igg agenda - rmds...minutes (v1.0) from igg meeting 31st august 2016 for approval today 2nd...
TRANSCRIPT
2nd November, 2016 1
IGG Agenda
Minutes from Previous IGG Meeting 10:15 – 10:20
Review of Action Items 10:20 – 10:40
CER Update 10:40 – 11:00
Gemserv Update 11:00 – 11:10
MRSO Update 11:10 – 11:20
ESB Networks Update 11:20 – 11:45
Retail Market Design Service Update 11:45 – 12:05
AOB 12:05 – 12:10
Next Steps 12:10 – 12:15
All participants are kindly requested to mute their phones when dialled into the forum conference call
2nd November, 2016 2
Minutes
Minutes (v1.0) from IGG meeting
31st August 2016
For Approval Today
2nd November, 2016 3
IGG Action Items
Updated IGG Action List issued in advance of
meeting
4 Actions closed since last IGG meeting
7 IGG Actions carried forward
2nd November, 2016 4
Update on Actions - Closed
AP No. Title
Org. Assigned
to Date Closed Date Raised
1013
MRSO Presentations - Suppliers to provide suggestions as to what they want to see in
the MRSO IGG Presentations in the future & suggest whether the current forum slide
deck is best placed on the RMDS website only rather than provided at all IGGs. Suppliers 31/08/2016 29/06/2016
1015
DR1180 New Registrations - Suppliers to provide comments on this DR ahead of the
next IGG. Suppliers 31/08/2016 29/06/2016
1012 CER to circulate the Terms of Reference of the IGG to all Participants via RMDS CER 28/09/2016 04/05/2016
1019
Revenue Protection - Suppliers to submit nominee details, if any, for the Revenue
Protection Group to ESBN via RMDS Suppliers 28/09/2016 31/08/2016
2nd November, 2016 5
Update on Actions - Open
AP No. Title
Org.
Assigned to Date Due Date Raised
948/1004
ESBN to analyse the process where Move out with no Move takes place and make
proposals based on existing Supplier processes for best business practise within this
area. Process must enable MPs to notify CMS when a move out without a move in takes
place. Proposal to be issued to market in the form of a DR. (The issue is an
amalgamation of 948 and 1004) ESBN 02/11/2016 14/01/2015
986
Technical Details - DR covering the importance of appropriate Technical Details (name
and phone) to the 016 to be drafted. Detail to be added to MPD 01 & 02 ESBN 02/11/2016 02/09/2015
1017
Green Source Verification Process Clarifications and revised timelines - Suppliers to
submit questions/comments to CER (via RMDS) on the Green Source Presentation
outlined by CER. Suppliers 02/11/2016 31/08/2016
1018
Retail Market Code - CER is in the process of considering framework and requirements
for a Retail Market Code. Suppliers are requested to submit comments/suggestions to
CER (via RMDS) relating to proposed framework, content and requirements. Suppliers 02/11/2016 31/08/2016
1020
CER Rebrand - CER to provide details of the CER Rebrand & Timelines to Suppliers via
RMDS. CER 02/11/2016 31/08/2016
1021
Suppliers are requested to submit comments on the Terms of Reference of the IGG to
CER via RMDS (linked to IGG Action 1012) Suppliers 02/11/2016 28/09/2016
1022
RMDS to circulate if possible the NI Retail Market Code to Suppliers (linked to IGG
Action 1018) Suppliers 02/11/2016 28/09/2016
6
CER Update
02.11.2016
Retail Market Assurance
Services for the Irish Electricity
Market
Lizzie Montgomerie
IGG
2 November 2016
Belfast
Assured Parties – November 2016
Gemserv 8
Number and type of live participants assured by Gemserv since 2005
NB this is not a reflection of the live market position.
11
7
27
8
4
Large
Small
Self Supplier
DSU
Export Supplier
Assurance Services: During October 2016
Gemserv 9
New Entrants
One Large Supplier
And One Complete
One Small Supplier
One Export Only Supplier
And One Complete
One SelfSupplier
Complete
Thank You
Lizzie Montgomerie
Head of Assurance
T: +44 (0) 20 7090 7750
W: www.gemserv.com
MRSO Update Gerry Halligan
2nd November 2016
12 esbnetworks.ie
Debt Flagging
Jul-16 Aug-16 Sep-16
Total MPRNs received 412Automated
Debt Flag
Automated
Debt Flag
Total CoLEs returned to outgoing supplier 215
Returned for other reason to outgoing
supplier (invalid MPRN, switch completed)17
Valid Debt Flags issued to gaining supplier 180 229 228
Total not cancelled 118 150 158
Total cancelled 62 79 70
Valid Debt Flags as % of total COS 0.7% 0.9% 0.8%
13 esbnetworks.ie
Debt Flagging
Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16
Total MPRNs received 763 509 356 400 379 420 463 428 374 412 0 0
Valid Debt Flags issued 529 229 164 198 163 199 217 208 147 180 277 228
Total Cancelled 51 79 71 48 54 58 54 61 45 62 79 70
0
100
200
300
400
500
600
700
800
900
Total MPRNs received
Valid Debt Flags issued
Total Cancelled
14 esbnetworks.ie
Objections – Erroneous Transfers
91
74
64
52 5247
5348
69 68
59
67
79
92
68
89
74
65
8690
160
85
105
85
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
0
20
40
60
80
100
120
140
160
180
No
. o
f C
oS
Co
mp
leti
on
s
No
. o
f O
bje
cti
on
s
No. of Objections
CoS Completions
15 esbnetworks.ie
Objections
Jul-16 Aug-16 Sep-16
No. of Objections 85 105 85
Cancellations from Objections 62 81 58
Objection emails to MRSO 11 15 12
Reasons:
Uncontactable by phone 1 2 1
Written communication 1
COS confirmed 10 12 11
Other
Escalation emails 3 2 3
16 esbnetworks.ie
Comments on query raised at last IGG on sharp
increase in objections for June 2016
• Sharp increase in objections for erroneous transfer recorded in
June (May 90 – June 160 – July 85)
• Increase mainly due to two losing suppliers
• Objections were raised against spread of gaining suppliers
• Analysis of cancellations from objections showed cancellations
were spread across gaining suppliers
• On average 70% of objections for ET are cancelled, the
cancellation figure for June is 73%
• The gaining suppliers would presumably have completed their own
investigations and were satisfied to cancel
• No increase in objection emails or escalations received in MRSO
• From MRSO perspective, Market Process for erroneous transfer
appears to be followed in respect of the data for June
Footer
ESBN Presentation to the IGG
Aileen Greaves
2nd November 2016
18 esbnetworks.ie
ESB Networks Update
• Revenue Protection Workshop was held
• Next meeting scheduled 16th November @ 10.30 same venue
• Progressing with CER issues around the Retail Work Plan
• Commented on IGG Terms of Reference
Footer
ESB Networks I-SEM Programme
Presentation to the IGG
Theresa O’Neill & James Long
2nd November 2016
20 esbnetworks.ie
ESB Networks I-SEM Programme - General Update
We are continuing to work with the RA’s , the I-SEM Project and the other Meter Data Providers through the
I-SEM Metering Working Group.
At this time there is no change to our understanding viz
• No Changes are indicated to the Harmonised Retail Market Schema or the COBL
• D+1,D+4,M+4,M+13 Working day Settlements will operate for ESBN for the I-SEM i.e. No Change to frequency
• Need to concurrently operate the SEM and the I-SEM until the Re-Settlement of the SEM has completed
• No Meter Data will be price effecting in the I-SEM and so I-SEM will not use the Price-Effecting category
• I-SEM Market Trials will run from June-Sept 2017
• The Go-Live date for the I-SEM is 1st Oct 2017
Discussion Request DR1182 was presented and discussed at the last IGG , and for information , no
further comments or queries have been raised with us.
21 esbnetworks.ie
ESB Networks I-SEM Programme – Price Effecting Units : Update
Price Effecting Units
SEM-O have identified 7 Supplier Units that are currently Non-Price Effecting , and they have started work with
MRSO to move them to become Price Effecting in the SEM. This means that Eirgrid will become the MDP for
them in the SEM. This is expected to be completed shortly.
Eirgrid and SEM-O have confirmed the Units that will move from Eirgrid being their MDP in the SEM to
MRSO becoming their MDP in the I-SEM. These are the current stats, at time of writing:
• 32 Distribution Connected GUs will become NPEG
• 12 SUs will become NPED
The current List of Distribution Connected Price Effecting Generator MPRNs is available on the RMDS website
Distribution Loss Factors | RMDS Please note : this list is subject to change over time
We are continuing to work closely with Eirgrid and SEM-O on the cutover implications and the timeline for their
moving in the I-SEM.
• This will include a detailed consideration of the timelines for the I-SEM Transitional Registration Lock-Down
period once it has been confirmed , and the Go-Live date for the I-SEM
22 esbnetworks.ie
ESB Networks I-SEM Programme – Market Trials : Update (1 of 2)
Unscripted Phase of the Market Trials & the RoI Retail Market
For the I-SEM Market Trials Unscripted phase, our intention for RoI Suppliers and Eirgrid TSO is to make
available
• For Suppliers; the 341,59x series of messages and 342 message for the Supplier’s own generators.
• For Eirgrid TSO; the 341,59x series of messages and 342 messages including those GUs and SUs that are
moved during market Trials so that MRSO becomes their MDP for Market Trials
Naturally this means that if you want to get these messages from the Market Trials then you will need to have a test
EMMA that is available for the duration of the Unscripted Market Trials phase
We expect that the Registration Data that we will set up in the Retail Market environment for the Unscripted
phase of Market Trials will mirror the I-SEM Transitional Registration details for SUs and Participant GUs
• This will include a practice cut-over of at least 1 of the Units that is moving from Eirgrid as MDP over to MRSO as
MDP
Note : we need to do more work to better understand what QH read data will be available during Market Trials for these
Units given that the actual SEM MDP at that time will still be Eirgrid . We’ll let you know the outcome in due course.
23 esbnetworks.ie
Looking for your Feedback
We are considering drafting a new Market Trials WP12 to accommodate Participant GU registration
changes being requested specifically for Market Trials
Q1 Would you see any need for this , and would you use it
We are considering drafting a new Market Trials WP14 purely as part of the Unscripted Market Trials
to accommodate Non Participant Generator Arrangements changes being requested specifically for
Market Trials
Q2 Would you see any need for this , and would you use it
Your feedback on Q1 and Q2 is welcome , and as normal, we can be contacted via the RMDS
mailbox.
ESB Networks I-SEM Programme – Market Trials : Update (2 of 2)
24 esbnetworks.ie
ESB Networks I-SEM Programme – Market Trials (Appendix 1)
Appendix 1
Links to related I-SEM Project publications
The I-SEM Project has published their Market Trial Strategy and Market Trial Plan documents.
http://www.sem-o.com/ISEM/General/Market%20Trial%20Strategy.pdf
http://www.sem-o.com/ISEM/General/Market%20Trial%20Plan.pdf
Note that the description of phases of Market Trials and the Timelines are detailed within these documents
The draft/proposed Transitional Registration Plan has also been published and was presented by the I-SEM
project team for discussion with the BLG on 19th October. (NB At time of writing the plan is to be finalised)
http://www.sem-o.com/ISEM/General/Transitional%20Registration%20Plan.pdf
http://www.sem-o.com/ISEM/General/BLG_Registration%20Presentation%2019%20Oct.pdf
25 esbnetworks.ie
ESB Networks I-SEM Programme – Market Trials (Appendix 2)
Appendix 2
Links to existing Retail Market Working Practices
https://rmdservice.com/working-practices-2/
WP12 To nominate / denominate a Supplier as a recipient of Participant Generator messages
WP14 Distribution Connected Non Participant Generator Export Arrangements Working Practice
Thank You
Footer
2nd November, 2016 27
Retail Market Design Update
Jessica Gregory
RMDS
2nd November, 2016 28
LTCA
LTCA Audit Update
• Audit commenced 05/10/2016
• ESBN data gathering meetings 5th-7th October
• Scenarios developed by External Auditor
• MP Workshop held 12/10/2016
• 2 week Supplier data gathering period comm. 17/10/2016
• EA initial data analysis commencing. 31/10/2016
• Weekly reports issued commencing 23/09/2016
LTCA Audit Look Ahead
• MP Visits start week comm. 31/10/2016
All information / updates / progress posted to RMDS Confidential Website
2nd November, 2016 29
2015 IGG Survey Action
Action 4 – Non-Attendance at Market Workshops
Noted a high percentage of respondents did not attend Forum Workshops. An exercise
shall be undertaken to understand why this is the case.
• Review of attendance at IGG Meetings 2015 and 2016
• Review of attendance at Market Workshops 2015 and 2014.
• 5 Suppliers have not attended any of the above reasons below.
A decision to add all DSU’s, Self Suppliers and Export Only Suppliers to the IGG
Distribution List was made.
Supplier 1 Supplier 2 Supplier 3 Supplier 4 Supplier 5
No Business Need
Would attend if a topic motivated them
Limited Resources
Read Minutes
Future plans for regular attendance
Worry about their infuence
2nd November, 2016 30
Next Market Release (Agreed it will not be 2016, but 2017/2018?)
Decision as to when the next Schema and Non Schema releases will take place are pending the
outcome to
ReMCoSG action 135 (CER/UR to provide a decision around the future Co-ordinated Market
Priorities and deliveries of such) and
WG action 145 (CER/UR to respond to ESBN/NIEs with a position on how to progress the
Schema Market Release, specifically whether ROI/NI is supported in progressing planning
activity for the 2018 Schema Release as detailed in the Co-ordinated Market Retail Delivery
Plan.)
Market Release Summary
2nd November, 2016 31
The core driver from CER for this DR is that for sites which do not elect a supplier
within 5 days of energisation, should not automatically be assigned to Electric Ireland..
The difference to the current process is that for sites < 30 kVA the customer will in
future have to contact a Supplier of choice who will submit a registration to ESBN with
the customer name, and receipt of the registration by MRSO becomes a requirement
before the site is energised.
This DR was brought to last Forum and Market Participants generally support the
principle of a mandatory selection of a Supplier before energisation. However a
number of questions have arisen with regards to how New Registrations are cancelled.
This DR is now therefore on Hold until the Cooling off DR has been finalised, as the
design of this will affect how New Registration cancellations are handled.
At Today’s Meeting: For Information as the DR completion is dependant on outcome
of DR 1184 (Cooling Off period)
DR1180 – New Registrations(Place Holder)
2nd November, 2016 32
CER’s Retail Market team asked ESB Networks in January 2015 to assess the impact of
the ISEM on the Retail Market in Ireland..
Whilst the SEM is to undergo a radical transformation arising from changes to European
legislation designed to create a single wholesale electricity market across Europe, the
intention of the RA’s I-SEM team is that there would be minimum impact for the Retail
Market and for Meter Data Providers arising from the I-SEM.
ESB Networks is one of the four Meter Data Providers represented at the I-SEM Metering
Working Group and have been considering the impacts of the I-SEM.
The proposed changes are fully detailed in MCR1182 and include changes to the Data
Processing and the Data Aggregation Retail Market business process between ESB
Networks and Market Participants.
At Today’s Meeting: For Approval as MCR
MCR1182 –Impact of I-SEM on the Retail Market
2nd November, 2016 33
The customers’ right to the cooling off period is detailed in Directive 2011/83/EU
on consumer rights, which was transposed into Irish legislations through the
Statutory Instrument S.I. No. 484 of 2013
Under this directive , customers have a right to a cooling off period of 14 days.
This includes situations when switching their gas and / or electricity accounts.
The cooling off period allows the customer to cancel the switch within a certain
time without incurring penalty.
The CER have completed a review on whether or not the a cancellation process
should be incorporated into the market design to allow for change of mind.
Options were presented to industry for comment, this resulted in selection of an
option which the majority of Suppliers supported.
DR1184 – Cooling off for COS(1/2)
2nd November, 2016 34
DR1184 – Cooling off for COS(2/2)
The Competition & Consumer Protection Commission’s website states that
the cooling off period is 14 calendar days.
The scenarios outlined in the DR were created based on 14 calendar days.
Once the customer contacts the Supplier, they have up to 4 days to send the
010 and the customer has 14 cooling off calendar days to exercise their
cooling off rights.(18 days total).
At Today’s Meeting: For Discussion
2nd November, 2016 35
DR1185 – Small Supplier Categorisation(1/2)
Currently the structure of the Small Supplier category does not facilitate
the business model of a Supplier having a small number of sites but
energy usage greater than 10MW power at peak demand.
The proposal is to change the current categorisation and assurance
approach within the Small Supplier category
the threshold of < 200 sites registered will continue to be part of the
criteria in qualifying and operating as a Small Supplier in the Retail
Market at all times
the threshold of 10MW power supplied at peak demand will not
apply as criteria where a Supplier indicates that their model is one
which is a small number of customers but where there will be greater
than 10MW power at peak demand.
2nd November, 2016 36
DR1185 – Small Supplier Categorisation(2/2)
The assurance body will determine the assurance assessment required for
each Small Supplier entering the Retail Market based on the segment(s)
the Supplier is entering and their Business model.
The Scope of Change to Design Documentation relates to amendments to
the Market Assurance and Market Entry Documentation.
At Today’s Meeting: For Approval
2nd November, 2016 37
Non Schema 2017 – Prioritisation
MCR NumberDR / MCR Description Comment
Delivery Event
DR1185 DR Small Supplier Categorisation For Approval at Forum on 2/11/2016 MMR
DR1184 DR Cooling Off for COS For Discussion at Forum 2/11/2016 NS / MMR
MCR1182 MCR I-Sem Changes For Approval at IGG on 2/11/2016 - delivered as part of I-SEM I-SEM proj
DR1180 DR New RegistrationsWaiting on Cooling off DR to be finalised prior to completion (reliant on Cooling off) NS
MCR1179 MCR Cessation of Eligible Cust Files on Extranet approved. To be impact assessed by ESBN NS
MCR1176 MCR Extranet Message Ordering Approved May 2016 NS
MCR1175 MCR Provide MP Bus Ref for Reading Approved June 2016 NS
MCR1169 MCRAddition of Postal Codes to two downloadable Meter Point Details Files Approved November 2015 (linked to MCR 1140 & Schema MCR ) NS
MCR 1141 MCR Supplier ID Validation on 260MM
With ESBN Currently. ROI still to determine best approach for ROI. With ESBN scope and design. Implemented in NI in 2015 on the 1st May 2015 and this was advised to the CDA Board at the CDA Board meeting that took place on 13th May 2015 ?
MCR1140 MCRNew RoI Postcodes into the Market Design(Eircodes)
Re-Versioned to cater for changes to GNI. Approved at IGG on 29/6/2016 (linked to MCR 1140 and Schema MCR NS
MCR 1135 MCRMarket Webservice as opposed to a Market Website to provide On-Demand Customer Information.... Read more
The MCR has been approved but has been put on hold. This is on hold due to concerns by CER that its implementation may have impacts on the central market systems NS
DR 1001 DRIncrease number of days for a Customer Read for a COS to match the Supplier Cooling Off Period - 7 Working Days
Brought to IGG meeting on 04.12.13 requesting withdrawal. Approval was not granted and this is now on hold. Outcome of DR 1184 may negate need for this DR. DR has to be reassessed in light of DR1184 ?
MCR 0062 MCRNew rule for MPD1 NQH Change of Supplier.... Read more
This MCR is on Hold. This must be reassessed in light of DR 1184 and LTCA WG outcomes. ?
Exclude first 3 as either Delivered outside of NS release
2nd November, 2016 38
Activity Role Action DateRank each of the changes highlighted in orange 1-7 with 1 being your top priority and 7 your least important. Items excluded are due to low probability of approval prior to mid 2017 or being subsumed into new DR/MCRs. Current applicability still to be determined. MPs Return to RMDS by 30/11/2016
Consolidate and formulate Market prioritised list. RMDS Issue to Market by 16/12/2016
Determine any action required to get prioritised MCR's approved. RMDSFormulate, plan & communicate by 11/01/2017
Communicate outcome of prioritisation exercise to Market at IGG RMDSPresent at IGG and issue email by 11/01/2017
Include Market feedback following delivery of list RMDS 18/01/2017
Provide ESBN list of prioritised MCRs for impact assessment. RMDS Issue to ESBN 19/01/2017
ESBN suggest proposed package of changes based on MP prioritisation and dependencies between MCRs, other work programmes. Proposed delivery dates of changes provided ESBN Issue to RMDS by TBD
Proposed package with delivery dates issued to Market for review & comment RMDS RMDS TBD
MPs MP TBD
Market Approval of Non Schema Package and delivery Date at IGG Market Approve at IGG in Q1 2017 TBD
CER approve Non Schema Package and delivery CER Approve Q1 2017 TBD
Non Schema Prioritisation 2017
2nd November, 2016 39
Extranet Screenshot issue - RMDS has been alerted by ESBN that a Supplier sent a
screenshot of the Extranet to one of it’s prospective customers. This is a breach of Data
Protection. Under no circumstances should Suppliers send Extranet screenshots to
Customers.
Working Practice 19 – Hardship PAYG. Some suppliers may have incorrectly been
advised to follow COS practises not agreed and contained in WP19. Please can all MPs
continue to follow the processes outlined in WP19 for hardship PAYG.
CER Lock Moratorium period for Christmas Period 2016.
Information for Suppliers
2nd November, 2016 40
2017 IGG & IGG Conference Call Dates – Full details are available on the RMDS website
under Reference Section/Guidance Documents
IGG/IGG Conference Call dates & Times 2017
ReMCoWG/IGG/CDA(8 week cycle)
Location IGG Conference Call(4 weeks after IGG)
11th January Dublin
8th February
8th March Belfast
5th April
3rd May Dublin
31st May
28th June Belfast
26th July
30th August Dublin
4th October
1st November Belfast
6th December
2017 Forum timings – As per WG Action 146 - CDA Meetings now only 1 hour 30 Minutes
CDA/WG/IGG in Dublin IGG/WG/CDA in Belfast
CDA 10:30 - 12:00 IGG 10:30 - 12:30
WG 12:30 - 13:30 WG 13:00 - 14:00
IGG 13:30 - 15:30 CDA 14:00 - 15:30
2nd November, 2016 41
Annual Tasks
Documents / Links
Meter Reading Calendar
Load Profile Indexes (6 Individual Files) – will be available
shortly.
Load Profile Indexes 2017
Unmetered PL Burn Hour Calendar 2017
Unmetered PL Index Values 24H 2017
Unmetered PL Index Values Dusk to Dawn 2017
Unmetered PL Index Values Dusk to Midnight 2017
Night Storage Heating Derived Profiles 2017
Derived Load Profiles 2017
Distribution Loss Factors 1.10.2016 - 30.09.2017
Site Specific Loss Factors effective 1.10.2016
ESB Networks Ltd – Statement of Charges
Christmas New Year Working Arrangements
IGG/CDA/ReMCoWG/ReMCoSG/Meeting Dates
2nd November, 2016 42
End of Year Working Arrangements Document covers period Friday 16th December 2016 to Tuesday 3rd
January 2017
This document is available on the RMDS website under guidance
documents. The link is http://rmdservice.com/guidance-documents/
The document is also placed on the calendar post for today’s IGG 2nd
November 2016.
2nd November, 2016 43
End of Year Working Arrangements
RMDS Support
The RMDS phone lines and email inbox will not be manned for the
period 23rd December 2016 to 3rd January 2017.
For emergencies during this period please contact Jessica Gregory on
+353 879548871.
BEST WISHES OVER THE FESTIVE
SEASON AND SEE YOU IN JANUARY
2017
2nd November, 2016 44
Upcoming Outages for ROI
http://rmdservice.com/outages-2016/
PLANNED OUTAGE NOTIFICATION
Outage Type Planned Outage
Start Date of Outage Saturday 5th November 2016
Start Time of Outage 08:00 hrs
Date of Restoration of Outage Saturday 5th November 2016 Restoration Time of Outage 18:00 hrs
Duration of Outage 10 hrs (approx.)
Jurisdiction Affected NI & ROI Electricity Markets
Reason for Outage To facilitate an upgrade of the TIBCO HUB infrastructure.
Market Systems Impacted TIBCO Market Messaging System
Backlog Impact / Comments Market Messages inbound and outbound will queue and be processed on resumption
of normal service.
System undergoing Outage TIBCO
2nd November, 2016 45
Upcoming Outages for ROI
http://rmdservice.com/outages-2016/
PLANNED OUTAGE NOTIFICATION
Outage Type Planned
Start Date of Outage Saturday 19th November 2016
Start Time of Outage 08:00 hrs
Date of Restoration of Outage Monday 21st November 2016
Restoration Time of Outage 06:00 hrs
Duration of Outage 46 hrs (approximately)
Jurisdiction Affected NI & ROI Electricity Markets
Reason for Outage NIE Networks Disaster Recovery Test
Market Systems Impacted TIBCO Market Messaging System
Market Website (NI only)
Secure Fileserver (NI only)
Backlog Impact / Comments Market Messages inbound and outbound will
queue and be processed on resumption of normal service.
System undergoing Outage TIBCO Market Messaging System
Market Website (NI only)
Secure Fileserver (NI only)
2nd November, 2016 46
IGG Meeting
AOB
2nd November, 2016 47
Next Steps
Diary dates for next IGG meeting:
Wednesday 11th January 2017 - Dublin
Dates included on Calendar of Events on RMDS
website www.rmdservice.com
2nd November, 2016 48
Next Steps
Diary dates for next Conference Call:
Wednesday 7th December 2016
Dates included on Calendar of Events on RMDS
website www.rmdservice.com
Call details are as follows:
Ireland Local Call Dial-In Number: 01 2475479
Std International Dial-In Number: +44 (0) 203 4333578
Conference code: 1663328269
2nd November, 2016 49
IGG Meeting
Thank You