ICT Unit - Business Plan 2013
Role of the ICT Unit:
To provide a range of Information and Communications Technology (ICT) services to the OPW which support its business functions, both
operational and strategic.
To manage and maintain OPW's server and storage area network estates.
To arrange for the supply, installation and maintenance of office equipment (e.g. PCs, printers, fax machines, photocopiers etc.)
To provide a telecommunications infrastructure for the OPW that supports its communications needs, both voice and data. This includes
telephones, mobile phones, tablet devices etc.
To assist in the delivery of ICT Training to meet Business Unit needs.
To manage the OPW’s Internet infrastructure (e-mail & Web access)
To provide advice to senior management on ICT issues
To ensure that the OPW ICT systems are secure from the threat of viruses, spyware and unauthorized access
To provide ICT expertise during the implementation of ICT projects within OPW
Services provided by the ICT Unit include:
Design, development and implementation of ICT systems to support the various functions performed by the individual Business Units in the
OPW.
Development, management and maintenance of computer networks.
Provision of Internet e-mail and Web facilities
Provision and support of a ll telecommunication services, computer hardware and software, directly or through third parties.
Provide a Help Desk facility for ICT and Office equipment issues
Procurement of a range of hardware, software and ICT-related services
1
ICT Unit - Business Plan 2013 Software development
Procurement, management and support of mobile devices (e.g. mobile phones, Blackberries etc.)
Management of printing and plotting facilities
Provide an ICT environment free from security threats
Advice to staff on how to get the most from information technology
Provide advice on Data Protection issues
Contribute to policy formulation
______________________
Liam Stewart
HEAD OF ICT UNIT
27th November 2012
2
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
Major Projects to be advanced in 2013:
(Prioritised)Public Service Reform - State Assets (2.4.4)
Property related matters (& 2.5.2)
1 Provide ICT support for the implementation of a new facilities management (to replace Facility Centre & Visibility)
Liam Kelly AP1 RFI issued to the market in November 2012.
New system to be operational by Q1 2014 (assuming procurement process commences in January 2013).
Project will incorporate the replacement of Visibility, the provision of a helpdesk function and an interactive portal for customers.
This is a very complex project cutting across
500K Internal• Property
Management• Property
Maintenance• Projects
Division• Architectural
Services• Engineering
Services• BMS• M&E• ICT Steering
Group
External:• Supplier• Other Public
Bodies• D/Per
Formal project management structure needs to be established.
Weekly internal meetings
Monthly progress meetings (Project Board).
Review by ICT Steering Group.
3
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
multiple business areas. The delivery of this project is dependent on the availability of resources.
Ireland's Presidency of
the EU in 2013 (2.5.7)
2 EU Presidency 2013
Liam Stewart PO
Peter Brady HEO
Provide 2 no. and possibly more full-time on-site ICT resources for the Presidency to assist with network troubleshooting, equipment set-ups etc. Sites involved are Dublin Castle, Castletown House and Farmleigh.
80K Internal:• Dublin Castle
staff• National
Historic Properties
• M&EExternal:
• Contractors• Internet service
providers• D. Foreign
Affairs
Regular progress meetings.
Cross Organisational objectives
3 Deliver a new ICT Strategy
Liam Stewart PO Business Unit buy-in is essential for the success of this initiative.
This process commenced in Q4 2012 and will continue into
The project is managed entirely in house, no substantial costs are envisaged apart from staff time.
Internal:• All business
units and support services in OPW.
• ICT Steering Group
• MAC• Senior
Reports submitted to ICT Steering Group.
4
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
2013. Workshops will take place with Business Units to establish priorities and business objectives. Process should be substantially competed by Q1 2013.
Draft ICT Strategy to be submitted for approval by ICT St eering Group by Q2 2013.
A figure of 10K should be included for quality assurance by external parties.
managers network
External:• Third party
review by consultant
• CMOD
eGovernment Strategy 2012-15
4 Deliver OPW action plan to support eGovernment Strategy
Liam Stewart PO Draft to be submitted to ICT Steering Group Q1 2013
N/A Internal:
• All Business Units
• ICT Steering Group
• MAC
External:• D/Per
5
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
Cross Organisational objectives
5 Enhance Electronic Informationand Document ManagementSystems across the OPW
(“Document Management”)
Liam Kelly AP1
Gráinne McDonnell, HEO
Alfresco has been running in trial mode in OPW for over 12 months and has gained in popularity as staff see its potential.
Formal roll-out has been delayed while awaiting the report on Records Management (John Gallagher). The creation of rules for naming conventions, metadata will be crucial features in the move to a document management system.
Upgrade Alfresco system to enterprise-ready version.
Software is free.
Staff training (20K)
Expert review (5K)
Internal:• MAC• ICT Steering
Group• All Business
Units• John
Gallagher's records management group
External:• LGMA
Regular meetings with pilot users to assess progress and resolve difficulties.
Reports submitted to ICT Steering Group.
6
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
(Q1/2013).
Conduct information sessions, workshops and publicity campaign on benefits of a document management system (incorporating recommendations from John Gallagher's team). (Q1/2013).
eGovernment Strategy
6 Assist Policy Unit in developing and “open data” policy for OPW. Provide technical support to assist Business Units in identifying
Liam Stewart PO
Liam Kelly AP1
Adrienne O' Driscoll HEO
Consultation with other public bodies, Dublinked etc. Q1/2013.
Staff information / publicity campaign Q1/2013.
Audit of data sets
None. Internal• Business Units• Policy Unit• Public
Relations Office
• FOI officer
Internal review meetings.
Reports to ICT Steering Group and MAC.
7
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
and preparing data sets for publication on the Web.
in OPW Q1 & Q2 / 2013.
Draft policy to be submitted to MAC Q2/2013
External• CMOD• D/Per• Dublinked
General 7 Upgrade obsolete database servers supporting critical Oracle applications: Integra, Facility Centre, WISKI database as some of these are 10 years old, well past end of life, and liable to fail without warning. Replacement servers can be re-purposed as applications are retired/replaced.
Peter Brady HEO
Liam Kelly AP1
Issue RFT to the market Q1/2013.
Place contract Q2/2013.
Roll-out new hardware Q2 /2013.
15K External• Successful
tenderer
Internal staff meetings in ICT Unit.
Updates to ICT Steering Group.
8
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
Provide additional server for DR.
Replace CorePay web and database servers with retired VMware servers.
Physical servers are required to avoid prohibitive Oracle costs.
Replace MIF Reports SAP-Business Objects/Facility Centre Web Server with Virtual Machine
General 8 Upgrade 20+ file and print servers at
Peter Brady HEO
Liam Kelly AP1
Issue RFT to the market Q1/2013.Roll-out new
80K • Internal • Business Units
Regular staff meeting in ICT Unit to assess
9
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
remote sites.
Existing services are end of life and out of support.
hardware Q2 & Q3/2013.
progress
General 9 Upgrade key VMware host servers and software in 52 & Trim. Current servers are approaching end of life. This is critical infrastructure
Liam Stewart PO
Liam Kelly AP1
Peter Brady HEO
Issue RFT Q1/2013.
Place contract Q2/2013.
Replace equipment Q2 & Q3/2013.
100K External• Successful
tenderer
Internal staff meetings in ICT Unit.
Updates to ICT Steering Group.
General 10 Upgrade disk controllers on Storage Area Network (SAN). Increase Disk Capacity. This is critical infrastructure
Liam Stewart PO
Liam Kelly AP1
Peter Brady HEO
Issue RFT Q1/2013.
Place contract Q2/2013.
Replace equipment Q2 & Q3/2013.
250K External• Successful
tenderer
Internal staff meetings in ICT Unit.
Updates to ICT Steering Group.
General 11 Redesign of OPW network. This will include the creation of
Liam Stewart PO
Liam Kelly AP1
Issue RFT Q1/2013.
Place contract
50K External• Successful
tenderer
Internal staff meetings in ICT Unit.
10
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
an independent Internet service into Trim HQ.
Peter Brady HEO Q2/2013.
Replace equipment Q2 & Q3/2013.
Updates to ICT Steering Group.
General 12 Upgrade bandwidth at remote sites (where resources allow and where it is technically feasible to do so)
Liam Kelly AP1
Peter Brady HEO
RFT to issue Q1/2013
Contracts placed Q1/2013
Services installed Q2 & Q3/2013
80K Internal:• Business units.
External:• Service
providers
Internal staff meetings.
Reports to ICT Steering Group on progress.
General 13 Assist Public Relations Unit in creating new OPW Web site
Liam Kelly AP1 Public Relations Unit to decide.
Staff time. Internal:• Public
Relations Unit• OPW Web site
review committee
External:• Public
Liaison with PRU.
General 14 Continue roll out of new personal computing equipment (and re-allocation of
Laura Burke HEO
Liam Kelly AP1
Roll out was held up for technical and logistical reasons in 2012.
Programmed roll-
None, apart from travel & subsistence.
Internal:• Business units.
Internal staff meetings.
Reports to ICT Steering Group on progress.
11
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
upgraded workstations).
out will commence in Q1/2013 and continue for the rest of the year.
Speed of deployment will be dependent on the availability of ICT staff and third parties.
All end users will require training in Windows 7 so that could slow up the roll-out.
General 15 Replace Lotus Notes e-mail with Zarafa.
Add in additional functionality such as calendar-sharing, self-service room
Grainne Mc Donnell HEO
Liam Kelly AP1
Prototype system currently up and running in ICT Unit.
Formal pilot to commence in Q1/2013. Target is to migrate 400 no. users at least by Q4/2013.
15K Internal:• Business Units
External:• Third party
company• LGMA
Internal review meetings.
12
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
booking and instant messaging.
General 16 Assist Accounts Branch with the upgrade of Integra.
Liam Kelly AP1plus others to be assigned.
Timescale will be determined by Accounts.
60K Internal• Accounts• Business Units• Management
Accountants External:
• Service Provider )(Capita IB)
Liaison with Accounts Branch.
Data Protection Legislation
17 In conjunction with Policy Unit, develop guidelines and policy in relation to Data Protection.
Liam Stewart PO
Laura Burke HEO
Guidelines to issue Q1/2013.
Draft policy to be submitted to MAC Q2/2013.
None. Internal:• Policy Unit• Personnel• MAC• John
Gallagher's records management committee
• Partnership?
External:• Data Protection
Commissioner
Internal review meetings.
13
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
General 18 Assist Heritage Services with the roll-out of EPOS devices at visitor sites.
Liam Kelly AP1
Peter Brady HEO
Agree timescale with Heritage services.
Costs to be covered by Heritage Services.
Internal:• National
Monuments• National
Historic Properties
External:• Service
Provider
Liaison with Heritage Services
General 19 Tender competition for mobile phone management (single provider)
Suzanne Mitchell HEO
Liam Kelly AP1
RFT to issue Q1/2013
New contract in place by Q2/2013.
This relates to monthly phone bills.
N/A Internal review meetings.
1.3.4 Corporate Services
20 Replacement of ASR (Industrial Personnel system)
Liam Kelly AP1
Grainne Mc Donnell HEO
Continue liaison with other Departments that have Industrial staff to determine agreed requirements.
Issue RFT Q2/2013.
Place contract
25K Internal:• Industrial
Personnel
External:• CMOD• Successful
tenderer• Other
Departments with industrial
Project Team to be established.
Regular meetings with Industrial Personnel and supplier
Progress reports to ICT Steering Group.
14
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
Q3/2013.
Implementation by Q4/2013
staff
General 21 Deployment of Fleet Management system for Engineering Services
Grainne Mc Donnell HEO
Liam Kelly AP1
Project was delayed in 2012 due to interventions by CMOD.
Project to formally commence Q1/2013.
System to go live by Q2/2013
25K Internal:• Engineering
services• CEW• ICT Steering
Group
External:• Etain Ltd.• Waterways
Ireland
System may be rolled out later to:
• National Monuments
• Furniture Branch
• BMS
Project team to be established.
Regular meetings with Engineering Services and supplier
Progress reports to ICT Steering Group.
Government Architectural Policy (2.5.4)
22 Building Information Modelling – Pilot Scheme
Liam Kelly AP1 ES, AS and M&E need to select a suitable project for a pilot project..
Hardware and software have been acquired. Training will
Internal:• Architectural
Services• Engineering
Working group meetings.
Monthly progress
15
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
ICT Unit will provide support services.
Timescales will be dependent on the type of project selected and its duration.
need to be funded). Additional costs will be incurred if a decision is taken to extend the scope of the pilot or to increase the proliferation of BIM within OPW.
Services• M&E• QS• ICT Steering
Group
External:• CITA• Construction
Industry
meetings with pilot users.
Formal report to be prepared for ICT Steering Group at the end of the pilot.
General 23 Investigate solutions to replace existing PQ system and improve archive search
Liam Kelly AP1
Grainne Mc Donnell HEO
Commence investigation in Q1/2013.
None at this point.
Internal:• Minister's
office• Policy Unit• Business Units
External:• Oireachtas
Liaise with Oireachtas and Minister's Office on requirements. Update them on progress.
General 24 Continue piloting Ubuntu (open source desktop operating system) with a
Liam Stewart PO
Fergal O' Brien EO
Project commenced in 2012.
Aim for at least 50 full-time users
None, apart from staff time.
Internal:• Business Units
Regular feedback sessions from plot group.
16
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
view to a live roll-out across selected sites in 2013.
in 2013.
General 25 Upgrade document search facility across OPW (Exalead)
Liam Stewart PO
Peter Brady HEO
Project is dependent on upgrade of hardware (see 8 above)
12K External:• Support
company
Meetings and communications with supplier.
General 26 Develop a Web-based system to replace current Art Management database.
Develop a Web-based system to catalogue National Botanic Gardens (NBG) art and museum collections, wirh aim, of extending this to other heritage site
Liam Kelly AP1 Art Management has agreed to use Collective Access (open source).
NBG have also expressed an interest in Collective Access .
Scope of work to be agreed with Art Management and NBG in Q1/2013.
Working prototypes to be available in Q2/2013.
None. Internal:• Art
management• Library• National
Botanic Gardens
Internal meetings with Art Management.
Internal meetings with National Botanic Gardens.
Updates to ICT Steering Group.
17
ICT Unit - Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by the Business Unit:
Staff responsible for the actions
Time scale and other
performance indicators
Estimated Costs
associated with the
Action/Project in 2013
Other key playersInternal/External
Review arrangements
collections
Cross Organisational objectives
27 Investigate Business Intelligence solutions
Liam Stewart PO
Liam Kelly AP1
A requirement for this type of application is emerging from business reviews in OPW.
Not possible to estimate at this point.
Internal:• Business Units
External:• Service
providers
Internal review meetings.
Cross Organisational objectives
28 Investigate Customer Relationship Management (CRM) Systems
Investigate the possibility of replacing the Correspondence Database for Engineering Services.
Liam Stewart PO
Liam Kelly AP1
A requirement for this type of application is emerging from business reviews in OPW.
Not possible to estimate at this point.
Internal:• Business Units
External:• Service
Providers• LGMA
Internal review meetings.
1.3.2 Flood Fisk Management
29 Provide assistance, as resources allow, in respect of GIS development in OPW
Liam Stewart PO
Liam Kelly AP1
Timescale for delivery is a matter for Engineering Services.
Not possible to estimate at this point.
Internal:• Business Units
External:• State Agencies• LGMA
Liaison with Engineering Services
Total Costs 1.327M
18
ICT Unit Business Plan 2013
Strategy Statement
Programmes:
Action to be taken by Business Unit
Staff responsible
for the actions
Time scale and other performance indicators
Estimated Costs associated with
the Action/Project in 2012
Other key playersInternal/external
Review arrangements
Actions in support of the Strategy Statement programmes:
ICT Support services
Increased scrutiny of costs incurred on printing telephony etc.
Liam Kelly APO
Suzanne Mitchell HEO
Adrienne O'Driscoll HEO
Ongoing.
Reports / Feedback to Line Managers.
None. Internal:• Business
Units
External:• Service
providers
Internal review meetings.
ICT Support services
Manage and support office equipment such as printers, plotters, copiers and fax machines
Laura Burke HEO
Ensure that support calls in respect of equipment are dealt with in a timely fashion in accordance with SLA.
Printer maintenance.
Est: 5K
Plotter maintenance
Est 15K
External:• Service
providers
Internal review meetings.
Customer feedback (Helpdesk survey)
ICT Support Manage and Laura Burke Ensure that support calls in N/A External: Internal review
19
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible
for the actions
Time scale and other performance indicators
Estimated Costs associated with
the Action/Project in 2012
Other key playersInternal/external
Review arrangements
services support personal computer estate
HEOPeter Brady HEO
respect of equipment are dealt with in a timely fashion in accordance with SLA.
• Service providers
meetings.
Customer feedback (Helpdesk survey)
ICT Support services
Supervision of external service providers, namely Helpdesk (Trim and Dublin) and “break-fix” service (remote sites).
Laura Burke HEO
Efficient performance of OPW Helpdesk.
Positive customer feedback on Helpdesk performance.
Call response times in accordance with SLA.
N/A External:• Service
providers
Internal review meetings.
Customer feedback (Helpdesk survey)
ICT Support services
Manage mobile phone estate
Suzanne Mitchell HEO
Up to date records on mobile phone usage.
Monitoring of mobile phone costs.
Accurate Asset Register.
Enforcement of mobile phone policy.
Good quality phones provided to those that need them.
N/A External:• Service
providers• Mobile
phone companies
Internal review meetings.
Spot checks.
20
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible
for the actions
Time scale and other performance indicators
Estimated Costs associated with
the Action/Project in 2012
Other key playersInternal/external
Review arrangements
ICT Support services
Manage digital camera estate
Suzanne Mitchell HEO
Accurate Asset Register.
Good quality cameras provided to those that need them.
N/A External:• Service
providers• Camera
companies
Internal review meetings.
Spot checks
ICT Support services
Manage and support storage area networks and virtualisation architecture
Peter Brady HEO
Aim for 99.9% server uptime
Aim for 99.9% SAN uptime.
160K External:• Service
providers
Internal review meetings.
ICT Support services
Manage and support security infrastructure inc. Mailsweeper, McAfee, Websense, Tipping Point, Endpoint, RADIUS, Netilla and firewall.
Peter Brady HEO
Ensure critical security systems are available at all times.
Est: 30K External:• Service
providers
Internal review meetings.
Automatic notifications of system failure.
ICT Support services
Manage and support local and wide area networks.
Peter Brady HEO
Aim for 99.9% router uptime
In house costs.
Data line costs, switch & router maintenance:
External:• Service
providers
Internal review meetings.
Automatic notifications of system failure.
21
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible
for the actions
Time scale and other performance indicators
Estimated Costs associated with
the Action/Project in 2012
Other key playersInternal/external
Review arrangements
Est: 200KICT Support services
Manage backup infrastructure
Peter Brady HEO
Regular updates to Business Units on backup schedules.
Backups run on schedule.
Est: 15K External:• Service
providers
Automatic notifications of system failure.
ICT Support services
Review desktop software usage using specialised tool to free up unused or little-used licences and return them to the common pool. Tool will also assist software licence compliance.
Gráinne McDonnell HEO
Tool to be run every 3-4 weeks.
6K maintenance cost.
External:• Service
provider
Internal review meetings
ICT Support services
Management of OPW's e-mail infrastructure (inc. Lotus Notes, Blackberry and Mailmeter)
Gráinne McDonnell HEO
24*7 uptime on e-mail system
Upgrade to be undertaken Q1/2012.
Est: 10K External:• Service
provider
Internal review meetings
System alerts.
ICT Support Manage and Peter Brady 24*7 uptime on phone Est: 80K (inc. data External: Internal review
22
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible
for the actions
Time scale and other performance indicators
Estimated Costs associated with
the Action/Project in 2012
Other key playersInternal/external
Review arrangements
services support OPW's telephony infrastructure (approx. 100 no. phone systems)
HEO systems switches with voice capability)
• Service provider
meetings
System alerts.
ICT Support Services
Develop software systems to meet business requirements
Liam Kelly APO
Small systems are developed as time and resources permit.
Not possible to determine at this point.
External:• Service
provider
Internal review meetings
ICT Support Services
Manage major software applications such as Visibility, CorePay, Facility Centre, Integra etc.
Liam Kelly APO
100% uptime on major applications during core business hours.
Approx. 100k External:• Service
provider
Internal review meetings
System alerts.
ICT Support Services
Provide back end support for Public Relations in managing the Intranet and the Web content management system.
Liam Kelly APO
Content management system available to PR as required.
Est: 15K External:• Service
provider
Internal review meetings
System alerts.
ICT Support Services
Manage and support Novell file servers at remote
Peter Brady HEO
100% uptime on Novell servers during core business hours.
Cost inc. in Infrastructure support.
External:• Oki
Internal review meetings
23
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible
for the actions
Time scale and other performance indicators
Estimated Costs associated with
the Action/Project in 2012
Other key playersInternal/external
Review arrangements
sites. System alerts.General Introduction of
new internal procedures in relation to procurement, document management, stock control and asset management
Laura Burke HEO
New procedures came into effect in 2012 and will be refined in 2013.
N/A N/A Internal review meetings
General Management of Uninterruptible Power Supply (UPS) systems
Peter Brady HEO
UPS systems have sufficient battery power to survive a short power cut.
20K (replacement of batteries)
External:• Service
providers
Internal review meetings
System alerts.General Management of
wireless networksPeter Brady HEO
100% uptime during core business hours.
Acceptable performance for end users.
Est: 25K External:• Service
providers
Internal review meetings
System alerts.
Total Costs €0.656M
24
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible for the actions
Time scale and other performance indicators
Other key playersInternal/external
Review arrangements
Cross-Functional /Internal ActionsRisk assessment and management
Liam Stewart PO
Risk review completed by end of Q1 2013.
ISO procedures should reflect controls for risk management
Internal:• Chairman & MAC• Internal Audit • Business Units
External:• Service providers
The risks will be reviewed quarterly
Ensure PMDS is carried out within the Business Unit and staff are trained as follows:- (1) as identified in the course of PMDS meetings for competency development (2) Training related to the business function(3) Personal development training
Liam Stewart PO
Personnel
The meeting of deadlines in completing interim and annual reviews under PMDS.
Personnel reporting to Management
The timely submission of Prioritised Training Needs for the Business Unit to T & D Section.
Internal:• Personnel&
Development Services
• Training & Development Unit
External:• D/per• CSTDC
As required under the PMDS guidelines
Ensure that staff are familiar with the QCS Plan and that prompt action is taken on correspondence, requisitions, PQs, FOI
All Staff Timescales in line with QCS commitments and reflected in ISO requirements
Internal:• QCS Officer• Policy Unit• Minister’s Office• Chairman’s Office
Review in line with central updating of QCS Action Plan at Business Unit Meetings
25
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible for the actions
Time scale and other performance indicators
Other key playersInternal/external
Review arrangements
Requests and representations in accordance with the guidelines in the QCS Plan and any relevant statutory obligations.Respond promptly to press queries to protect the reputation of the Office.
• Public Relations
External:• Questions Office• Deputies• Members of the
Public• Journalists/Media
Health & Safety Responsibilities
All staff To monitor Health & Safety issues and incidents.To review the Office’s Safety Statement (This is a statutory requirement).
Internal:• Personnel/Internal
Facilities Mgt.• Health & Safety
Unit
External:• HSA
SMAC meetings to review Safety
ISO Accreditation All staff Investigate the possibility of ISO 27001 and ITIL accreditation.and identify improvements.
Common procedures for common activities across business units (Take the best procedure in one section and make it common for all)
External:NSAI
As required
26
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible for the actions
Time scale and other performance indicators
Other key playersInternal/external
Review arrangements
Official Languages responsibilities
All staff To contribute to the OPW's compliance with language responsibilities under the Official Languages Act, 2003 and the Office Official Languages Scheme
Internal:• Policy Unit• Press & Media
Relations Office
External:• Official Languages
Commissioner• Dept of Arts,
Heritage & the Gaeltacht
• Clients and Customers
• General Public
Review regularlyto ensure compliance
Compliance with legislation:• Data Protection Acts• Procurement
Directives
Laura Burke HEO
Ongoing Internal:• ICT Unit
External:• Data Protection
Commissioner• NPPPU, D/PER• EU Commission
Internal meetings.
Familiarity and compliance with OPW practices and
All Staff Ongoing Internal:• Personnel
27
ICT Unit Business Plan 2013Strategy
StatementProgrammes:
Action to be taken by Business Unit
Staff responsible for the actions
Time scale and other performance indicators
Other key playersInternal/external
Review arrangements
procedures as contained in Office Notices.
• Business Units submitting appropriate instructions.
28