ibe0584 langholm fra rev 4 jun2017€¦ · 1.1 background ... map to identify properties at risk of...
TRANSCRIPT
DOCUMENT CONTROL SHEET
Client Dumfries & Galloway Council
Project Title Langholm
Document Title Flood Risk Assessment
Document No. IBE0584/Apr17
This Document
Comprises
DCS TOC Text List of Figures List of Tables No. of Appendices
1 1 40 1 1 1
Rev. Status Author(s) Reviewed By Approved By Office of Origin Issue Date
1 Draft Final D McGinnis M Brian A Jackson Belfast Feb 2013
2 Final D McGinnis M Brian A Jackson Belfast Aug 2013
3 Draft Rev A Sloan A Jackson A Jackson Belfast Dec 2016
4 Final rev A Sloan A Jackson A Jackson Belfast 2017
Langholm Flood Risk Assessment
Langholm Flood Risk Assessment
IBE0584/Apr2017 i Rev 4
TABLE OF CONTENTS
1 Introduction ............................................................................................................................... 1 1.1 BACKGROUND .................................................................................................................. 1 1.2 AIMS AND SCOPE .............................................................................................................. 2
2 Data Collection ......................................................................................................................... 3 2.1 METHODOLOGY ................................................................................................................ 3 2.2 TOPOGRAPHICAL SURVEY DATA......................................................................................... 3 2.3 HYDROLOGICAL DATA ....................................................................................................... 4 2.4 REVIEW OF HISTORIC FLOODING EVENTS ........................................................................... 5
3 Assessment of River Flows ..................................................................................................... 8 3.1 METHODOLOGY ................................................................................................................ 8 3.2 CATCHMENTS ................................................................................................................... 8 3.3 FEH STATISTICAL ANALYSES ............................................................................................ 9
3.3.1 QMED estimation ............................................................................................. 9 3.3.2 Pooling group development ............................................................................ 10 3.3.3 Flood frequency curve estimation .................................................................. 11 3.3.4 FEH Rainfall-Runoff method .......................................................................... 11 3.3.5 Adopted flood frequency curves and hydrographs......................................... 12
3.4 CLIMATE CHANGE PROJECTIONS...................................................................................... 14 4 Assessment of Flood Levels ................................................................................................. 15
4.1 MODEL CONCEPTUALISATION .......................................................................................... 15 4.2 MODEL CONSTRUCTION .................................................................................................. 16 4.3 MODEL CALIBRATION AND VERIFICATION .......................................................................... 18 4.4 REVIEW OF DRAINAGE NETWORK ..................................................................................... 18 4.5 INUNDATION MAPPING..................................................................................................... 19
5 Option Development and Analysis ....................................................................................... 21 5.1 OPTIONS ........................................................................................................................ 21 5.2 ECONOMIC ANALYSIS ...................................................................................................... 22
5.2.1 Assessment of damages ................................................................................ 22 5.2.2 Assessment of costs ...................................................................................... 24 5.2.3 Benefit cost ratio ............................................................................................. 24
6 Flood Forecasting and Warning ........................................................................................... 26 6.1 INTRODUCTION............................................................................................................... 26 6.2 ASSESSMENT OF REQUIREMENTS .................................................................................... 26 6.3 REGULATORY AND INSTITUTIONAL FRAMEWORK ............................................................... 28 6.4 FLOOD EARLY WARNING SYSTEM (FEWS) SCOTLAND ....................................................... 28 6.5 HYDROMETRIC DATA AVAILABILITY ................................................................................... 29
Langholm Flood Risk Assessment
IBE0584/Apr2017 ii Rev 4
6.5.1 Raingauge data .............................................................................................. 29 6.5.2 Rainfall radar data .......................................................................................... 29 6.5.3 River flow and level data ................................................................................ 30 6.5.4 Catchment and river models .......................................................................... 31
6.6 PRELIMINARY DESIGN ..................................................................................................... 31 6.6.1 Likely achievable lead-times .......................................................................... 32 6.6.2 Implications of infrequent flood events ........................................................... 33
6.7 IMPLEMENTATION ACTIVITIES AND COSTS ......................................................................... 34 7 Gravel Berm Assessment ...................................................................................................... 40 8 Conclusions and Recommendations ................................................................................... 41 9 References .............................................................................................................................. 43
Langholm Flood Risk Assessment
IBE0584/Apr2017 iii Rev 4
LIST OF FIGURES
Figure 1.1: Location of Langholm ........................................................................................................... 1
Figure 2.1: Annual maximum flow data at Canonbie gauging station ..................................................... 5
Figure 2.2: Historic Flooding Incidents ................................................................................................... 7
Figure 3.1: Catchment Boundaries ......................................................................................................... 9
Figure 3.2: Flood frequency curves River Esk (upstream of Ewes Water confluence), Ewes Water and Wauchope Water ................................................................................................................................... 13
Figure 4.1: Extent of Hydraulic Model .................................................................................................. 17
Figure 6.1: Hydrometric Data & Indicative Forecasting Model Components ....................................... 35
Figure 6.2 Typical Property Entrance at Waterside .............................................................................. 36
Figure 6.3 Typical Properties at Waterside ........................................................................................... 36
Figure 6.4 Pedestrian Gate at Mill (Note Gap below door) ................................................................... 37
Figure 6.5 View from River towards Caroline Street ............................................................................. 37
Figure 6.6 Access Gate at Elizabeth Street .......................................................................................... 38
Figure 6.7 Wall at George Street ........................................................................................................... 38
Figure 6.8 Unsealed Drainage Outlet at George Street ........................................................................ 39
Figure 6.9 Open access to river at George Street ................................................................................ 39
Langholm Flood Risk Assessment
IBE0584/Apr2017 iv Rev 4
LIST OF TABLES Figure 1.1: Location of Langholm ........................................................................................................... 1
Figure 2.1: Annual maximum flow data at Canonbie gauging station ..................................................... 5
Figure 2.2: Historic Flooding Incidents ................................................................................................... 7
Figure 3.1: Catchment Boundaries ......................................................................................................... 9
Figure 3.2: Flood frequency curves River Esk (upstream of Ewes Water confluence), Ewes Water and Wauchope Water ................................................................................................................................... 13
Figure 4.1: Extent of Hydraulic Model .................................................................................................. 17
Figure 6.1: Hydrometric Data & Indicative Forecasting Model Components ....................................... 35
Figure 6.2 Typical Property Entrance at Waterside .............................................................................. 36
Figure 6.3 Typical Properties at Waterside ........................................................................................... 36
Figure 6.4 Pedestrian Gate at Mill (Note Gap below door) ................................................................... 37
Figure 6.5 View from River towards Caroline Street ............................................................................. 37
Figure 6.6 Access Gate at Elizabeth Street .......................................................................................... 38
Figure 6.7 Wall at George Street ........................................................................................................... 38
Figure 6.8 Unsealed Drainage Outlet at George Street ........................................................................ 39
Figure 6.9 Open access to river at George Street ................................................................................ 39
Langholm Flood Risk Assessment
IBE0584/Apr2017 v Rev 4
APPENDICES
APPENDIX A Historic Flooding
APPENDIX B Pooling Group Details
APPENDIX C Flood Maps
APPENDIX D Options 2-4
APPENDIX E GIS Database of Assets
APPENDIX F Intangible Costs
APPENDIX G Average Annual Damage Assessment
APPENDIX H Present Value Damages
APPENDIX I Damages & Defence Costs Assumptions
APPENDIX J Detailed Costs of Each Option
APPENDIX K Present Value Costs
APPENDIX L Optimism Bias Calculation
APPENDIX M Summary of Benefit/Cost Calculations
APPENDIX N Gravel Berm Assessment
Langholm Flood Risk Assessment
IBE0584/Apr2017 1 Rev 4
1 INTRODUCTION
1.1 BACKGROUND
In 2007, Dumfries & Galloway Council commissioned a Strategic Flood Risk Assessment Study to
gain a better understanding of the risk of flooding and potential socio-economic consequences across
the entire council area. This study used the then recently published indicative River & Coastal Flood
Map to identify properties at risk of flooding and estimate the long-term economic costs of flooding.
Within the Dumfries & Galloway Council area, a total of 4,537 properties were estimated to be prone to
flooding (AEP 0.5%) with long-term Net Present Costs of some £875million.
Langholm is located at the confluence of three rivers the River Esk, Wauchope Water and Ewes
Water. The River Esk and the Ewes Water have their confluence to the north of Langholm, and the
Wauchope Water joining the main watercourse, from a south westerly direction, in the centre of the
town. Figure 1.1 provides a plan of the area indicating the respective routes of the three watercourses.
Figure 1.1: Location of Langholm
Langholm Flood Risk Assessment
IBE0584/Apr2017 2 Rev 4
According to the Strategic Flood Risk Assessment, Langholm has more properties at risk of flooding
than any other town in Dumfries & Galloway, with 524 properties within the 0.5% AEP flood inundation
zone. The associated long-term Net Present Costs are approximately £100million and are also the
highest within the council area. In response to this analysis Dumfries and Galloway Council appointed
RPS to undertake a detailed Flood Risk Assessment of the urban area of Langholm.
1.2 AIMS AND SCOPE
To accurately define the flood risk to the area and determine whether a feasible flood alleviation
scheme could be developed the study incorporated the following work and analysis:
Review of historical flooding incidents in Langholm
Hydrological analysis of the River Esk, Wauchope and Ewes Water
Detailed 1D/2D hydraulic modelling of 1:10, 1:25, 1:50, 1:100, 1:200 and 1:1,000 year return
periods and assessment of climate change impact
Assessment on the impact of flooding on the urban drainage network
Revised flood extent and depth mapping for a range of modelled return periods
Outline Design and assessment of feasible flood protection options to alleviate the risk of
flooding.
Economic Analysis of the proposed flood alleviation scheme in accordance with the Green
Book Methodology
Assessment for the potential for flood forecasting in Langholm
Assessment of the benefits or otherwise in removing the substantial gravel berms deposited
within Langholm.
Langholm Flood Risk Assessment
IBE0584/Apr2017 3 Rev 4
2 DATA COLLECTION
2.1 METHODOLOGY
Following the initial start up meeting, RPS requested from Dumfries and Galloway Council all
information currently held that was useful in the execution of this project. This included:
LiDAR data
OS mapping of the area including 1:50,000, 1: 10,000 and 1: 2,500 mapping.
Scottish Water GIS Data for the urban network within Langholm
Briefing note on Gravel Extraction 2004.
Scottish executive IFSAR/Intermap DGM Data
Any drainage records/data held by Dumfries and Galloway Council
RPS had already retrieved the following documents from the Dumfries and Galloway Council website
which were utilised at various stages of the project:
Biennial Flooding Reports
Strategic Flood Risk Appraisal (JBA 2007)
Current Local Plan
New Local Development Plan
Mastermap building polygon data was also requested to enable quick and accurate representation of
flood plain properties within the 2D domain of the computational model for use in the Benefit Cost
analysis.
2.2 TOPOGRAPHICAL SURVEY DATA
Following receipt of the above information RPS carried out a detailed walk over survey of the
Langholm area and specifically the following reaches of watercourse:
Wauchope Water - Springhill through to the Esk
Ewes Water - Whitsheils Bridge to the Esk
River Esk- Duchess Bridge through to Skipper’s Bridge
The detailed walk over survey served a variety of purposes including:
Identifying structures and the necessary spacing and locations of cross sections so a detailed
survey specification could be produced.
Langholm Flood Risk Assessment
IBE0584/Apr2017 4 Rev 4
Gaining a thorough understanding of the areas likely to flood based on the strategic flood
map. This was necessary at this stage in order that a specification for a property threshold
survey could be developed. This was subsequently used for completion of the flood damage
assessment later in the project.
Assessment of roughness values within the watercourses for hydraulic modelling purposes.
Identify any specific health and safety risks which needed to be included within the survey
specification.
Subsequent to the walk over survey RPS produced a survey specification based on the “The EA
National Standard Contract for & Specification for Surveying Services v3”, requesting the following
data sets:
required spacing of river cross sections,
the level of detailed required at each cross section,
flood plain spot heights for checking LiDAR accuracy,
hydraulic structure geometry,
any identified culvert inlet, outlet & manhole details following a review of the Scottish Water
Data.
photographs at each cross section location
AutoCAD drawings of all bridges and hydraulic structures
AutoCAD/geo-referenced drawings of cross section locations.
the data was requested in ASCII (.txt) format to facilitate entry into Infoworks RS1D/2D.
The survey was undertaken by DG Design and Aspect Surveys and was completed in May 2012.
2.3 HYDROLOGICAL DATA
RPS requested from SEPA, data for the Canonbie gauging station and other nearby gauging analysis
which was necessary to undertake the hydrological analysis and flood forecasting feasibility element of
the project. Canonbie Station is located along the River Esk upstream of the confluence of the Liddel
Water, some 12.5 km downstream of Langholm. Annual maximum flow data was provided by SEPA
for the station between 1988 and 2011. RPS supplemented this record with data available from the
HiFlows-UK database (Environment Agency 2011). The resulting series of annual maximum flows is
shown in Figure 2.1 below.
Langholm Flood Risk Assessment
IBE0584/Apr2017 5 Rev 4
0
100
200
300
400
500
600
70019
62
1964
1966
1968
1970
1972
1974
1976
1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
Hydrological year
Annu
al m
axim
um fl
ow (m
³/s)
Annual maximum flow 5-year moving average Linear (Annual maximum flow)
QMED=364m³/s
Figure 2.1: Annual maximum flow data at Canonbie gauging station
The graph shows that over time, there is no strong trend in peak flows. However, there are two periods
with a sequence of high floods: 1964–1968 and 2000–2008.
The five highest floods on record are shown in Table 2.1 below.
Table 2.1: Highest Floods on Record (River Esk at Canonbie)
Date Flow (m3/s) Multiple of QMED
17/02/1997 577 1.59
09/10/1967 571 1.57
12/10/2005 567 1.56
31/10/1997 549 1.51
06/10/1964 539 1.48
2.4 REVIEW OF HISTORIC FLOODING EVENTS
The flood prevention team at Dumfries & Galloway Council maintains a database of flood incidents. In
addition to current flood events directly recorded, the database has been populated with:
incidents reported in the “Biennial Reports” prepared by the Council between 1997 and 2009;
and
records held by SEPA hydrology teams.
As part of this study, RPS has reviewed the records related to flooding incidents near Langholm.
These records are shown on a map in Figure 2.2.
Langholm Flood Risk Assessment
IBE0584/Apr2017 6 Rev 4
RPS undertook a literature and media search to identify other flood incidents not currently included in
the database. As part of the research, RPS interviewed Mr R. Harling, resident of 10 George Street.
Mr Harling provided some photographs taken during the flood event of 31 October 1977 and these are
shown in Appendix A. Key flood incidents identified are shown in Table 2.2 and are also included in
Figure 2.2.
Table 2.2: Additional Flood Incidents
Date Scale or magnitude Sources November 1898 Possibly the highest known
flood on the River Esk. Peak river levels were reported as a “few feet” below the arches of the Telford Road bridge
Eskdale & Liddelsdale Advertiser (2010)
31 October 1977 Highest flow since at least 1960 and possibly much longer. Walls adjacent to George Street and Elizabeth Street were overtopped
SEPA river flow data at Canonbie Photos by resident R. Harling (see Appendix A)
8 January 2005 High flow event, water levels reported to reach up to 100 mm below top of wall along George Street and Elizabeth Street
SEPA river flow data at Canonbie Anecdotal evidence by resident R. Harling
19 November 2009 Highest flows during the last 2 years. No flooding occurred within Langholm but river levels reached near the top of the walls along George Street and Elizabeth Street. Similar to January 2005 event
SEPA river flow data at Canonbie Anecdotal evidence by resident R. Harling
Of the highest flows at Canonbie gauging station (Table 2.1), there are a number of records for which
no information on flooding or near-flooding can be found at Langholm. Most notably are the highest
and second highest flows during February 1997 and October 1967. One of the reasons could be that
the Canonbie gauging station is located 12.5km downstream of Langholm with one additional (major)
tributary confluence with the River Esk downstream of Langholm. Therefore river flows at Langholm
could have been lower than some other events for which a flood incident was reported. However, it is
likely that when river flows exceeded 500m3/s at Canonbie, water levels at Langholm are within
500mm from the top the walls along George Street and Elizabeth Street
Langholm Flood Risk Assessment
IBE0584/Apr2017 8 Rev 4
3 ASSESSMENT OF RIVER FLOWS
3.1 METHODOLOGY
The assessment of peak river flows and hydrographs follows the methodologies as set out in the Flood
Estimation Handbook (FEH) (Centre for Ecology and Hydrology 2008). The following methodologies
have been used in this study:
1. Statistical method (single site and pooling group approaches) (Robson & Reed 2008)
2. FEH Rainfall-Runoff method (Reed et al. 2008).
Note that the Revitalised FEH rainfall-runoff method has not been used, as this method has not been
validated for Scottish catchments and is therefore currently not accepted by SEPA.
The FEH methods used in the assessment have been undertaken using the FEH CD-ROM 3 (Centre
for Ecology and Hydrology 2009) and WINFAP-FEH 3 (Wallingford HydroSolutions Limited 2009).
3.2 CATCHMENTS
River flows were estimated for the three rivers and associated catchments shown in Table 3.1. The
catchment boundaries are shown in Figure 3.1.
Table 3.1: Flood Estimation Catchments
River Location Drainage area (km2)
Average elevation (mAOD)
Average annual rainfall (mm)
Esk Upstream of Ewes
Water confluence
291 298 1471
Ewes Water At confluence with
River Esk
80 296 1391
Wauchope Water At confluence with
River Esk
41 239 1279
Langholm Flood Risk Assessment
IBE0584/Apr2017 9 Rev 4
Figure 3.1: Catchment Boundaries
3.3 FEH STATISTICAL ANALYSES
3.3.1 QMED estimation
The median annual flood (QMED) for each catchment was estimated initially using FEH catchment
descriptors. This estimate was then further revised using a suitable donor station. The potential donor
stations considered for all three catchments are shown in Table 3.2.
Table 3.2: Potential Donor Stations for QMED Estimation
Location Catchment Area (km2) Comments
River Esk at Canonbie 495 Nearest downstream station River Esk at Netherby 842 Station downstream of Canonbie Ettrick Water at Brockhoperig 38 Upland station north of River Esk
catchment boundary
In this case, all potential donor stations in Table 3.2 result in very similar adjustments to the QMED
based on catchment descriptors. RPS have therefore adopted the gauging station at Canonbie for the
following reasons:
Langholm Flood Risk Assessment
IBE0584/Apr2017 10 Rev 4
The record length at Canonbie is 49 years and up to date annual maximum flow data was
supplied by SEPA for this station. The QMED estimation at this station is therefore highly
reliable.
Canonbie is the nearest downstream station along the River Esk. Using this station ensures
that the estimated QMEDs at Langholm are consistent with observations further downstream.
The QMED estimates for all catchments are shown in Table 3.3 below.
Table 3.3: QMED Estimates
River Location QMED from catchment descriptors (m3/s)
QMED adjusted (m3/s)
River Esk Upstream of Ewes Water
confluence
168 195
Ewes Water At confluence with River Esk 44 51
Wauchope
Water
At confluence with River Esk 32 37
3.3.2 Pooling group development
Pooling groups were constructed for the three catchments in Table 3.1. Each pooling group was
reviewed to remove all stations not suitable for QMED estimation or pooling. Subsequently additional
stations were added to ensure the total record length was at least 500 years.
Each pooling group was then assessed for homogeneity which indicates how hydrologically similar the
pooling group is to the catchment. In line with the recommendations within the FEH, the number of
stations in the pooling group has not been reduced when the group was heterogeneous as it is
statistically more critical to have a total record length of 500 years or more. Instead, the degree of
homogeneity will inform which FEH method (statistical or rainfall-runoff) is adopted.
The degree of homogeneity for each catchment is shown in Table 3.4 below. Full details of the pooling
groups are included in Appendix B.
Langholm Flood Risk Assessment
IBE0584/Apr2017 11 Rev 4
Table 3.4: Pooling Group Characteristics
River Location Number of stations
Total record length (years)
Homogeneity
River Esk Upstream of Ewes
Water confluence
14 516 Acceptable
homogeneous
Ewes Water At confluence with
River Esk
14 523 Strongly
homogeneous
Wauchope Water At confluence with
River Esk
15 525 Heterogeneous
3.3.3 Flood frequency curve estimation
Flood growth curves and frequency curves were constructed for each of the three pooling groups.
Both the Generalised Logistic (GL) and Generalised Extreme Value (GEV) distribution functions
provided a good fit of the River Esk pooling group’s annual maximum flow data. However, the
generalised logistic function results in slightly higher flow rates and has therefore been used in the
assessment. For the other two catchments, only the Generalised Logistic function resulted in an
acceptable fit and has therefore been adopted. Table 3.5 below shows the results for each catchment.
Table 3.5: Pooling Group Results for Selected Probabilities
Annual Exceedence Probability (AEP)
Peak Flow (m3/s)
River Esk Ewes Water Wauchope Water
50% (QMED) 195 51 37
1% 406 102 81
0.5% 455 112 91
0.2% 528 127 105
0.1% 591 138 118
3.3.4 FEH Rainfall-Runoff method
An FEH Rainfall-Runoff model was set up for each of the catchments as an alternative method of
calculating peak flows. Additionally, the rainfall-runoff model can also be used to create a flood
hydrograph matching the peak flows estimated using the statistical method.
The model parameters were taken from the catchment descriptors for each catchment. Subsequently,
the storm duration was varied to identify the critical storm duration for the catchment.
Langholm Flood Risk Assessment
IBE0584/Apr2017 12 Rev 4
The results of the analyses are shown in Table 3.6.
Table 3.6: Rainfall-Runoff Results for Selected Probabilities
Annual Exceedance Probability
(AEP)
River Esk Ewes Water Wauchope Water Storm
duration (hrs)
Peak flow (m3/s)
Storm duration
(hrs)
Peak flow (m3/s)
Storm duration
(hrs)
Peak flow (m3/s)
50%
(QMED)
25 124 9.5 40 9.5 22
1%
21
354 8.5 128
7.5
71
0.5% 412
7.5
151 84
0.2% 497 189 105
0.1% 19 578 224 124
3.3.5 Adopted flood frequency curves and hydrographs
There are discrepancies between the results from the pooling group analysis (Table 3.5) and the FEH
rainfall-runoff method (Table 3.6). For each catchment, therefore the most applicable method based
on FEH guidance has been utilised. Relevant criteria are whether the pooling group is homogeneous
and, to some extent, which method results in the highest flow estimates. Table 3.7 shows the method
adopted for each catchment.
For a given catchment, the difference between the two methods is an indicator of the uncertainty
associated with the flow estimates. Although this only applies to some extent— both methods share
some assumptions as well as input data— it provides a meaningful indicator of the reliability of the
estimates. Therefore the percentage difference between the two methods has been calculated for one
of the key annual exceedance probabilities, 0.5% (see Table 3.7).
Table 3.7: Method Adopted for Each Catchment
River Adopted Method Justification Percentage difference for 0.5% AEP
River Esk Pooling group Pooling group is acceptably homogeneous and also results in higher flows than rainfall-runoff method.
-9%
Ewes Water Rainfall-Runoff Pooling group is strongly heterogeneous and results in lower flows than rainfall-runoff method.
-26%
Wauchope Water
Rainfall-Runoff Pooling group is heterogeneous. Rainfall-runoff method results in similar, although slightly lower flows than rainfall-runoff method up to the 0.5% AEP event.
8%
Langholm Flood Risk Assessment
IBE0584/Apr2017 13 Rev 4
The final adopted flow rates for each catchment are shown in Table 3.8 and Figure 3.2.
Table 3.8: Adopted Peak Flows
Annual Exceedance Probability (AEP)
Peak Flow (m3/s) River Esk Ewes Water Wauchope Water
50% (QMED) 195 40 22
20% 243 54 30
10% 277 72 40
4% 324 92 51
2% 363 110 61
1% 406 128 71
0.5% 455 151 84
0.2% 528 189 105
0.1% 591 224 124
0
100
200
300
400
500
600
0.1%1.0%10.0%100.0%Annual exceedance probability (AEP)
Peak
flow
(m³/s
)
River Esk Ewes Water Wauchope Water
Figure 3.2: Flood frequency curves River Esk (upstream of Ewes Water confluence), Ewes
Water and Wauchope Water
Langholm Flood Risk Assessment
IBE0584/Apr2017 14 Rev 4
3.4 CLIMATE CHANGE PROJECTIONS
Climate change projections indicate a likely increase of precipitation during the winter season and high
rainfall events (Defra 2010). This could potentially result in an increase in river flood flows.
In this assessment, RPS has taken the impact as a 20% increase of present day flow rates by the
2080s in line with Dumfries & Galloway Council guidance (2007) and that of SEPA.
Note that the “present day” flow estimates presented above theoretically represent the period between
1960 and 2010 approximately as this assessment is based on data collected during this period.
Langholm Flood Risk Assessment
IBE0584/Apr2017 15 Rev 4
4 ASSESSMENT OF FLOOD LEVELS
4.1 MODEL CONCEPTUALISATION
For this project RPS used Infoworks ICM to undertake the numerical modelling of the three
watercourses in the vicinity of Langholm. Infoworks ICM is an integrated hydrological & hydraulic
modelling package developed by Innovyze. It incorporates the well established Infoworks CS
hydraulic simulation engine, 2D capabilities and the functionality of a GIS database management
system. InfoWorks ICM includes full solution modelling of open channels, below ground drainage
networks, floodplains, embankments & hydraulic structures. Additionally, the 2-dimensional areas
within Infoworks ICM are modelled through a triangular flexible mesh which allows for high levels of
detail in specific areas (for example at river banks and around buildings) and a broader approach in
other areas (for example open floodplains). This can give better results compared with a rectangular
grid approach utilised in some other packages.
RPS constructed a 1D in bank and 2D out of bank InfoWorks ICM model for the reaches of the three
rivers as follows:
Wauchope Water – Springhill through to the Esk
Ewes Water - Whitsheils Bridge to the Esk
River Esk- Duchess Bridge through to Skipper’s Bridge
During a site visit undertaken by RPS it was established that the channel immediately upstream of the
Skipper’s Bridge is a relatively steep reach of the Esk. Subsequently even if the bridge acted as a
control point during an extreme event it is extremely unlikely to have a backwater effect on the flood
levels in Langholm. RPS therefore determined that just downstream of Skipper’s Bridge would be a
suitable point for the downstream boundary of the numerical river model.
The model developed provided river flow and water level estimates sufficiently accurate for:
Assessing the impact of proposed flood risk management options
updating SEPA’s Indicative River & Coastal Flood Map;
providing real-time river level forecasts; and
applications for CAR licences, if required.
Langholm Flood Risk Assessment
IBE0584/Apr2017 16 Rev 4
4.2 MODEL CONSTRUCTION
The in-bank portion of the river models was defined from cross-sectional data, with LIDAR data being
used for the floodplain. Bridge, weir, control & defence structures on the river were defined using
survey data of their geometry. Calibration coefficients for structures were left as default in line with
recommended practice where no specific afflux information is available.
Upstream boundary conditions & input hydrographs for the model were provided from the Hydrological
Assessment. Downstream boundary conditions for the River Esk were defined by a normal depth
boundary downstream of the Skipper’s Bridge thereby ensuring that any backwater effect from this
structure was accounted for in the model. The downstream boundary conditions for the Ewes Water
and the Wauchope were defined by the River Esk at their confluence.
1D modelling used either extended cross sections and/or ‘spills’ and storage areas to ensure the full
floodplain extent was incorporated in the model and all areas of flood storage were included. For
1D/2D modelling, RPS constructed a 1D in channel model combined with a 2D flood plain model
which provides an accurate assessment of both the in channel flow regime and floodplain flow paths.
For an accurate assessment of 2D flow paths the bare earth DTM data was used within the modelling
package to generate the computational mesh, the mesh was then augmented to include buildings and
incidental defences which will affect flow paths. Building footprints were defined by a GIS shape file
which was then used to reduce the conveyance through the building in the 2D mesh. All flood
receptors were contained within the 2D modelling domain with extended 1D sections only used for the
Ewes Water upstream of Whitshiels Bridge and the main River Esk channel downstream of Langholm.
The extent of the integrated hydraulic model of the River Esk, the Ewes Water and the Wauchope
Water near Langholm, developed by RPS is shown in Figure 4.1. This model included a 2-dimensional
hydrodynamic model of the floodplain with a 1-dimensional or integrated model of the river channel,
incorporating all bridges and other hydraulic structures. The maximum mesh size used in the model
was 100m2 (generally this gives an element size of 75m2) which was considered sufficient for
modelling the larger open spaces. Within the urban environment the mesh was refined using building
polygons which force the mesh to define the building outlines and therefore streets with the result that
mesh size in the more urbanised areas ranged between 0.5m2 and 40m2 depending on the width of
streets and density of buildings. A global roughness of 0.06 was applied across the 2D model domain
which although high for streets and roads, gives a better representation of other features in the urban
environment, including vegetation. Similarly within the 1D model a global roughness of 0.06 was
employed on account of the relatively rocky bed and generally lightly vegetated banks.
Langholm Flood Risk Assessment
IBE0584/Apr2017 18 Rev 4
4.3 MODEL CALIBRATION AND VERIFICATION
The computational river models were calibrated by comparing predicted flood levels with field
observations. Historical data including photographs and recorded flood data was used, where
available, during the calibration and verification of the computational model. Any observed flood levels
were used in conjunction with gauging data from the Canonbie Gauging station to estimate the
associated flow and return period at Langholm, the estimated flows were then input to the model and
various parameters adjusted to replicate the observed levels. Anecdotal evidence collected by RPS
from local residents and media was also used to help calibrate and verify the computational models.
The model was also calibrated at low flows to ensure the model provides representative water levels
for a wide range of events.
A key aspect is verification of 2D flow paths within urban areas. After initial model runs were
completed a walk over survey was undertaken to check the accuracy of the predicted flow paths
including ascertaining the impact of incidental defences including walls, bridges and underpasses etc.
Subsequently further modifications are made to the DTM, the model re-run and the process repeated
iteratively until the flood extent is assured. Sensitivity to model roughness was also assessed, indeed
this was one of the principal variables used in the validation process to achieve the best fit with the
anecdotal records of flooding.
The calibrated river models were run to determine water levels for a range of storm events for both the
present day and future scenarios.
4.4 REVIEW OF DRAINAGE NETWORK
From experience RPS recognise that during major fluvial flooding events, urban drainage networks
frequently cannot operate as designed because outfalls to the river can no longer drain under gravity.
This means that rainwater falling behind flood defences can cause storm drainage pipes to surcharge
once capacity within the network is exceeded. This can lead to out of sewer flooding to properties
which may have otherwise been protected from direct fluvial flooding. In addition should sewage or
storm water pumping stations be directly affected by fluvial flooding this can cause an entire network
to surcharge in a relatively short period of time. Pollution of watercourses can also be a major problem
environmentally once sewage networks surcharge.
There is no drainage network model available for Langholm and therefore it is not possible to quantify
the impact of elevated river levels by numerical modelling. Subsequently, RPS have undertaken a
review of the Scottish Water data for the wastewater and drainage network within the vicinity of the
town and cross referenced those areas of the network which are deemed to be protected by defences.
The primary objective of this exercise was to establish the potential for elevated river levels during an
extreme event to have an adverse impact on the ability of the drainage network to function.
Langholm Flood Risk Assessment
IBE0584/Apr2017 19 Rev 4
The review determined that there are no areas within Langholm where the drainage network is
protected by defences. Additionally there was no key infrastructure, such as pumping stations, which
are affected by flooding. In areas where the drainage network is affected by fluvial flooding it was
confirmed that all manholes will be inundated by fluvial flooding either prior to, or at the same time at
which the piped network surcharges. From this high level review it can be concluded that the risk of
flooding in Langholm is not exasperated by the influence of elevated river levels on the drainage
network.
4.5 INUNDATION MAPPING
Currently, flood extent information is available through SEPA’s Indicative River & Coastal Flood Map.
As this map is derived from NextMap DTM data only, in contrast to topographic survey or LiDAR data,
a more accurate flood extent and flood depth map is required to assess the impacts of flooding at
Langholm.
RPS have incorporated the newly acquired survey data and existing LiDAR into the Infoworks
hydraulic model. Due to Infowork’s GIS based approach, this enables us to display and extract flood
extent information without any further post processing. This ensures that all analyses are consistent
and that any spurious flood extent results can be directly addressed in the hydraulic models.
Flood maps have been generated for a range of annual exceedance probabilities (AEP):
1. 50% (1/2)
2. 10% (1/10)
3. 4% (1/25)
4. 2% (1/50)
5. 1% (1/100)
6. 0.5% (1/200)
7. 0.5% (1/200), under climate change conditions
8. 0.1% (1/1000)
Flood maps show the following information:
Potential extent of flood waters (vector polygon data); and
Depth of water (contoured grid data, and/or vector polyline data).
The flood maps show a high level of detail due to the underlying topographic survey data and 2-
dimensional modelling approach. The flood maps are presented in Appendix C. Data has also been
provided in CAD/GIS format to the Dumfries and Galloway Council (AutoCAD 2007 and MapInfo
Langholm Flood Risk Assessment
IBE0584/Apr2017 20 Rev 4
Professional V7) for future use and SEPA (ArcGIS shapefiles) for incorporation into the Indicative
River & Coastal Flood Map.
For the Langholm Flood Risk Assessment, these flood depth and flood extent maps form the basis for
the outline design of a flood protection scheme and the economic assessment of flood risk and the
benefits of such a scheme.
Langholm Flood Risk Assessment
IBE0584/Apr2017 21 Rev 4
5 OPTION DEVELOPMENT AND ANALYSIS
5.1 OPTIONS
In addition to the flood mapping the main output of the Langholm Flood Study is the outline design and
benefit/cost analysis for three flood risk management options. RPS initially considered a wide range of
potential flood risk management options including flood storage, flood plain restoration, flood warning
and flood protection.
The location of Langholm at the confluence of three rivers makes the practical implementation of
effective flood storage difficult. Even when only the River Esk was considered the volume of storage
required to significantly reduce flood levels in Langholm was estimated to significantly exceed the
potential volume available. For example the difference in volume between the 1:200yr and 1:100yr
flood events on the Esk is circa 3 million m3 a volume that isn’t practical to provide within the confined
valley of the Esk.
Flood plain reinstatement was also rejected due to the existing highly developed nature of Langholm
and the tight constraining valley in which it is situated.
Limited modification of the conveyance capacity of the channel by removing the build up of gravel
between the Telford Bridge and the suspension footbridge in Langholm was also considered, see
Chapter 7.
The possibility of implementing a flood warning system, see Chapter 6 was also examined and found
to be viable with opportunity to create a system with sufficient warning time to allow reactive measures
to be implemented, and when combined with some minor improvements to existing structures was
considered to be a potential option.
However the RPS review of flood risk management options concluded that the only feasible means of
preventing flooding in Langholm during high return period events was the provision of hard defences.
The defence structures required for three different scenarios of flood protection- 1:25, 1:50 and 1:200
year return periods, were therefore identified and taken forward for cost/benefit analysis.
Hard defences include the construction of new flood walls or embankments and/or the modification of
existing flood walls to the required structural standard and level of protection. Where possible hard
defences should be set back from the channel banks to allow space for flood waters and reduce the
impact of the flood defence scheme on water levels upstream and downstream of the proposed
defence location. Setting defences back from the channel also improves access to rivers and helps
minimise the visual impact of a flood defence scheme. The choice of flood defence structure (i.e. flood
Langholm Flood Risk Assessment
IBE0584/Apr2017 22 Rev 4
wall, flood embankment, etc.) along with the alignment of defences is based on space constraints,
visual impact and the results of the hydraulic modelling of options.
The do-nothing scenario must also be considered in all option appraisals as the base case against
which other options are compared. The base case should generally be the ‘status quo’ option, which
should represent the genuine minimum input necessary to maintain services at, or as close as
possible to, their current level. In this scenario no action is taken to sustain, maintain or improve
existing flood defences. If no works were undertaken, the threat of overtopping of the banks of the
River Esk would remain resulting in the possibility of frequent flooding damage to property in addition
to causing considerable anxiety to local residents.
The options taken forward for analysis were therefore:
Option1- Do Nothing
Option 2- Hard defences to protect against 0.5% AEP flood
Option3- Hard defences to protect against 2% AEP flood
Option 4- Hard defences to protect against 4% AEP flood
The locations of the flood defence structures for Options 2 to 4 are presented in Appendix D, together
with cross-sections through the defences at a number of locations. The maps also highlight the areas
protected by the defences.
5.2 ECONOMIC ANALYSIS
RPS undertook a preliminary benefit-cost analysis to demonstrate the economic case for the identified
options. This involved an assessment of the benefits (i.e. reducing flood impact) and the costs of the
options over a 100 year design life span. This approach ensures that Dumfries and Galloway Council
has a robust economic argument which shows that the preferred option provides best value for money.
This approach ensures a clearly identified audit trail which transparently shows how the preferred
option would be cost-effective and delivers real value for the community of Langholm.
5.2.1 Assessment of damages
The assessment of the benefits of flood protection measures involves quantifying avoided flood
damages over the design life span of the scheme. These avoided flood damages were estimated from
Langholm Flood Risk Assessment
IBE0584/Apr2017 23 Rev 4
the flood inundation maps produced during this project, combined with various spatial data sets of
households, business and other economic “receptors”.
Properties/assets identified as at risk were classified according to The Benefits of Flood and Coastal
Risk Management: A Handbook of Assessment Techniques (Defra, 2013), also known as “The Multi-
Coloured Manual” with property damage figures updated to 2016 values. The Flood Hazard Research
Centre recommends a proportional approach in benefit appraisals. This requires quantifying and
enumerating only those receptors likely to dominate the benefit assessment. While the road network
through Langholm, the monuments and open park areas would be considered assets they are not
likely to dominate the benefit assessment. With this said a review of the appraisal process can be
carried out in order to consider further assets if the resulting benefit cost ratio (BCR) is marginal.
Properties/assets were grouped in the following categories:
Residential Properties – information detailing the house type, finished floor level and nature of risk to
the property will be recorded.
Non-residential Properties (NRP) (commercial/industrial) – A similar database to the residential
properties will be prepared but will include the property floor area.
Other Assets – A monetary value will be assigned to emergency service costs as recommended from
the Flood and Coastal Defence Project Appraisal Guidance.
Intangibles – The resulting benefits from providing a greater standard of protection in terms of stress
and health problems avoided by victims of flooding.
The GIS database showing the classification of properties/assets and depths of flooding for various
return periods is presented in Appendix E.
Flood damage was estimated using standard values for flood depths and resulting damages as set out
in the Multi Coloured Manual. The values used for the damage assessment are representative of 2016
prices, and therefore did not require any adjustment. The prices were capped for each property type
based on data on house prices obtained from Registers of Scotland, and capped for non-residential
properties using data on rates obtained from Scottish Assessors Association. Damage values were
calculated for as many of the assets identified as being at risk from flooding as possible in order to
derive an overall estimate of the potential damage. Emergency costs were derived as a percentage of
the residential property damages.
Langholm Flood Risk Assessment
IBE0584/Apr2017 24 Rev 4
The intangible costs have been calculated based on FCDPAG 3 Supplementary Note: Reflecting
socio-economic equality in appraisal and appraisal of human related intangible impacts of flooding.
The results of these calculations are presented in Appendix F.
The results of the average annual damage assessment for each of the four options are presented in
Appendix G for both residential and industrial/commercial assets. The intangible costs have also been
included. Summaries of the costs are also presented. A figure is also included in Appendix G which
shows individual properties together with the damage figures.
The estimated damages of the scheme over its lifespan were then evaluated in terms of their Net
Present Value. All damages were discounted over the 100 year design lifespan using discount rates
as recommended in The Green Book to determine the present value damages. Full details of this is
presented in Appendix H.
A full list of assumptions used in the calculation of damages can be found in Appendix I.
5.2.2 Assessment of costs
The whole life costs of the options are made up from several components including the initial capital
cost and maintenance costs. The initial capital costs were determined from current market rates and
RPS’ extensive experience of flood alleviation works. RPS works with a local contractor, on a
consultancy basis, to ensure the rates used in the cost assessment are accurate and up to date. To
establish maintenance costs RPS have estimated the frequency of maintenance required and then
worked with Dumfries and Galloway Council to establish costs based on the predicted maintenance
programme.
The detailed costs of each option are presented in Appendix J. These costs were used to calculate the
Present Value costs over the lifetime of the scheme (assumed to be 100 years). Details of this are
presented in Appendix K. An optimism bias of 60% is usually applied to costs at the pre-feasibility
stage, however RPS have reduced this to 56.4% and the reasons for this are presented in Appendix L.
A full list of assumptions used in the calculation of defence costs can be found in Appendix I.
5.2.3 Benefit cost ratio
The costs and benefits as described above are presented in Table 5.1. These values have then been
used to calculate the benefit cost ratio for each option. Full details of the summary are presented in
Appendix M.
Langholm Flood Risk Assessment
IBE0584/Apr2017 25 Rev 4
The table shows that the option with the highest benefit/cost ratio is Option 2, hard defences to protect
against a 0.5% AEP flood.
Table 5.1: Summary of Economic Analysis
COSTS & BENEFITS (£)
Option 1 Do Nothing 2 0.5% AEP 3 2% AEP 4 4% AEP
COSTS:
PV Capital Costs 0 5,090,341 3,180,125 1,865,274
PV Operation & maintenance costs 0 28,813 28,813 28,813
PV Costs 0 5,119,154 3,208,938 1,894,087
Optimism Bias Adjustment 0 2,887,203 1,809,841 1,068,265
TOTAL PV COSTS 0 8,006,356 5,018,778 2,962,351
BENEFITS:
Total Capped PV Damages 14,031,255 3,166,244 8,766,500 11,757,707
Total PV Intangible Benefits - 721,057 106,462 2,504
Total Capped PV Benefits 0 11,586,068 5,371,217 2,276,052
DECISION MAKING CRITERIA:
BENEFIT/COST RATIO - 1.45 1.07 0.77
Langholm Flood Risk Assessment
IBE0584/Aug2016 26 Rev 3
6 FLOOD FORECASTING AND WARNING
A new flood warning scheme for the River Esk is to be launched by SEPA in March 2017. The scheme
has the potential to benefit 751 properties in Langholm from advance notice of flooding, giving
communities and business time to take action to reduce the damage and disruption that flooding can
cause. This section has been retained as it was part of the August 2013
6.1 INTRODUCTION
As part of this flood study, a range of flood risk management options were considered, including flood
protection measures and other flood risk reduction measures. A flood warning scheme was considered
as this could reduce the impact of a flood to communities and business. The key benefits of a flood
warning scheme are:
• Individuals and business are able to move valuable items away from a flood risk zone. Flood
warning would increase the time available to move property including cars, furniture,
equipment, items of emotional value etc.
• Emergency services would be able to have adequate resources on stand-by and mobilise
these in a timely manner.
• Temporary flood protection measures (including flood gates, sand bags, pumping equipment,
etc) could be prepared and implemented depending on the expected magnitude and timing of
a flood. This could be relevant both to Dumfries & Galloway Council and emergency
responders (resourcing of staff and equipment) as well as individuals (property level protection
measures).
• Flood forecasting and warning would provide detailed information to inform road closures and
evacuations to minimise risks to human health.
6.2 ASSESSMENT OF REQUIREMENTS
A flood forecasting and warning system for Langholm and the River Esk would need to meet the
following requirements:
• Spatial coverage. Flood warnings are required for all properties and businesses at risk of
flooding from the rivers for flood events up to 0.1% AEP conditions. This includes properties
along the River Esk, the Ewes Water and the Wauchope Water near Langholm. Optionally,
the system should provide warnings for properties in Eskdalemuir along the White Esk and in
Longtown along the River Esk.
• Flood types. The forecasting system would only need to provide warnings for flooding from the
River Esk and its tributaries. Other flood sources, including overland and groundwater flooding
are not included. SEPA currently provides high level flood warnings for different regions in
Langholm Flood Risk Assessment
IBE0584/Apr2017 27 Rev 4
Scotland which includes the risk due to overland runoff. Site-specific flood warning for
overland and groundwater flooding is not considered technically feasible or sufficiently
accurate at the present time.
Forecast accuracy. Flood warnings should be issued based on sufficiently accurate forecasts
of river levels and flood extents within the areas at risk of flooding. The accuracy of any flood
forecasting system is difficult to assess due to the uncertainty in a large number of sub-
systems and input datasets. However, minimum levels of accuracy in water level of 300 mm
are considered sufficient for flood warning purposes. The development of forecasting systems
must consider the likelihood of false alarms versus the likelihood of not predicting floods. Both
should be minimised although in reality some trade-off between the two may be required
depending on the factors contributing to the forecast uncertainty. The required level of
accuracy is also affected by any water level flood warning thresholds and the distance
between the thresholds at a particular location.
Forecasting lead times. Flood warnings will need to be issued at least 3 hours before river
levels reach critical levels. Where possible, forecasting lead times should be more than 3
hours and ideally 6 hours or even longer. Although forecasts can be produced for longer
periods in advance, for example 24 hours, forecasts will become less and less accurate
primarily due to the uncertainty in rainfall predictions.
Operation of flood protection structures. If applicable, flood forecasts should be adequate for
the operation of flood gates and other flood protection temporary works. For example, water
level forecasts at the location of a flood gate must be timely and sufficiently accurate to enable
a timely closure while also avoiding unnecessary closures.
Embedded in existing structures. Where possible, the forecasting and warning system should
be integrated in existing organisational and technical structures. This is to prevent
unnecessary duplication of efforts, minimise costs and maximise the potential for
improvements and lessons learnt from an integrated approach. For example, both the Met
Office and SEPA run various forecasting and warning schemes across Scotland which may be
suitable for providing flood warnings in Langholm.
System improvements. The system should be relatively easy to adapt and improve depending
on changing needs. Additionally, it should be possible to integrated newly acquired data and
improved modelling techniques without a complete re-development of the system.
Flood warnings dissemination. Flood warnings should be issued to Category 1 and 2
responders (including emergency services, Dumfries & Galloway Council and transport and
utility companies). Additionally, residents and business should be able to receive flood
warnings directly.
Community acceptance. The flood warning system should be accepted and supported by the
local community, including residents, businesses and others community groups. A widely
accepted and well communicated flood warning system could increase the preparedness for
flooding and resilience during and after a flood.
Langholm Flood Risk Assessment
IBE0584/Apr2017 28 Rev 4
6.3 REGULATORY AND INSTITUTIONAL FRAMEWORK
In Scotland, flood risk management is undertaken by a number of authorities and public agencies.
While legislation and key guidance is provided by the Scottish Government, other duties are devolved
to Local Authorities, SEPA and emergency services.
SEPA has provided flood warning and forecasting services since the agency was established in 1996.
Over the last decade, however, it has expanded its flood warning services, including the development
of a hydrometric network and real-time flood forecasting modelling.
SEPA’s role as a flood warning authority was formalised with the Flood Risk Management (Scotland)
Act in 2009. The agency has now a statutory duty in providing flood warning and forecasting services.
Implementation of a river and coastal flood forecasting software framework, “Flood Early
Warning System (FEWS) Scotland” (see next section).
Implementation of a flood warning dissemination programme, “Flood Warning Direct”.
Implementation of a joint SEPA and Met Office flood forecasting service covering all areas in
Scotland, “Scottish Flood Forecasting Service”.
Flood emergency response is a joint responsibility between SEPA and other Category 1 and 2
Responders (including Local Authorities, police and fire & rescue services). All Category 1
Responders have direct access to SEPA’s and the Met Office’s flood forecasts allowing for a timely
and targeted incident management. Local residents and business also can sign-up to receive flood
warnings through the Flood Warning Direct service.
6.4 FLOOD EARLY WARNING SYSTEM (FEWS) SCOTLAND
In 2006, SEPA implemented a real-time flood forecasting platform known as the “Flood Early Warning
System (FEWS) Scotland”. Initially, the platform was developed to integrate real-time hydrometric
data, hydrological models and hydraulic models for the Rivers Clyde, Kelvin and Irvine. Since then the
system has expanded and currently includes hydrometric data from all of SEPA’s telemetered
hydrometric stations and forecasting models for rivers in Glasgow, Edinburgh, Aberdeenshire and
Moray. Additionally, tidal forecasts are available within the system for key locations along the Scottish
coast.
FEWS Scotland is an implementation of the Delft-FEWS software by Deltares. Delft-FEWS is based
on “open” software principles and standards and allows, in principle, any dataset, model or reporting
method to be integrated. FEWS Scotland is linked with SEPA’s hydrometric telemetry system
(raingauge, river level and river flow data) and also receives Met Office radar rainfall data (actuals and
forecasts). These data are automatically fed into a range of hydrological and hydraulic model which
Langholm Flood Risk Assessment
IBE0584/Apr2017 29 Rev 4
are run automatically or when initiated by the user. Models used within FEWS Scotland include
primarily Probability Distributed Model (PDM) rainfall-runoff models, ISIS river hydraulic models and
Delft-3D Flow estuary models. Forecasts can be readily interpreted by SEPA’s flood warning duty
officers to prepare and issue flood warnings. Additionally, Category 1 and 2 responders have direct
access to the forecasts through web-based reports.
6.5 HYDROMETRIC DATA AVAILABILITY
To assess the feasibility of a flood warning scheme for the Langholm area, we have assessed the
extent of the existing hydrometric network. Relevant data include rainfall (raingauge and radar), river
levels and river flows.
6.5.1 Raingauge data
For flood warning we assume that rainfall data would be used from SEPA’s network of raingauges
only. Although the Met Office also operates a large number of raingauges, these are not considered as
these are not directly integrated with SEPA’s telemetry system. All nearby raingauges are shown in
Table 6.1 below. The locations of the raingauges are also shown Figure 6.1.
Table 6.1: Overview of nearby SEPA and Met Office raingauges
Location Operator Easting (m) Northing (m) Approximate elevation (mAOD)
Telemetry
Braidlie SEPA 347670 596673 190 yes
Solway Bank SEPA 330717 577413 130 yes
Eskdalemuir Observatory
Met Office
323502 602731 240 not in SEPA systems
6.5.2 Rainfall radar data
Weather radar data is available from a number of radar stations across Scotland. The nearest radars
are shown in Table 6.2 below. Note that although these stations are operated by the Met Office, the
data from these stations is currently available within FEWS Scotland.
Langholm Flood Risk Assessment
IBE0584/Apr2017 30 Rev 4
Table 6.2 suggests that the radars are too far from the catchment to provide detailed rainfall data. At a
distance of more than 75 to 100 km the radar resolution is reduced to 5 km. Typically for flood
forecasting radar data with a resolution of 2 km or 1 km preferably is required.
Table 6.2: Nearest MetOffice rainfall radar locations
Location Easting Northing Distance to Langholm
Comments
Holehead 261790 682835 120 km Radar resolution at this distance is 5 km which may not be sufficiently accurate for flood forecasting Munduff Hill 318820 703225 120 km
High Moorsley
433873 545572 105 km
6.5.3 River flow and level data
There are currently two river gauging stations within the River Esk catchment. Key details for these
stations are shown in Table 6.3. The locations of the gauging stations are also shown Figure 6.1.
Table 6.3: River gauging stations information
Station location NGR Relation to required flood warning locations
Flow rating information
River Esk at Canonbie
339695, 575108
12 km downstream of Langholm
9 km upstream of Longtown
Natural channel hydraulic control. The river bed is thought to be eroding, however, and the station’s rating curves has been reviewed twice since the start of the records in 1962 (Environment Agency, 2011). Spot gaugings have been taken up to the median annual flood (QMED) approximately which indicates that high flow estimates may be inaccurate.
Liddel Water at Rowanburnfoot
341450, 575950
Velocity-area station on straight gravel bedded reach. High flows may bypass the station and are not gauged. Spot gaugings have been taken up to 0.7 × QMED which indicates that high flow estimates may be inaccurate.
Langholm Flood Risk Assessment
IBE0584/Apr2017 31 Rev 4
Table 6.3 indicates that the existing river gauging stations could be used for flood warning at
Longtown. The stations have little benefit for flood warning at Langholm as they are located
downstream of the town.
6.5.4 Catchment and river models
As far as we are aware, no hydrological or hydraulic models of the River Esk catchment have been
previously been prepared for or made available to Dumfries & Galloway Council or SEPA.
As part of the current study, a detailed integrated 1D-2D hydrodynamic models has been developed
for the River Esk, the Ewes Water and the Wauchope Water at Langholm. This model would be
available for flood forecasting. The model would need to be adapted to enable integration into FEWS
Scotland. Alternatively, if unique stage-discharge relationships exist at the locations required for flood
warning, these relationships may be used to provide water level forecasts.
No hydraulic models are presently available for the river reaches at Eskdalemuir and Longtown.
6.6 PRELIMINARY DESIGN
A flood forecasting and warning scheme for Langholm and optionally Eskdalemuir and Longtown
should be integrated into FEWS Scotland and operated by SEPA. The main reasons area:
SEPA is the statutory flood warning authority and operates in partnership with the Met Office
an end-to-end system of hydrometric data collection, real-time flood forecasting and flood
warning.
Hydrometric data and catchment models for the River Esk can be directly integrated in FEWS
Scotland.
In addition to these key reasons, FEWS Scotland and SEPA’s wider flood warning capabilities meet all
requirements as set out above.
To develop a flood forecasting system the existing hydrometric network may need to be expanded.
This could include one or more additional raingauges, and in particular within the upper parts of the
Esk catchment. Additional river flow gauges would be beneficial within the upstream catchments of the
White Esk and Ewes Water. A river level gauge would be beneficial along the River Esk in Langholm.
Langholm Flood Risk Assessment
IBE0584/Apr2017 32 Rev 4
Real time flood forecasting for Langholm (and Eskdalemuir and Longtown) can be achieved through a
combination of hydrological rainfall-runoff models and river hydraulic models.
Rainfall-runoff models would be required to predict the river runoff as a result of current or future
rainfall. Here the Probability Distributed Model is a well-proven modelling packages that can be used
to model the Upper or White Esk, the Ewes Water and the Liddel Water (see Figure 6.1). Both
raingauge data and radar rainfall data could be used for real-time input into the models. Currently
there are no gauging stations in these catchments which could be used for calibration of the models.
Initially, the models could be developed relying on a number of catchment characteristics including
topography and land use. In time, when the hydrometric network is further developed, newly acquired
data can be used to improve the model accuracy by calibration.
Runoff from other sub-catchments could be modelled in real-time by scaling of the hydrographs
modelled through the rainfall-runoff models. Here the most suitable donor catchments and scaling
factors could be estimated by comparison of the modelled flows with recorded flows at the Canonbie
gauging station.
Real-time river hydraulic modelling would be required to forecast the routing of the hydrographs
through the catchment. Here a simple hydraulic routing model can be developed for the River Esk
between Eskdalemuir and Langholm. For the locations where flood warnings are required, river levels
will need to be estimated. This could be achieved either through a hydraulic model run in real-time or
alternatively through an offline assessment of a stage-discharge relationship at these locations. These
relationships could then be used in real-time to estimate levels from river flow forecasts modelled
through the hydraulic routing models. At Langholm, the hydraulic model developed as part of this
study could be used. Some model modifications will be required if the hydraulic model itself needs to
be run in real-time.
Note that all the above forecasting activities, including data collection, hydrological and hydraulic
modelling are all automated and integrated within the FEWS Scotland software.
At each flood warning location, Eskdalemuir, Langholm and Longtown, three flood warning thresholds
will need to be established corresponding with SEPA’s “Flood Alert”, “Flood Warning” and “Severe
Flood Warning” status levels. The thresholds would be based on different water levels and flood
extents at each location. For example a suitable “Flood warning” threshold may be defined at the
threshold at which properties start being inundated.
6.6.1 Likely achievable lead-times
An indication of the likely forecasting lead times that may be achieved, are shown in Table 6.4. Table
6.4 shows that a minimum lead time of 3 hours may be achieved for Langholm. For Eskdalemuir, this
Langholm Flood Risk Assessment
IBE0584/Apr2017 33 Rev 4
minimum lead time may not be possible without relying on rainfall forecasts. Rainfall forecasts would
be required at this location due to the quick responding upper catchment. Operationally, rainfall
forecasts are available through the rainfall radar network. As indicated above, the spatial resolution of
the radar data is however not likely to be sufficiently small to provide accurate rainfall forecasts and
therefore water level forecasts.
Table 6.4: Indicative lead times
Flood warning location
Time-to-peak in rainfall-runoff
modelled catchment (hrs)
Additional flood wave travel time to location (hrs)
Estimated lead-time without rainfall
forecasts (hrs)
Likely to achieve target of 3 hrs?
Eskdalemuir 2.2 0.0 2 Would require rainfall forecasts
Langholm 2.2 4–8 6–10 Yes, target of 6 hrs feasible.
6.6.2 Implications of infrequent flood events
The effectiveness of a flood warning scheme depends highly on the perception and awareness of
residents and businesses. Flood warnings may not be received by all individuals whose properties are
at risk of flooding. If flood warnings are received, some may not take any action or may take ineffective
actions.
In Langholm, flooding of large numbers of properties is not expected for flood magnitudes below the
4% AEP flood conditions. However the rarity of significant flooding, in itself, may not affect how people
respond to a flood warning. More important is the accuracy of the forecasts both in terms of correctly
forecasted flood incidents (hit) and in terms of correctly forecasted absence of significant flooding
(correct negative). It is essential to minimise the number of false alarms as this may lead to a reduced
response to future flood warnings.
Infrequent flooding may, however, require additional awareness raising to ensure that individuals and
businesses are aware of the flood warning scheme and know how to act in the case of a warning
being issued. Additionally, different means of disseminating flood warnings should be considered. For
Langholm Flood Risk Assessment
IBE0584/Apr2017 34 Rev 4
example, in the long term fewer people may actively sign up to receive direct flood warnings and
therefore issuing flood warnings through loudhailers etc may be beneficial.
6.7 IMPLEMENTATION ACTIVITIES
6.7.1 Flood Warning Infrastructure
To implement a flood warning scheme for Langholm, Eskdalemuir and Longtown the following
programmes of work are recommended:
1. Improvements to SEPA’s hydrometric network in the River Esk catchments. This is likely to
require at least one new raingauge and one new river flow gauging station in the upper parts
of the catchment, which would be integrated within the existing network. A rain gauge is
relatively easy to install and maintain. A flow gauging station requires more planning and
design. As a minimum, a cableway and gauging hut with stilling well would need to be
installed, and in some cases also an in-bank flow control structure. Maintenance and ongoing
calibration would need to be undertaken by SEPA’s local hydrology team. Additionally, water
level recorders should be installed at Langholm, Eskdalemuir and Longtown.
2. Development and calibration of real-time rainfall runoff models for the White Esk, Ewes Water
and Liddel Water catchments.
3. Development and calibration of river routing and hydrodynamic models as required between
the rainfall-runoff modelled catchments and flood warning locations. Existing models may be
adapted to be able to run under real-time conditions.
4. Assessment of flood warning thresholds (Flood Alert, Flood Warning and Severe Flood
Warning) at each flood warning location.
5. Integration of all forecasting models into FEWS Scotland.
6. Consultation and awareness raising with stakeholders including local residents and training of
local emergency responders.
It is envisaged that any implementation plan would be lead by SEPA as the flood warning authority
supported by Dumfries and Galloway Council.
Implementation costs would include one-off hydrometric network and model development costs, and
ongoing data collection and maintenance costs. Assuming that the system would be implemented and
owned by SEPA, a large proportion of these costs may be subsumed within current flood warning
operations budgets. Additional costs may include any expansion of the hydrometric network (capital
and maintenance costs) and the development of hydrological and hydraulic models for the Esk
catchment.
Langholm Flood Risk Assessment
IBE0584/Apr2017 35 Rev 4
Further consultation with SEPA would be required to agree the approach to funding and
implementation of a flood warning scheme.
Figure 6.1: Hydrometric Data & Indicative Forecasting Model Components
6.7.2 Flood Resilience Improvements
In addition to consideration of the infrastructure required to implement a flood warning system an
assessment of the potential for minor flood protection improvement works to improve the effectiveness
of flood warning was also undertaken. This involved examining the flood outlines for the more frequent
events (≥4% AEP) to identify those locations with a low flooding threshold. This assessment indicated
that the first onset of property flooding occurs at Langholm Mill upstream of Ewes Bridge during a
1:5yr event however no flooding of properties within the town of Langholm is anticipated until at least
the 1:10yr event. During this event the principal areas of flood impact are along the main River Esk
between the Telford Bridge and the suspension footbridge, principally at Elizabeth Street and George
Street. Flooding was also identified at Francis Street, Mary Street and from Waterside down to the
Wastewater Treatment Works. Some flooding from the Wauchope Water was also identified to the
rear of properties at Caroline Street.
Langholm Flood Risk Assessment
IBE0584/Apr2017 36 Rev 4
A detailed site walkover was undertaken to determine if the indicated flooding was likely to affect
properties and identify the scope for minor works to be undertaken to improve flood protection in these
areas. This identified that whilst gardens on the river side of the road and the road at Mary
Street/Francis Street will flood it is unlikely that water would actually enter the properties. Similarly the
properties at Waterside appear to be sufficiently elevated, Figures 6.2 and 6.3, that inundation would
be restricted to roads, paths and open spaces.
Figure 6.2 Typical Property Entrance at Waterside
Figure 6.3 Typical Properties at Waterside
Langholm Flood Risk Assessment
IBE0584/Apr2017 37 Rev 4
At the Mill on Glenesk Road, some minor works to the rear wall, pointing and the provision of a
watertight flood gate where there is presently a pedestrian gate as shown in Figure 6.4 would improve
flood protection at this site.
Figure 6.4 Pedestrian Gate at Mill (Note Gap below door)
The properties at Caroline Street also appear to be sufficiently elevated as shown in Figure 6.5, that
actual flooding of residential property would not be anticipated, some sheds, garages and gardens
would however be affected.
Figure 6.5 View from River towards Caroline Street
Langholm Flood Risk Assessment
IBE0584/Apr2017 38 Rev 4
At Elizabeth Street the top of the Kerb is generally above the 1:10yr flood level however there are a
few locations, such as that shown in Figure 6.6, where some form of flood gate is required to maintain
this level of protection. Improving the integrity of the flood protection along Elizabeth Street would
protect 3-4 properties from direct flooding during a 1:10yr event. However it should be noted that these
measures would not necessarily provide the normal 300mm freeboard above the flood level.
Figure 6.6 Access Gate at Elizabeth Street
Similarly the wall at George Street, Figure 6.7, should provide protection from at least a 1:10yr flood
event, however the integrity of this defence is compromised by unsealed outlets and river access as
shown in Figures 6.8 and 6.9.
Figure 6.7 Wall at George Street
Langholm Flood Risk Assessment
IBE0584/Apr2017 39 Rev 4
Figure 6.8 Unsealed Drainage Outlet at George Street
Figure 6.9 Open access to river at George Street
Consequently it is recommended that all uncontrolled outlets through the wall are either removed or
fitted with appropriate non-return valves and that the river access is fitted with a suitable flood gate to
maintain the integrity of this structure during high flow events. Completing these works would have the
effect of protecting additional properties from direct flooding during a 1:10yr flood event, although
again the freeboard may be less than 300mm.
Langholm Flood Risk Assessment
IBE0584/Apr2017 40 Rev 4
7 GRAVEL BERM ASSESSMENT
cbec was sub-contracted by RPS to model the River Esk, Ewes Water and Wauchope Water at
Langholm using a fully 2D hydraulic method to investigate potential changes to water level, channel
velocities and bed shear stress resulting from removal and modification of gravel bars upstream and
downstream of the Thomas Telford Road Bridge. The full report of this assessment is contained in
Appendix N with the main conclusions detailed below.
Removal of gravels on the right bank of the Esk upstream of the Telford Road Bridge down to the
confluence with the Wauchope Water has a very slight beneficial effect on water levels through the left
and middle bridge openings, but produces very little difference in levels through the right opening.
Levels upstream of the bridge on the Esk and Ewes Water are reduced slightly, but levels downstream
of the bridge are not significantly changed.
If the right hand bar from the bend on the Esk upstream of the Telford Bridge down to the confluence
of the Wauchope Water is reduced in size by gravel removal, it will likely re-form due to sediment
supply from the Esk and from the large bar at the confluence of the Ewes Water and the Esk. In turn, if
this large bar is removed, it will likely reform from sediment supply from the Ewes Water.
Figure 7.1: Gravel bar, looking upstream
Langholm Flood Risk Assessment
IBE0584/Apr2017 41 Rev 4
8 SUMMARY AND RECOMMENDATIONS
Langholm is located along the River Esk at the confluence of two of its tributaries: the Ewes Water and
the Wauchope Water, therefore Langholm effectively lies at the junction of three rivers, each carrying
significant discharges. The Dumfries & Galloway Council Strategic Flood Risk Appraisal, August 2007,
indicated that Langholm had more properties at risk of flooding than any other town in Dumfries &
Galloway. Consequently the Council commissioned RPS to undertake a detailed assessment of the
flood risk within Langholm and identify potential measures to address this risk.
A computational river model of the River Esk from Duchess Bridge through to Skipper’s Bridge,
including the Wauchope Water from Springhill through to the Esk, and the Ewes Water from Whitsheils
Bridge to the Esk, was developed in order to predict water levels for a range of design storm events.
The model was used to produce accurate flood extent and flood depth maps required to inform and
assessment of the impacts of flooding at Langholm. The results of this detailed assessment indicate
that the flood risk in Langholm (268 properties within the 1:200yr flood extent) is not as great as was
indicated by the earlier Strategic Assessment (524 properties).
Currently, flood extent information for development planning is available for the whole of Scotland
through SEPA’s Indicative River & Coastal Flood Map. Using local topographic surveys and LiDAR
data, RPS has produced more accurate flood extent and flood depth maps for Langholm in order to
understand local flooding mechanisms and provide more accurate estimates flood levels, flood extents
and the number of properties at risk. The information can be used by Dumfries & Galloway Council in
preference to the SEPA Indicative River & Coastal Flood Map outputs to secure floodplains against
future development and provide detailed flood risk advice in relation to Langholm.
The Flood Risk Management (Scotland) Act 2009 requires the production of Flood Risk Management
Plans covering each Local Plan District. Two sets of complementary plans will be produced, Flood
Risk Management Strategies produced by SEPA, and Local Flood Risk Management Plans produced
by lead local authorities, both of which will be at the heart of efforts to tackle flooding in Scotland.
Langholm lies within the Solway Local Plan District and the flood maps produced for the Langholm
Flood Risk Assessment can therefore be used to inform the Local Flood Risk Management Plan for
Solway.
RPS has considered possible flood management options for Langholm and concluded that the only
feasible type of defence is the provision of hard defences. Hard defence schemes were developed for
three different scenarios of flood protection- 1:25, 1:50 and 1:200 year return periods. The financial
feasibility of providing the proposed defence schemes was investigated by a cost benefit analysis and
the option that produced the highest benefit/cost ratio was for hard defences to protect against a
1:200yr or 0.5% AEP flood.
Langholm Flood Risk Assessment
IBE0584/Apr2017 42 Rev 4
As part of the study, RPS also considered the development and implementation of a flood warning
scheme for Langholm and potentially Eskdalemuir and Longtown. This included assessing whether
such a scheme was suitable, in terms of both its likely benefits and technical feasibility. The
programme of works to implement a flood warning scheme was presented, along with a summary of
minor works to enhance protection up to a 1:10yr event. It is envisaged that any implementation plan
for a flood warning system would be lead by SEPA as the flood warning authority, supported by
Dumfries and Galloway Council. Further consultation with SEPA is required to agree the funding
mechanism and implementation approach for a flood warning scheme.
RPS sub-contracted cbec to undertake an assessment of impacts to water levels and velocities from
the removal of gravel bars in the study area. The assessment concluded that there would be minimal
flood risk benefit gained by the removal of the existing gravel bars which are likely to reform due to
sediment from the Ewes Water.
Langholm Flood Risk Assessment
IBE0584/Apr2017 43 Rev 4
9 REFERENCES
Centre for Ecology and Hydrology, 2009. FEH CD-ROM 3, Wallingford.
Centre for Ecology and Hydrology, 2008. Flood estimation handbook (five volumes), Wallingford: Centre for Ecology & Hydrology.
Defra, 2010. UK Climate Projections; User Interface. Available at: http://ukclimateprojections-ui.defra.gov.uk.
Defra, 2010. The Benefits of Flood and Coastal Risk Management: A Handbook of Assessment Techniques.
Defra, 2001. FCDPAG3 Flood and Coastal Defence Project Appraisal Guidance: Economic appraisal.
Defra. FCDPAG3 Supplementary note: Reflecting socio-economic equity in appraisal and appraisal of human related intangible impacts of flooding.
Dumfries & Galloway Council, 2007. Supplementary Planning Guidance No.8; Flooding, Available at: http://www.dumgal.gov.uk/CHttpHandler.ashx?id=380&p=0.
Environment Agency, 2011. HiFlows UK. Available at: http://www.environment-agency.gov.uk/hiflows/91727.aspx.
Eskdale & Liddesdale Advertiser, 2010. Down Memory Lane. Available at: http://www.eladvertiser.co.uk/home/down-memory-lane-1.692983.
HM Treasury. The Green Book, Appraisal & Evaluation in Central Government.
Office for National Statistics, Retail Price Index. Available at http://www.ons.gov.uk.
Reed, D.W. et al., 2008. Restatement and application of the flood studies report rainfall-runoff method. Volume 4 of the Flood Estimation Handbook, Wallingford: Centre for Ecology & Hydrology.
Registers of Scotland, 2012. House Price Statistical Report.
Registers of Scotland, Scotland's House Prices. Available at http://www.eservices.ros.gov.uk.
Robson, A.J. & Reed, D.W., 2008. Statistical procedures for flood frequency estimation. Volume 3 of the Flood Estimation Handbook, Wallingford: Centre for Ecology & Hydrology.
Scottish Assessors Association, Rateable values for non-residential property. Available at http://www.saa.gov.uk.
Wallingford HydroSolutions Limited, 2009. WINFAP-FEH 3, Wallingford.