Page 1: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

1

I-80 at Gilman StreetInterchange Roundabouts

07 February 2018

1

2

Presentation Overview

» Project Planning Process

» Project Components

» Project Implications

» Future Steps

Page 2: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

2

3

Gilman Street Vicinity Map

Illustrations are conceptual 

drafts subject to change

Project Area

San Francisco Bay

80

N

4

CollisionData 2012‐2015

West Bound On-RampInjuries + Fatalities: 38% above State Average

Total: 52% below State Average

West Bound Off-RampInjuries + Fatalities: 19% below State Average

Total: 115% above State Average

East Bound Off-RampInjuries + Fatalities: 3% below State Average

Total: 33% below State Average

East Bound On-RampInjuries + Fatalities : 95% above State Average

Total: 35% above State Average

GILM

AN

ST

WB I-80

EB I-80

80

N

Illustrations are conceptual 

drafts subject to change

Interchange is also 

identified by the 

City of Berkeley as 

“high stress” for 

bicyclists.Source: 2017 City of Berkeley 

Bicycle Plan

Page 3: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

3

5

Past Studies

» West Berkeley Parking and Circulation Study (1998)

» Gilman Street Interchange Improvement Study (2005)

» Draft Project Study Report (PSR) (2005)

» West Berkeley Circulation Master Plan Report (2009)

» Project Study Report‐Project Development Support (PSR‐PDS) (2014)

These studies concluded: » Signalization and stop signs would both fail.

» No room for diamond interchange.

» Only workable solution is roundabouts.

6

Project Partners

» Caltrans

» Alameda County Transportation Commission (ACTC)

» City of Berkeley

» City of Albany

Consultant Team Key Members

» Parsons – Project Management

» OMNI‐MEANS – Roundabout Design

» TJKM – Traffic Engineering

» PlaceWorks – Public Engagement

Page 4: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

4

7

Project Purpose

» Improve safety for all modes of transportation.

» Simplify and improve the navigation, mobility, and traffic operations at the I‐80/Gilman Street interchange.

» Reduce congestion, vehicle queues and conflicts at the I‐80/Gilman Street interchange.

» Improve local and regional bicycle connections and pedestrian facilities through the I‐80/Gilman Street interchange.

8

Project Planning Meetings To Date

» March 15, 2016: Meeting with Public Agencies

» March 17, 2016: Meeting with Community Based Organizations

» March 24, 2016: Meeting with Business Owners

» April 14, 2016: Meeting with Pacific Steel Casting

» April 27, 2016: Open House

» May 4, 2016: Meeting with Business Owners

» August 26, 2016: Meeting with Golden Gate Fields

» August 29, 2017: Meeting with Business Owners

» Late 2017 – 2018:  On‐going meetings with City of Berkeley, City of Albany, and 

other stakeholders

Page 5: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

5

9

DesignElements

» Two roundabouts

» Landscaped areas

» Sidewalks and at‐grade path 

through interchange

» Pedestrian / bike  overcrossing 

(POC) over 

I‐80 to the north or south

» Gilman Street cycle track to new 

signal at Fourth Street

» Bike improvements from Gilman / 

Fourth Street to Codornices Creek

» New access to Golden Gate Fields 

stables

» Bay Trail gap closure at foot of 

Gilman Street

80

Golden Gate FieldsTom Bates RegionalSports Complex

Pacific Steel

Red‐D‐Arc

Gilm

an St

Gilm

an St

N

Illustrations are conceptual

drafts subject to change

10

Design Elements Southern POC Option

Page St

W Frontage Rd

Eastshore HwyEastshore Hwy

Gilm

an St

Harrison St

2nd St

Golden Gate FieldsTom Bates Regional Sports Complex

80

N

Illustrations are

conceptual drafts 

subject to change

Bay Trail

10

Page 6: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

6

11

Design Elements Northern POC Option

W Frontage Rd

Eastshore HwyEastshore Hwy

Gilm

an St

Harrison St

2nd St

Golden Gate FieldsTom Bates Regional Sports Complex

80

N

Illustrations are

conceptual drafts 

subject to change

Bay Trail

11

12

Roundabout Operations

» Only need to watch for traffic coming from one direction at a time

» Shorter, simpler pedestrian crossings

» Slower traffic

» Pedestrian refuges

» Landscape separation

» Shared‐use path

Raised central island

Landscape buffer

Pedestrian path

Truck apron

Entry deflection

Splitter island

Pedestrian refuge

v

Illustrations are conceptual

drafts subject to change

Page 7: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

7

13

Roundabout Safety – Why Roundabouts?

» Improves overall safety

» According to the Federal Highway Administration, installing a roundabout 

typically results in:

• 76% reduction in injury collisions

• 90% reduction in fatality collisions

• 40% reduction in pedestrian injuries

• 75% fewer conflict points compared to standard intersections

Source: Federal Highway Administration, Safe Roads for a Safe Future, 2015.

14

Travel Paths Through Roundabouts

From Gilman St to 

I‐80 West80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

Gilman St

NIllustrations are conceptual

drafts subject to change

Page 8: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

8

15

Travel Paths Through Roundabouts

From Gilman St 

To Golden Gate 

Fields and 

Eastshore State 

Park

80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman StGilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

NIllustrations are conceptual

drafts subject to change

16

Travel Paths Through Roundabouts

From Eastshore

State Park to I‐80 

East80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman StGilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

NIllustrations are conceptual

drafts subject to change

Page 9: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

9

17

Travel Paths Through Roundabouts

From West 

Frontage Road 

south Gilman 

Street to I‐80 East

80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman StGilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

NIllustrations are conceptual

drafts subject to change

18

Travel Paths Through Roundabouts

From I‐80 East to 

Gilman Street80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman StGilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

NIllustrations are conceptual

drafts subject to change

Page 10: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

10

19

Travel Paths Through Roundabouts

From I‐80 West to 

Gilman Street80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman StGilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

NIllustrations are conceptual

drafts subject to change

20

80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman StGilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

Bike and Pedestrian Improvements at the Roundabouts

Sidewalk or shared use path on north side

Bike only exit

Gilman St crossing

Shared Use Path on south side

NIllustrations are conceptual

drafts subject to change

Bike and Pedestrian Connection

Page 11: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

11

21

Travel Paths Through Roundabouts

Pedestrian/ 

Bicycle route 

from West 

Frontage Road, 

north of Gilman 

Street, to east

80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

NIllustrations are conceptual

drafts subject to change

Gilman St

22

Travel Paths Through Roundabouts

Pedestrian/ 

Bicycle route 

from West 

Frontage Road, 

south of Gilman 

Street, to east

80

Eastshore

Hwy

Eastshore

Hwy

I‐80 EB Offramp

I‐80 EB Onramp

Gilman St

2nd St

2nd St

GoldenGateFields

Tom BatesRegionalSports Complex

NIllustrations are conceptual

drafts subject to change

Gilman St

Page 12: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

12

23

Roundabout Visual Simulation

For information purposes only –Not to scale

Illustrations are

conceptual drafts 

subject to change

Eastern Roundabout viewed from northwest near Golden Gate Fields

24

Pedestrian Overcrossings Southern POC Option

Page St

W Frontage Rd

Eastshore HwyEastshore Hwy

Gilm

an St

Harrison St

2nd St

Golden Gate FieldsTom Bates Regional Sports Complex

80

N

Illustrations are

conceptual drafts 

subject to change

Bay Trail

24

Page 13: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

13

25

Pedestrian Overcrossings Northern POC Option

W Frontage Rd

Eastshore HwyEastshore Hwy

Gilm

an St

Harrison St

2nd St

Golden Gate FieldsTom Bates Regional Sports Complex

80

N

Illustrations are

conceptual drafts 

subject to change

25

Bay Trail

26

Pedestrian Overcrossing Features

Separate bicycle and pedestrian areas

Bay Bridge east span path

University Avenue bike/pedestrian overcrossing

Page 14: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

14

27

South Pedestrian Overcrossing Option

For information purposes only –Not to scale

Illustrations are

conceptual drafts 

subject to change

Visual simulation from Interstate 80 Eastbound looking north

28

South Pedestrian Overcrossing Option

For information purposes only –Not to scale

Illustrations are

conceptual drafts 

subject to change

Visual simulation from Bay Trail southwest of Gilman Street

Page 15: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

15

29

South Pedestrian Overcrossing Option

For information purposes only –Not to scale

Illustrations are

conceptual drafts 

subject to change

Visual simulation from Eastshore Highway southeast of Gilman Street

30

North Pedestrian Overcrossing Option

For information purposes only –Not to scale

Visual simulation from Interstate 80 Westbound looking south

Page 16: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

16

31

North Pedestrian Overcrossing Option

For information purposes only –Not to scale

Visual simulation from west end of Gilman Street

32

North Pedestrian Overcrossing Option

For information purposes only –Not to scale

Visual simulation from Harrison Street looking west

Page 17: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

17

33

Two‐Way Cycle Track

Bancroft Way, Berkeley

San Pablo Ave, Albany

Bancroft Way, Berkeley

34

Gilman Street Cycle Track (Southern POC)

Cycle Track

Gilman St

2nd St

4th St

80

City of BerkeleyRecyclingCenter

Red‐D‐Arc

Pacific Steel

N

Illustrations are

conceptual drafts 

subject to change

34

Page 18: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

18

35

Gilman Street Cycle Track (Northern POC)

Cycle Track

Gilman St

2nd St

4th St

80

Red‐D‐Arc

Pacific Steel

City of BerkeleyRecyclingCenter

N

Illustrations are

conceptual drafts 

subject to change

36

Gilman St to CodornicesCreek Connection

Restriped parking and crosswalks

New bicycle sharrows

New traffic signal at Gilman and 4th St

4th St

Gilman St

N

5th St

Harrison St

Codornices Creek

Illustrations are conceptual

drafts subject to change

Page 19: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

19

37

Bay Trail Gap Closure

Golden Gate Fields Stables

Tom Bates RegionalSports Complex

San Francisco Bay

80

N

Illustrations are conceptual

drafts subject to change37

New Bay Trail to be Installed by EBRPD

Existing Bay Trail

New Bay Trail to be Installed by Project

38

Project Implications

» Vehicle Queuing

» Right‐of‐Way issues

» Change in access between Gilman and Eastshore Highway

» Changes to Golden Gate Fields access

Page 20: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

20

39

2nd St

Gilman St

City of Berkeley Recycling CenterRed‐D‐Arc

Pacific Steel

ESH

Un

ion

Pa

cif

ic R

ailr

oa

d

Westbound Vehicle queues extend 183’ 

Vehicle Queue

Queuing

N Illustrations are conceptual

drafts subject to change

80

40

Right-of-way acquisition for Northern POC

Right‐of‐Way AcquisitionThe project requires ROW takes on west side of freeway.

Southern POC requires no additional right‐of‐way acquisitions on east side of freeway.

Northern POC requires limited right‐of‐way acquisition at Red‐D‐Arc / Airgas, Pacific Steel and Budget Rent‐a‐Car (where curb cuts will be moved from Gilman to Second).

Right of way take

2n

d S

t

Gilman St

City of Berkeley Recycling CenterRed‐D‐Arc

Pacific Steel

ES

H

Un

ion

Pa

cif

ic R

ailr

oa

d

N Illustrations are conceptual

drafts subject to change

80

Budget Rent‐a‐Car

Page 21: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

21

41

Harrison

St

Change in Vehicular Access 

N

Illustrations are conceptual

drafts subject to change

Eastshore Hwy

City of Berkeley Recycling Center

PublicStorage

2nd St

Gilm

an St

Red‐D‐Arc / Airgas

80

42

SB EastshoreHighwayAccess via Second St

From I‐80/Gilman St to Southbound Eastshore Highway

Northbound Eastshore Highway to Gilman St/ I‐80 ramps

Illustrations are conceptual

drafts subject to change

I-80 EB Offramp

PacificSteel

2nd St

Gilm

an St

80

Page St Berkeley 

Forge & Tool

N

Page 22: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

22

43

Options to Address Change in Access

» Enhanced paving, streetscape and signage

» Full roundabout access northbound

• Access to and from Eastshore Highway north of Gilman

• Includes right turn from Gilman westbound to Eastshore Highway northbound

• Access from Gilman to Eastshore Highway southbound would still be closed

» Right turn only northbound

• From Gilman westbound to Eastshore Highway northbound only

» One‐way Second Street south of Gilman Street

• From Gilman to Page Street

44

Harrison  St

Options to Address Change in Access

New Paving, Enhanced Streetscape and Signage

From I‐80/ Gilman St to Northbound EastshoreHighway

From Southbound EastshoreHighway to Gilman St/I‐80 ramps

Second St

City of Berkeley Recycling Center

Eastshore

Hwy`

I‐80 EB Onramp

Public Storage

Sec

ond

St

to E

asts

hore

Hw

y

Harrison Stto Eastshore Hwy

Gilman StIllustrations are conceptual

drafts subject to change

80

N

Page 23: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

23

45

Options to Address Change in Access

New Paving, Enhanced Streetscape and Signage

Visual simulation of Second Street looking north from Gilman

46

Second St

Red‐D‐Arc

Pacific Steel

I‐80 EB Onramp

Union Pacific Railroad

Gilman St

ESH

City of Berkeley Recycling Center

Options to Address Change in Access

Full Roundabout Access Northbound

» Bike and vehicle access to northbound Eastshore Highway from the roundabout

» Right turn lane from Gilman westbound

» Would not include direct access from roundabout to Eastshore Highway southbound

Illustrations are conceptual

drafts subject to change

80

N

Page 24: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

24

47

Options to Address Change in Access

Full Roundabout Access Northbound

Implication #1

Longer, 

unacceptable 

queuing

Westbound Vehicle queues extend 350’ creating conflicts with Second Street.

Vehicle Queue

Red‐D‐Arc

Pacific Steel

I‐80 EB Onramp

ESH

City of Berkeley Recycling Center80

Second St

Gilman St

Illustrations are conceptual

drafts subject to change

N

Union Pacific Railroad

48

Three right turns 

from a single 

lane could 

confuse 

motorists

With all right turn options, the right turn pocket begins prior to Second St. requiring 3 right turn movements to be signed: Second St, Eastshore Hwy and Eastbound I-80

Options to Address Change in Access

Full Roundabout AccessNorthbound

Implication #2

Illustrations are conceptual

drafts subject to change

Red‐D‐Arc

Pacific Steel

I‐80 EB Onramp

ESH

City of Berkeley Recycling Center80

Second St

Union Pacific RailroadGilman St

N

Page 25: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

25

49

Full take of Red‐

D‐Arc building 

and business 

Additional right of way impacts to buildings result in full parcel take and relocation of business

Right-of-way take

Options to Address Change in Access

Full Roundabout AccessNorthbound

Implication #3

Pacific Steel

I‐80 EB Onramp

Gilman St

ESH

City of Berkeley Recycling Center

80

N

Union Pacific Railroad

Illustrations are conceptual

drafts subject to change

Red‐D‐Arc

50

Gilman St

Un

ion

Pa

cif

ic R

ailr

oa

d

Options to Address Change in Access

Right Turn only from Gilman St westbound to EastshoreHighway northbound

Second St

Red‐D‐Arc

Pacific Steel

I‐80 EB Onramp

Union Pacific Railroad

Gilman St

ESH

City of Berkeley Recycling Center

Illustrations are conceptual

drafts subject to change

80

N

Page 26: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

26

51

Options to Address Change in Access

Right Turn Only Implications

Queuing returns to previously predicted levels

Same ROW take as for roundabout with full northbound access

Shorter queuing length means that adequate signage could be provided

Illustrations are

conceptual drafts 

subject to change

52

SB EastshoreHighwayAccess via Second St

From I‐80/Gilman St to Southbound Eastshore Highway

Northbound Eastshore Highway to Gilman St/ I‐80 ramps

Illustrations are conceptual

drafts subject to change

I-80 EB Offramp

PacificSteel

2nd St

Gilm

an St

80

Page St

Berkeley Forge & Tool

N

One‐way southbound

Parking Lane

Travel Lane

Page 27: I-80 Gilman 02072018€¦ · 2/8/2018 4 7 Project Purpose » Improve safety for all modes of transportation. » Simplify and improve the navigation, mobility, and traffic operations

2/8/2018

27

53

Changes to Golden Gate Fields Access

Golden Gate Fields Stables

Tom BatesRegionalSports Complex

San Francisco Bay

80

N

Illustrations are conceptual

drafts subject to change53

Bay Trail

54

Future Steps

» City presentations

• Berkeley Transportation Commission:  February or March

• Albany City Council:  February or March

» On‐going outreach

» Preparation of environmental document

» On‐going design and project refinement

» Construction:  Late 2019 through 2022