i. introduction ii. radiation safety department

140
c •• PALISADES NUCLEAR PLANT HEALTH PHYSICS ISSUES STEAM GENERATOR REPLACEMENT PROJECT AGENDA MAY 2, 1990 I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT ORGANIZATION III RADIATION PROTECTION PROGRAM .. A. Program Parameters B. Operational Health Physics c. A LARA D. Traininq E. Radioactive Waste F. Decontamination IV. CONTAINMENT OPENING - HVAC V. OLD S.G. REMOVAL, HANDLING, AND TRANSPORT VI. OLD S.G. STORAGE VII. SELF ASSESSMENT DRY FOEL STORAGE A.,--. 2-

Upload: others

Post on 08-May-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

c

••

PALISADES NUCLEAR PLANT HEALTH PHYSICS ISSUES

STEAM GENERATOR REPLACEMENT PROJECT AGENDA

MAY 2, 1990

I. INTRODUCTION

II. RADIATION SAFETY DEPARTMENT ORGANIZATION

III • RADIATION PROTECTION PROGRAM

.. A. Program Parameters

B. Operational Health Physics

c. A LARA

D. Traininq

E. Radioactive Waste

F. Decontamination

IV. CONTAINMENT OPENING - HVAC

V. OLD S.G. REMOVAL, HANDLING, AND TRANSPORT

VI. OLD S.G. STORAGE

VII. SELF ASSESSMENT

VII~ DRY FOEL STORAGE

A.,--. 2-

Page 2: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

• SGRPOUTAGE

RADIOLOGICAL SERVICES ORGANIZATIONAL CHART ·

04390

...._ _ ____.~ - - - - - ~R~~ - - - - - 4.__ __ .....i RADIOLOGICAL SERVICES PROJECT RADIATION

MANAGER PROTECTION MANAGER

PL.~NT TRAINING PROJECT

I ~---i---CJ ALARA ALARA

COORDINATOR ALARA COORDINATOR I

ENGINEERING

PLANT PROJECT

0-RAnloLoGrc'AL "MATERIAi.ScONiiOi. 0 AD:MINIS1RA TOR

- - - -

AUX CL I SIG~ CTMTCL . CAFCL

Page 3: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• ' PALISADES STEAM GENERATOR REPLACEMENT PROJECT

ASST PROJ MGR JO~IS•

ORGANIZATION

PROJECT MANAGER D W JOOS

..------------..------------+------------,·····························································

ROJECT ADNIN/CONTROL M C SNIEGOWSIU

COST C LARNER••

SCHEDULE M DAVIS•

SCHEDULE TECH F DeBOURBON •

RECORDSIADlllH P LUNDELL•

SECRETARY J VANDENBERG •

OFFICE CLERK J WESNER•

'11lAINING D MORGAN•

'l1lAININO P RIG<rZZI

• CONTRACT PERSONNEL .. PERSONNEL ON LOAN

RAD PROTECTION M L LESINSKI •

Al.ARA ENGINEER K BARR•

RADWASTE ENGINEER M CERNY•

'IBAINING ENGINEER D ELDRIDGE•

RP OPERATIONS D DINGER•

SIU: COORDINATOR JS RIDLEY

Sl'lll COORDINATOR K SCHNEIDER

~

UCENSING ENGR AND CONSTR QUAUTY ASSURANCE J L KUENIN •• W CIARK •• K E MARBAUGH ••

UCENSING ENGINEER QA ENGINEER S SCHOWENWEISNER • P PAPAIOANNOU RC HIRZEL •

MECH ENGR QA ENGINEER T NcELROY • II L HIRZEL •

CIVIL ENGR QA ENGINEER K CHAO•• II R SMITH•

ENGINEER QA ENGINEER G DAVIS•• JD HESS•

ENGINEER QA ENGINEER C JOHNSON•• J E WERNER••

ENGINEER SENIOR OFFICE CLERK H MORGAN• DJ HOFFMAN

'Yl/90

Page 4: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

••

BECl-ITEL ALARA LIAISONS

•SHIFTLY COMMUNICATION AND INFORMATION FOR CONSTRUCTION AND RSD

•PERFORM ALARA COORDINATION MEETINGS FOR UNIQUE WORK EVOLUTIONS

•BPCo CRAFT ALARA ORIENTATION

•INITIAL VvORK PACKAGE INPUT AND REVIEW

•ENSURE SEQUENCE OF EVENTS INCLUDED IN WORK PACKAGES

,.

•PROVIDE INPUT FOR MAN-REM ESTIMATES AND RWP GENERATION

Page 5: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

.,

-

e===::;=~=:":::::::::==:a;::::iENGikEERING J:OR SPRING OUTAGE •

! . I • IENGINE~RING FOlf FALL OUJAGE • I

• I

.. •

. .

1 : IREPLAC~MENT S/li MODIFICATION HO~K : •

--------------,OLD SIG INTERIM STORAGE BLDG CO'NSTRUCTIQN . . r-___. ____ ...,S(CURITY Bl.DG MODincATION~

.__ __ __.!RETAINING :HALL CONSTRUCTION

--------lCONTAINMENT ACCESS FACILIJY CONSTQCTION •

.___ __ _.ISPRlNG OUTAGE (S/G REPLACEMENT PREP HPRK)

::===::=====:::====~AUL ROAD. CONSTRUCTION

..

tSTART F~LL (S/G hEPLACEMtNT) OUT~GE

tF.UEL OFFLbAO COMPl.ETE

tPCS SYST£M RELEA~EO TD CONTRACTOR:

t~UTTING CONTAINM(NT OPENI~G COMPL~TE

• CJRIG:OLD S/G:s OUT oF:coNTAIN~ENT 0

RIG NEM SIG'S IN10 CONTAiNMENT Cl . . • RIG. FITUP. HELO f! NOE PCS. ELBOWS -' ---

INSTALL LINER ~L. PLACE.CONCRET( & INSTAJ_L TENDON I , I

PCS WORK COMPLETE t RELEASED t

• CORE R£LOAD COfl!PLETE O

PERFORk ILRT/C~TMT SIT .c:J

REACTOR CRif ICAL o • PLANT ON LINE t . .

PALIS DES STEAM GENERATOR REPLACEMENT.PROJECT .._ ___________ ..__ _________ __._ _ __... ________ ...:...., ___ '"'"3.11t i ef I

. I I

Page 6: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

t ..

·-

REPLACEMENT STEAM GENERATOR IMPROVEMENTS

•BETTER SLOWDOWN (minimize future sludge lancing)

•BETTER TUBE SUPPORTS (minimize denting) -Horizontal Grid - Egg Crate -Vertical Grid -Batwing Strips

•HANDHOLES

-4, 6 n on lower and intermediate shells for inspecti'ons

•INSPECTION PORTS

· -2, 2" above tubesheet secondary face

•RECIRCULATION AND CHEMICAL CLEANING NOZZLE ~

-For recirculation of secondary water -For circulation of chemical cleaning fluid

•BIGGER MANWAYS

-All 18" inside diameter

•SURFACE PRETREATMENT

Page 7: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

STEAM GENERATOR

REPLACEMENT

PROJECT

RADIATION PROTECTION

PROGRAM ,•

"

Page 8: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

,,..... {

STANDARDS

•:MEET REQUIREl\fENTS OF 10CFR20

•FOLLOW GUIDELINES IN NRC REGULATORY GUIDES 8.8 AND 8.10

•FOLLOW GUIDANCE PROVIDED IN:

-CPCo Radiation .Safety Plan

o Palisades Plant Health Physics procedures

-Project Plan

o Project Radiation Safety Plan o Project specific procedures and plans

Page 9: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

,,-

MANAGEMENT GUIDELINES FOR PROGRAM DEVELOPMENT

•MINIMIZE 11\.fPACT ON PLANT MANPOWER AND FACILITIES

•MINIMIZE CHANGES TO THE EXISTING PROGRAMS

•MAXIMIZE COMMUNICATION AND INTEGRATION OF PROJECT, PLANT AND REPAIR CONTRACTOR

•UTILIZE LESSONS LEARNED FROM PLANT OPERATIONS, PAST SGR PROJECTS, AND PAST NRC CONCERNS

-· ~

•PROVIDE AS A MINIMUM, STANDARD PALISADES RADIOLOGICAL PROTECTION SERVICES

Page 10: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

GOALS

•l\1INIMIZE RADIATION EXPOSURE TO WORKERS AND THE PUBLIC

•MINIMIZE PERSONNEL CONTAMINATIONS

•MINIMIZE SPREAD OF CONTAMINATION

•MINIMIZE GENERATION OF RADIOACTIVE WASTE

•MINIMIZE SCHEDULE IMPACT DUE TO RADIOLOGICAL CONCERNS

•MAXl1\1IZE POSITIVE LONG TERM EFFECTS ON PLANT AND PROGRAMS ,

Page 11: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• MEEllNGS/INTERFACE

•RSD PLANT AND PROJECT

-Weekly RSD Staff -Daily Shift Turnover -Monthly/Weekly Project ALARA Committee -Monthly/Bimonthly SGRP Planning -Weekly Pre-Outage Readiness -Monthly Plant ALARA Committee

•BECHTEL/SGRP

· -Plan of the Day - prior to each shift -Weekly Schedule - 4 week look ahead -Weekly Action Item -Monthly Project Status

•PLANT/SGRP

-Plant Status - each morning or shift -Daily Schedule ... each afternoon

" -Outage Management - weekly

Page 12: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SGRP LESSONS LEARNED

•MOCK-UP TRAINING

-Mock-up on more job evolutions -More aggressive mock-up needed

•CLEANLINESS

-Must be stringently maintained -Internal piping, cavity, work areas, etc. -Cleanliness training required

•RADIOGRAPHY

-Radiography plan drafted for control -Communication between RSD and radiographer

•COMMUNICATIONS

-Wireless headsets -Closed circuit television . ,,

-Portable radios

•DEDICATED TECHNICIAN COVERAGE

" -Workers report to Crewleader prior to entry -Coverage technicians know when workers entering area -Dedicated technician familiar with area work -Maximizes coverage efficiency and consistency

Page 13: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

COOK VS PALISADES

•DUAL UNIT SITE

•PROCEDURE REWRITE

•ONSITE NVLAP ACCREDITATION JN-PROCESS

•RADWASTE FACILITIES NEEDED

•RECENT SWITCH TO OFFSITE LAUNDRY

•SINGLE UNIT SITE

•NO PROCEDURE REWRITE

•ONSITE NVLAP DOSIMETRY AVAILABLE ·

•RADWASTE HANDLING FACILITIES ADEQUATE

•OFFSITE LAUNDRY ALREADY IN USE

.· •

0. AH . f

Page 14: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

- --- -

• • SGRP COMPARISON OF

~

PEAK RADIATION SAFETY STAFFING Point HB DC Palisades* Beach Robinson Cook Contractor House

Health Foreman & Leads 6 3 10 [f_ Physics ·Seniors 32 70 53 99 Juniors & Access 32 33 41 24 Control

Totals 70' 106 . 104 138** (103)

Dosimetry Technicians 15 4 3 Clerks 36 2 8

Totals 36 17 15** (11)

Dec on Foremen 4 2 Technicians 52 35 60

Totals 56 37 60**

' (45)

*Projected Numbers-**At peak staffing, 75% will be dedicated to SGRP (#)

.. I

- --- ------ ------------------

Page 15: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• i~i ill iO ~~ ~~ 11 tfl !RD ~~D ~~I lz ~

i;; 8.: 8~ ~ 0 ~

0 Cl c~ ~I= ~

§~ C I I I D

l'CMl-11

MISOUT "'~e ~ ·!ll ... ~ >

a

~ "'

~I -<

I ~I' GJ ~ia I I I I

~ " ,.

l1 I I I I g m! <

llWPWAU. > ...

~u I I I ii I I I I I I I I I ~~

!2g ;1 · -<

.. '

Page 16: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• • SGRP COMPARISONS

' HP PORTABLE SURVEY INSTRUMENTS

Point DC Beach Cook Palisades*

Dose Rate Instruments

R0-2 0 23 25

R0-2A 10 15 12

Teletector 6 10 20

Gamma Survey Instruments 8 10 (15)

Total 24 58 57 (15)

Air Samplers

High-Vol Grab Samplers 7 15 15

Lo-Vol Continuous Monitors 12 17 12

Total ... 19 32 27 '·

*Will be used for SGRP and balance of Plant (emergency use instruments only)

Page 17: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• I '

I ·'

SGRP c·oMPARISONS HEAL TH PHYSICS INSTRUMENTATION

I '· Point DC

I Beach Cook Pa 1i sades ""

Contamination Monitors

PCM-18 0 5 4

Portable Friskers 20 30 49*

Count Room Instruments

Gros~ B-G Counter 3 3 2

Gross 12 Counter 0 0 2

Alpha Scintillator 3 1 2*

Gamma Spectrograph 1 1 2*

Area Radiation Monitors

Remote Monitors 1 4· 4 ..

*Will be used for SG"RP and Balance of Plant <.

Page 18: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• SGRP COMMUNICATIONS

•WIRELESS HEADSETS

-Radiation Safety Technician use

-Reliable communication within containment

oCrewleader to job cov~rage technicians o Between dedicated technicians

-Inside to outside containment communication

o Access control to Crewleader oCount room to job coverage technicians

•CLOSED CffiCUIT TELEVISION (CCTV)

-ALARA tool

-Aids in continuous coverage of high dose jobs· ,·

-Aids in monitoring long term jobs

o Automatic cutting o Automatic welding

•HAND HELD RADIOS

-Communication between BPCo and RSD

, -Necessary for multi:msource radiography

Page 19: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

••

ELECTRONIC DOSI ETRY / WITH COMPUTER INT RFACE

•WHAT IS IT?

" -Secondary dosimeter . -LED displays accumulated dose and dose rate -Accumulated dose and dose rate alarms

•WHAT DOES IT DO?

-Automatically rezeroes -Sets dose alarm from computer margins or def a ult setting

-Sets dose rate alarm from RWP or default setting -Instantly updates MIS computer for personnel dose on entry

-Stores total accumulated dose and highest dose -rate seen

•HOW DOES IT WORK?

-Worker inserts dosimeter into reader . ,.

-Enters SS no. and RWP no. "

•WHY USE ELECTRONIC DOSIMETRY?

"-Alarming capabilities -More easily read than pocket ion chambers -Instant ~omputer updating aids dose tracking and personnel dose reporting ·

-Minimizes dosimeter discrepancies

Page 20: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

AIRBORNE CONTR.OL

• •DECONTAMINATION

-Initial Containment -On-going -Tool(Equipment

•CONTAINMENTS

-Pipe Cutting -Pipe End Decon -Fi ltr ati o n/Venti I ati on

•RESPIRATOR

-Fit Test -MPC Tracking

•AIR SAMPLING

-CAM -Grab

Page 21: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• MAN-REM ESTIMATE METHOD

•CONSTRUCTION MAN-HOURS

•CONSTRUCTION. WORK LOCATIONS

•RADIATION SURVEY DATA FOR LOCATIONS

•WEIGHTING FOR OCCUPANCY IN

-Low Dose -General Area Dose -High Dose

For Each Task

• •WEIGHTING FOR RCA EFFICIENCY

-Dress· In/Out -Respirator -Special Dosimetry . -Tool Checkout

•PLANT HISTORIC DATA

•OTHER SGRPs

•ESTIMATE

..

Page 22: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

••

SGRP

MAN-REM ESTIMATE

CONSTRUCTION SCOPE: 573.7

CPCo SCOPE: 125.5

TOTAL PROJECT: 699.2

, . ...

Page 23: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SGRP MAN-REM ESTIMATE REVISION 1 (4/19/90)

ill.k.

1. Health Physics/Decon

2. Plant Support

3. Construction Opening

4. Rigging and Supports

5. S/G Modifications ..

6. PCS Piping

7. Insulation

8. New Pipe Systems (BD/Recirc)

9. Secondary Piping

• 10. Old S/G Storag~ Facility

11. Instrument Sample System

12. HVAC

13. Scaffold and Tents

14. Temporary Services

15. Project Support (Tours, Inspections, etc.)

16. Testing & Inspection (NOE)

11: Prep Outage 1989

Man-Rem

109

16

5

86

12

171

48

41

10

1

1

8

81

17

58

29

13

Page 24: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

STEAM GENERATOR REPLACEMENT DOSE SUMMARY

PLANT .s.G TOT AL DOSE CBEM)

SURBY-2 3 2141

SURRY-1 3 1758

TURKEY POINT-3 3 2151

TURKEY POINT~4 · 3 1305

~·J-. rQINT BEACH-1 2 576 , 8~

'H 8 ROBINSON-2 3 1206

(:f NDIAN POINT-3 4 541

4 561 DC COOK-2 . ~

PALISADES 2 699 (ESTIMATED)

. "'

• -­a

Page 25: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

TECHNIQUES TO SAVE DOSE

•REDUCE FROM 6 CUT TO 5 CUT METHOD

•PERFORM LOOP CUTS ~VITHOUT REMOVING MANWAYS

•REMOVE ALL PRIMARY COOLANT SEAL FLUSH FILTERS

•PERFORM CUT PIPE END INTERNAL DECON

•CCTV

•SURROGATE TOUR

•MOCK-UP TRAINING

•RSD HEAD SET COMMUNICATIONS SYSTEM

Page 26: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• ALARA REVIEW PROCESS .;..JI;<, ...

)~ ,# •WP&IR

-Bechtel ALARA review -SGRP ALARA review

•FACILITY CHANGE PACKAGE

-CPCo design review -ALARA checklist -CPCo ALARA approval

•RWP

-CPCo RWP ALARA review -CPCo ALARA approval

•PRE-JOB BRIEFING -...

-Lead technician or crewleader -Duty HP, RWP technician or ALARA ..

•IN-PROGRESS AND POST-JOB REVIEWS

-ALARA (SGRP, CPCo)

•LESSONS LEARNED

-ALARA

Page 27: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

-PROJECT SOURCE TERM REDUCTION

DECEMBER '89 SOURCE IDENTIFICATION/ PRIORITIZATION (34)

JANUARY '90 ACTION PLAN TO IMPLEMENT BEST OPTIONS

FEBRUARY '90 SGRP COST/BENEFIT ANALYSIS ON SHARED CHEMICAL DECON OF LETDOWN, REGEN Hx, LETDOWN Hx LOOP

MARCH '90

APRIL '90

. MAY '90

SGRP COST/BENEFIT ON CUT/REMOVE OF FIVE SOURCES, THREE QUALIFIED

WALKDOWNS TO EVALUAT·E UPGRADED SHIELDING FOR SOURCES NOT QUALIFIED FOR REMOVAL

BECHTEL COST/BENEFIT ~OF THE . THREE LINES IDENTIFIED 'f3Y SGRP

Page 28: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

PIPE END DECONTAMINATION •:MECHANICAL DECONTAMINATION

I '

-Grit blast at a 45° angle ' '

-Glass bead for smoothing : -Vacuum and pressure equilization -Closed circuit TV -No damage to base material

•USED SUCCESSFULLY AT:

-IP-3 SGRP -Muhleberg -Obrigheim

•WHEN COMBINED WITH SHIELDING, AVERAGE DOSE REDUCTION FACTOR OF - 20

•ESTIMATED WASTE (if 6 cut method)

-6.6 cf coborundum (grit) -3.6 cf glass beads ,.

-6 small dust cans -3 RBU filters (1 cl)

•NO l\flXED WASTE " .

•DOSES FROM 5000 mRem/hr TO 250 mRem/hr

•PIPE END MACHINING PERFORMED WITHOUT RESPIRATORS

Page 29: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

PCS PIPE END DECONTAMINATION EQUIPMENT

PRESSURE GAGE I

. POSITION OF SPECIMENS DURING TEST

PRESSURE PIPE .

SUCTION PIPE

DECON MANIPULATOR

CLAMPING DEVICE

SEAL DISC

Page 30: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• ALUMINUM OXIDE GRIT BLASTING

PROCESS EQUIPMENT

•RECIRCULATING BLAST UNIT

•MANIPULATOR

•FRONT BOX

•SEAL DISC

•ALUMINUM OXIDE/GLASS BEADS

•CCTV -· .,

Page 31: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

PRIMARY SYSTEM CHEMICAL DECON

•J'NDEPENDENT STUDY

•ESTIMATED COST: $1,650,000.00

•ESTIMATED MAN-REM COST: 30 MAN-REM

•ESTIMATED MAN-REM SAVINGS: 25 MAN-REM

•SCHEDULE REQUIREMENT: 3-5 CRITICAL PATH DAYS

•ADDITIONAL CONSIDERATIONS

-PCS Dam Installation -Core Support Barrel Removal -Disruption of Missie Shield Logistics -Loss of Lay Down Areas -Manways Will Remain On (No Jumps) -Low External Dose Contribution

•RESULTS

-Negative Cost/Benefit " -Negative Schedule Impact

-Negative Logisti.cs

Page 32: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

MINIMIZING CHANNEL· HEAD RADIATION FIELDS

•INDEPENDENT INDUSTRY SURVEY

•AVERAGE. PLANT DOSE RATES:

13 R/hr TUBESHEET 10 R/hr GENERAL AREA

•PALISADES OLD STEAM GENERATORS

5 R/hr TUBESHEET 3.5-5 R/hr GENERAL AREA

•FACTORS FOUND TO MITIGATE RAD FIELDS:

MATERIAL -LOW COBALT CONTENT -TUBES BRIGHT ANNEALE

SURFACE -REDUCED ROUGHNESS -REDUCED PLATEOUT -REDUCED RAD LEVELS

CHEMISTRY -pH 7.1 --LITHIUM 2.2 ppm (MAX) -DISSOLVED 0 2 <5ppb

I'

-HYDROGEN PEROXIDE INJECTION

,-

Page 33: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

SIG SURFACE ENHAN.CEMENT

OBJECTIVE: PROVIDE A UNIFORM MICROSMOOTH SURFACE

•MECHANICALLY CLEAN AND SMOOTH SURFACE

-Brush to remove scale and debris

-Flapper wheel and buff to a smoothness of 40 RMS

•ELECTROCHEMICALLY POLISH TO REMOVE MICRO ROUGHNESS

-Conf arming cathode

-Standard electrolyte and technique

-Rinsing with demin water

-Final smoothness featureless at 1 OOX scanning electron microscope

Page 34: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• SGRP TRAINING

•GENERAL EMPLOYEE TRAINING (GET)

-INPO 87-008 "Guidelines for GET"

-GET updated as necessary for SGRP

•PROJECT ORIENTATION (GET UPDATE)

-SG RP workers currently on-site

-Update on Project specifics

of acilities

oplans and procedures

•CONTRACT TECHNICIANS ... .. -INPO 87-008, "Guidelines for RPT Training"

-Entrance exam for incoming knowledge and skills

-Procedure training and exam

-OJT

-Continuing Training

- - .

Page 35: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SGRP TRAINING (CONTINUED)

•SUPERVISOR ALARA SEMINAR

-BPCo supervision

-Motivational ALARA techniques

-Points out ALARA responsibilities

-Shows causes of unnecessary exposure

-Familiarization with RP paperwork

•MOCK-UP TRAINING

-Required prior to RWP sign-in

-Pipe-end decon

-Machining

-Welding

-Channel head jumps as necessary "

, r

Page 36: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

DECONTAMINATION

•INITIAL CONTAINMENT DECON

-Allows access -Reduces respiratory requirements -Reduces personnel contaminations

•GENERAL AREA DECON

-Maximizes co-nta.mination control -Maximizes productivity -Minimizes protective clothing requirements -Minimizes use of respirators

. -Minimizes personnel contaminations

•SPECJAL DECON REQUIREMENTS

··. ·· -~·- · -Thermal shield

-Liner plate -Steam generators

•CONTRACTOR DECON SERVICES

-Tools and equipment " -Respirators

-Protective clothing

Page 37: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

RADIOACTIVE MATERIALS PROGRAM

•MINIMIZATION OF VOLUME GENERATED

-Prevention of material and equipment from becoming. contaminated

-Pre-job planning, material lists

-Decontamination of materials and equipment

-Re-use of equipment which has been contaminated

•MINIMIZATION OF VOLUME BURIED

"

-Segregation of reusable material which inadvertently ends up in the trash

-State of the art supercompactor

-Vendors available for special requirements

Page 38: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• 0 ....

0 'I

. !

·•

CUBIC FEET THOUSAND

llJ 0

-.J 0

00 0

78.000

.......

....... 0

105,000

en -I m

:D )> )> ~ oQ

)> :E m < )> z m :0 en m )>

-u -t ~ G) m mm -t 0 m :n < 0 z c 0 :D (/)

:;l z E :o ~ -~m 0 -t -u 0- mr ....... en l> ::tw

G)O mm z~ mm :D z )> -t -t -u m :n DO

c.... m 0 -I

Page 39: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

t-w w l..J._

u -OJ :J u

STEAM GENERATOR REPAIR PROJECTS POINT BEACH, COOK AND PALISADES (ESTIMATE)

SGRPs

35,000 ,...----------------------.

30,000

25,000

20,000

15,000

10,000

10,000

5,000

POINT BEACH COOK PALISADES (ESTIMATE)

RADWASTE VOLUME BURIED

·~"' . •,;:-. __ ,.. ...... --

Page 40: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• CONSTRUCTION OPENING

•ORIGINAL CONTAINMENT CONTRUCTION UTILIZED AN OPENING

•OTHER OPERATING FACILITIES EQUIP:MENT HATCHES OPEN TO THE ATMOSPHERE

•SIZE AND LOCATION OF OPENING I I

2.~ • Z"it;

•STEEL AND CONCRETE ..

-Survey and disposition

-Temporary enclosure -HVAC -Local containments and ventilation

I \

\

•ENGINEERING CONTROLS

-Grab samples -CAMs

,-HEPA outlet ...

•WALL REINSTALLATION

•TESTING

Page 41: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

REQUIREMENTS FOR OPENING CONTAINMENT DOOR

•HEALTH PHYSICS NOTIFICATION

-Crew leader stops or limits area jobs with airborne potential

-CAMs operability and source checked

-Grab sample taken prior to opening (not mandatory)

-Grab sampler loaded

-Inner vicinity floor smeared to ensure < lOK dpm/100cm2

•FUEL HANDLING SUSPENDED

•FUEL HANDLING BUILDING VENTILATION EXHAUST IN OPERATION

•CONTAINMENT PURGE SUPPLY FANS TAGGED OFF

•IODINE REMOVAL UNITS OPERABLE

•PERSONNEL AIR LOCK OPERABLE/DOOR NORMALLY CLOSED

•WEATHER CONDITIONS FACTORED INTO DECISION TO PROCEED

f'

Page 42: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

MITIGATION OF RELEASE FROM CONSTRUCTION OPENING

•WHEN REQUIRED

-CAM alarm

-649' G/A air sample result > 25% MPC

•ACTIONS REQUIRED

-Commence air sampling immediately

-Contain source if known

-Activate 12

removal units if 12 present

- -Verify HVAC operability

-Verify in-flow

-Close temporary door if possible (ctuantify release if not possible)

•PRIOR TO NEXT OPENING

-Investigate cause

-Determine future preventive measures

. . . ...... ~,

Page 43: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

STEAM GENERATOR DESCRIPTION

•TWO UNITS

•462 TONS EACH

•60 FEET LONG

•20 FEET IN DIAMETER

• •1718 CURIE CONTENT EACH

•40 mRem/Hr MAXIMUM SURFACE DOSE RATE ESTIMATE (DRY)

"

f' . . '

I

• i I

Page 44: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

RIGGING AND TRANSPORT

•RIGGING INSIDE CONTAINMENT

•RETAINING WALL OUTSIDE CONTAINMENT

•RIGGING OUTSIDE CONTAINMENT

•HAUL ROUTES

•EVENT ANALYSIS

,.

"

. ,....

Page 45: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

·------::BLuE STAR MEMORIAL HIGHWAY

- 6

OUTAGE BUILDING

LEGEND

+ GROUM>Wt:ll

• AIR SN1PLING STATIONS

,A TLD STATIONS

• ...

Page 46: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

EVENT ANALYSIS

•SCENARIO*

-SIG drop outside of containment

-Seal welded nozzle caps come off

•ASSUMPTIONS

-Curie content 1718

-Bre~thing rate from Section C.2.(C) of Regulatory Guide 1~4

-Dose conversion factors from Tables E. 7 to E.10 of Regulatory Guide 1.145

-10% of activity in steam generator is released and 1 % of that r~leased goes airborne

* Present design analysis drop scenario shows that n.a breach of SIG can occur and nn release of radioactivity will occur in case of an accidental drop

"

. . . ----·-~:-.....-··¥-'!*."~

Page 47: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• • , ·EVENT ANALYSIS (CONTINUED)

•CALCULATED DOSE COMPARISON TO IP-3

STEAM GENERATOR WHOLE BODY DOSE DROP LOCATION PALISADES IP-3

(_i....JrJ~ ~ CRITICAL ORGAN DOSE PALISADES IP-3

CONTAINMENT 0. 10 mRem 0.3 mRem 30 mRem 118 mRem

STORAGE FACILITY 0.58 mRem 2.3 mRem 153 mRem 1030 mRem

•10CFR100 GUIDELINE ·

-300 REM TO THYROID OR CRITICAL ORGAN - 25 REM TO WHOLE BODY

NOTE: THE PRESENT DESIGN ANALYSIS DROP SCENARIO SHOWS THAT llil BREACH OF THE STEA~ GENERATOR CAN OCCUR AND llil RELEASE OF ACTIVITY WILL OCCUR IN THE CASE OF AN ACCIDENTAL DROP.

•SITE EMERGENCY PLAN WOULD COVER THE INCIDENT

Page 48: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• T~SFER FOR RECYCLING

•ADV ANT AG·ES

-S/Gs would be immediately and ultimately disposed of

-Burial space would be minimized

•DISADVANTAGES

-High exposl ire rate if not deconned

-Additional time, expense and man-rem if deconned

-Cost, time and man-rem required for shipment

-Many ship:rnents required

-M_any potential accident scenarios would need to be addressed ~ .·

-Potential objections or additional requirements by states traversed ·

-Application of technology to this situation untested

• •· r

Page 49: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

BARGE AND BURY

•ADVANTAGES

-S/Gs would be immediately and ultimately disposed of

-Future uncertain cost increases would be avoided

DISADVANTAGES

-SIG surface exposure rates would be higher than if delayed

-There would be additional man-rem and expense over interim storage

-Potential problems associated with shielding and loading intact S/Gs -·

-Many potential accident scenarios would need to be addressed · . " "

-Site preparations and rigging/loading could negatively impact schedule

-Project schedule delays could· result in storage until • spring

-Uncertainty in ability to bury outside of Michigan could. drastically alter this approach ·

Page 50: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

ON-SITE STORAGE

•ADV ANT AGES

-No credible accident scenario

-Handling is simplified and time required for disposition is reduced ·

-At the end of plant life, the radiological hazard will be greatly reduced (1/10 original in 24 mo. then Tl/2 is 5 .2 yrs)

-Future improvements in technology could be applied

~DISADVANTAGES

;I

-This is an interim solution, final disposition will occur during decommissioning

-Uncertainty in future disposal costs

Page 51: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• STEAM GENERATOR DISPOSAL OPTION COMPARISON .

r •

Page 52: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

'

• FATE OF OTHER REMOVED STEAM GENERATORS

•SURRY (1 & 2)

•H B ROBINSON 2

•POINT BEACH 1

•TURKEY POINT 3 & 4

•INDIAN POINT 3

•DC COOK2

1 SHIPPED FOR STUDY 5 ON-SITE STORAGE

3 ON-SITE STORAGE

2 ON-SITE STORAGE

6 ON-SITE STORAGE

4 ON-SITE STORAGE ..

4 ON-SITE STORAGE

Page 53: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

COMPARISON OF STEAM GENERATOR STORAGE FACILITIES

WALL ROOF EXTERNAL PLANT THICKNESS THICKNESS DOSE RATE

PALISADES 2'-6" 1 I -6" (MIN) <0.5 MR/HR

INDIAN PT 3 3'-0" 1'-6" (MIN) <0.5 MR/HR

DC COOK 2 2 I -6 H 2' -6" < 1.0MR/HR

TURKEY PT 3 & 4 2'-0" 1 I -0" <2.5 MR/HR

PT BEACH 1 2'-0" 2'-0" <2.5 MR/HR

SURRY 1 & 2 3'-0" NOT <0.5 MR/HR AVAILABLE

ROBINSON 2 2'-0" 2'-0" < 1.0MR/HR

Page 54: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

DESIGN PARAMETERS OF PALISADES OLD STEAM GENERATORS

INTERIM STORAGE FACILITY

•LOCATION

-Approximately 2200ft northeast of the containment

•DIMENSION

-Length 129' 4" -Width 29' 0" -Height 28' 9 1/4" (maximum)

•NUMBER OF STEAM GENERATORS

-2

•WALL TIIlCKNESS

-2' 6"

•ROOF TIIlCKNESS

-1' 9" to 2' 1"

" •SURFACE RADIATION LEVEL

-0.S mR/hr on exterior

.,,

Page 55: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• I

• INTERIM STORAGE FACILITY (CONT)

•OFFSITE BOUNDARY

-Van Buren State Park is the closest offsite boundary at 1200 ft north of the facility

•NEAREST ON-SITE STRUCTURE:

-Outage Building at 275 ft away

•LOCKED AND POSTED ACCESS DOOR

•SURVEILLANCE PROGRAM RADIATION, CONTAMINATION

•MAXIMUM ALLOW ABLE BUILDING WALL SURF ACE DOSE RA TE 0.5 mR/Hr

•S/Gs COATED TO SEAL SURFACE.

•CLOSED SUMP -·

•SEALED BUILDING •

•REMOTE SAMPLING PORTS

Page 56: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• ISF OFF-SITE DOSE

•ASSUMPTIONS

-200 mRem/hr SIG dry surface dose rate*

-Right cylinder 930.62" long, 155.5" diameter

-ISF 130' long, 30' high, 30' wide

-1200' to nearest fence (worst case)

-Tourist at fence 100% of the time

-Sky shine included

-Nearest residence 3000 ft, 100% occupancy

•LIMITS •

-EPA 40CFR190.10(a) limit = 25 mRem/yr

-ISF dose to fence = 5.0 E-4 mRem/yr "

-ISF dose to nearest resi~ent = 1.0 E-5 mRem/yr

*Conservative compared to expected value of 40 mRem/hr •

Page 57: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

·•

ENVIRONMENTAL SAMPLING PROGRAM

•ONGOING

-PRESENT ENVIRONMENTAL MONITORING PROGRAM

o Direct Radiation oAirborne oWaterborne­olngestion

•IN ADDITION

"

-DURING S/G

oDirect Radiation olngestion

-AFTER STORAGE

oDirect Radiation oWaterborne

Page 58: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

Name

David W. Joos R.H. Beck Mark Rubin John A. Zwolinski Brian E. Holian Bob Pierson Keith Wichman Chen P. Tan Arnold Lee P •• K. Beckman Kelly V. Cedarquist Tom Newton Mark Caruso Jake Wechselberger Emmett Murphy Winston W. Liu Tom Tai Mark L. Lesinsuf Jim Kue:min W i 11 i am C 1 ark Cris Hillrr.an J.G. Lewis Herman M. Esch David P. Hoffman Ken Berry Bud Gerling

NRC/CPCo/BPC Meeting

May 3, 1990

Palisades Plant Site

Affiliation

Attachment 3

CPCo/VP Energy Supply Services/SGRP Mgr Bechtel NRR/NRC NRR/ADP/DRSP NRR/PM-Palisades NRR/PDIII-1/DRSP NRR/DET/EMCB NRR/DET/ESGB NRR/DET/EMEB Bechtel CPCo/iSI CPCo/ISI NRC/NRR/SRXB NRR NRR/DET/EMCB Reactor Inpsector NRC RIII Bechtel CPCo SGRP/RP CPCo SGRP/Licensing CPCo SGRP/Eng & Const CPCo Falisades/Prcj~cts CPCo/SGRP CPCo/Palisades/Planning CPCo/VP Nuclear Operation5 CPCo/Director Nuclear Licensing CPCo/Pal/A&TA Supervisor

Page 59: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

NRC PRESENTATION and TOUR

DATE: MAY 3, 1990

LOCATION: MANAGERS CONFERENCE ROOM

SUBJECT: SGRP, SG IMPROVEMENTS and SECONDARY SYSTEM IMPROVEMENTS

AGENDA: 8:00 INTRODUCTION D V JOOS

8:15 VIDEO

8:30 PROJECT PLAN D V JOOS

9:00 SG & SECONDARY IMPROVEMENTS C T HILLMAN

10:00 SGRP OUTAGE SCHEDULE A K BECKMAN

11:30 LUNCH

12:00 SURROGATE TOUR ON LASER DISK J S RIDL!Y

1:00 PLANT TOUR OUTSIDE CONTAINMENT TURBINE BLDG SFP INSIDE CONTAINMENT SG HAUL ROUTE SG INTERIM STORAGE NEY SGs

4:30 CLOSEOUT

J G LEVIS

D V JOOS

" ,•

Page 60: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

. t . •

~&l1D®&lID[g@ .. · @1f(g&UMfl @~OO~lru&LF@OO

OO~~l1&©~~[g001f ~OO@~~©if

PALISADES

s G R p·

Page 61: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

PROJECT PLAN

'

1. INTRODUCTION

2. MISSION & GOALS

3. ORGANIZATION

4. SCOPE & RESPONSIBILITIES

5. PROJECT SCHEDULE

6. OUTAGE SCHEDULE -

7 . BUDGET ~

Page 62: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SGRP MISSION

"TO ACCOMPLISH THE STEAM GENERATOR REPLACEMENT WITHIN

BUDGET, ON OR AHEAD OF SCHEDULE, AND WITH HIGH QUALITY .

IN ADDITION, ALL PROJECT OBJECTIVES SHOULD BE

ACCOMPLISHED SAFELY AND WITH RADIATION EXPOSURE AS LOW

AS REASONABLY ACHIEVABLE." .·

Page 63: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SAFETY

SCHEDULE

• COST

-COMPLIANCE

QUALITY

SGRP PROJECT GOALS

• NO LOST-TIME ACCIDENTS • RADIATION EXPOSURE LESS THAN

679 MAN-REM e NO OVER-EXPOSURES • LESS THAN 215 CONTAMINATIONS • LESS THAN 10,000 CUBIC FEET

RADWASTE FOR BURIAL

e 21 DAYS SPRING OUTAGE CRITICAL PATH 75 DAYS REPLACEMENT OUTAGE CRITICAL PATH

• LESS THAN $103 MILLION

• NO NRC CIVIL PENALTIES .. • LESS THAN 45 NRC NON­

COMP~IANCE POINTS . • NO ENVIRONMENTAL VIOLATIONS • NO WORKER SAFETY VIOLATIONS

e COMPLIANCE WITH REQUIREMENTS • MINIMIZE REWORK .

Page 64: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• PALIS}\DES STEAM GENERATOR REPLACEMENT PROJECT

ORGANIZATION

PROJECT MANAGER D 1' JOOS

ASST PROJ MGR JG LEWIS

.----------...---------+--------"'---•••oooooo•oOoHooo•oHooooooooooooooooooooooooooooooooooo•oo

ROJ ADMIN/CONTRO M C SNIEGOWSKI

RAD PROTECTION M LESINSKI

RADIATION PROTECTION PLANNING AND SCHEDULING FACILITIES AND SERVICES

CONTRACTS SOURCE-TERM REDUCTION

ADMINISTRATION DECONTAMINATION

RECORDS MANAGEMENT . RADlfASTE

' '·

UCENSING J KUEMIN

ENGIR AND CONSTR W Cl.ARK

STRATEGY DEVELOPMENT ENGR AND CONSTRUCTION

SUBM11TAL PREPARATION AND DEFENSE PROCUREMENT

NRC COMMUNICATIONS TESTING AND INSPECTIONS

QUALITY ASSURANCE K MARBAUGH

AUDIT AND SURVEIWNCE PROGRAM

QUALITY PROGRAM DEVELOPMENT AND LICENSING

Page 65: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

l. l i ~ l ' ~ ! .j l

1 l

.j ·.:

PALISADES STEAM GENERATOR REPLACEMENT PROJECT BECHTEL ORGANIZATION

PROJECT ENGINEERING C BROWN

DESIGN ENGINEERING

UCENSING

FIELD SERVICES MANAGER H CHARNEY

FIELD ENGINEERING

FIELD PROCUREMENT

FIELD CONSTRUCTION

FIELD COST/SCHEDUUNC

FIELD Al.ARA

FIELD SAFETY

FIELD QUAUTY CONTROL

PROJECT MANAGER AK BECKMAN

ASST PROJECT MANAGER R L BECK

BECHTEL-KWU COORD C DIPPOLD

PCS WELDING

QUAUTY ASSURANCE ENC P DADLANI

COST/SCHEDULE SUPV H MUELLER

COST AND SCHEDUUNC

PROJ PROCUREMENT HGR H ZEIGER

PROCUREMENT

!Vl/90

Page 66: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SGRP SCOPE & RESPONSIBILITIES

• PROJECT MANAGEMENT

• COMPLETION & DELIVERY OF THE STEAM GENERATORS

• ENGINEERING AND CONSTRUCTION

• • TESTING & INSPECTION

• FACILITIES

• LICENSING

• RADIATION PROTECTION , . .,

• QUALITY ASSURACE/QUALllY CONTROL

e SECURITY

"'

Page 67: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

Budget Rev: 2A

SGrRP TOTAL PROJECT BUDGET

ALL COSTS OOO's

CONTRACTOR $54516

RAO PRO $9740

OWNER MGMT $7701 CONTINGENCY $7352

' '

QA $1725 FACILITIES $2570

MAINT UPGRDS $2750 AFUDC $3959

. TESTING $4307 A & G $7337

Desk Reference 4.1.1

ih=========================-=-===-~--=-=--~=====================~~====--=-=·--==-======~

Page 68: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• NRC MEETING

STEAM GENERATOR STATUS UPDATE

TOPICAL AGENDA

MAY 3, 1990

EXISTING STEAM GENERATORS

* Steam Generator History

- operation and tube plugging history ..

- corrosion mechanisms

* Current Problems and Remedies

- tube support plate growth

- denting and cracking

- IGA/SCC

* Chemistry Performance

- sludge lancing

- chemistry with the Reverse Osmosis unit

REPLACEMENT STEAM GENERATORS ,•

* Steam Generator Design Improvements

- stainless steel eggcrate supports

- recirculation ring

increased blowdown line size

* Secondary Side Improvements

copper removal

- blowdown system enhancements

• * Future Plans

- Steam Generator Reliability Program

·-- ·---~-- -.····-······.----- .... ~· .. -··-.- ... ·····--.----~,---·-··-,·-~·-··-·"' _____ Pasze ... ":. .. _l_. ____ .,, ... _·-..--····-··------------·-··--··-·- -·--- .

Page 69: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SG AND SECONDARY IMPROVEMENTS

• EXISTING STEAM GENERATORS

SG HISTORY

CURRENT PROBLEMS AND REMEDIES

CHEMISTRY PERFORMANCE

• REPLACEMENT STEAM GENERATORS

DESIGN IMPROVEMENTS

• SECONDARY SIDE IMPROVEMENTS

• FUTURE PLANS ,,

-·- ---------· .... ··. ··-··-·- -·· -·--- ~-----.--. ... ' -·- -·- ·---····· -.-• ···-----------:~· .... ···:··· ----- ............ ·-·· ,.. ... ···--·- .. .

.· "

Page 70: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

••

PALISADES STEAM GENERATOR OPERATING HISTORY

- JAN 1973 FIRST TUBE FAILURE AFTER ONE YEAR OF OPERATION; WASTAGE ATIACK, PLUGGED FIRST 11 ROWS (1,400 TUBES; 8%)

- AUG 1973 EXCESSIVE LEAKAGE; PLUGGED ALL TUBES WITH GREATER THAN 60% WASTAGE DEFECTS

- MAY 1974

-1975 TO

1982

;. MAR 1982

• AU.G 1983

(340 TUBES)

PLANT WAS STILL OFF LINE FOR RX VESSEL REPAIRS. FAILURE MECHANISM WAS IGA; SYSTEM FLUSHED AND WATER TREATMENT CHANGED TO ALL-VOLATILE TREATMENT (APPROXIMATELY 920 PLUGGED; 16% PLUGGED TOTAL) .

WASTAGE ESSENTIALLY ARRESTED; 1085 PLUGGED OVER 8 YEARS (ADDITIONAL 6%) DENTING WAS OCCURRING AT A MINOR RATE; TUBE SUPPORT PLATES BEING LOCKED UP

2 LEAKING TUBES IN A-SG; DEVELOPMENT- BEGUN ON A ECT PROBE CAPABLE OF TRAVERSING THE FULL LENGTH OF THE TUBES FOR BETTER DETECTION OF CIRCUMFERENTIAL CRACKS AND IGA

BEGAN OUTAGE WHICH WAS EXTENDED 11 MONTHS BY REQUIRED QUALIFICATION OF THE RECENTLY DEVELOPED 4C4F ECT PROBE. TESTING REVEALED A SUBSTANTIAL NUM.BER OF POSSIBLE IGA INDICATIONS (PLUGGED APPROXIMATELY 280 TUBES)

:• .... ····.- .. ···. - .. ····:·-.:~·- .. ····

Page 71: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

OPERATING HISTORY· CONTINUED

- NOV 1985 A ROUTINE REFUELING OUTAGE WITH NO ABNORMAL SG INSPECTION RESULTS; DENTING CONTINUING

- DEC 1987 FIRST OUTAGE DUE TO SG LEAKS IN OVER 5 YEARS. CIRCUMFERENTIAL CRACK AT 13TH SUPPORT PLATE OF B-SG; BORIC ACID ADDED TO SECONDARY !;;ICE TO HELP MITIGATE DENTING, PRECEDED BY SLUDGE LANCING

- AUG 1988 TUBE LEAK IN B-SG; CIRCUMFERENTIAL CRACKS AT 13TH SUPPORT PLATE; 34 TUBES PLUGGED

- DEC 1988 WELD DEFECT ON B-SG TUBE PLUG; PREVENTIVE PLUGGING OF 9 TUBES

- JAN 1989 CIRCUMFERENTIAL CRACK AT 3RD SUPPORT PLATE; PREVENTIVE PLUGGING OF 238 TUBES

- OCT 1989 ADDITIONAL 145 TUBES PLUGGED DUE TO CRACKING IN HIGH STRESS REGIONS

"' . ·TOTAL TUBES PER SG 8519; PRESENTLY A-SG HAS 2044 TUBES

PLUGGED (24%) AND B-SG HAS 2442 TUBES PLUGGED (29%)

·:··= ... ~ "'"·~·- ·...,. ·., ..... ·::-: ... --·.·::.:· .• :-~1"1·:-:·:1~4': ': .... -, ...... : .. ~· . .:...1,:'l'-.""';!"",..:.-.;.:·-i .• ,.<":'~'.\.~~~=.~:-~.··.:r~·-<T>tu_:nY.l~.:~~~.r.;~:-.~---:":r_-.~~~J;'!'.R'•-..~7 ""~·.::=..:-..-ry-~,,.,...1.)a.v ........ ~····.,.":"· .. ~::-·-·-. - ~·-.. :- -·· .. "·· -:-;· · .· ·: - .·• .• . """: ·· - .......... ·- ....... . . . . .

Page 72: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

PLUGGED/YEAR

STEAM GENE.RATOR TUBE PLUGGING

73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89

YEAR

- SGA - SGB

SG FORCED OUTAGES: 73-1, 74-2, ~2-1, 87-1, 88-2, 89-1

CUMULATIVE. PERCENT 307.~·~~~~~~~~~~~~~~~~~~~----.

257.

20"

157.

10"

57.

o"

~ .

73 74 75 76 77 78 79 BO 81 62 83 84 65 86 87 88 89

YEAR

. . .-:.,. :.'..; ·-·--":">:~~·~'\:--,.•~·-'C:-. .... ':"'·"'-'·:c~~~-~~~"n.:·f..·:·...::.R'!'~r.;_.,rk-.\~~:lt'-'F~.·";C""~"°>\~~'l'.":~..:~1~?~";t~?"-:7~~·~·,::.o.~··,?-'l~}'h~u .. :-o~~ ... ~.": ... ~~-... - .•. ·.-·-·····-..:".:~ .• - ........ ~-~:"' ... "·:"'~ _:;::. ~; · •·. :·-·. · : .. -·. ··;. --· -··>· · .• :--·.:· _,. .--· -:·-: - .... -...~.·--· ~-·:··;:··.· --

Page 73: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• EXISTING STEAM GENERATORS

• CORROSION MECHANISMS

WASTAGE

DENTING

IGA/s·cc -

e CURRENT PROBLEMS AND REMEDIES

TUBE SUPPORT PLATE GROWTH

DENTING AND CRACKING

IGA/SCC

• CHEMISTRY PERFORMANCE

SLUDGE LANCING

CHEMISTRY WITH THE REVERSE OSMOSIS UNIT

Page 74: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

IMPROVEMENTS

e STAINLESS STEEL EGGCRATE TUBE SUPPORTS

• MINIMIZE FLOW STAGNATION .•

• REDUCE POTENTIAL FOR DENTING • MINIMIZE STEAM BLANKETING

e LARGER MANWAYS"

e MODIFIED INSPECTION PORTS

e INTEGRAL MAIN STEAM FLOW RESTRICTOR

e IMPROVED SLOWDOWN CAPABILITY

e ELECTROPOLISH PCS HEADS

- - -~~~.r.;;-z-:!:.{~ ... -::-;.t;.:.-1'.'.":~~-~?;"~[...r.~.~f{\~·~·~:f!.'J.'o.~.';·:;:1,'.1.?~:·:7~.";~·:"';::;.:~·r-··.·~:.;;·.~·/--... ·._<,":": ... ~•-·1:.;.·7~';··.·:!" ~--. ;;, •..::·: :--..':···: ~:~-·'!".:· .. ···· ~-,:.:_:· ·;- :.:.: ,-.;·-~.~-: --~. _.-. ... ~: _,. ~~.::·"'::;·.··'.!!' .... ~:. ~;..,.,.·.--~· -::r:·- .,~. -~- : .. ·• -. : •• ·.-; ',&. .. _.- •• ~,.. ·:·,_: ... -;.·. -.- ·"":P'I<•:"'.·

Page 75: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

;I

• . .

SECONDARY SYSTEM IMPROVEMENTS

• COPPER REMOVAL

MAIN CONDENSER RETUSING

FEEDWATER HEATER AND DRAIN COOLER REPLACEMENT

OXYGEN CONTROL

CONDENSER BOOT REPLACEMENT

CORROSION PRODUCT REMOVAL

ORGANIC REMOVAL

SECONDARY WATER QUALITY

WATER QUALITY INSTRUMENT UPGRADE,, ··

• PHASE II SLOWDOWN SYSTEM ENHANCEMENTS

INCREASE SLOWDOWN AND RECIRC PIPE SIZE

INCREASE CAPACITY OF SLOWDOWN HX

LARGER FLOW SLOWNDOWN PUMPS

.. _,""'':"'T·"-""~;"1:••·~··.-.~-• -~"T"';'f"' •-.·-·;·~·-··- .. - -·-··--.·,--•·· --~.-- ... ····•-· ·· • • • ,_. " --··· -,- . ··- ····- -;-· -·- -·- ... __ • .._... •. ··~- • ·- .• ··•·······. • •• •

---------------

Page 76: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

FUTURE PLANS

• STEAM GENERATOR RELi.ABiLiTY PROGRAM

PROGRAMMATIC ASPECTS

OPERATION ENHANCEMENTS

MAINTENANCE ENHANCEMENTS

Page 77: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• •

I

• Pre-Outage SGR Activities

• SGR Activities During Plant Defueling

• 75 Day SGR Critical Path Activities

• SGR Activities During Plant Refueling

.-.. ·-· --·- - ·- .... _.,,....~---.....--·--"- ...... -·.-·-· -----..---·-·· ·:· -· -..,....----··········-·· ··---··· .... ---- ·-··-.-.--- --·· ...... -- ----~·-·-·:--····

Page 78: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

:I.All r Offll E

fl!OLR!n!ll & DUVEL l!E!MjmR YE%£L PALISADES SGRP 1qqo FALL OUTAGE SCHEDULE pWuo=~~'~l"E~m ........ g~~~~=m~q~g~~~ra""""'~~"'~c~e~n~•tAl.---.;~~'="~~-----~-~~---(P

fUI UP!IQ!Nll£!!C ft\ DP91DI& JllOllvt Uta PlAJE

~ C!llCIEI'£ maa fllll lftHllG Pll!lll IMCf ~5J!!l!E Llt'f:ll PlAIE

._P"°_YE_lll_IE_~_PE_m _ _...i .

/DCey. A!ll '® lf'JC lfllGlllG EllU !Pt£11T

'· ~AIGGlllG EIUIPllEIU

~[ OLD 'JTEM r.EHERATlm

~ 11£11 'JIElft GEll~TDll5

IE"'YE/!!£.PlAC£/!lllfl 5EC0!!Pffif ' !!JI( P!Pll!(i

pr Bii) Q££OI! Pt3 P[PlllG

F'""Tt f!!!) ,, PC'J PIP(llG

?ECDMDqlU rTPlll l"ESTS

P£f!lEL 'l"mR I 5I!llllUP IE5!1N§

~l'AfEQLD REHOR 911D CQMJAl!l!Qf tLEAINP

~ COllCREIE

l!ISCALL TEI!~ ~ -

~l PlltllfDEllCE'J

(IH'E.GRAT[JI LEAK ~I[ rt5T t (LAT I I

Sl"RllCNllllL lMIUIUP JES£ 'ftT Pl.MT ON

r" '!'ilft GD!Dlfl!'Olt flf !IP. KLDlll'JG 11 lmtUO!

Page 79: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

I~ -

• Mock-up Channel head & PCS Piping

PCS Cutting and Machining PCS Welding PCS Decontamination PCS Nozzle/Elbow Fit-up

Old Steam Generator Storage Building

Training

Detailed Planning

Reinforced Earth Wall

Assemble Platform and Rigging Equipment Outside of Containment Opening

. ·--.,····-· -- ·- ····-· - -·-...,-··- ... ---· --· ··--··-- _____ ,, ___ ------=--·--·· ----- "::•·'~-~ --~-·-·- ....... , - ... ····~ ·-

Page 80: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

-.

• SIEMENS

SG-Mock Up Steam Generator Replacement Ringhals 2/Sweden Personnelt-, Equipment Training and OuaHficatioR .. ·-

·-.-·- ., .. - ... -- ..

89PWR124 UBKWU U444PT

Page 81: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

I ~

I -~ ·; ;i 'i

.. ; .;

I:

.,i

., ..

3/4• JT. --11-

A INF S IPS

50 X 4mm

• CONSTRUCTION PLATFORM

s

l'•O• ·ic 6• UNREINFORCED CONC. LEVELLING PAO CTVP.•

611.41 •

10

ET9

Ci) "·'· 12' "·'· 22'

122.53' !

FACE OF WALL

TO" O' C,1,1', COl'ING ITYlll

ET9 ET9 ET9

14.76 •

• 5.4 IC.S.F.

~ 5LIP JT.

20

14,76 •

R.S. 16' • J.5 IC.S.F,

ELEVATION FRONT FACE

Top rowof lie strips, second course of full panels

SCALE • 1· • 10'

IJ!J~J"~":":"r.~~~~~.-7METALSTRIPS

,,'

IA.

25 ° EL 625.5 o

'\. .~

6K••T'~. ...,._ __ BLOCK

610.84 08.38

605.92

R.S. 12' 2.8 K.S.F.

WALL

Page 82: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

.TSIDE LIFT -­~YSTEM FOOTING

(LATER,.

REINFORCED EARTH VOLUME rSEE NOTE 4)

FRONT FACE ---....lh: REINFORCED EARTH VALL

.-.-.. ... -·-····--

LOOSE

DENSE CMJN. J

lLATERJ 3·-0·

1·-0· 1·-0· 2G'·O· • ROAD BASE

LAYER OF GEOGRID I CTENSAR SR-2 OR EQUIVALENT)

COMPACTED STRUCTURAL Fill

22·-o· 1 o·-o·

SEE NOTE 5

' SECTION@

UTSIOE l IF. SYSTEM f OQJI NG . (LATERJ '

3·-0· (MJN.J

~Q.Mf>ACTED STRUCTURAL FILL

__ OMPA~TED DUNE S~ CBORR WI

EXCAVATED AND RECOMPACTED DUNE SAND

Page 83: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

1 o·-o· 1 o·-o· s·-o· s·-o· 1 o·-o· 10'·0'"

2'·6· ( TYP I

• 0 • •

3 ° ~ CONTAINMENT ~. AZ 120•

--~r-1-=~..i:;~--~----~--+-~---1--+-~~-h~~--~~~~===-----

, ,, ELEV.=62.7

~

RI OUTS/0£ LIFT SYS. FOOTING-

22·-o· 22·-o· IT\'P 1 Pl r~ ,

u_ ::z: u -z ::z: ----<( VI .... _ w>< a: l.LJ :i.c ..... ·u 0

m

I I I I I 1. I I I I I I I I I

. '

.. ' I

ii !I

Page 84: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

,,. ..

&16e R•r •11•t1ll , •• •1441r,

( ,..... ..,,.. ,,,_ , .. ' --------

,. ...... .

... ..... ,, ..

,, .... • •••

~,,,.,._,,~,.,,,,,, •1'1111116 f llffM•f

• .,,,.,,,,, ,,,,. ,,,,.,,.

.,,, 1.6., r••.,.lcAr fflr 1.6 . • ,,,.. rlA

I I

'''·,..,

ll'l1"t'11r1•it 1 ., ,,,,.,,, •11•. r111·1•'1

Page 85: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

·,·'·.'·<}' ::::._:: :··.: .... . . . ,", ...... :·=.: ·.· ·:-:=:=::->· ·.:

. ~::

..

. ti

Install Temporary Power

Install Scaffolding

Insulation Removal

Interference Removal

Tendon Detentioning and Removal

Cutting Containment Wall Opening

.,,

Page 86: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

,,, ,.,.. . ..

··-~·1i

,•

: ·. ·•·r •;.

... - .. -- - ...... ....., ......

..

.. 11 ... .,.~ MO.i. !ti I • •

Page 87: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

-.

• ---

,-. I l I I I I

4.. . A 1- ~ 2. ~ 0 t,'(wi ~-i I

?!o'' 7~0"

I I I I

I 11

:-Et. lo"l~ .. O MA'l<. L C>\)i.,IC>E.

\._,,_~is'-~ J-t111J. l~~lt>E

,.

Page 88: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

;I

120·

CONSTRUCTION OPENING

PARTIAL PLAN - CONTAINMENT· WALL AZ. 85° TO 145'

SCALE: 11 • = 1 '·0·

f' --~------------

Page 89: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

I

• t;J vt .

~ 11'11",:!.,:. ~~ II -~

( .......... ---------------a.. ~ ·- '::;;:;;:id--: - -- ---

l . J

. ·--- ----'t---+-·--+----4--f---i-·--+---+-, -·--i---t. .. :~

J I )-.~ ·'"~:.111·;,,.I'~ ,.,,~.!;..;: .;.~.~ .. ;.i#..,;;,~ .~.ll •• ."':a..·: ... --~-.::,.·;-,, ... in.,;

.....

I 1,-r-91 : lN' I I I

Ni: I I I

' I I I

I

I•, :: ' t-.. : IJ : ---t-:,lt--+:---+-~ - .. ,,....... __ -f-1 __ J~._J.,, -·-i ·1 ~ ·.,. .. '·t::··=· =_,,,=-=····~=· ·===--==· '==· '~=-· .... =-··=--"?:!~~-~1 ........... ·1i~

• ··I t::l ====--==----=:::::.-~--~---~-~~ -.- '

-..:::! .... '

.-t ...

I I I

J ·•

.•·

f . ..

·'

Page 90: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

• '

I

i I

!

I I

..I

·- -\.!,!~.

.

. . . . • . .. . ..

I

./ ,-- .

.. I

t! ~ -

.

I

' ~

I p 'I ~

l '.!

• 1

Jim

,,.. ... • t"" •

: ' -. -' J

. • I

I

.~

±f ! -

~ .... - i--

.. •

.1

' t-· i--,.

- -

,__ -

I . I

1 f+ -' I

~ I . ~

b~~~: ==;~9~~n+ I ~

:1-- -

' I ~ ~ --,r-

~ I

~

·U J ;! :

. ...... m

. '· ·~ •• ~1 . .•..

' ...

~ -

~ -I

i

Page 91: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

::L .. ~ ... .

,IJI

' . • . ~- ..

I

I --+-, _,, .r.-".,,, ... ~1nua· hl.O ~ u-....u.-...v:::f , .. A:or11• ., • ~

.... fld'• ••

•:.. ..•.. ,,, '•

co~•:-t. . ,, .. , o,,

,, l

\

. • I l

' I

•' r • ,. I ••

•••• ••••

'. " ' .. ,. --·

II• .•

2~·~ .... >

,

r ·-· ... i . ··-··· .. ·-· ...... -

: I tilt~ ' . , . . . , .

Page 92: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

e I

• •._L ___ 3'-G,~

fr \ 0 ~ s- \ ' "'R€'BI\ ~ @ rz... s-m.1 "1 c:, ---T-llt]

., ..... . . • • lJ . . -. . .. •.

• • • . . . . . /:::J

• r • • _I> • -~

' • ,

}'A 58,

A- 'SCC.il..M ~ab

. .

B'' 1(~ CAA~ Cc:iM:ra ~\.lo.JS.

3 .. J( 2'" .;-n FF'G.°ME"R ANcs"l-E!: .. \IElimCM..

A\ \'-\'" S°?AClN6

~\C-A. L TE:t{iXJ.,l S~E~n-l

~s \i:>€ '20'-V

2.Q+- '/R. Ow ScX>O psi Cot4c ~e:-re

Page 93: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• .·. .

·. t.:.:

• Complete Cut and Remove Concrete Block at Containment Opening

• Install and Load Test S/G Rigging Equipment

• Remove M/S and F /W Piping

Prepare Concrete Surface .. •

• Machine Cut and Decon PCS Piping

• Rig-Out Old S/Gs

• Rig-In New S/Gs

• • Remove S/G Rigging Equipment

• Template and Weld Prep PCS Piping

• Fit-Up and Weld PCS Piping

• Install New Liner Plate -·

Install Concrete Reinforcing and Tendon Ducts .,

• Form and Place Concrete at Containment Opening

• Install Tendons

"' • NOE and PWHT PCS Piping

• Install M/S and F /W Piping

• Hydrotest S/G Secondary Side and Piping

• --·~~-:.-..·-.~~-----~---..,."":'"_:_ ... ·.-.,,..,,.-'°-~"t-·----· . ..,., •-.r·---.···: ··---···-·-· ... --:···- .... -·-· ..... ___ ....... ,,__ •.. - ··.- ··--·· . -.- .... ' -- .. .

Page 94: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

·.· .. . ·.·.

. ';.-:

. . . . . . . ·:· .

•.

.•.·.

. · ..

j

- ~ -~ ...

I

i !

~

I 60 . .. . ii :i .

•'

·: . ..

.. -· ·-- ---· .. -. . ...

.4

• \

'! •••

. .

. . .

. .

:.. . . . ~ .. · ... . . -

.. . . ---•

.. . . . . . . . . .

--+- .. . . ., . ' ... . .~. -. -. -.. -.-' . . . ~ . . . . .. ...... . . . . . . . . • . •

·------~--~··---- I

Page 95: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

IUillli)I .......... ... .... ..... • , lll•Allt

-~., ....

. ..

.......

'

+ ------~!--

'

Page 96: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

\ • ./-

··.·•

.•

0 ·' Cll ..

_......_ ____ ,irtb.INW._V MAM

0 .. N •

1~\.aY ftUCIC ,

. . 91\.L. &l

S\\.\.. &UM ~.)

PLAN 'VIEW r:".' -:::-

Page 97: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

1 I ~ i

.. • • . .. . .. I•• . . ... .• . ~ '.

. . . . ·. · .. .. : .. . .. .. •

-l--+---~=-· .-~':k· --·

:.

. ,. ·.: . .. :• . .

··~ . ·. ·.:

.... .... : .. · •:

. ·.· ... .. . : • : ,0

•: ...•

· ... • .: . . .. . .. • . .

·.• ~ ..

. .. • ~ ..

• .. .

. •

r1L.1~·-· J.._('fYP)

!L.M"•t T.O. •TM . e...11.-.

Page 98: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

ftll 1.4 , • .,. 1 ... rAl#"I"" ........ ,, .. ,, ,. ....... , ...... . . ""' .,.,,._ --••r .. _.,. ..... _ ..... .,. ,. ....

.. •• t" #•Aw:.;::• ,,,,,.... 11•r '· .. ,.,.r.,,,, m""

"NOT~-··-· . TMI• "-OCIDUft II. .SIMILA"

...:==- '°" M ·"o-e II "eV!~ "'" .• ~N!W M IN6TAL.LATION ·- - -

Page 99: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

,.

.. . . . . .•.... ··.

T3 .. ·. t. ,·.· 3' . I ... : P. .. r d<

. •. .. : . . . .

. . . . 'IA • • ...

'

_SECTION 1!>•1!> , · • • • " , • - .. ·- _!..P90M O'Mt ..... •tot'

. . . .. ....... ·:. .. . . . ,, .... -: .• ... · ~

.. : ..

. " . . . . ... . . . · . . . . . . .

... •

I t ~ : • •

. .. .

. . ., ..

Page 100: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

if CMlfllt#,.611r ••.••. .,. -•&

. . . . .

'• ·-· • '·I

,,. .. '''v1tr1•11

,, ..• •r••'

o-o

&ll>e NIP' --II

''" ••1t111rr

' .,,,. .,.,...,,

( ,..,, • .,.. .,,,_ ,.. J

,, ...... ,

~#/Ira.er- •l'DllN• ' .... #llf

'''' I.I>., TllllNl&llTI' J•r •·•· ,,,,, ,,,,.,,,

I I

r•r1111r1011 , ., '''*•"' ow~. ,,,.,...,

Page 101: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

•• · .

HOT­LEG •. A

REACTOR VESSt.L

.. '•

,, - .

X-LEG1A

..

Page 102: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• r 1 I I I I

· I I

HOT LEG I I l ~-------l--------i

* \ ,/' ',, I

\ / ' I * .,/' ',, I

/ ' ,. ' / '

/ ' \ , ' \ \ \ \ •. \ \ \ \ \

\ ' _..L.-----1......;it-r---r----,-*

PART OF THE OLD .S~ Ga

CUTTING COLD LEG ELBOWS

• AND HOT LEG •

COL[ LEG

Page 103: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

I • '

INDIAN POINT UNIT 3 STEAM GENERATOR REPLACEMENT

r·-----·-·-·-·-·-·-·--------~ I

I I

I I

I I

r·-·-·-·-, I I PIPE END •

I I

I •

I •

I i i I 1 I

2 I . ! 1 ' SEAL DISC I I I 2 OECON MANIPULATO" I .

3 FRONTOOX I i_4 _ ~~NOZZ~~- _ _j I

I I

l'AESSUAE SECTION

WITH GRIT VESSEL

ftEC\AIMER SECTION

1'1l.TEft SICTIOH

-------DUST

COLLECTOft

V5

ve V3 AR

F

V2 AA

,.._..,_\.,. AE F

EX

I , . •

I I

I

• , . I

I

PRESSURE SYSTEM

. ;

SUCTION SYSTEM

' LEGEND I AE AIR EJECTOft I A" Alft REGUlA TOft

I I EX !XHAUST SYSTE!'i

F fill£"

L.---·-- ·-~~TK!N~~~~~-·-·....,_·-·_j V VALVES

Re•ctor Coolant Pipe Decontamination System Diagram

Page 104: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

, I ' / 8 ' , '

/ ' , ' / ' , '

/ ' , ' / ' , '

/ '

STEAM GENERATOR REMOVAL

• -

• ···- > ••• ~ • - •

,,

I I I I

I )

Page 105: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

.. \ ' \

\

\

' -' ~· ' \

. I

"

TRIAL FIT OF STEAM GENERATOR

Page 106: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

••

-z :c 0 ...... ,... ,.,, C).

I () rno C) I

' ( "

I ITl

.C)

..

-------------------· - ------------ --------------~------ --~-~--------------

--------~------- -~-------/~

/' /'

Page 107: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• • SIEMENS

SG-Mock Up Steam Ge'1erator Replacement Ringhals 2/Swffen . Personnell., Equipment Training and Qualification

89 PWR 125 UBKWU U444PT

Page 108: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

;,

.. ' .

• SIEMENS

Page 109: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

•• i '

I

! .

'

i : I :

I :

I

W1 W3 /5 ' I

• W4 /6

'

PREPARATION OF ELBOWS

Page 110: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SIEMENS

--~·

.. :,:~r •• '--·-·

...-·~---·-·-·- ···-·.~··--.···-----~.-- ..... - ·--· ····~ ·-. -

:.. .. .· · .• - ... : - . . ..

-:

Contactless measure­lnel"t cl b"ee-dirften­aD.i coordinates

_;..·.1 ; ... · .

........ ~

Page 111: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

SIEMENS

Upport pads "

.fOOzzles for piping conAectk>ns

88PWR162e . -~ffig. 8

••

Page 112: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

l l j

. 'i

!

~

. ;~· . " . . . : ~.ii .....

Fix point

I. . ... ·~rial measul.ingf system

·J

.,. '!ai:'

ContmB measurement of the pipes after dismantling of the steam generator

87 PWR 203

Fig. 1~

Page 113: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

W1

·--.-~,--·-..-••--.;•"A•-·-,••-•• o • • • •" • ••' ' ••• ' - ••, . .

I

I i I I

WELD IN COLD LEG ELBOW

W3/5

'#4/6

6

Page 114: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

~31 0103 NI 0131'\

•'

9/ VM

S/£M

• •

Page 115: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

----....ti-------------·~·...;;; .. IWM

(NEW WGU>

£NEW Weu:>

... _...__ .... ,. .... "." --- ........... . . . •

• . .. . f'

Page 116: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

..

• •

Install Removed Interferences

Install New S/G and Piping Insulation

Remove Temporary Power

Tension and Grease Tendons

Perform Containment SIT

Page 117: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

--·- ·- .!. . . -- ·- -~ __ ... .. ., ____ :_ .

... ...

..

. ..... --- --

' I

•• =• ••. ,.J. •..

• .f i I ' i

'\

• •

Page 118: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• PRESENTATIONS

CONTAINMENT CONSTRUCTION OPENING •••••••••••••••••••••• APRIL 12

NARROW-GAP WELDING •••••••••••••••••••••••••••••••••••. APRIL 2 6

RA.DIATION PROTECTION ••••••••••••••••••••••.•.••••••••• MAY 2

SG and SECONDARY SIDE IMPROVEMENTS •••••••••••..•.•••.• MAY 3

PIPE and PIPE SUPPORTS. • • • • • • • • • • • • • • • • • • • • 8 • • • • • •

FSAR ANALYSES. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . RIGGING AND HAULING •••••••••••••••••••.••••••••.••••••

-· ..

. ti

• ..,. .. ,

Page 119: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

FCP DESCRIPTION

Blowdown System Piping - Phase I Recirculation System Piping - Phase I Wide Range Instrumentation Tubing - Phase I Breathing Air Station Relocation - Phase I Rigging and Support Installation - Phase I Reinforced Earth Retaining Wall Aux Bldg Modification for CAF Overall SG Replacement Program Temporary Commodities Old Steam Generator Storage Facility Outside Rigging Inside Rigging CCW Surge Tank Room Tubing Relocation CCW Surge Tank Room Roof Slab Removal Containment Construction Opening PCS Piping Replacement Main Steam System Piping Modification Emergency FW System Piping Modification Blowdown System Piping - Phase II Recirc System Piping - Phase II Steam Generator Sample System Wide Range Level Instrumentation Foundation Structure for Rigging Platform CVCS Piping/Valve Relocation Steam Generator Replacement Main Feedwater System Modification

SCHEDULE

Completed Completed Completed Completed Completed April 13 June 15 June 15 June 15 May3 June 15 June 15 June 15 June 15 June 15 June 15 June 15 June 1 June 15 June 15 June 1 June 15 May21 June 15 June 15 ,. May15 "

Page 120: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

INTERIM OLD SG STORAGE FACILITY

• 0 Structural l)esign of Storage Facility

0 Seismic Design Considerations

0 Other Natural Phenomena

0 Flooding

0 Fire Protection and Fire Hazards

0 Electrical Design Considerations

0 Radiological Impact (Onsite and Offsite Doses)

-· 0 Radiological Consequences of Abnormal Events

0 Surveillance Requirements ,. .,

0 Structural Adequacy of SG Supports

0 Security Access Controls

0 Construction Impact

0 Technical Specification Impact

• 0 FSAR Impact

Page 121: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

CONTAINMENT ·coNSTRUCTION OPENING

0 Containment Design Parameters

0 Containment Structural Adequacy

0 Shutdown Cooling System Operation Coordin.ation

0 Impact on Safety-Related Equipment during Construction

0 Temporary HV AC Consideration

0 Missile/Tornado and Depressurization Considerations

0 Containment Access Control and Security Control

"' ~

0 Replacement Materials (concrete, rebar, sheathing, liner plate) and Construction Details

" 0 Radiation Protection

0 Temporary Enclosure Consideration

0 Fuel Building/Containment Interface

Page 122: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

CONTAJNMENT CONSTRUCTION OPENING (cont)

0 Liner Plate Protection Considerations-

0 Protective Coating on Liner Plate

0 Procedural Controls

0 Waste Disposal

0 Removal and Reinstallation of Tendons

0 Mockup Training

• 0 Inspection Method/Criteria

0 Performance Tests

0 Technical Specification Impact _.

.. 0 FSAR Impact

' r

Page 123: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

RIGGING INSIDE CONTAINMENT

0 Structural Evaluation of Rigging Loads on Existing Polar Crane Rail, Containment Shell and Reactor Cavity Shield Walls

0 Heavy Load Consideration

0 Load Test of all Lifting Systems and Components

0 Impact on Plant Security System

0 Fire Protection System Considerations

0 Electrical Design Considerations

0 Procedural Controls

,. -o Consequences of Dropping Old/New "SG, Rigging,

or Other Equipment

0 Radiation Protection ;I

0 Technical Specification Impact

0 FSAR Impact

I

Page 124: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

HAUL ROUTES AND RIGGING OUTSIDE CONTAINMENT

o Structural Evaluation of Access Roads

o Evaluation of Underground Utilities

o Assessment of Nearby and Overhead Facilities for Interferences

0 Load Test of all Lifting Systems and Components

0 Structural Evaluation of Rigging Platform, Structural Supports, and Foundation

0 Flood Control

0 Procedural Controls ,,.

Impact on Fire Protection .,

0

0 Impact on Plant Security System

0 Impact on Electrical ·Systems

Page 125: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• HAUL ROUTES AND RIGGING OUTSIDE CONTAINMENT (cont)

o Transportation Incidents (loss of transporter control, transporter overturning, etc.)

o Consequences of Dropping Old/New SG, Rigging, or Other Equipment

o Technical Specification Impact

o FSAR Impact

Page 126: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• L

RETAINING WALL OUTSIDE CONTAINMENT

o Structural Adequacy of the Structure·

o Evaluation of Underground Utilities ..

o Assessment of Nearby and Overhead Facilities for Interferences

o Procedural Controls

o Construction Impact

o Separation from Containment

o Impact on Containment/Tendon System

o Impact on Fire Protection

o Impact on Plant Security System

o Impact on Electrical Systems

o Design Life of the Structure

o Technical Specification Impact

o FSAR Impact

Page 127: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

PIPING SYSTEMS INSIDE CONTAINMENT

o . Seismic Design Considerations

o Missile Design Considerations

o Pipe Support Design Considerations

o High-Low Pressure Interfaces

o Interfacing LOCA

o Pipe Penetrations (LLRT, Heatup, etc)

o Pipe Breaks (MSLB, HELB, etc.)

o Single Failure Criteria

o Environmental Qualification Impact ..

o Code Compliance and Reconciliation

o Containment Heat Load Considerations "

o Containment Heat Sink Considerations

o Thermal In~ulation Removal and Replacement

,. P"'

. ••• .. •- -·. • -- ••• .. •·.:•·,.····· .···--,-·-r•··••• •·.;.•···-····---······

Page 128: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• PIPING SYSTEMS INSIDE CONTAINMENT (cont)

0 Heavy Load Considerations

0 Protective Coating

0 Hydrogen Generation

0 Pipe Severance an~ Reconnection Technique

0 Radiological Impact of Pipe Cutting

0 Waste Disposal

0 Return-to-Service Testing

0 Technical Specification Impact

0 FSAR Accident Analyses .I'

0 FSAR Impact

. ~

• -. .

o••· •• ...-··-,-- .-.•···.- .·--.-- 0 - ••• •"•'• '"-• ··-.-• n• -· O•••o ·-. •• --~ .•- •••• ,_ o •"": •"•"'." •• T• - • • • •• • •

Page 129: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

"

SG BLOWDOWN AND RECIRCULATION PIPING -SPRING OUTAGE INSTALLATION

0 Structural Evaluation of Pipe Support Loads (permanent and temporary) on .Containment Interior Structures

0 Seismic Design Considerations

0 Missile Design Considerations

0 Protective Coating

0 Impact on Subcompartment Analysis

0 Containment Heat Sink Considerations

0 Hydrogen Generation

Heavy Load Considerations ,.

0 ~

0 Technical Specification Impact

0 FSAR Accident Analyses

0 FSAR Impact

. ··-··· - ··~--·· ·· .. ·~-. ·-·· ····-········-- ...... ~-··

Page 130: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

WIDE RANGE LEVEL INSTRUMENTATION

0 Potential Changes to Setpoint

0 Review of FSAR Accident Analyses

0 Review of Set Point Index

0 Enyironmental Qualification Impact

0 Regulatory Guide 1.97 Compliance

0 Fire Protection Considerations

0 Single Failure Criteria

0 Electrical Power Supply Considerations

0 Structural Evaluation of Instrumentatjon Support Loads on Containment Interior Structures

0 Seismic Design Considerations

0 Technical Specifi~ation Impact

0 FSAR Impact

• - .

··-.-·••-·--···· -·· •••• ·~.··••••·••·•••-r.···--·•·-· -······:-- •• .•.· • • ···-•• .. '

Page 131: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• WIDE RANGE LEVEL INSTRUMENTATION -SPRING OUTAGE INSTALLATION

0 Structural Evaluation of Instrumentation Support Loads on Containment Interior Structures

0 Seismic Design Considerations

0 Impact on Subcompartment Analysis

0 Containment Heat Sink Considerations

0 Hydrogen Generation

0 Technical Specification Impact

0 FSAR Accident Analyses

FSAR Impact " 0 ,

'. r

Page 132: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• INTERFERENCE REMOVAL AND REINSTALLATION

0 Consequences of Load Drop

0 Laydown Load Consideration

0 Impact on Safety Systems During Removal/Reinstallation

0 Impact on Fire Protection System

0 Impact on Security System

• 0 Loss of Offsite Power

0 Procedural Controls

0 Return -to-Service Testing ,.

Technical Specification Impact .,

0

0 FSAR Accident Analyses

"' 0 FSAR Impact

Page 133: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

TEMPORARY RIGGING COMPONENTS INSIDE CONTAINMENT - SPRING OUTAGE INSTALLATION

o Structural Evaluation of Rigging Component Loads on Containment Dome Trusses and Liner Plate

o Seismic Design Considerations

o Impact on Subcompartment Analysis

o Containment Heat Sink Considerations

o Hydrogen Generation

o Protective Coating

o Heavy Load Considerations

,.

o Heavy Load Consideration Not Addressed in Existing Plant Procedures

o Technical Specification Impact

o FSAR Accident Analyses

o FSAR Impa~t

Page 134: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• BREATHING AIR SYSTEM - SPRING OUTAGE INSTALLATION

0 Structural Evaluation of Support Loads on Containment Interior Structures

0 Pipe Support Design Consideratio_ns

0 Seismic Design Considerations

0 System Interface

0 Performance Tests

0 Technical Specification Impact

0 FSAR Accident Analyses

0 FSAR Impact _,. .,

. , r

Page 135: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• STEAM GENERATOR REPLACEMENT FC -

0 Comparison with Existing SG Design

0 Code Compliance and Reconciliation

0 Structural Adequacy of Existing SG Support System

0 Thermal Insulation Removal and Replacement

0 Missile Design Considerations

0 Seismic Design Considerations

0 Containment Heat Load Considerations

0 Containment Heat Sink Considerations

./'

0 Containment Net Free Volume Considerations

0 Procedural Controls

" 0 System Interface

0 Equipment Qualification Program Evaluation

- -- .. -·--- .. ,.,..-.~ ·- .. - ·-·-······· .. ···---·---···.-··--- .. --.---7--..--------·-·-·-·7.•-.··-· --···· ··---~-.--. ··.····

Page 136: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• STEAM GENERATOR REPLACEMENT FC (cont)

0 PCS Flow

0 Flow-Induced Vibration

0 Temperature Difference between Hot and Cold Legs

0 Pressure Drop Across the Core

0 ALARA Considerations

0 Return-to-Service Testing

0 Technical Specification Impact

0 Evaluation of FSAR Accident Analyses

" ~

0 FSAR Impact

Page 137: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

..

OVERALL SG REPLACEMENT PROJECT

0 Comparison with Existing SG Design

0 Code Compliance and Reconciliation

0 Structural Considerations

0 Missile Design Considerations

0 Seismic Design Considerations

0 Procedural Control During Construction

0 Operational Procedure Review

0 System Interface

0 Equipment Qualification Program Re~iew ~

0 PCS Flow

0 Flow-Induced Vibration

0 Temperature Difference between Hot and Cold Legs

Page 138: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

• OVERALL SG REPLACEMENT PROJECT (cont)

0 Pressure Drop Across the Core

0 ALARA Considerations

0 Return-to-Service Testing

0 Technical Specification Impact

0 FSAR Accident Analyses Review

0 FSAR Impact

Page 139: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

.. 0

Page 140: I. INTRODUCTION II. RADIATION SAFETY DEPARTMENT

-------

... -

FSAR CHAPTER 14 SAFETY ANALYSES

FOR THE REPLACEMENT STEAM GENERATORS

• DISPOSITION OF ALL CHAPTER 14 EVENTS CCPCo, ANF, CE>

• THE DISPOSITION IS BASED ON REPLACEMENT STEAH GENERATOR DESIGN DIFFERENCES AND RESULTING PLANT OPERATING CONDITIONS

• ONLY TWO EVENTS ARE DISPOSITIONED AS REQUIRING REANALYSIS:

1. FSAR 14.15, STEAH GENERATOR TUBE RUPTURE CSGTR), DUE TO -A LARGER TUBE INSIDE DIAMETER

2. FSAR 14.18.2, HAIN STEAH LINE BREAK CMSLB) CONTAINMENT RESPONSE (INCREASED SECONDARY INVENTORY)

• PRELIMINARY RESULTS TO THE SGTR AND THE MSLB CONTAINMENT EVENTS ARE ACCEPTABLE (ACCEPTANCE CRITERIA BEING HET> - ..

• THE ACCEPTABLE COHPLETION OF THE EVENTS REQUIRED WILL SUPPORT THE REPLACEMENT OF THE STEAH GENERATORS UNDER THE 10CFR50.59 P~OCESS

·,