![Page 1: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/1.jpg)
·egis In Joint Venture With \ ID()
ADB-Financed Flood Damage Emergency Reconstruction Project,National and Provincial Roads, Ministry of Public Works and TransportCS1- Detailed Design and Implementation Supervision (0015) Consultant
Phnom Penh, 5 February 2016Our Ref: FDERP-AFITU16/1443
Mr. Nay ChamnangDirector of Road Infrastructure DepartmentProject Manager .Flood Damage Emergency Reconstruction ProjectAdditional FinancingMinistry of Public Works and Transport
Subject: Submission of Quarterly Progress Report No.6 October-December 2015(
Dear Mr. Chamnang,
Please find enclosed the 3 copies Submission of Quarterly Progress Report No.6 forOctober-December 2015, for your information and records.
Please forward relevant copies to ADS and AusAID as indicated for their information.
-Cc: PCMU, ADS, MEF
Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom Penh CAMBODIA
Head Office 15 Avenue du Centre - CS 20538 Guyancourt 78286 Saint-Quentin-en-Yvelines Cedex - FRANCE; Tel.: Fax: (33-1) 39 41 4000E-Mail: www.egis-international.fr
![Page 2: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/2.jpg)
EGIS International
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 1
Quarterly Progress Report No.6 January 2016
Royal Government of
Cambodia
Ministry of Public Works and Transport
FLOOD DAMAGE EMERGENCY RECONSTRUCTION PROJECT (FDERP)
[ADB LOAN No. 2852-CAM (SF) and GRANT No. 0285-CAM (EF)]
AND
FLOOD DAMAGE EMERGENCY RECONSTRUCTION PROJECT-ADDITIONAL FIANCING (FDERP-AF)
[ADB LOAN No. 3125-CAM (SF) and GRANT No. 0285-CAM (EF)]
Construction Supervision
Quarterly Progress Report No. 6
October - December 2015 (Q4/2015)
PART A: FDERP AND PART B: FDERP-AF
Version A
In Association with
VIDO Engineering Consultant Co. Ltd.
![Page 3: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/3.jpg)
Egis International Document Quality Information
Project Name: Flood Damage Emergency Reconstruction 1-additional Financing
Project Grant No.0285-CAM (EF) and 13125 -CAM (SF)
Construction Supervision
Report Name: Quarterly Progress Report No.6 (Q4/2015); October - December 2015
PREPARATION, REVIEW AND AUTHORISATION
Prepared by: Carl E SerentsenlY A Samol
Position: Project Manager (CSC)
Reviewed by: Nay Chamnang
Position: Project Manager, PIU
Approved by: Kern Sorey
Position: Project Director, PIU
ISSUE REGISTER DISTRIBUTION LIST
Ministry of Public. Works and Transport
Asian Development BankAus AID, Phnom Penh
Date Issued No. of Copies
2
21
REVISION, PREPARATION, REVIEW ISSUE
Issued toRevision Date Prepared by Reviewed by Distribution
List by:
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF)Quarterly Progress Report No.6
Page 12January 2016
![Page 4: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/4.jpg)
Egis International Document Quality Information
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 3
Quarterly Progress Report No.6 January 2016
Document quality information
General information
Author(s) Carl E Berentsen/Ya Samol
Project name FLOOD DAMAGE EMERGENCY RECONSTRUCTION PROJECT-ADDITIONAL FINANCING
Document name Quarterly Progress Report No. 6
Date January 2016
Reference
Addressee(s)
Sent to:
Name Organization Sent on (date):
H.E. Kem Borey Ministry of Public Works and Transport January 2016
Mr. Nay Chamnang Ministry of Public Works and Transport
Copy to:
Name Organization Sent on (date):
Mr. Nicolas Morice Egis International January 2016
History of modifications
Version Date Written by Approved & signed by:
![Page 5: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/5.jpg)
Egis International Parts A & B
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 4
Quarterly Progress Report No.6 January 2016
Table of Contents Preamble ................................................................................................................................... 5
Part A: FDERP .......................................................................................................................... 7
Executive Summary ................................................................................................................. 8
Summary of FDERP timeframe and costs ........................................................................... 10
I. MAIN ACTIVITIES DURING THE QUARTER(Oct - Dec 2015) ......................................... 13
II. PROPOSED KEY ACTIVIIES FOR NEXT QUARTER (Jan- Mar 2016) ........................... 13
PHOTO GALLERY FOR FDERP ..................................................................................................... 13
Part B: FDERP-AF .................................................................................................................. 14
Executive Summary ............................................................................................................... 15
i. General ....................................................................................................................................... 15
ii. Loan Progress .......................................................................................................................... 15
iii. Overall Project Progress ........................................................................................................ 15
iv. Financial Progress .................................................................................................................. 17
v. Distribution of Loan Funds ................................................................................................... 20
vi. Construction Progress ........................................................................................................... 21
Summary of FDERP-AF timeframe and costs .................................................................... 27
Comparison between Original Scope and Current Scope of works ................................ 28
Summary of FDERP-AF Issues requiring Actions ............................................................. 29
I. ACTUAL ACTIVITIES DURING THE QUARTER(July - Sept 2015) ................................ 30
II. PLANNED ACTIVITIES DURING NEXT QUARTER(Oct-Dec 2015) ................................ 32
PHOTO GALERY FOR FDERP-AF................................................................................................. 33
![Page 6: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/6.jpg)
Egis International Parts A & B
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 5
Quarterly Progress Report No.6 January 2016
FDERP
FDERP-AF
Provincial Center
CW:អនុគម្រោង
Battambang
Siem Reap
K.Thom
K.Cham
Prey Veng
B.Meanchy
Phnom Penh
CW3, CW6a, CW6b, CW6c& CW7 CW9b& CW9a
CW1, CW2, CW4 & CW5
CW11& CW12 (CW11/12)
CW15 & CW16
CW10a, CW10b & CW10c CW14
CW13
CW8
Preamble Prior to the ADB Review Mission from March 25 to April 7, 2015 progress of activities of FDERP
and FDERP-AF under MPWT were reported on a monthly basis.
In accordance with ADB's April 2015's MOU/Section H (Project Reporting); this was changed to
quarterly progress reports from April 1 onwards in order to streamline the reporting.
This report is prepared as a summary of activities, both in planning, design, construction and
financial issues during the period of October through December 2015.
To simplify reading the report is split in two parts: Part A: projects under FDERP (No. Loan
2852) where the loan is already closed and Part B: FDERP -AF (Loan No. 3125).
The location of the projects is shown in the following maps.
![Page 7: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/7.jpg)
Egis International Parts A & B
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 6
Quarterly Progress Report No.6 January 2016
![Page 8: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/8.jpg)
Egis International Part A: FDERP
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 7
Quarterly Progress Report No.6 January 2016
FLOOD DAMAGE EMERGENCY RECONSTRUCTION PROJECT (FDERP)
[ADB LOAN No. 2852-CAM (SF) and GRANT No. 0285-CAM (EF)]
Quarterly Progress Reports
October – December 2015
Part A: FDERP
January 2016
![Page 9: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/9.jpg)
Egis International Part A: FDERP
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 8
Quarterly Progress Report No.6 January 2016
Executive Summary
1. A reconnaissance mission was conducted by ADB to Cambodia in December 2011,
which was initiated after severe typhoons, devastated 18 of the country’s 24 Provinces in
September and October 2011.The subsequent MOU which was issued by ADB in
February 2012, initiated the “Flood Damage Emergency Reconstruction Project”
(FDERP). FDERP was approved on 27 March 2012. The loan became effective on 14 May 2012, and was scheduled for closure on 30 September 2015;
2. FDERP costs USD 67.18 Mill, of which Asian Development Bank (ADB) financed USD 55Mill, the Government of Australia provided a grant of USD 5.25 Mill and the Royal Government of Cambodia contribution was USD 6.93 Mill.
3. FDERP was guided by the Project Administration Manual (PAM) dated March 2012, updated January 2013. The PAM requires the FDERP Implementing Agencies (IAs) to submit monthly progress reports to the Executing Agency (EA)/ Project Coordination and Monitoring Unit (PCMU) to submit Quarterly Progress Reports to ADB;
4. Final Joint review Mission for FDERP was conducted from 29 June to 16 July 2015. 5. This Quarterly Progress Report cover the period from October through December 2015. 6. Loan Closing was 30 September 2015 as planned. Three subprojects (CW7, CW6b and
CW8) are under Defect Liability Period after this loan closing date.
![Page 10: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/10.jpg)
Egis International Part A: FDERP
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 9
Quarterly Progress Report No.6 January 2016
Table 1A: Civil work contracts under Defect Liability Period
No. Contractor Province (Road)
Work Description Contract
Amount($) Project Status
CW 6b (Stage 3)
Kampong Cham
PR270
Reconstruction of 1) CW6b-1:Svay Tahen
Bridge, 9m x 51m 2) CW6b-2: Phum Thmey
Bridge, 9m x 80m 3) CW6b-3: Rokar Koy
Bridge 9 x 20m
2,927,997.55 (Original)
3,209,323.61 (Amended)
Contract awarded on 08-Jan-13 Start Date: 29-Apr-13 Completion date: 15-June-15
End of defect liability: 15-June-16 (under Defect Liability Period) Final Cost: $3,143,713.55
CW 8 (Stage 3)
Battambang/
Banteay Meanche
y
PR159
Reconstruction DBST 34.6km (8.0m wide = 6.0m DBST + 2 x1.0m shoulder)
8,795,645.58 (Original)
9,852,155.89 (Amended)
Contract Signed on 30 Sept 2013 Start Date: 25 October 2013 Completion Date: 31 July 2015 End of defect liability: 31 July 2016 (under Defect Liability Period) Final Cost: $9,852,155.89
CW 7 (Stage 3)
Kampong Cham
PR270
Reconstruction of DBST 8.1 Km (8.0m wide = 6.0m DBST + 2 x1.0m shoulder)
1,431,562.20
Contract Signed on 20-Dec-13 Start Date: 23-Dec-13 Completion date: 6-Jan-15 End of defect liability: 6-Jan-16 (under Defect Liability Period, pending Contract’s repair of Defect) Final Cost: $1,215,598.92
![Page 11: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/11.jpg)
Egis International Part A: FDERP
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 10
Quarterly Progress Report No.6 January 2016
Summary of FDERP timeframe and costs
Table 2A:
No. Project Name
Date of Award
Start Date Contract Period, days
Intended date
Time Extension Actual Completion Amount ($)
Period, days
Until Period, days
Until Original Amended Final
1 CW1 22-May-12 22-May-12 245 22-Jan-13 496 30-Sep-13 486 20-Sep-13 3,383,059.32 3,711,743.27 3,321,647.01
2 CW2 22-May-12 22-May-12 300 18-Mar-13 - - 300 18-Mar-13 1,992,174.25 - 1,797,574.63
3 CW3 22-May-12 22-May-12 300 18-Mar-13 - - 300 18-Mar-13 1,328,276.54 - 1,145,847.27
4 CW4 6-Dec-12 19-Dec-12 300 15-Oct-13 - - 275 20-Sep-13 806,898.27 - 697,445.59
5 CW5 8-Jan-13 11-Jan-13 300 11-Nov-13 338 15-Dec-13 338 15-Dec-13 1,325,663.24 - 1,077,305.26
6 CW6a 6-Dec-12 6-Dec-12 365 19-Dec-13 492 12-Apr-14 492 12-Apr-14 1,268,752.17 - 1,072,124.31
7 CW6b 18-Apr-13 29-Apr-13 300 23-Feb-14 777 15-Jun-15 777 15-Jun-15 2,927,997.55 3,209,323.61 3,143,713.55
8 CW6c 11-Apr-13 11-Apr-13 300 23-Feb-13 399 15-May-14 399 15-May-14 1,522,735.70 - 1,402,110.50
9 CW8 30-Sep-13 25-Oct-13 600 17-Jun-15 644 31-Jul-15 644 31-Jul-15 8,795,645.58 9,852,155.89 9,852,155.89
10 CW7 20-Dec-13 23-Dec-13 300 19-Oct-14 379 6-Jan-15 379 6-Jan-15 1,431,562.20 - 1,215,598.92
Total = 24,782,764.82 26,449,385.14 24,725,522.93
![Page 12: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/12.jpg)
Egis International Part A: FDERP
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 11
Quarterly Progress Report No.6 January 2016
Comparison between Original Scope and Current Scope of works (Table 3A)
FDERP: Scope of Work Per PAM 2012 No. Contract No. PSC Bridge RC Bridge Box Culvert Pipe Culvert DBST Laterite Comments
1 CW1 63m (1) - - - 2.0 km - () : Numbers of structures
2 CW2 96m (1) - - - - -
3 CW3 45m (1) - - - - -
4 CW4 48m (1) - - - - -
5 CW5 80m (2) - - - - -
6 CW6 - - - - 8.5km -
7 CW7 - 96m (5) - - - 32.5km
8 CW8 - - - - 34.6km -
Total 332m (6) 96m (5) - - 45.1km 32.5km
FDERP: Current Scope of Work (30/9/15) No. Contract No. PSC Bridge RC Bridge No. of Box
Culverts No. of Pipe Culverts
DBST Laterite Comments
1 CW1 68.1m (1) - 2 4 2.7km - () : Numbers of structures
2 CW2 96m (1) - - - - - culverts are new
3 CW3 45m (1) - - - - -
4 CW4 48m (1) - - - - -
5 CW5 84m (2) - - - - -
6 CW6a - - - 29 8.1km -
7 CW6b 151m (3) - - - - - Added Scope after Inception Mission in July 2012 8 CW6c - 60m (3) 4 - - -
9 CW7 - - - 16 8.1 km -
10 CW8 - 36m (1) 15 48 34.6km -
Total 491.5m (9) 96m (4) 21 97 53.5 km -
![Page 13: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/13.jpg)
Egis International Part A: FDERP
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 12
Quarterly Progress Report No.6 January 2016
Figure 1A : Sketch of FDERP and FDERP-AF (*) along NR70 and PR270 in Kampong Cham Province
(58 km)
44.3km
24.3km
Peam Chikong
Roka kong
NR6
NR7
CW9b (*)
1 bridge (40m)
CW6c
(7 Structures)
CW6b
(3 Bridges)
Kampong Cham Town
CW6a
(DBST
8.1km)
CW7
(DBST 8.1 km)
CW9a (*)
(DBST 16.19km)
Existing NR70
(DBST 13.53km)
Existing new Bridge
(Prek Koy Bridge)
NR70
PR
270
4.0km 16.0km
CW3
(1 Bridge)
Prey To Toeung
![Page 14: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/14.jpg)
Egis International Part A: FDERP
Grant No.:0285-CAM (EF) and Loan No.: 2852-CAM (SF) P a g e | 13
Quarterly Progress Report No.6 January 2016
I. MAIN ACTIVITIES DURING THE QUARTER(Oct - Dec 2015)
Conduct supervision to project under defect liability period (CW7, CW6b and CW8)
Issued PCR (Project Completion Report).
Prepare a “Lessons Learned” Report to MPWT
Prepare a “Compressed Management and Inspection Report “ outline for MPWT reference
II. PROPOSED KEY ACTIVIIES FOR NEXT QUARTER (Jan- Mar 2016)
Site Inspections during Defect Liability Period of civil works CW6b and CW8.
Have Contractor (Tan Kim Eng) for CW7 repaired the defects identified by the Engineer
during inspection prior to end of defect liability period and issue Defect Liability Certificate if
the defects have been repaired and acceptable to the Engineer.
PHOTO GALLERY FOR FDERP
CW6B:
Existing Bridge CW6b-1 (2013) Bridge CW6b-1 under DLP (Sep 2015)
CW8:
Existing road at PK4+500 (Nov 2013) Guide post installing at PK 18+000 (June 2015)
![Page 15: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/15.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 14
Quarterly Progress Report No.6 January 2016
FLOOD DAMAGE EMERGENCY RECONSTRUCTION PROJECT-ADDITIONAL FINANCING
(FDERP-AF)
[ADB LOAN No. 3125-CAM (SF) and GRANT No. 0285-CAM (EF)]
Quarterly Progress Report
October – December 2015
Part B: FDERP-AF
January 2016
![Page 16: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/16.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 15
Quarterly Progress Report No.6 January 2016
Executive Summary
i. General 1. FDERP-AF was approved on 11 April 2014. Loan and Grant Agreement was signed on
23 April 2014 and became effective on 30 May 2014 with a loan closing date of 30 September 2017.
2. FDERP-AF is financed through ADF loan of SDR48,545,000 Mill (equivalent to 67.6 Million at time of loan signing in April 2014) and a grant from the Government of Australia of USD A$7.6 Mill (equivalent to $6.68Mill). The Royal Government of Cambodia contributes USD 9.0 Mill;
3. MPWT receives a loan of SDR14.563 (equivalent to $22.5 Mill at the time of loan signing) and a grant of $1.5 Mill to rehabilitate/improve flood damaged national and provincial roads and bridges in 5 provinces: Battambang, Banteay Meanchey, Siem Reap, Kampong Thom, Battambang and Kampong Cham.
4. Last Joint review Mission was conducted from 21 September to 7 October 2015. 5. Due to lack of progress of CWs 16, 9a, 10b and 10c, Employer issued warning letters
per Clause 50.2 of Contract Documents after Consultant had issued several warning letters.
6. This Quarterly Progress Report covers the period from October to December 2015.
ii. Loan Progress
Last ADB and Australian Aid Joint Review Mission
7. A review mission for the project was undertaken from 21 March to 2 October 2015 to review implementation progress of the project, identify key implementation issue and propose action to improve implementation. The mission undertook field visits to subproject areas from 21 to 25 September 2015. A kick-off and wrap up meetings is proposed on 2 October 2015. It was reported that Project implementation as of end of Q3 was well on track.
iii. Overall Project Progress
9. Overall Progress is slightly behind schedule. The actual progress for last quarter was on
track due to progress made in CW13, however the overall progress at the end of this quarter is estimated to be 60.5% compared to a forecasted 66.7% (Figure 1B). This is because stagnant progress for CW16, 9a, 10b and CW10c and CW14 was just awarded. Under Stage 2 civil works, two civil work contracts were completed (CW9b and CW11/12) while CW10a was expected to be completed by October but is extended to 10 June 2016 due to still outstanding issues observed at completion (re-appearance of cracks#2 and 3). Under Stage 3, CW13 was completed on 9 December 2015 which is within the contract period. Contractors CW16, CW10b, CW10c and CW9a cannot catch up due to lack of equipment and manpower.
10. Several warning letters have been issued by the Engineer in an attempt to improve the situation. However, the Contractors had not taken serious actions. Therefore, the Employer issued first warning letters per Clause 50.2 of the Contract Documents on 9 December 2015 to CW10b and CW10c, and on 11 December 2015 to CW16 and CW9a,
![Page 17: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/17.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 16
Quarterly Progress Report No.6 January 2016
giving Contractors 14 days to act. Follow-up site visits were held on 18, 25 and 26 to the projects concerned. Still no significant progress was observed. Therefore the Employer issued last warning letters to CW10b, 10c and CW9a on 30 and 31 December 2015 giving Contractors 21 days to act to catch up.
11. Bid opening for CW14 was held on 18 September 2015 and contract signing is on 11 December 2015 after receipt of ADB’s NOL dated 30 November 2015.
12. Physical progress of civil works is slipping behind schedule, is estimated to be 46% vs a target of 52% (Figure 2B). This is due to late progress for stage 3 contracts.
Figure 1B: FDERP-AF - Overall Progress as of 28 December 2015
Figure 2B: Overall Progress of Civil Work as of 28 Dec 2015
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
FDERP-AF Overall Work Progress in %: MPWT (Dec 15)
Actual Planned
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
FDERP-AF Civil Work Progress in %: MPWT (Dec 15)
Actual Planned
![Page 18: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/18.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 17
Quarterly Progress Report No.6 January 2016
iv. Financial Progress
13. Cumulative contract awarded is shown in Table 1B. One contract award, CW14, is made
during this period. Two contract amendments for CW10a and CW13 are issued. No variation on consultant service is issued during this period.
14. Comparison of actual contract award vs projection per PAM 2014 is shown in Figure 3B. Note that the latter is the cost shown in the PAM. All civil work contracts were awarded in this Quarter. It is observed that the total contract award up to this quarter is $23.37 Mill compared to a projection of $25.9 Mill. This difference is due to the late procurement for CW14, and the contractually awarded contract amounts are less than the estimated contract amount.
15. The variation of budget allocation against time is also plotted in Figure 3B. It is observed that the allocation budget for MPWT is reduced due fluctuation of SDR against US Dollars. It appears that there is no sufficient of fund to implement CW14 (with estimate cost of $3.750 Mill in Procurement plan dated 7 August 2015) unless more re-allocation is made. Table 1B: Cumulative Contract Awards by MPWT
Cat. code
Description
Cumulative Contract Award
As of 30-Sep-2015 (up to Q3/2015), USD
Cumulative Contract Award As of 30-Dec-2015
(up to Q4/2015), USD
Actual Contract Award Value
during Q4/2015, USD
01A Civil work 20,517,657.88 23,376,761.11 2,859,103.23
03A Consultants
Services 2,500,000.00 2,500,000.00 -
Cumulative Disbursement by MPWT
Cat. code
Description
Cumulative Disbursement
As of 30-Sep-2015 (Up to Q3/2015), USD
Cumulative Disbursement
As of 30-Dec-2015 (During Q4/2015), USD
Actual Disbursement
Value in Q4/2015, USD
01A Civil work 7,334,259.68 8,824,159.13 1,489,899.45
01A Equipment 10,800.00 10800.00 -
03A Consult. Services 1,118,409.66 1,298,659.11 180,249.45
04A Management. Costs 85,831.00 1,77,199.20 91,368.2
Total 8,549,300.34 10,310,817.44 1,761,715.1
![Page 19: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/19.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 18
Quarterly Progress Report No.6 January 2016
Figure 3B: Actual and planned contract awards, and budget of MPWT as of Q4/2015
16. Actual cumulative disbursement of civil works is estimated to $8.12 Mill compared to actual cumulative contract award of $23.3 Mill as of 30 November 2015 (Figure 4B). The Disbursement is far behind the contract award since the contractors under FDERP-AF are slow in issuing their IPCs due to slow physical progress of CW15, CW16, CW10b, CW10c and CW9a. The consultant is pushing for this to improve.
17. A comparison between a planned disbursement and actual disbursement is shown in Figure 5B. A planned disbursement is computed as proportion to cumulative disbursement in Section IV. Costs and Financing (“F. Contract Disbursement S-Curve of PAM 2014). Based on this calculation, it appears that actual disbursement is behind the target.
Figure 4B: Actual Contract Award vs Actual Disbursement as of Q4/2015
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Mill
ion
s
Cumulative CWs Contract Awards
Actual
Planned, PAM
Budget
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Mill
ion
s
Actual contract award vs actual disbursement
Actual Disbursement
Actual Contract award
![Page 20: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/20.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 19
Quarterly Progress Report No.6 January 2016
Figure 5B: Actual vs Planned Disbursement as of Q4/2015
0.00
5.00
10.00
15.00
20.00
25.00
30.00
Mill
ion
s
Planned vs actual disbursement
Actual Disbursement
Planned disbursement
![Page 21: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/21.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 20
Quarterly Progress Report No.6 January 2016
v. Distribution of Loan Funds
Table 2B:
OUTPUT ADB AusAID Total
Allocation Revised
Contracts
Current Savings/Shortf
alls
Future Variations/expense
Predicted Shortfall/Savi
ngs Remark
i) Civil Work Contractor
22,500,000 1,500,000 24,000,000
CW9b Seaboard 938,000.00 231,403.07 savings
CW10a Ung Simsia 2,126,833.70 -84,343 shortfall
CW11/12 Seaboard 2,799,980.19 231,533.45 savings
CW13 Heng Sambath 1,792,390.00 using contingencies
CW15 Visvakam 2,334,526.33
CW16 Banteay Srei 2,233,310.02
CW9a Banteay Srei 2,749,789.91 CW10b Visvakam 2,497,238.36
CW10c Visvakam 3,045,589.37
CW14 Swee-Cam (JV) 2,859,103.23
Total Civil Works 22,500,000 1,500,000 24,000,000
ii)Equipment 12,000
iii) Consultancy Service 2,500,000 2,500,000.00 -70,668.08 VO#6, shortfall
iv) Incremental Management Costs 477,200
Total 25,489,200 1,500,000 24,000,000
![Page 22: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/22.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 21
Quarterly Progress Report No.6 January 2016
vi. Construction Progress
Stage 2 Subprojects:
Three Direct Contracts were awarded in Q3/2014 and two of which were completed.
CW10a is extended to 10 June 2016 due to some added works of mainly repair of cracks.
CW9b:
Emergency Reconstruction of Prek Chiek Bridge on provincial road (PR) 270 in Kampong Cham
Province (contract amount: $938,000). Completion certificate was issued on 15 June 2015. A
final cost of the project is $706,595.93. A saving of $231,404.07 is recorded. Defect Liability
Period is until 15 June 2016.
CW10a:
Emergency Reconstruction of Provincial Road PR156D in Banteay Meanchey (contract amount: $2,126,833.7). The works per original scope was completed. However, the project has experienced delays mainly due to added works such as repairs of deep cracks in 4 locations along the riverbank and added side drains at the beginning Section of the road. The cracks were repaired based on special designs by the consultant’s geotechnical specialist. Contract variation orders are compiled into proposed CA#1 which were obtained in ADB’s NOL on 14 December 2015 and the CA#1 was signed on 23 December 2015. In December 2015, Cracks #2 and #3 re-appeared followed by settlement. Consultant and Contractor are working together to have this issue resolved.
CW11/12:
CW11&12: Emergency Reconstruction of 8.15 km of PR 264E and 7.375 km of PR 264D in
Kampong Thom (contract amount: $2,799,980.19). Contract amendment #1 for using part of
Contingencies was approved and signed on 18 August 2015. The Completion Certificate was
issued on 3 September 2015 and the project is now under Defect Liability Period until 3
September 2016.
Stage 3 Subprojects
CW13:
Emergency Reconstruction of 18.75 km of Laterite Road on PR 1570 in Battambang Province
(Contract: $1,792,390). The project has been substantially completed per scope under CA#1.
However, it was observed during ADB’s Mission that the end of part of the road, which is low
due to tempering with existing access road, was inundated and caused some damage to laterite
surface. Therefore, concrete slab acting like drift where water can overflow. The concrete road
surface was proposed and treated as additional work (variation). The construction of concrete
slab has been done. CA#2 was prepared using remaining amount in contingencies and was
submitted for PRC for review and approval on 7 November 2015 and Contract Amendment#2
(CA#2) was signed on 25 November 2015. Completion Certificate is issued on 9 December
2015. The Project now is now under Defect Liability Period.
CW15:
CW15: Emergency Reconstruction of 6 km Concrete Pavement on National Road (NR) 63 in
Siem Reap Province (Contract amount: $2,334,526.33). This sub-project had experienced slight
delays at the start-up and slow progress. During ADB’s Mission in October, the donor expressed
their concern on accidents which may result from different levels between concrete slab and
shoulder, and the adding berms along the concrete slab adjacent to river. These concerns have
![Page 23: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/23.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 22
Quarterly Progress Report No.6 January 2016
been addressed to minimize the accident as Contractor is raising the levels of shoulder and is
making proposal for construction berms.
The Contract is intended to be completed on 30 December 2015. But, the contractor cannot
completed the work per above date. Contractor is applying for time extension for review and
approval and time extension is endorsed and approved until 21 March 2016 by the Employer.
CW16:
Emergency Reconstruction of 11.20 km of Double Bituminous Surface Treatment (DBST) Road
on Provincial Road 265F in Siem Reap Province (contract amount: $2,233,310.02). CW16
experienced slight delays at the start-up due to slow mobilization of contractor, lack of
manpower and equipment. The Project is still slow, physical progress of 27% after 10 months
after start date. Contractor period is 14 months. Several meetings were arranged between
Contractor, Consultant and Engineer to improve work progress.
Consultant issued several warning letters, then after coordination meeting with PCMU, the
Employer issued first warning letter per Clause 50.2 of Contract Document on 11 December
2015 to the contractor (Banteay Srei) to take actions in order to rectify situation, if not default will
be resulted. After 14 days, follow up site visit was conducted and it was observed that some
progress was made. Still more effort needs to be done by Contractor in order to complete the
works on time and to avoid penalty.
Extraordinary meeting with all stakeholders (including Senor Officers from ADB, MEF, PCMU,
MPWT, Consultant, and Contractor) is planned on 13 January and joint follow up site visit is
planned on 21 January 2016.
Four ruin locations were discovered along the road, but impact of one ruin at PK10+200 is
notable according to joint site visit by APSARA and DPWT of Siem Reap on 2nd December
2015. It was decided to leave a section of road 200m undisturbed from PK10+100 to
PK10+300.
CW9a:
CW9a: Emergency Reconstruction of 16.19 km (PK.6+636 – PK.22+826) DBST Road on NR
No. 70 in Kampong Cham Province (Contract amount: $2,749,789.91). This subproject was
awarded on 24 June 2015 to Banteay Srei with conditional NOL from ADB on personnel and
equipment. After 6 months, only 25% of embankment was completed. Within remaining 12
months of contract period, the Contractor cannot even complete the embankment if with such
speed of progress.
Consultant issued several warning letters to the Contractor before Employer issued first warning
letter on 11 December 2015 per Clause 50.2 of the Contract Document giving 14 days for
Contractor to act. Follow up site visit was conducted on 26 December 2015, it was found that no
notable progress was made. Therefore, Employer issued last warning letter to Contractor giving
21 days to comply with specific items, mainly mobilization at least 3 teams for road works and at
least 3 teams for structure works.
Extraordinary meeting with all stakeholders (including Senor Officers from ADB, MEF, PCMU,
MPWT, Consultant, and Contractor) is planned on 13 January and joint follow up site visit is
planned on 21 January 2016.
![Page 24: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/24.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 23
Quarterly Progress Report No.6 January 2016
CW10b:
Emergency Reconstruction of 6.4km (PK8+000- PK 14+400) DBST Road, 15m RC bridge and
40m PSC decks Bridge on PR No. 156D in Banteay Meanchey Province (Contract amount:
$2,497,238.36). This subproject was awarded on 24 June 2015 to Visvakam Samnang with
conditional NOL from ADB on personnel.
After 6 months since start date, little progress has been made on road work or on bridge works
due to lack of equipment and manpower on site.
Consultant issued several warning letters to the Contractor before Employer issued first warning
letter on 9 December 2015 per Clause 50.2 of the Contract Document giving 14 days for
Contractor to act. Follow up site visit was conducted on 25 December 2015, it was found that no
notable progress was made. Therefore, Employer issued last warning letter to Contractor giving
21 days to comply with specific items, mainly mobilization at least 3 teams for road works and at
least 3 teams for drainage works, and have specialized teams to do bridge works.
Extraordinary meeting with all stakeholders (including Senor Officers from ADB, MEF, PCMU,
MPWT, Consultant, and Contractor) is planned on 13 January and joint follow up site visit is
planned on 21 January 2016.
CW10c:
CW10c: Emergency Reconstruction of 10.06 km (PK14+400 – PK24+460) DBST Road and
75m Concrete Bridge on PR No. 156D in Banteay Meanchey Province (Contract amount:
$3,045,589.37). This subproject was just awarded with conditional NOL from ADB on personnel.
After 6 months, notable progress has been made on earth work but no progress is made for
bridge work.
Consultant issued several warning letters to the Contractor before Employer issued first warning
letter on 9 December 2015 per Clause 50.2 of the Contract Document giving 14 days for
Contractor to act. Follow up site visit was conducted on 25 December 2015, it was found that no
notable progress was made on bridge work. Therefore, Employer issued last warning letter to
Contractor giving 21 days to comply with specific items, mainly mobilization at least 3 teams for
drainage works, and have specialized teams to do bridge works.
Extraordinary meeting with all stakeholders (including Senor Officers from ADB, MEF, PCMU,
MPWT, Consultant, and Contractor) is planned on 13 January and joint follow up site visit is
planned on 21 January 2016.
![Page 25: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/25.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 24
Quarterly Progress Report No.6 January 2016
Table 3B: Status of Civil Work Implementation
Stage 2 Subprojects
No. Contractor Province (Road)
Work Description Contract Amount Project Status Civil Works Implementation
completed
CW9b (Stage 2)
Seaboard Kampong
Cham (PR270)
Reconstruction of Prek Chiek Bridge, 9m x 40m, PSC deck unit
$938,000.00
- Completed on 15 June 15 and Completion Certificate issued on 15 Jun 2015 - Under Defect Liability Period - Gross Claim: $706,595.93
Saving: $231,403.07
CW10a (Stage 2)
Ung Siamsia
Banteay Meanchey (PR156D)
Reconstruction of 8.0km DBST of PR156D
$2,126,833.70 - NOL to CA#2 on 14 December 2015 - Contract Amendment#1 signed on 23
Dec 2015
86% (completion pending repair of Cracks)
CW11/12 (Stage 2)
Seaboard
Kampong Thom
(PR265E and
PR265D)
Reconstruction Laterite road 8.15km of PR265E 7.375 km DBST of PR256D
$2,799,980.19
- Completed on 3 September 2015 and Completion Certificate issued on 4 September 2015.
- Defect Liability Period until 3 Sep 2016.
- Gross Claim: $2,568,446.74
Saving: $231,533.45
Stage 3 Subprojects
No. Contractor Province (Road)
Work Description Contract Amount
Project Status Civil Works Implementation
completed
CW13 Heng
Sambath Battambang (PR 1570)
Reconstruction of 18.75Km Laterite Road
$1,792,390.00
- Completion Certificate was issued on 9 December 2015 with defect liability period until 9 December 2016.
- Gross Claim: $1,786,288.29 Saving: $6,101.71
CW15 Visvakam Siem Reap
(NR63) Reconstruction of 6.0km Concrete Pavement
$2,334,526.33
- Advance: $350,178.95,
- Time extension 21 Mar 2016 - Progress Planned: 100% vs.
Actual: 60.65% as of 28th Dec 2015)
-Base Course Overly from PK 1+750 to PK 6+050-100% completed; -Concrete Pavement Slab 1,360 Panels completed/2,000 Panels; (remaining 640 Panels) -Scarifying work from PK 0+050 to PK 1+700
![Page 26: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/26.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 25
Quarterly Progress Report No.6 January 2016
(BHS)
Base-Course work from PK 0+050 to PK
0+200 (BHS)
-Concrete pavement is going to processing
on PK 3+022 to PK 3+124 (BHS)
-Box Culvert 1@1mx2m, L=10m at PK 2+528
-Production of RC Pipes Culvert for Cross
and Side Drainage and Man holes.
-Road Berm along Shoulders from PK 1+750
to PK6+050 (BHS).
-RC Barriers along critical area.
CW16 Banteay
Srei Siem Reap (PR265F)
Reconstruction of DBST road 11.2km
$ 2,233,310.02
- Advance: $334,996.5 - Time wise: 10 months/14 months,
71%
- Progress planned: 50 % (revised 35%) vs. Actual: 27% (as of 17/Dec/15) -Employer’s first warning letter: 11 Dec 2015 per Clause 50.2 -Follow up site visit: 18, 25 Dec 15
- Embankment: 70% - Subgrade: 27% - Subbase: stockpile approx..5000cum - Base course stockpile 300 cum
- Drainage 13% (pre-casted pipe 376nr. installed 18 locations)
-Preparation of box culverts -Ruin area#4: 200m left undisturbed
CW9a Banteay
Srei K.Cham (NR70)
Reconstruction of 16.19Km DBST Road
$2,749,789.91
- Advance: $412,468.49 - Time wise: 6 Month/18 months,
30%
- Progress Planned: 21.83% vs. Actual: 11.17% (as of 25/12/15)
- Employer’s first warning letter: 11 Dec 2015 - Follow up site visit: 26 Dec 15 - Employer’s last warning letter: 31 Dec 2015
- UXO clearance done - Clearing & Grubbing 36% - Embankment 25% - PCs pre-casted 594 nr.
![Page 27: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/27.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 26
Quarterly Progress Report No.6 January 2016
CW10b Visvakam B.Meanchey
(PR156D) Reconstruction of 6.4Km DBST and Concrete Bridges
$2,497,238.36
- Advance: $374,585.75 - Time wise: 6 Month/16 months,
34%
- Progress Planned:12% (revised 9.8) vs. Actual: 5.2% (as of 31 Dec 15)
- Employer’s first warning letter: 9 Dec 2015 - Follow up site visit: 25 Dec 15 - Employer’s last warning letter: 30 Dec 2015
- UXO clearance 100% - Re-survey: 100%
- Soil investigation done - Embankment: No progress - pile: 11 nr delivered to site
CW10c Visvakam B.Meanchey
(PR156D)
Reconstruction of 10.06Km DBST and 75m of Concrete Bridges
$3,045,589.37
- Advance: $456,838.41 - Time wise: 6 Month/16 months,
34%
- Progress Planned:30.26% vs. Actual: 18.85%
- Employer’s first warning letter: 9 Dec 2015 - Follow up site visit: 25 Dec 15 - Employer’s last warning letter: 30 Dec 2015
- UXO clearance done (except at 75m bridge)
- Re-survey: 100%
- Clearing & Grubbing: - Embankment: 37% - Subgrade 51% - Subbase 6% - pile production: 23/80
![Page 28: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/28.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 27
Quarterly Progress Report No.6 January 2016
Summary of FDERP-AF timeframe and costs
Table 4B:
No. Project Name
Date of Contract
Agreement Start Date
Contract Period, days
Intended date
Time Extension Actual Completion Amount ($)
Period, days
Until Period, days
Until Original Amended Final
1 CW9b (SB)
10-Jul-14 10-Jul-14 300 6-May-15 40 15-Jun-15 340 15-Jun-15 938,000.00 - 706,595.93
2 CW10a (USS)
10-Jul-14 10-Jul-14 365 10-Jul-15
10-Jun-16
2,126,833.70 $2,211,177.34
*) -
3 CW11/12
(SB) 10-Jul-14 10-Jul-14 420 3-Sep-15 - - 420 3-Sep-15 2,799,980.19 2,799,980.19 2,568,446.74
4 CW9a (BTS)
24-Jun-15 24-Jun-15 540 15-Dec-16
2,749,789.91 -
5 CW13 (HSB)
20-Jan-15 20-Jan-15 420 15-Mar-16 - - 323 9-Dec-15 1,792,390.00 1,792,390.00 1,786,288.29
6 CW15 (VSK)
30-Dec-14 30-Dec-
14 365 30-Dec-15 447 21-Mar-16
2,334,526.33
7 CW16 (BTS)
27-Feb-15 27-Feb-
15 420 22-Apr-16
2,233,310.02
8 CW10b (VSK)
24-Jun-15 24-Jun-15 480 16-Oct-16
2,497,238.36
9 CW10c (VSK)
24-Jun-15 24-Jun-15 480 16-Oct-16
3,045,589.37
10 CW14
(SW-Cam) 11-Dec-15
11-Dec-15
480 4-Apr-17 2,859,103.23
(Name of Contractor): SB: Seaboard, USS: Ung Simsia, HSB: Heng Sambath, BTS: Banteay Srei, VSK: Visvakam Samnang; SW-Cam: SWEE-Camdeg *) Signed Contract Amendment#1: $2,211,177.34 (23 Dec 2015) ; PRC’s approval/ADB’s NOL: $2,226,913.78 (14Dec2015)
![Page 29: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/29.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 28
Quarterly Progress Report No.6 January 2016
Comparison between Original Scope and Current Scope of works
FDERP-AF: Scope of Work Per PAM 2014 No. Contract No. PSC Bridge RC Bridge Box Culvert Pipe Culvert DBST Laterite Concrete road Comments
1 CW9b 40m (1) - - - - - - () : Numbers of
structures 2 CW10a - 30 (1) - - 11.2km - -
3 CW11/12 - - - - 7.5km 8.15km -
4 CW9a - - - - 16.19km - -
5 CW13 - - - - - 19.7km -
6 CW15 - - - - - - 6.0km
7 CW16 - - - - 11.3km -
8 CW10b 75m (1) - - - 4.5km - -
9 CW10c - - - - 9.3km -
10 CW14 - - 24.8km -
Total 115m (2) 30m (1) - - 84.79km 27.85km 6.0km
FDERP-AF: Current Scope of Work (31/12/15) No. Contract No. PSC Bridge RC Bridge Box Culvert Pipe Culvert DBST Laterite Concrete road Comments
1 CW9b 40m (1) - - - - - - () : Numbers of
structures 2 CW10a - - 4 11 8.0km - -
3 CW11/12 - - 5 30 7.37km 8.15km -
4 CW9a - - - 13 16.19km - -
5 CW13 - - - 38 - 18.75km -
6 CW15 - - - 11 - - 6.0km
7 CW16 - - 3 39 11.2km -
8 CW10b 40m (1) 15m (1) 3 14 6.4km - -
9 CW10c 75m (1) - 6 21 10.06km -
10 CW14 - - 4 47 - 22.0km
Total 155m (3) 15 m (1) 25 224 59.22km 48.9km 6.0km
![Page 30: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/30.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 29
Quarterly Progress Report No.6 January 2016
Summary of FDERP-AF Issues requiring Actions
Table 5B:
Project Issues Required Actions
CW10a Cracks re-appear after water recedes
1. Consultant is working with Contractor to have cracked repaired
CW15 Contractor cannot complete by 30 December 2015 as planned.
1. Contractor applied for time extension which was approved until 21 March 2016.
CW16 Slow progress, no equipment, no manpower ruin discovery@ PK10+125
1. Meeting between senior management of MPWT and contractor top management in order to push for progress.
2. Employer issued a warning letter according to GCC Clause 50.2 of Contract Document
3. Leave 200m section from PK10+100 to 10+300 undisturbed
CW9a Little progress, no equipment, no manpower
1. Meeting between senior management of MPWT and contractor top management in order to push for progress.
2. Employer issued 2 warning letter per GCC Clause 50.2 of Contract Document
CW10b No progress on road works, drainage structures and bridges, no equipment, no manpower
1. Meeting between senior management of MPWT and contractor top management in order to push for progress.
2. Employer issued 2 warning letter per GCC Clause 50.2 of Contract Document
CW10c Little progress on drainage structure and bridge
1. Meeting between senior management of MPWT and contractor top management in order to push for progress.
2. Employer issued 2 warning letter per GCC Clause 50.2 of Contract Document
CW14 UXO late
Consultancy Service
Inputs for senior management staffs are insufficient due to extension for CW14
VO#6 with zero added cost is prepared
![Page 31: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/31.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 30
Quarterly Progress Report No.6 January 2016
I. ACTUAL ACTIVITIES DURING THE QUARTER(Oct - Dec 2015)
Prepared and Issued safeguard monitoring report No. 13 (July– September 2015)
Prepared and Issued Quarterly Progress Report #5 (July– September 2015)
Prepared and Issued Contract Completion report for CW13
Issued contract amendment #2 for CW13
Issued contract amendment #1 for CW10a
Conducted monthly progress meetings with the Contractors
Reviewed recommendation for further time extension for CW15 until 21 March 2015.
Prepared and Issued Subproject Final Design Report CW14.
Prepared and issued resettlement categorization reports for CW14 where several public consultations have been conducted.
Prepared safeguard monitoring report No. 13 (July– September 2015)
Assisted BEC in procurement from bid opening to contract award of CW14
MPWT has resettlement categorization reports for CW14 verified by third party consultant with a report issued for each project.
Coordination meeting with APSARA regarding location of ruins, following by joint visits between DPWT and APSARA to CW16, ruin at PK10+200. It was decided to keep 200m undisbursed.
Continue supervision of Stage 3 civil works CW15, CW13, CW16, CW9a, CW10b, CW10c and CW14.
Recommend contract variations for approval of the Client.
Review and certify IPCs and Advance Payment requested by Contractors
Continue supervision of Stage 2 civil work (CW10a)
Continue supervision of Stage 3 civil works (CW15, CW13 and CW16)
Continue construction supervision for CW9a, CW10b and CW10c.
Approve construction materials, Shop drawings
Recommend variations for approval of the Client.
Review and certify IPCs and Advance Payment requested by Contractors
Arrange coordination meeting between Client’s senior management and contractor’s top management to speed up progress for CW10b and CW10c, and CW16 and CW9a.
Advised and assisted Employer in issuing warning letters to 2 contractors of 4 above contracts.
Follow up site visits
![Page 32: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/32.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 31
Quarterly Progress Report No.6 January 2016
Social Safeguards, LGAP
Quarterly Labor and Gender Action Plans (LGAPs) from October to December
2015
1. Quarterly Labor and Gender Action Plans (LGAPs) are being prepared by MPWT. These
are based on monthly forms issued by MPWT for completion by contractors. Contractors are
reporting difficulties in meeting the 25% quota of unskilled female labor. Table 6B
summarizes quarterly information for Stage 2 and Stage 3 contracts.
Table 6B: MPWT Stage 2 and Stage 3 Contracts – Percentage of Unskilled Female Labor
Project Oct- 2015 Nov- 2015 Dec- 2015
Sex M F M F M F
CW10a 2 2 0 0 0 0
Tot 4 0 0
CW13 0 0 0 0 0 0
Total 0 0 0
CW15 49 9 25 4 26 6
Total 58 29 32
CW10b 4 0 10 6 15 8
4 16 23
CW10c 11 6 11 5 11 7
17 16 18
CW9a 5 4 13 13 15 16
9 26 31
CW16 13 7 19 8 19 8
Total 20 27 27
Project Oct- 2015 November- 2015 December- 2015
CW10a 50% 0% 0%
CW13 0% 0% 0%
CW15 15% 14% 19%
CW16 0% 37% 30%
CW9a 35% 31% 51%
CW10b 44% 50% 35%
CW10c 35% 30% 39%
![Page 33: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/33.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 32
Quarterly Progress Report No.6 January 2016
II. PLANNED ACTIVITIES DURING NEXT QUARTER(Jan-Mar 2016)
Continue supervision of Stage 2 civil work (CW10a)
Prepare and issue subproject contract completion reports for CW10a
Prepare and issue subproject contract completion reports for CW14
Coordination meeting with MEF and ADB on contractual issue for CWs9a, 16, 10b and 10c.
Coordination meeting with all stakeholders on contractual issue for CWs9a, 16, 10b and 10c.
Follow-up site visits after stakeholder meetings.
Conduct monthly progress meetings with the Contractors
Continue supervision of all Stage 3 on-going civil works
Approve construction materials, Shop drawings
Recommend variations for approval of the Client.
Review and certify IPCs and Advance Payment requested by Contractor
prepare for ADB Joint Review Mission
![Page 34: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/34.jpg)
Egis International
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 33
Quarterly Progress Report No.6 January 2016
PHOTO GALERY FOR FDERP-AF
Comparison of subproject Status (prior to and now)
Description Prior to Construction Under Construction or after completion
CW9b
PSC Deck Bridge 40m
PR270
Kampong Cham
Province
(Seaboard)
December 2013
September 2015 (DLP)
CW10a
DBST road 8.1km
PR156D
Banteay Meanchey
(Ung Simsia)
December 2013
December 2015
![Page 35: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/35.jpg)
Egis International
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 34
Quarterly Progress Report No.6 January 2016
CW11
Laterite Road
8.15km
PR264
Kampong Thom
(Seaboard)
December 2013
30 June 2015 (completed)
CW12
DBST Road
7.3km
PR264
Kampong Thom
(Seaboard)
September 2013
July 2015 (completed)
![Page 36: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/36.jpg)
Egis International
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 35
Quarterly Progress Report No.6 January 2016
CW13
Laterite
18.75km
PR1570
Battambang
(Heng Sambath)
September 2013
December 2015 (completed)
CW15
Concrete Pavement
6.0km
NR63
Siem Reap
(Visvakam)
September 2013
December 2015(box culvert)-Time Extended
![Page 37: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/37.jpg)
Egis International
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 36
Quarterly Progress Report No.6 January 2016
CW16
DBST road
11.2km
PR265F
Siem Reap
(Banteay Srei)
2013
Dec 2015 (Embankment)
CW9a
DBST Road
16.19km
NR70
Kampong Cham
(Banteay Srei)
September 2013
December 2015 (Under Construction)
![Page 38: ID()gdb.mef.gov.kh/fderp-af/contents/uploads/2013/07/... · Project Office Ministry of Public Works and Transport, 4th Floor, Northern Building, Corner Norodom Blvd and 106 St, Phnom](https://reader034.vdocuments.us/reader034/viewer/2022050406/5f83706dfbcd8f242a104507/html5/thumbnails/38.jpg)
Egis International Part B: FDERP-AF
Grant No.: 0285-CAM (EF) and Loan No.: 3125-CAM (SF) P a g e | 37
Quarterly Progress Report No.6 January 2016
CW10b
DBST Road 6.40km and
2 Concrete Bridges
PR156D
Banteay Meanchey
(Visvakam)
Bridge #2 of CW10b
December 2015 Pipe culvert formworks
CW10c
DBST Road 10.06km and
a 75 m Concrete Bridge
PR156D
Banteay Meanchey
March 2015
December 2015 (ADB Mission), water goes down