HVDC Market Projects and participants with hyperlinks
Last revised
January 2020
If you would like to update or add to any of the information then please contact
us.
31/01/2020 1 www.warwickHVDC.co.uk
![Page 2: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/2.jpg)
Electricity prices Business cases for interconnectors are generally (if not always) underpinned by price differentials between two markets. Price differentials generally need to be material and forecast to be sustained over the longer term (15-20 years plus). Short term price differentials are also relevant and can be driven by time zone and generation mix differences. Click the logo below to see the latest electricity price summary reports from the European Commission. Numerous commercial electricity exchanges can provide access to detailed, real-time prices and analysis for Europe and worldwide.
31/01/2020 2 www.warwickHVDC.co.uk
![Page 3: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/3.jpg)
31/01/2020 www.warwickHVDC.co.uk 3
Interested in any of these projects?
For expert advice, analysis, training, or consultancy, on a long or short-
term basis, please contact us at:
www.warwickhvdc.co.uk
Monthly updates and news will be posted but we also offer retained
support packages from minimum 15 hours per year to keep you fully up to speed with information, opinion and advice in this
market.
![Page 4: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/4.jpg)
UK and Ireland HVDC sub sea connections
31/01/2020 4 www.warwickHVDC.co.uk
![Page 5: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/5.jpg)
Channel cable
GreenLink
CelticLink
IceLink
Blyth
Bicker Fen
Exeter
Chilling
Lovedean
Kingsnorth
Sellindge
Zeebrugge
Maasvlakte
Tourbe
GridLink
Conneforde
Peterhead
Germany
Richborough
Grain
NeuConnect
BritIB
IFA
31/01/2020 5 www.warwickHVDC.co.uk
UK & Ireland Interconnectors
Built In Construction In Development
![Page 6: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/6.jpg)
UK and Ireland HVDC sub-sea Interconnectors (1)
Project name Website hyperlink Route length
Technology Suppliers Published cost
Completion date
EU or National support?
Latest status
Anglo-French Marine: ~57 km Land: ~8 km
160 MW 100 kV bipole
ABB 1961 - decommission
ed
Decommissioned
IFA IFA Marine: 70 km Land: 15 km
2 GW 270 kV Cable x 8 LCC
GEC, Alstom NEXANS + Prysmian
1986 Complete
BritNed BritNed Marine: 250 km Land: 10 km
1 GW 450 kV MI bipole LCC
Siemens / BAM, ABB
£500m 2012 Complete
Western Link Western Link Marine: 385 km Land: 37 km
2.25 GW 600kV MI bipole
LCC
Siemens, Prysmian
£1.2bn 2018 Complete
Moyle Moyle Interconnector Marine: 64 km Land: 9 km
(500 MW) 2 x 250 kV monopole LCC
NEXANS, Siemens
£150m 2002 Complete
East West East West Interconnector
Marine: 186 km Land: 75 km
500 MW 200 kV XLPE sym.
monopole VSC
ABB ABB
€560m 2012 Complete
Caithness - Moray
Caithness - Moray Marine: 113 km Land: 48 km
1.2 GW 320 kV XLPE VSC
ABB / NKT £970m 2019 Complete
Nemo Link Nemo Link Marine 130 km Land 11 km
1 GW 400 kV XLPE bipole VSC
Siemens Sumitomo
€690m 2019 Complete
NSL* North Sea Link Marine 720 km Land 10 km
1.4 GW 515 kV MI bipole VSC
ABB Prysmian / Nexans
€2bn 2021 EPCI status UK Cap & Floor
Construction
IFA2* IFA2 Marine 208 km Land 32 km
1 GW 320 kV XLPE bipole VSC
ABB Prysmian
> €600m 2020 EPCI status UK Cap & Floor
Construction
Eleclink* Eleclink Tunnel 51 km Land 18 km
1 GW 320 kV XLPE VSC
Siemens / Balfours Prysmian
> €500m 2020 EPCI status UK Cap & Floor
– Exempt
Construction
Viking* Viking Marine 635 km Land 131 km
1.4 GW 525 kV XLPE or MIND
bipole VSC
TBC TBC 2022 EPCI status UK Cap & Floor
Move into construction
phase Awarded
Key
Built In Construction In Development
Whilst this is only a guide please contact us if you would like to update or add to
this information.
31/01/2020 6 www.warwickHVDC.co.uk
![Page 7: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/7.jpg)
UK and Ireland HVDC sub-sea Interconnectors (1)
Project name Website hyperlink Route length
Technology Suppliers Published cost
Completion date
EU or National support?
Latest status
Green Link*
Green Link Marine 180 km Land 30 km
500 MW Bipole or sym. Monopole VSC
TBC TBC 2023 EPCI status UK Cap & Floor
Tender live New Directors
FAB Link* FAB Link Marine 180 km Land 49 km
1.4 GW 320 kV 2 x bipole VSC
TBC €1.2bn 2021 EPCI status UK Cap & Floor
Brexit delay Marine licenses secure
Celtic Link * Celtic Link Marine 500 km Land 100 km
700 MW 320-500 kV
TBC €1bn 2025 EPCI status Priority status
EirGrid Consultation EU Funding
GridLink * GridLink Marine: 140 km Land: 14 km
1.4 GW TBC TBC 2022 EPCI status UK Cap & Floor
Tender summer 2019
PQQ started
Key
Built In Construction In Development
Whilst this is only a guide please contact us if you would like to update or add to
this information.
31/01/2020 7 www.warwickHVDC.co.uk
![Page 8: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/8.jpg)
UK and Ireland HVDC sub-sea Interconnectors (2)
Key
Built In Construction In Development
Whilst this is only a guide please contact us if you would like to update or add to
this information.
31/01/2020 8 www.warwickHVDC.co.uk
Project name Website Route length Technology Suppliers Published cost
Completion date
EU or National support?
Latest status
NeuConnect* NeuConnect Marine: 650 km Land: TBC
1.4 GW 500kV TBC TBC 2023 EPCI status UK Cap & Floor
Views sought on vital new electricity link for Britain
Tender underway UK connection agreed
AQUIND*
AQUIND Marine: 180 km (estimate)
Land: 60 km (estimate)
2 GW 320kV XLPE 2x sym. monopole VSC
TBC TBC 2021 EPCI status UK Cap & Floor
PQQ underway Statutory consultation on
proposals Planning Inspectorate approval
NorthConnect *
NorthConnect
Marine: 655 km Land: 3 km 1.4 GW 500 kV bipole
or sym. monopole
TBC £1.3bn 2022 EPCI status UK Cap & Floor
Tender underway Marine licences approved
UK onshore consents granted
Channel Cable*
Channel Cable
130 km total 1.4 GW 400 kV bipole
TBC TBC TBC TBC
Atlantic SuperConnection
Altantic SuperConnecti
on
Marine >1000 km Land 10 km (estimate)
1-2 GW >500 kV (estimate)
TBC up to €4bn (estimate)
2025 Concept
IceLink IceLink Marine >1000 km Land 10 km (estimate)
800 MW-1.2 GW >500 kV (estimate)
TBC up to €4bn (estimate)
TBC Concept
BritIB BRITIB Marine >1300 km Land TBC
1.8 GW 525-600 kV bipole VSC multi-terminal
TBC TBC TBC Concept
Western Isles Link*
Western Isles
Marine 80 km 600 MW 320 kV monopole
Tender in final stages
£780m 2021 RIIO Ofgem provisionally reject
Shetland (2) HVDC
Shetland HVDC
Marine: 260 km Land: 10km
600 MW TBC £710m 2024 RIIO R3 CFD not awarded Project future now uncertain
![Page 9: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/9.jpg)
UK and Ireland HVDC sub-sea Interconnectors (2)
Key
Built In Construction In Development
Whilst this is only a guide please contact us if you would like to update or add to
this information.
31/01/2020 9 www.warwickHVDC.co.uk
Project name Website Route length Technology Suppliers Published cost
Completion date
EU or National support?
Latest status
Eastern Link* Eastern Link >400 km >500 kV (estimate)
TBC TBC TBC RIIO T2 Early stage tender notice issued
Gallant Gallant HVDC
Marine: ~35km Land: ~35 km
500 MW TBC TBC 2023 Concept
Maali MAALI ~ 400 km 600 MW 320 kV TBC TBC 2025 Concept
MAREX MAREX 1.5 GW (estimate) TBC TBC 2025 Concept
Greenwire North
1 GW Superseded by Greenlink
Greenwire South
1.3 GW Superseded by Greenlink
![Page 10: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/10.jpg)
UK and Ireland HVDC wind farm connections
31/01/2020 10 www.warwickHVDC.co.uk
![Page 11: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/11.jpg)
UK and Ireland
HVDC wind farm connections
Project name Website hyperlink
Route length
Technology
Suppliers Published cost
Completion date EU or National support?
Latest status
Seagreen *
Seagreen 65km offshore
25km onshore
1075MW, DC
Nexans - cable
2024 R3 CFD Nexans Supplier
Sofia /* Doggerbank ***
Forewind Marine: >165 km
TBC NKT up to €360M
(estimate)
TBC R3 CFD Registration of Interest for Sofia
NKT Supplier / Update
Key
Built In Construction In Development
Whilst this is only a guide please contact us if you would like to update or add to
this information.
31/01/2020 11 www.warwickHVDC.co.uk
![Page 12: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/12.jpg)
UK and Ireland HVDC OHL connections
31/01/2020 12 www.warwickHVDC.co.uk
![Page 13: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/13.jpg)
UK and Ireland
HVDC OHL connections
Project name Website hyperlink Route length Technology Suppliers Published cost EU or National support?
Completion date
Key
Built In Construction In Development
Whilst this is only a guide please contact us if you would like to update or add to
this information.
There are currently no overhead HVDC lines in the UK or Ireland
31/01/2020 13 www.warwickHVDC.co.uk
![Page 14: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/14.jpg)
Europe excluding UK and Ireland
HVDC Interconnectors
31/01/2020 14 www.warwickHVDC.co.uk
![Page 15: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/15.jpg)
Europe ex UK and Ireland
HVDC sub-sea Interconnectors (1)
Project name
Website hyperlink Route length Technology Suppliers Published cost Completion date
SACOI 1 & 2 SACOI 140 km 300 MW 200 kV monopole LCC
Alstom GE
1968/1988/1992
NorNed NorNed Marine: 578 km Land: 2 km
700 MW 450 kV bipole
€600m 2008
SAPEI SAPEI Marine: 420 km Land: 15 km
1 GW 500 kV bipole LCC
ABB. PRYSMIAN
€730m 2011
NordBalt Nordbalt Marine: 400 km OHL: 53 km
700 MW 300 kV bipole VSC
ABB €552m 2015
COMETA/Romulo Romulo/COMETA Marine: 240 km Land: 7 km
200 MW 250 kV bipole
Siemens, Prysmian, Nexans
€375m 2012
Baltic Cable Baltic Cable 250 km 600 MW 450 kV
$280m 1994
Greece-Italy (GRITA) GRITA Marine: 160 km Land: 40 km
500 MW 400 kV
ABB Prysmian
2001
Estlink 1 (Finland – Estonia)
EstLink1 105 km 350 MW 150 kV bipole VSC
ABB €110m 2007
Estlink 2 (Finland – Estonia)
EstLink2 Marine: 170 km Land: 12 km OHL: 14 km
650 MW 450 kV monopole
Nexans, Siemens €320m 2014
SwePol SwePol Marine: 239 km Land: 15 km
600 MW 450 kV monopole
ABB 2000
LitPol LitPol Back-to-back convertors
500 MW 400 kV/330 kV
ABB €340m 2015
MONITA MONITA Marine: 433 km 500 kV bipole ABB, NEXANS
€800m 2018
Aland HVDC Aland 158 km 100 MW 80 kV VSC
ABB 2015
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 15 www.warwickHVDC.co.uk
![Page 16: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/16.jpg)
Europe ex UK and Ireland
HVDC sub-sea Interconnectors (2)
Project name
Website hyperlink Route length Technology Suppliers Published cost EU or National support?
Completion date
Skagerrak 1&2 Skagerrak 1-3 Marine: 127 km OHL: 113 km
500 MW 250 kV
Alcatel, ABB 1976/2007
Skagerrak 3 Skagerrak 3 Marine: 127 km OHL: 113 km
500 MW 350 kV
Alcatel, ABB 1993
Skagerrak 4 Skagerrak 4 Marine: 140 km Land: 104 km
700 MW 500 kV VSC
Prysmian, Nexans, ABB
2.8bn DKK (approx. €375m)
2014
Fenno-Skan 1 Fenno Skan Marine: 233 km OHL: 33 km
500 MW 400 kV
ABB 1989
Fenno-Skan 2 Fenno Skan Marine: 233 km OHL: 103 km
800 MW 500 kV
ABB 2011
Gotland 1 Gotland Marine: 96 km OHL: 7 km
20 MW/30 MW 100 kV/150 kV
ABB 1957 Decommissioned 1986
Gotland 2 & 3 Gotland 2&3 Marine: 96 km OHL: 7 km
130 MW/150 kV 260 MW/150 kV
ABB 1983 (2) 1986 (3)
Kontek Kontek Marine: 52 km Land: 119 km
600 MW 400 kV monopole
ABB NKT
1995 2016 upgraded
Konti-Skan 1 Konti-Skan 1-2 Marine: 87 km OHL: 86km
250 MW 250 kV
ABB 1965
Konti-Skan 2 Konti-Skan 1-2 Marine: 88 km OHL: 61 km
300 MW 300 kV
ABB 1991
Storebaelt Storebaelt Marine: 32 km Land: 26 km
600 MW 400 kV monopole
Siemens 2010
NordLink * NordLink Marine: 516 km Land: 54 km OHL: 53 km
1400 MW 525 kV MI bipole VSC
Nexans, ABB, NKT €1.5bn - €2bn EPCI status 2020
CobraCable CobraCable Marine: 307 km Land: 22 km
700 MW 320 kV XLPE bipole VSC
Prysmian, Siemens
€621m EPCI status Complete
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 16 www.warwickHVDC.co.uk
![Page 17: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/17.jpg)
Europe ex UK and Ireland
HVDC sub-sea Interconnectors (3)
Project name
Website hyperlink
Route length
Technology Suppliers Published cost
Completion date
EU or National support?
Latest status
EuroAsia / Parallel National Greek project
EuroAsia 1500 km Stage 1: 1 GW VSC
Stage 2: 2 GW VSC >400 kV
bipole
TBC €3.5bn 2020/21 EPCI status Project at risk Planning Approved
EuroAfrica EuroAfrica 1707 km 2 GW TBC > €3bn 2020/21 Euro Africa news Elia investment Jan 18
SACOI 3 SACOI 3 200 km (estimate)
400 MW 200 kV bipole VSC
TBC TBC 2023 Project news
ELMED Marine: 192 km
Land: 37 km
600 MW TBC TBC 2022 Feasibility
Italy – Albania Italian projects >1000 MW 400-500 kV
TBC
Italy – Algeria Italian projects TBC
Sicily – Libya Sicily Libya > €220m TBC
NorNed 2 580 km (estimate)
700 MW > 5.3bn NOK (> €640m)
Statnett joins project
NorGer NorGer >600 km 1.4 GW >400 kV
> 12bn NOK (> €1.4bn)
Statnett joins project
Slovenia-Italy Italian projects >1000 MW 350-500 kV
TBC
Italy-Croatia Italian projects TBC
Romania-Turkey
Romania-Turkey
400 km 600 MW 400 kV
€600m Feasibility
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 17 www.warwickHVDC.co.uk
![Page 18: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/18.jpg)
Europe ex UK and Ireland
HVDC sub-sea Interconnectors (4)
Project name
Website hyperlink
Route length Technology Suppliers
Published cost
Completion date
EU or National support?
Latest status
Hansa Powerbridge* Powerbridge 300 km 700 MW 300 kV bipole
€600m (estimate)
2025/2026 Consenting
ANAI (Spain/France/UK)
Anai >1500 km 2 GW 2026 TBC
Kontek 2 & 3 Kontek
600 MW 400 kV
> 2030 Feasibility
Great Belt 2 (Stoerbalt 2)
Storebaelt
~ 60 km TBC
Denmark – Poland TBC
Cobra 2 COBRAcable ~ 330 km Est 2035 Concept
LEG1 (Greece, Libya, Egypt)
LEG1 Marine: 347 km Land: TBC
> 2GW 400-500 kV
> €1.6 bn (estimate)
2021 Feasibility
Tunur Phase 1 / 2 (Tunisia)
Tunur Phase 1: 250 MW Phase 2: 2 GW
Authorisation sought
Suedlink SuedLink 4 GW (total) 320 kV XLPE
> €14bn (estimate)
2025 Cost estimate trebles Contract Notice
Project News
Lithuania Poland (Harmony Link) ***
TBC 700MW, VSC 2025 Feasibility Latest Status
Ariadne Interconnection
Adriadne Marine 328km Land 32km
500MWx2, VSC Bi-pole
Est 1bn Euro 2022 Tenders live
Biscay Gulf Biscay-Gulf Marine: 280 km Land: 90 km
2 x 1000 MW bipole
€1.9bn 2025 RTE and REE perform additional analysis to
secure the project Consenting & Surveys Supplier event April
2018
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 18 www.warwickHVDC.co.uk
![Page 19: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/19.jpg)
Europe ex UK and Ireland
HVDC off-shore energy projects
31/01/2020 19 www.warwickHVDC.co.uk
![Page 20: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/20.jpg)
Europe ex UK and Ireland
HVDC wind farm connections (1)
Project name
Website hyperlink Route length Technology Suppliers Published cost Completion date Latest status
Dolwin 1 Dolwin1 Marine: 75 km Land: 90 km
800 MW 320 kV sym. monopole VSC
ABB 2015 Fully Commissioned
Dolwin 2 Dolwin2 Marine: 45 km Land: 90 km
916 MW VSC ABB 2016 Fully Commissioned
Dolwin 3 Dolwin3 Marine: 80 km Land: 80 km
900 MW 320 kV XLPE bipole
GE, Prysmian
2018 Fully Commissioned
Sylwin1 Sylwin1 Marine: 160 km Land: 45 km
864 MW 320 kV XLPE bipole VSC
Siemens, Prysmian
2015 Fully Commissioned
Borwin 1 Borwin 1 Marine: 125 km Land: 75 km
400 MW 150 kV sym. monopole VSC
ABB €400m 2010 Fully Commissioned
Borwin 2 Borwin 2 Marine: 125 km Land: 75 km
800 MW 300 kV sym. monopole
Siemens, Prysmian
2015 Fully Commissioned
Helwin 1 Helwin1 Marine: 85 km Land: 45 km
576 MW 250 kV sym. monopole VSC
Siemens, Prysmian
2015 Fully Commissioned
Helwin 2 Helwin2 Marine: 85 km Land: 45 km
690 MW 320 kV XLPE VSC
Siemens, Prysmian
2015 Fully Commissioned
Troll A Troll A Marine: 70 km 88 MW + 100MW 60 kV VSC
ABB 2005 + 2015 Fully Commissioned
Borwin 3 Borwin 3 Marine: 130 km Land: 30 km
900 MW Siemens, Prysmian
2019 Fully commissioned
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 20 www.warwickHVDC.co.uk
![Page 21: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/21.jpg)
Europe ex UK and Ireland
HVDC wind farm connections (1)
Project name
Website hyperlink
Route length
Technology Suppliers Published cost
Completion date
EU or National support?
Latest status
Modular Offshore Grid (MOG)
MOG Marine: >40 km
800MW/100MW 60kV
ABB Hellenic (Export)
Up to €400m
2020 Expected 2020 Array cables
installed
Dolwin 5+ 6 Dolwin 6 Marine: 45 km
Land: 45 km
900 MW Siemens, Nexans
2023 Under construction
update
Borwin 4 Borwin 4 Marine: 141 km
Land: 30 km
Paused
Borwin 5+6* Borwin 5+6 Development
OST-2-4 OST 2-4 2029
Sylwin 2 Sylwin 2 (no specific
site)
Marine: 160 km
Land: 45 km
Report
South Aegean 1 & 2
South Aegean
600-800 MW €1.8bn 2026 Consenting
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 21 www.warwickHVDC.co.uk
![Page 22: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/22.jpg)
Europe ex UK and Ireland
HVDC OHL
31/01/2020 22 www.warwickHVDC.co.uk
![Page 23: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/23.jpg)
Europe ex UK and Ireland
HVDC OHL connections (1)
Project name
Website hyperlink
Route length
Technology Suppliers Published cost
Completion date EU or National support?
Latest status
LitPol litpol 163km 500kV Back to Back
2015 Complete
France - Spain
France-Spain 64km 2GW 320kV XLPE
2x bipole VSC
Siemens Prysmia
n
2014 Complete
LitPol2* LitPol2 Concept
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 23 www.warwickHVDC.co.uk
![Page 24: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/24.jpg)
Global excluding Europe
HVDC Interconnectors, wind farms and OHL
31/01/2020 24 www.warwickHVDC.co.uk
![Page 25: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/25.jpg)
North America & Canada (1)
Project name
Website hyperlink
Project Type
Route length
Technology Suppliers Published cost
Completion date
Status
Quebec – New England (USA)
Quebec OHL OHL: 1500 km
2 GW (total) Multi-terminal
ABB 1986/1990/ 2016
Commissioned
Neptune (USA) Neptune Subsea 100 km 660 MW 500 kV
Siemens Prysmian
2007 Commissioned
Transbay (USA)
Transbay Subsea 85 km 400 MW 200 kV
Siemens Prysmian
2010 Commissioned
Cross sound (USA)
Cross_sound Subsea 39km 330 MW 150 kV VSC
ABB 2002 Commissioned
Hudson (USA) Hudson OHL Land (& River): 5 km
660 MW 2013 Commissioned
Vancouver Island (Canada)
Vancouver Island Subsea Marine: 33 km
OHL: 42 km
ABB 1968/1977 Partially Decommissioned
Maritime Link (Canada)
Maritime Link Subsea Marine: 170 km
500 MW 200 kV
ABB Nexans
2017 Commissioned
Labrador Island (Canada)
Labrador Island
Subsea Marine: 30 km
OHL: 1070 km
900 MW 350 kV
2017 Commissioned
Bi Pole I, II and III
Manitoba Hydro
OHL Bipole III >1388km
>2GW 500kV
Bi-pole III Siemens
1970’s, 1970’s and 2018
Commissioned
Atlantic Wind Connection (USA)
Atlantic Wind Connection
Wind 1 GW 320 kV XLPE
Bechtel Alstom (GE)
2019 Under Construction
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 25 www.warwickHVDC.co.uk
![Page 26: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/26.jpg)
North America (2)
Project name
Website hyperlink
Project Type Route length Technology Suppliers Published cost
Completion date
Status
Vermont Greenline (USA)
Vermont Greenline
Sub-sea Marine: 60 km Land: 25 km
400 MW $600m 2020 Bid process open for
future capacity
Maine Greenline (USA)
Maine Greenline
Sub-sea 90 km 1 - 1.2 GW 2020 TBC
Maine Power Express (USA)
Maine Power Express
Sub-sea Marine: 322 km Land: 168
km
1.04 GW 320 kV
TBC Consents being sought
Grain Belt Express (USA)
Grain Belt Express
OHL 1255 km 4 GW $2.3bn Missouri regulators approve
Transwest Express (USA)
Transwest Express
OHL 1000 km 3 GW 600 kV
TBC
Deepwater 1 & 2 (USA)
Deepwater Wind
Wind 1 GW Partnership announced
with National Grid USA
Atlantic Link (USA)
Atlantic Link 1 GW Current Status
Juan de Fuca (USA – Canada)
Juan de Fuca Subsea & Land
Marine: 550 MW ABB TBC
Mexico Mexico BAJA Contract
model
OHL 1500 km 1.4 GW 500 kV
Tender underway
Conference Oct 18
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 26 www.warwickHVDC.co.uk
![Page 27: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/27.jpg)
North America (3)
Project name
Website hyperlink
Project Type Route length
Technology Suppliers Published cost
Completion date
Status
West Point (USA)
Westpoint Sub-sea 100 km 1000 MW TBC TBC
Champlain Hudson (USA)
Champlain Hudson
Sub-sea 400 km 1000 MW 300-320 kV
bipole
$2.2bn 2021 Mar 18 – strong support expressed by authorities
New England (USA)
New England Sub-sea Marine: 140 km Land: 60
km
1000 MW 300-320 kV
bipole
TBC Feb 18 – officials
express strong support
Sunrise Wind (USA)
Sunrise Wind Wind 880 MW 2024 Current Status Cable Deal
Empire Wind (USA)
Empire Wind Wind 816 MW > $3 billion (estimate)
2024 Current Status
Vineyard Wind ***
Vineyard Wind
Wind 804MW Current Status Latest News
Skipjack Windfarm
Skipjack Windfarm
Wind 2022 Current Status
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 27 www.warwickHVDC.co.uk
![Page 28: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/28.jpg)
South America
Project name
Website hyperlink
Project Type Route length
Technology Suppliers Published cost
Completion date
Rio – Madeira (Brazil)
Rio-Madeira OHL 2375 km 7.1 GW 600 kV
ABB Alstom
2013/2014
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 28 www.warwickHVDC.co.uk
![Page 29: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/29.jpg)
Africa
Project name
Website hyperlink
Type Route length
Technology
Suppliers Published cost
Completion date
Status
Inga-Kolwezi (D.R. of Congo)
Inga-Kolwezi
OHL 1700 km 560 MW 500 kV
ABB 1982/2009 Commissioned
Cahora Bassa (South Africa – Mozambique)
OHL 1417 km 1.92 GW 533 kV
ZAMCO (~ Alstom, ABB,
Siemens)
1975/1998 Commissioned
Caprivi Link (Namibia)
950 km 300 MW 350 kV VSC
ABB, KEC, Jyoti
~ €306m 2009 Commissioned
Kenya – Ethiopia (Eastern Electric Highway)
1044 km 500 kV Siemens, KEC,
$1bn 2019 Under Construction
Eygpt – Saudi
Egypt Saudi OHL Marine: 16 km
Land: 1500 km
3 GW 500 kV
Tender
Western Power Corridor
Western Power
Corridor
OHL Concept
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 29 www.warwickHVDC.co.uk
![Page 30: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/30.jpg)
India
Project name
Website hyperlink
Project Type
Route length Technology Suppliers Published cost Completion date
Status
Sileru – Barsoor
OHL 196 km 400 MW 200 kV
1989 Decommissioned
Rihand – Delhi (India)
OHL 816 km 1.5 GW 500 kV
ABB, BHEL $250m 1991 Commissioned
Chandrapur – Padghe
OHL 752 km 1.5 GW 500 kV
ABB, BHEL 1999 Commissioned
Talcher -
Kolar (India)
OHL 1450 km 2.5 GW 500 kV
Siemens 2003 Commissioned
Ballia – Bhiwadi (India)
OHL 780 km 2.5 GW 500 kV
Siemens 2010 Commissioned
Mundra -Haryana (India)
Mundra - Haryana OHL 989 km 2.5 GW 500 kV
Siemens 2012 Commissioned
North-East Agra (India)
OHL 1780 km 8 GW 800 kV
ABB, BHEL 2015 Commissioned
Champa – Kurukshetra
OHL 1287 km Phase I: 3 GW Phase II: 6
GW 800 kV
GE 2017 Phase I Commissioned
Raigarh – Pulagur
1830 km 6 GW 800 kV ABB, BHEL $840m 2019 Under construction
Pulagur – Thrichur
154 km 2 GW 320 kV ABB, BHEL 2020 Under construction
India – Sri Lanka
India Sri Lanka
OHL & Subsea
Land: 235 km Subsea: 50 km
1GW Feasibility complete
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
30 31/01/2020 www.warwickHVDC.co.uk
![Page 31: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/31.jpg)
China (1)
Project name
Website hyperlink Type Route length Technology Suppliers Published cost Completion date
Yunnan – Guangdong
Yunnan - Guangdong OHL 1418 km 5 GW 800 kV
Siemens 2009
Xiangjiaba – Shanghai
Xiangjiaba – Shanghai
OHL 1980 km 6.4 GW 800kV
Siemens, XD Xi’an Power Rectifier
Works, ABB
2010
Jinping – Sunan Jinping – Sunan OHL 2090 km 7.2 GW 800 kV
ABB $3.5bn 2012
Hami - Zhengzhou
OHL 2192 km 6.4 GW 800 kV
China XD Electric Company
23.4bn CNY (approx. €2.9bn)
2014
Xiluodo – West Zhejiang
OHL 1680 8 GW 800 kV
2014
Irkutsk - Bejing (Russia – China)
OHL 6.4 GW 800 kV
2015
Xiluodo – Hanzhou
OHL 6.4 GW 800 kV
2015
Humeng - Shandong
OHL 6.4 GW 800 kV
2015
Goupitan – Guangdong
OHL 3 GW 2016
Jinsha River 1 OHL 6.4 GW 80 kV
2016
Zhungdong - Chengdu
OHL 11 GW 1100 kV
2016
Jinsha River 2 OHL 6.4 GW 800 kV
2018
Humeng – Liaoning
OHL 6.4 GW 800 kV
2018
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 31 www.warwickHVDC.co.uk
![Page 32: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/32.jpg)
China (2)
Project name
Website hyperlink
Type Route length
Technology Suppliers Published cost
Completion date
China - Hainan
Hainan Subsea
Nanao 3 terminal (China)
Subsea 32km VSC 3 terminal 200MW 160kV
2013
Zhoushan 5 terminal (China)
Subsea 141km VSC 5 terminal 400MW 200kV
2014
Jinsha River 2 OHL 6.4GW 800kV
2019
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 32 www.warwickHVDC.co.uk
![Page 33: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/33.jpg)
East and South-East Asia (1)
Project name
Website hyperlink
Project Type Route length Technology Suppliers Published cost
Completion date
Status
Hokkaido – Honshu (Japan)
Hokkaido-Honshu
Subsea Marine: 42 km 300 MW 250 kV
JP Power (Japan) 1979/1980 Commissioned
Kii Channel (Japan)
KII Channel Subsea Marine: 50 km Land: 50 km
1.4 GW 250 kV
Hitatchi 2000 Commissioned
Haenam – Jeju (South Korea)
Haenam Subsea Marine: 96 km Land: 5 km
300 MW 180 kV
Alstom Nexans
1998 Commissioned
Jindo – Jeju (South Korea)
Jindo-Jeju Subsea 105 km 400 MW 250 kV
Alstom LS Cable and System
$415m 2014 Commissioned
Khanom – Koh Samui 1 - 3 (Thailand)
Khanom Subsea 24 km 100 MW 33 kV
Nexans 1996/2007 Commissioned
Leyte – Luzon (Philippines)
Leyte Luzon Subsea Marine: 21 km Land: 430 km
440 MW 350 kV
ABB Marubeni Corp of Japan
Upgrade – NR Eelctric
1996 Upgraded 2013/14
Commissioned
Buk-Dangjin – Godeok (South Korea)
Underground with short
subsea
Marine: 7 km Land: 26 km
1.5 GW 500 kV GE/KAPES Under Construction
Seoul (South Korea)
Seoul OHL 4 GW 500 kV
GE KAPES
$320m 2021
Asia Super Grid (China – South Korea)
Asia Super Grid
Sub-sea TBD TBC
Visayas Mindanao (Philippines)
Link Sub-sea PhP 51.7bn (approx. $1.03bn)
2020 NKT awarded €100m contract
Project News
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
33 31/01/2020 www.warwickHVDC.co.uk
![Page 34: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/34.jpg)
East and South-East Asia (2)
Project name
Website hyperlink
Project Type
Route length Technology Suppliers Published cost
Completion date
Status
Malaysia – Singapore
Malaysia Singapore
TBC
Sarawak / SARPEN (Malaysia)
Sarawak Sub-sea Marine: 676 km Land: 1000 km
Concept
Java – Sumatra (Malaysia)
Sumatra Java
On hold
Philippines – Saba
TBC
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
34 31/01/2020 www.warwickHVDC.co.uk
![Page 35: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/35.jpg)
Australasia
Project name
Website hyperlink
Type Route length
Technology Suppliers Published cost
Completion date Status
Directlink (Australia)
59 km 180 MW 80 kV VSC
ABB 2000 Commissioned
Murraylink (Australia)
176 km 220 MW 150 kV VSC
2002 Commissioned
Basslink (Australia)
Basslink Subsea 290 km 500 MW 400 kV LCC
Siemens, Prysmian
2006 Commissioned
Inter-Island (New Zealand)
Subsea 617 km 1.2 GW 350 kV bipole
Siemens, ABB
1965/1992/2013 Commissioned
Australia-Singapore Power Link project
Sun Cable
Sub-sea 3750km 2027 Development Project Investor
Basslink 2 + similar schemes*
Concept
Marinus Link Tasmania – Victoria ***
Marinus Link
Sub-sea 1500 MW 2028 Concept
Gippsland coast - Star of the South
Star of the South
Sub-sea Feasibility
Whilst this is only a guide please contact us if you would like to update or add to
this information.
Key
Built In Construction In Development
31/01/2020 35 www.warwickHVDC.co.uk
![Page 36: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/36.jpg)
HVDC Cable manufacturers Please click on the company logo to link to their web site
Please contact us if you would like to update or add to this information.
31/01/2020 36 www.warwickHVDC.co.uk
![Page 37: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/37.jpg)
Please contact us if you would like to update or add to this information.
HVDC Converter manufacturers Please click on the company logo to link to their web site
31/01/2020 37 www.warwickHVDC.co.uk
![Page 38: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/38.jpg)
Please contact us if you would like to update or add to this information.
Marine Installers Please click on the company logo to link to their web site
31/01/2020 38 www.warwickHVDC.co.uk
![Page 39: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/39.jpg)
Top European construction companies 2018
Click image to see full list
Please contact us if you would like to update or add to this information.
Top UK civil contractors 2018
Click image to see full list
Top 10 biggest construction companies worldwide 2018
Click image to see full list
Civil Contractors
31/01/2020 39 www.warwickHVDC.co.uk
![Page 40: If you would like to update or add to any of the ...€¦ · NEXANS + Prysmian 1986 Complete BritNed BritNed Marine: 250 km Land: 10 km 1 GW 450 kV MI bipole LCC Siemens / BAM, ABB](https://reader036.vdocuments.us/reader036/viewer/2022081408/605ffeb245e7b71dcf1a987b/html5/thumbnails/40.jpg)
31/01/2020 www.warwickHVDC.co.uk 40
Interested in any of these projects?
For expert advice, analysis, training, or consultancy, on a long or short-
term basis, please contact us at:
www.warwickhvdc.co.uk
Monthly updates and news will be posted but we also offer retained
support packages from minimum 15 hours per year to keep you fully up to speed with information, opinion and advice in this
market.