuit breaker to isolate the faulty

    circuit.

    ELECTROMAGNETIC INDUCTION RELAYS:

    Electromagnetic induction relays operate on the principle of

    induction motor and widely used for protective relaying

    purposes involving a.c. quantities. They are not used with D.C.

    quantities owing to the principle of operation. An induction

    relay essentially consists of a pivoted aluminum disc placed in

    two alternating magnetic fields of the same frequency but

    displaced in time and space. The torque is produced in the disc

    29

  • 8/6/2019 III II Project

    30/51

    by the interaction of one of the magnetic fields with the

    currents induced in the disc by the other.

    The important types of structures are commonly used for

    obtaining the phase difference in the fluxes and hence the

    operating torque in induction relays:

    (i) shaded-pole structure

    (ii) Watt-hour meter or double winding structure

    (iii) Induction cup structure.

    SHADED-POLE STRUCTURE:

    The general arrangement of shaded pole structure is shown in

    figure. It consists of a pivoted aluminum disc free to rotate in

    the air-gap of an electromagnet. One-half of each pole of the

    magnet is surrounded by a copper band known as shading ring.

    The alternating flux s in the shaded portion of the poles will,

    owing to the reaction of current induced in the ring, lag behind

    the flux u in the unshaded portion by angle . These two a.c.

    fluxes differing in phase will produce the necessary torque to

    rotate the disc.The driving torque T is given by

    T s u sin

    Assuming the fluxes s and u to be proportional to the

    current I in the relay coil,

    T I^2sin

    30

  • 8/6/2019 III II Project

    31/51

    This shows that driving torque is proportional to the square of

    current in the relay coil.

    WATT-HOUR METER OR DOUBLE WINDING

    STRUCTURE:

    This structure gets its name from the fact that it is used in

    Watt-hour meters. The general arrangements of this type of

    relay are shown in figure. It consists of a pivoted aluminum

    disc arranged to rotate freely between the poles of two

    electromagnets the upper electromagnet carries two winding;

    the primary and the secondary. The primary winding carries

    the relay current I1 while the secondary winding is connected

    to the winding of the lower magnet. The primary current

    induces e.m.f in the secondary and so circulates a current I2 in

    it. The flux 2 induced in the lower magnet by current in

    secondary winding of the upper magnet will lag behind 1 by

    an angle . The two fluxes 1 and 2 differing in phase by

    will produce a driving torque on the disc proportional to 1

    2sin.

    31

  • 8/6/2019 III II Project

    32/51

    INDUCTION CUP STRUCTURE:

    This figure shows the general arrangement of an induction cup

    structure. It most closely resembles an induction motor; expect

    that the rotor iron is stationary, only the rotor conductor

    portion being free to rotate. The moving element is a hollow

    cylindrical rotor which turns on its axis. The rotating field is

    produced by to pairs of coils wound on four poles as shown.

    The rotating field induces current in the cup to provide the

    necessary torque. If 1 and 2 represent the fluxes produced

    by the respective pairs of poles, then torque produced is

    proportional to 1 2 sin where is the phase difference

    between two fluxes. A control spring and the back stop for

    closing of the contacts carried on an arm are attached to the

    spindle of the cup to prevent the continuous rotation.

    32

  • 8/6/2019 III II Project

    33/51

    Induction cup structures are more efficient torque producers

    than either shaded-pole or the watt-hour meter structures.

    There fore this type of relay has very high speed and may have

    an operating time less then 0.1second.

    STATIC RELAYS

    The term static implies that the relay has no moving parts.

    This is not strictly the case for a static relay, as the output

    contacts are still generally attracted armature relays. In a

    protection relay, the term static refers to the absence of

    moving parts to create the relay characteristic. Introduction of

    static relays began in the early 1960s. Their design is based onthe use of analogue electronic devices instead of coils and

    magnets to create the relay characteristic. Early versions used

    discrete devices such as transistors and diodes in conjunction

    with resistors, capacitors, inductors, etc., but advances in

    electronics enabled the use of linear and digital integrated

    33

  • 8/6/2019 III II Project

    34/51

    circuits in later versions for signal processing and

    implementation of logic functions.

    While basic circuits may be common to a number of

    relays, the packaging was still essentially restricted to a single

    protection function per case, while complex functions required

    several cases of hardware suitably interconnected. User

    programming was restricted to the basic functions of

    adjustment of relay characteristic curves. They therefore can

    be viewed in simple terms as an analogue electronic

    replacement for electromechanical relays, with some additional

    flexibility in settings and some saving in space requirements.

    In some cases, relay burden is reduced, making for reduced

    CT/VT output requirements. The term static relay refers to a

    relay which incorporates solid state components like

    transistors, diodes etc., for the measurement or comparison of

    electrical quantities. The static network is so designed that it

    gives an output signal in the tripping direction whenever a

    threshold condition is reached.

    The output signal in turn operates a trip device whichmay be electronic or electromagnetic. The need for the static

    relays arose because of the requirement of fast and reliable

    protective schemes for the modern power systems which is

    growing both in complexity and fault levels. The scheme

    should be fast so as to preserve dynamic stability of the system

    34

  • 8/6/2019 III II Project

    35/51

    as the character and loading approach design limits. The

    supply problem associated with the thermionic valves has been

    solved with the use of semi-conductors. The transistors have

    made it possible to achieve greater sensitivity and at the same

    time excellent mechanical stability which is not possible with

    the electro-mechanical relays. It is to be noted here that is

    usually not economical to replace existing electro-mechanical

    relays with their static counter parts just to reduce

    maintenance. The protective relays, now -a-days, are being fed

    by iron cored current transformer and hence excessive

    saturation should be avoided to ensure high speed and

    discriminative operation the static relays reduce the burden on

    the current transformer .It is interesting to note that the static

    relays have first been commercially manufactured for the

    distance and differential protective schemes whereas the much

    simpler over current relays have not been brought out.

    The reason behind this that distance and differential

    schemes are more amenable to mathematical analysis whereas

    the over current characteristics are more of empirical nature.Therefore, a static over current relay cannot compete with the

    conventional electro-mechanical relay. With the use of static

    relays it has been possible to obtain many varied and complex

    distance protection characteristics which are impossible to

    obtain with the conventional electro-mechanical relays.

    35

  • 8/6/2019 III II Project

    36/51

    Transistor relays are the most widely used static relays.

    In fact static relays are generally mean Transistor relay. The

    fact that a transistor can be used both as an amplifying device

    and as a switching device makes this component suitable for

    achieving any functional characteristics.

    The transistor circuit can not only perform essential

    functions of relay such as comparison of inputs, summation

    and integrating them but they also provide necessary flexibility

    to suit the various relay requirements the advantages of

    transistor relays can be summarized as follows:

    The power consumption is low and hence provides less

    burden on C.Ts and P.Ts as compared to the

    conventional electro mechanical relays.

    The relays are fast in operation.

    No moving parts, hence friction or contact troubles are

    absent and as result minimum maintenance is required.

    The relays have greater sensitivity as amplification of

    signals can be obtain very easily.

    The relay has a high reset pick-up ratio and the reset is

    very quick

    The use of printed circuits avoids wiring errors and

    facilitates rationalization of batch production.

    It is possible to obtain wide range of characteristics

    approaching more or less to the ideal requirements.

    36

  • 8/6/2019 III II Project

    37/51

    Transistor relays, however, have the following limitations:

    1. The characteristics vary with temperature and ageing.

    2. The reliability of the scheme depends upon a large

    number of small components and their electrical

    connections.

    3. The relays have low short time over load capacity

    compared with electromechanical relay.

    NUMERICAL RELAYS

    INTRODUCTION TO MICOM

    MiCOM is a comprehensive solution capable of meeting all

    electricity supply requirements. Central to the MiCOM

    concept is flexibility. MiCOM provides the ability to define an

    application solution and, through extensive communication

    capabilities, to integrate it with power supply control system.

    Additional Features for the P442 Relay Model:

    Single pole tripping and auto-reclose.

    Real Time Clock Synchronization - Time

    synchronization is possible from the relay IRIG-B input.

    Fiber optic converter for IEC60870-5/103

    communication (optional).

    16 Logic Inputs - For monitoring of the circuit breaker

    and other plant status.

    21 Output relay contacts - For tripping, alarming, status

    indication and remote control.

    37

  • 8/6/2019 III II Project

    38/51

  • 8/6/2019 III II Project

    39/51

    TESTING OF RELAYS BY ANNUAL INSPECTION

    All relays shall be given an annual inspection. This inspection

    should include the following:

    1. A visual inspection should be made of all relays on a

    terminal including the tripping auxiliaries and accessories.

    Any draw out type relay should be withdrawn from its case

    for a close-up examination. All other, including auxiliaries,

    should at least have covers removed. Included in this visual

    inspection should be a check for loose connections, broken

    studs, burned insulation, and dirty contacts. Each relay

    should be checked to be in agreement with its setting sheet.

    39

  • 8/6/2019 III II Project

    40/51

    On some distance relays it may have been necessary to set

    the taps on something other than specified values in order to

    get proper calibration.

    2. b. A test trip should be made of all relay systems. All relay

    elements which initiate some protective function should be

    checked. This includes reclosing, carrier starting, or any

    similar type function. After proving that tripping relays will

    successfully trip the circuit breaker and that all reclosing

    schemes work, continuity checks should be used, where

    applicable, to complete the checkout of the circuit breaker

    trip circuits.

    TEST PROCEDURES

    Tests to be performed during routine maintenance are

    determined by the type of relay to be tested. The following

    tests should be included for all electromechanical relays.

    1. A visual inspection of the relay cover can reveal valuable

    information. Any excessive dust, dirt, or. Metallic material

    deposited on the cover should be noted and removed, thus

    preventing such material from entering the relay when the

    cover is removed. A cover glass which is fogged should be

    cleaned. Fogging is in most cases a normal condition due to

    40

  • 8/6/2019 III II Project

    41/51

    volatile materials being driven out of coils and insulating

    materials, and is not an indication of a problem.

    2. Mechanical adjustments and inspection should be made

    according to instructions shown following:

    (1) Check to see that all connections are tight. Several loose

    connections could indicate excessive vibration which should

    be corrected.

    (2) All gaps should be checked that they are free of foreign

    material. If foreign material is found in the relay, the case

    gasket should be checked and replaced if necessary.

    (3) All contact or armature gaps should be measured and

    values compared with previous measurements. Large

    variations in these measurements may indicate excessive wear,

    and worn parts should be replaced. Also an adjusting screw

    could have worked loose and must be tightened.

    (4) All contacts except those not recommended for

    maintenance should be burnished, and measured for alignment

    and wipe.

    (5) Since checking bearings or pivots usually involves

    dismantling the relay, it is recommended that such a test be

    41

  • 8/6/2019 III II Project

    42/51

    made only when the relay appears to be extremely dirty, or

    when subsequent electrical tests indicate undue friction.

    3. Electrical tests and adjustments should be made

    according to the instructions shown following:

    (1) Contact function.-Manually close or open the contacts, and

    observe that they perform their required function; such as trip,

    reclose, or block.

    (2) Pickup.-Gradually apply current or voltage to see that

    pickup is within limits. The current or voltage should be

    applied gradually in order to yield data which can be compared

    with previous or future tests and not be clouded by such effects

    as transient overreach.

    (3) Dropout or reset.-To test for excess friction, reduce current

    until the relay drops out or resets. Should the relay be sluggish

    in resetting or fail to reset, then the jewel bearing and pivot

    should be examined. A four power magnification is adequate

    for examining the pivot, and the jewel bearing can be

    examined with the aid of a needle which will reveal any cracks

    in it. If dirt is the problem, the jewel can be cleaned with an

    orange stick and the pivot can be wiped clean with a soft, lint

    free cloth. No lubricant should be used on either the jewel or

    pivot.

    42

  • 8/6/2019 III II Project

    43/51

    PORTABLE TEST KITS

    Portable test equipment type ZFB for distance relays:

    In testing high speed distance relays it is important to apply

    simulated fault conditions suddenly, otherwise the behavior of

    the relay in service may be different from its behavior in test.

    Checking the relay characteristic by reducing the voltage or by

    increasing the current until the relay operates is not realistic, asthe voltage and current change simultaneously in magnitude

    and phase angle when a fault occurs in service.

    Relay System

    Variables

    Factor Reducing Test

    Interval

    Factors lengthening Test

    Interval

    Type of RelaysComplex (distance,

    differential),

    Simple (hinged armature

    plunger).

    Age of Relays New installations with

    little operating history.

    Systems 20 years or olderwhere insulation aging,

    etc., can be a problem

    5-10 years old with a good

    operating history

    Environment Dusty area, contaminated

    atmosphere, temperature

    extremes.

    Clean and/or air

    conditioned area.

    History and

    Experience

    Subjected to severe or

    frequent faults. Often

    required adjustmentswhen tested.

    Subjected to moderate or

    few faults.

    43

  • 8/6/2019 III II Project

    44/51

    Current Rating Relays rated 5 amperes

    which are called upon to

    carry 7 or 8 amperes due

    to load requirements.

    Relays operated at or below

    their 5 ampere rating

    Control Voltage Relays operated in batterycircuit more than 5

    percent above nominal

    relay rated voltage of

    nominal relay rated

    voltage

    Relays operated in batterycircuit within _+ 5 percent

    Station Service Station service voltage

    supplied is more than 5

    percent above nominal

    relay rated voltage.

    Station service Voltage

    supply operated within + 5

    percent of

    Table 1.- Criteria to determine possible alteration of the test period for relays

    This causes transient mechanical, electrical and magnetic

    conditions in the relay which may cause overreach unless its

    operating time exceeds four cycles, during which the transient

    conditions will have disappeared.

    Description:

    The test equipment is contained in three portable metal cases.

    a. Supply unit

    b. Control unit

    c. Fault impedance unit plus external current transformer

    Supply unit:

    The unit comprises:

    44

  • 8/6/2019 III II Project

    45/51

    1. Three single phase transformers (T1, T2 and T3) ratio

    420,400,380/110, 63.5V connected Y/Y to form a three phase

    transformer bank. Transformer is used to supply the control

    unit at 100V or 63.5V as designed and is continuously rated

    at 12A secondary output. This transformer also has a further

    115V secondary winding rated at 300mA to give an auxiliary

    supply to the fault contactor in the control unit. Transformers 2

    and 3 are used nearly to supply quadrate or polarizing voltage

    to relays that require such voltages in addition to the normal

    fault voltage. These transformers are continuously rated at 1A

    secondary.

    2. Fault selector switch is included to facilitate quick selection

    of fault in the scheme. Having once connected the 3-phase

    voltage and current leads to the relay scheme, anyone of the

    measuring or starting relays in the scheme can quickly be

    selected by the 6 position switches. This avoids possible

    human error when changing connections from the relay in

    the scheme to another.3. The selector switch connections are arranged such that

    when injecting into a phase to neutral connecting measuring

    relay the fault voltage and current are supplied from

    transformer T1 of the main supply bank while T/Fs T2 and

    45

  • 8/6/2019 III II Project

    46/51

    T3 supply the necessary quadrate voltage for the starting

    relays in the scheme.

    When injecting into a phase-phase connected measuring relay

    the fault voltage and current are again supplied from

    transformer T1 while additional voltage connection for the

    starting relay is taken from transformer T3.

    Control unit:

    The unit comprises:

    1. The source impedance (L2) tapped to provide a range of 0.5

    to 24ohms. This impedance is used to control the relay current

    and vary the source to line (fault) impedance ratio, in

    conjunction with the fault impedance L1 and R1.

    2. The voltage auto-transformer (T4) which is connected

    across the line impedance via the fault contactor is tapped in

    10% and 1% steps from 0-100%.

    3. The load impedance which is connected in series with the

    line impedance via the load push button, permits load current

    to be passed the relay coils prior to the fault being applied.

    The load resistance is fixed to give a current of approximately5A for phase to phase faults and 2A for phase to earth faults

    4. The fault contactor is energies from the 115V ac supply

    from the supply unit via the bridge rectifier and the push

    button. The contactor is fitted with an economy resistance

    when the coil is continuously rated.

    46

  • 8/6/2019 III II Project

    47/51

    5. The current reversing switch is included to enable the

    current supply to the relay to be reversed and so check that the

    relays are measured in the correct direction.

    FAULT IMPEDANCE RELAY:

    This unit represents the line impedance as seen by the relays

    under the fault condition. The impedance is made up from a

    tapped choke L1and tapped resistance R1. The choke is the

    type as used for the source impedance L2 and has ohmic range

    of approximately 0.5ohm to 24ohms in 8 steps. The angle of

    the choke varies approximately between 72 and 82

    depending upon the ohmic tap. The resistance has 15 taps

    giving an ohmic range of approximately 0.2 to 10ohms.

    PERSONALITY DEVELOPMENT:

    The outdoors provides an extremely powerful medium for

    training students in new skills or helping them to improve old

    ones, largely because outdoor learning is experimental in

    nature .Our Industrial training certainly served the purpose. As

    We all learn through experience. The basic idea behind our

    training was to provide motivation and we were very much

    benefited by it as it provided an encouraging physical and

    psychological security framework for these experiences, as

    well as theoretical and practical aids. Our training program

    focused on teamwork and Interpersonal Skills Management

    47

  • 8/6/2019 III II Project

    48/51

    and provided ample opportunity for us to understand its

    importance and develop better relationships. It helped us to

    appreciate the changes we will encounter later in life. The

    training program also provided an insight to our behavior

    patterns in different situations. These aspects helped us in

    overcoming areas of concern or weakness and provide a

    platform for all-round development of an individual

    personality. Another aspect which this training brought to the

    fore was safety. Safety has been the overriding concern in the

    practical world. This is particularly true in the outdoor, where

    the potential for danger is often higher.

    SUGGESTIONS FOR OUR FORTHCOMING

    BATCHES & MOTIVATION FOR THE

    INDUSTRIAL TRAINING:

    Try to attain permission from industries as early as

    possible so that there will no tension at the last minute

    Students should form themselves into groups and create

    their own websites which would feature the lists of the

    students, their resume, tour plans, the companies to be visited

    and the benefits which the sponsors would get.

    48

  • 8/6/2019 III II Project

    49/51

    Maintain dignity at the industries you visit so that our

    juniors will also be benefited. It will also help to improve our

    college name and fame.

    Through this tour we got idea about industrial

    environment and we can behave well in the industrial training

    that will be in 4rth year-2nd Semester.

    With these experiences we got knowledge about

    communication, corporate culture & competitive world. More

    of all I got the reason why I have to work hard in my B-Tech.

    Through this tour I felt I lessen my fear to talk with

    Corporate Workers and I improved my communication skills.

    CONCLUSION

    Lines or feeders can be protected by several methods. Each

    method has some advantages and some limitations .The classes

    of protective relays used for line protection.

    Roughly in ascending order of cost and complexity are:

    Instantaneous over current relay

    Directional over current relay

    Time over current relay

    49

  • 8/6/2019 III II Project

    50/51

    Distance relay

    Pilot(Pilot wire, power line carrier or microwave) relay

    Graded time lag and graded over current protection is used

    for single radial feeders where time lag can be permitted.

    Differential protection is of unit type. It gives us fast relaying

    pilot wire differential relaying used for short lengths. In

    distance protection distance relaying is based on measurement

    of impedance between relay location and fault point. It has

    three types namely impedance type, reactance type, mho type.

    The relay operates if the impedance is below the set value .In

    distance protection if electro magnetic relays are replaced by

    static relays then the operation will be more reliable. Because

    in electro magnetic relays, the relay operates with moving coil

    but in static relays the relay operates without moving coil.

    In distance protection the operation will be more efficient by

    Fast operation

    Independent zones of operation

    Current transformer supervision

    Voltage transformer supervision

    50

  • 8/6/2019 III II Project

    51/51

    REFERENCES

    1. A Text book on Power System Engineering -

    A.ChakrabarthiM.L.Soni

    P.V.Gupta

    U.S.Bhatnagar

    2. Switch gear and protection - Sunil.S.Rao

    3. Instruction Manuals - MRT I, Stage-I

    4. Protective Relays Application Guide, 3rd edition.

    ALSTOM T&D Protection and Control, 1987.

    5. IEEE Transactions on Power Delivery, Vol. 16, No.2, pp.

    238-246, April 2001.