hydrology of the chase creek watersheda100.gov.bc.ca/appsdata/acat/documents/r3745/chasefinal...the...
TRANSCRIPT
Riverside Forest Products Limited
HYDROLOGYof the
CHASE CREEK WATERSHED
(FIA Activity 2029021)Prepared for
By
March 31, 2005
TABLE OF CONTENTS
1.0 INTRODUCTION .................................................................................................... 1
2.0 BACKGROUND ...................................................................................................... 1
3.0 REVIEW OF EXISTING INFORMATION ............................................................ 3
3.1 PREVIOUS REPORTS .............................................................................................. 33.2 HYDROMETRIC DATA SOURCES............................................................................ 5
4.0 ANALYSIS............................................................................................................... 7
4.1 DISCHARGE DATA ................................................................................................ 74.2 TIMMING OF PEAK FLOW...................................................................................... 84.3 MAGNITUDE OF PEAK FLOW................................................................................. 94.4 DURATION OF RUN-OFF HYDROGRAPH............................................................... 104.5 MINIMUM FLOWS ............................................................................................... 114.6 MEAN DAILY DISCHARGE BY MONTH................................................................ 124.7 ANALYSIS OF WATER LEVELS ............................................................................ 134.8 CLIMATE CHANGE .............................................................................................. 13
5.0 DISCUSSION......................................................................................................... 15
6.0 CONCLUSIONS..................................................................................................... 15
TABLES
TABLE 1Chase Creek – Flood Frequencies.
TABLE 2Chase Creek – Summary of Discharge Data.
TABLE 3Chase Creek – Mean Monthly Discharge.
TABLE 4Chase Creek – Water Levels for Upper Chase/Charcoal versus Discharge for Chase
Creek at the Mouth.
FIGURES
FIGURE 1Location Map of the Chase Creek Watershed.
FIGURE 2Location Map of Hydrometric Stations.
FIGURE 3Mean Daily Discharge by Period
FIGURE 4Year Vs Magnitude of Peak.
FIGURE 5Year Vs Duration of Peak Flow Period.
FIGURE 6Mean Daily Discharge for April
FIGURE 7Mean Daily Discharge for May
FIGURE 8Total Annual Precipitation as a Five-year Moving Average
File:504-003 Project:22080 Date: March 2005
Hydrologyof the
Chase Creek Watershed(Forest Investment Account # 2029021)
1. INTRODUCTION This report summarizes the results of Phases I and II of the Chase Creek InterpretiveReport into the hydrology of the Chase Creek watershed [refer to Appendix A for copyof the Standards Agreement]. The report includes a summary of the availablestreamflow data collected by Water Survey of Canada [WSC] for Chase Creek since 1911as well as the water level data for two stations operated for Riverside Forest ProductsLimited in the upper watershed since 2000. The report also includes a summary of theanalytical work carried out on the data and the initial interpretation of the watershedhydrology. This report will be submitted to Technical Sub-committee of the Chase Creek WatershedCommittee for review [Phase III]. This review will provide direction for the preparationof the draft interpretive hydrology report [Phase IV].
2. BACKGROUND This project, the Chase Creek Interpretive Report, was proposed to develop a betterunderstanding of the hydrology of the watershed based on the actual streamflow dataavailable. The results of this project would also be available as the basis for futurehydrology modeling when an appropriate model becomes available. The hydrology of Chase Creek has been a concern to the residents of the watershed forthe past 15 years. In 1996 there was a major flood that caused damage to much of theprivate property along the mainstem in the central portion of the watershed as well aswithin the Village of Chase. Following this flood there were several studies undertakento assess the potential affects that forest development may have had on the 1996flooding. In addition in 1999 Riverside Forest Products Limited prepared a report titledChase Creek Watershed Management Plan to address a major mountain pine beetleinfestation. That report was based on a Total Chance Plan for the watershed andassessed the potential impacts of various levels of spread of the pine beetle andsubsequent effects on peak flows. Due to the limited streamflow and climate data forthe watershed and the lack of an effective hydrology model, it was not possible toproduce statistically valid estimates of the changes to the watershed hydrology frompotential pine beetle/harvesting scenarios. The Chase Creek watershed is approximately 285km2 [drainage area to WSC station08LE112], with Chase Creek flowing west and north from the Ptarmingon and Fly hillsarea to its confluence with the South Thompson River at the Village of Chase [refer toFigure 1]. Charcoal Creek is the largest of its tributaries with a drainage area ofapproximately 98km2. The Chase Creek watershed has an H60 elevation of 1147m[Chase Creek IWAP, 1997].
Hydrology of the Chase Creek Watershed Page 3
File:504-003 Project:22080 Date: March 2005
Water Survey of Canada has collected streamflow data in the Chase Creek watershedsince 1911. Data is available for two stations. The first, station 08LE005 known as ChaseCreek near Chase was operated on a discontinuous basis from 1911 until 1968 [refer toFigure 2]. The second station, station 08LE112 known as Chase Creek near the Mouth,has been operated continuously since 1996 [refer to Map 2]. Riverside Forest ProductsLimited has collected water level data during the spring freshet at two stations in theupper watershed since 2000. One station is located near the mouth of Charcoal Creek atthe Chase-Falkland Road and the other on upper Chase Creek at the Chase-FalklandRoad [refer to Figure 2].
3. REVIEW OF EXISTING INFORMATION
The following sections are from a literature review with specific remarks extracted fromreports regarding the hydrology of Chase Creek.
3.1 Previous Reports
Hydrology Study Chase Creek Watershed1
� Chase Creek Experienced significant floods in 1935, 1948,1972, 1975, 1982,1983, 1990, 1993, and 1996.
� Major flood damage occurred in 1935, 1975, 1982, 1990, 1993 and 1996.� Mean annual precipitation - 277mm rainfall and 127mm snowfall.� Maximum monthly precipitation on record at Chase is 170.1mm occurring in
December 1971.� Recent extreme rainfall event occurred on May 29, 1996 when 27.6mm of
rain was recorded.� Mean monthly temp for Chase and Salmon Arm correlate very well.� Most flood events are primarily snowmelt generated.� Appears to be a slight trend towards greater 24-hour storms in May and
June but probably not significant in terms of runoff.� Only extreme rain event (second highest recorded) that coincides with
extreme runoff was recorded in 1996.� No changes in typical temp, furthermore, unusually high values (temp) do
not always correspond to unusual floods, confirming that SWE and rainfallare factors in spring flood generation.
� Projected that at H60 elevation (1147m) snow would normally be gone byearly May and at 1800m it would not be fully melted until mid June.
� Base length of snowmelt hydrograph is generally 4 to 6 weeks (peakingbetween early May and June) with a rapid rise to the peak flow and anequally rapid recession to the base flow.
� Many short duration hydrographs with relatively low peaks in response torainstorms
� Normal annual peak flow is snowmelt generated and may or may not occurin combination with a rainstorm.
� Max daily flows caused by rainfall alone can occur throughout the non-wintermonths, but appear to give rise to maximum daily flows less than half oftypical snowmelt freshet peaks.
1 Steffan, Robertson and Kirsten (Canada) Inc (SRK). 1997
Hydrology of the Chase Creek Watershed Page 4
File:504-003 Project:22080 Date: March 2005
� Flood frequency analysis for Chase Creek (Table 1) based on regionalanalysis;
Return Period(yr)
Max Daily Flow (m3/s)
Mean annual 18.4 5 23.5
10 27.7 20 31.8 50 37.0
100 41.0 200 45.1
Table 1. Flood Frequencies for Chase Creek
� Date of peak runoff does not change as a result of logging.� After 1970, logging appears to have had an impact on the magnitude of
peak flow (max increase in peak flow calculated at 10%).� The floods of 1996 were very unusual hydrological events and not
necessarily attributable to land use changes, although may have beenexacerbated by such changes.
� Chase Creek is over recorded for water licenses.� A decreasing trend in April 1 snow water equivalent is evident regionally,
with peaks in 1956, 1975, 1982, 1983, and 1993. Of these 1982, 1983 and1993 were years with significant floods on Chase Creek.
� The 1990 and 1993 floods were a result of extreme hydrological conditions,major floods occurred in the Salmon River at the same time.
� Indications are that the upper and lower reaches of Chase Creek and theCharcoal Creek channel below the reservoir have bankfull capacities lessthen the mean annual flood.
Analysis of Historic Stream Channel Changes2
� Bed material is gravel, and banks are sand, or sand overlaying gravel, whichare easily erodible when they are not vegetated.
� Between 1930 and 1951, upper Chase Creek became very unstable andcontributed large quantities of coarse sediment to the mainstem reachbetween the Chase Falkland Road crossing and Charcoal Creek, part ofwhich has been transported downstream over the last 40 years.
� A failure of the China Lake spillway (early 70's) resulted in severe ongoingerosion of the spillway channel that transported large amounts of bed loadto Chase Creek.
� Channel instabilities appears to be related to the transport of coarsesediments.
� Channel capacity is much less in reaches storing the “sediment wedge” thathas been migrating downstream.
2 Northwest Hydraulics Consultants Ltd. 1997
Hydrology of the Chase Creek Watershed Page 5
File:504-003 Project:22080 Date: March 2005
Landslide Inventory for Upper Chase Creek3
� 52% of landslides natural or of unknown causes.� 52% of landslides deposited material in creek.
Chase Creek Erosion and Flood Control4
� 1948 flood resulted from a rapid snowmelt caused by warm rainfall� 1975 flood (SRK Report) resulted from an intense rainstorm during the last
stages of the spring snowmelt
3.2 Hydrometric Data Sources
Since the early 1900s there have been two hydrometric stations established byWater Survey of Canada in the Chase Creek watershed. The first is station, ChaseCreek near Chase [08LE005], was a manual gauge located approximately 3.6kmsoutheast of Chase, and 5.6km upstream of the mouth [refer to Figure 2]. Thisstation was in operation from 1911 to 1912, 1915 to 1923, 1927 to 1930, andfrom 1963 to 1968. Station 08LE005 was a staff gauge read once a day duringperiod 1 (1911 - 1930) at varying times (in a few years time of reading was notreported). Throughout period 2 (1963 - 1968) the gauge was recorded twice aday, typically at 7:00 am and 7:00 pm. A remark on the file indicates that that therecords are good5. Discharge and water level data are available and were recordedbeginning in late March or early April, and ending in late September early October.Thirteen stage discharge curves were used over the period of record.
The second station, Chase Creek near the mouth [08LE112], is locatedapproximately 15m downstream of the Paquette bridge in the Village of Chase[refer to Figure 2]. This station is currently active and has been in operation since1996 with continuous water level record (period 3, 1996 - 2002). Station 08LE112is an automated hydrometric station that transmits data via a landline throughoutthe year. This station is currently using stage discharge curve table # 11.
Riverside Forest Products Limited has collected freshet water level data since 1999at locations on upper Chase Creek and Charcoal Creek at bridge crossings on theChase-Falkland Road.
3 Kamloops Forest Region, 19964 Department of Lands, Forests and Water Resources, 19755 Personal communication with Lynne Campo, Pacific and Yukon Region, Water Survey Canada
Hydrology of the Chase Creek Watershed Page 7
File:504-003 Project:22080 Date: March 2005
4. ANALYSIS
4.1 Discharge Data
The mean daily streamflow data (annual hydrographs) for Chase Creek, have beenincluded in Appendix B. This included data for stations 08LE005 and 08LE112. Thefollowing tables provide a summary of the daily and monthly discharges.
TABLE 2. Chase Creek - Summary of Discharge Data
MaximumInstantaneous
Discharge
Maximum DailyDischarge
Minimum DailyDischarge
YearFlow
(m3/s)Date
occurredFlow
(m3/s)Date
occurredFlow
(m3/s)Date
occurredStation 08LE005
1911 --- --- --- --- 0.057 September 161912 --- --- 13.7 May 16 0.076 August 121915 --- --- 8.5 May 20 0.311 August 151916 --- --- 7.22 July 3 0.255 September 61917 --- --- 11.9 May 29 0.142 April 11918 --- --- --- --- 0.255 September 201919 --- --- 7.22 May 28 0.014 August 111920 --- --- 7.65 June 8 0.000 April11921 --- --- --- --- 0.142 August 161922 --- --- 11.0 June 4 0.028 September 151923 --- --- 10.5 June 23 0.127 September 131963 --- --- 9.29 May 23 0.193 September 91964 --- --- 16.0 June 3 0.371 August 251965 --- --- 15.0 June 1 0.413 August 221966 --- --- 9.20 May 7 0.156 September 91967 --- --- --- --- 0.088 September 281968 --- --- --- --- 0.215 August 12
Station 08LE1121997 40.6 May 16 33.3 May 15 0.26 Jan 271998 20.8 May 3 18.2 May 3 0.004 August 291999 35.1 May 25 21.5 May 25 0.007 March 192000 17.0 May 22 12.63 May 22 0.159 August 252001 11.2 May 24 8.55* May 24 0.019 September 112002 37.2 May 22 37.2 May 22 0.005 August 14
* The flow identified is the maximum daily discharge recorded during the 2001 freshet period,the actual maximum daily discharge for the year was 9.03m3/s and occurred on December 31,2001.
Hydrology of the Chase Creek Watershed Page 8
File:504-003 Project:22080 Date: March 2005
TABLE 3. Chase Creek - Mean Monthly Discharge (m3/s)
Year Jan Feb Mar Apr May June July Aug Sept Oct Nov DecStation 08LE005
1911 --- --- --- --- --- 3.5 1.29 0.244 0.098 0.105 --- ---1912 0.358 --- --- 1.82 7.66 2.55 0.678 0.128 0.344 0.18 0.187 ---1915 --- --- --- --- --- 2.44 1.88 0.545 0.325 --- --- ---1916 --- --- --- --- 3.57 4.02 2.68 0.777 0.279 0.255 --- ---1917 --- --- --- 0.287 6.01 5.98 1.39 0.429 0.206 --- --- ---1918 --- --- --- --- 4.12 0.735 0.61 0.315 --- --- ---1919 --- --- --- 0.487 3.62 2.15 0.304 0.019 0.014 --- --- ---1920 --- --- --- 0.462 3.55 5.09 1.58 0.316 0.565 --- --- ---1921 --- --- --- --- --- --- 0.765 0.204 0.17 --- --- ---1922 --- --- --- 0.31 2.77 3.75 0.305 0.118 0.07 --- --- ---1923 --- --- --- 1.1 3.02 3.91 1.52 0.315 0.117 --- --- ---1963 --- --- --- --- 5.09 2.23 1.0 0.398 0.267 --- --- ---1964 --- --- --- 0.688 4.17 7.41 1.85 0.626 1.72 --- --- ---1965 --- --- --- --- 6.08 4.11 0.887 0.923 0.657 --- --- ---1966 --- --- --- 1.66 4.89 2.71 0.848 0.352 0.18 --- --- ---1967 --- --- --- --- --- --- 0.388 0.167 0.135 --- --- ---1968 --- --- --- --- --- --- 0.689 0.358 0.631 --- --- ---Mean 0.358 --- --- 0.852 4.58 3.85 1.11 0.384 0.362 0.18 0.187 ---
Station 08LE1121996 --- --- --- --- --- --- --- --- 0.500 0.681 1.31 0.7171997 0.475 0.484 1.04 4.31 13.9 3.91 2.86 0.814 0.633 1.59 1.55 0.6361998 0.361 0.609 1.51 3.91 7.80 0.935 0.431 0.097 0.067 0.286 0.487 0.2231999 1.24 --- --- 3.21 8.75 7.17 --- --- --- --- --- ---2000 0.338 0.326 0.538 4.72 7.85 4.62 1.26 0.338 --- --- --- ---2001 0.323 0.389 0.485 1.53 5.36 2.19 0.499 --- --- --- 0.517 2.332002 0.273 0.266 0.288 3.18 10.8 4.46 0.459 0.020 0.117 0.42 0.152 0.114Mean 0.502 0.415 0.772 3.48 9.077 3.881 1.102 0.317 0.329 0.744 0.803 0.804
The spring freshet usually occurs between April and June, but has started as earlyas late March and as late as early to mid-July. Refer to Appendix C for a completesummary of the mean monthly discharge, the maximum and minimum dailydischarges, and the total monthly discharge.
4.2 Timing of freshet Flows
For station 08LE005, the date of the peak flow typically occurred in May or June.At station 08LE112 the date occurred in May for all recorded years. The minimumdaily flows typically occurred in August and September at both stations.
The start of the freshet period on the hydrograph (beginning of rising limb) variesannually. In order to capture any potential trends in the timing of the start of thefreshet, it was necessary to establish the method by which the “freshet” isdefined. Based on a review of the data it was decided that a threshold dischargeof 2m3/s would be used to define the start of the freshet. This flow was also usedto determine the end of the freshet. The dates that this flow occurred were usedto calculate the start of the freshet.
Hydrology of the Chase Creek Watershed Page 9
File:504-003 Project:22080 Date: March 2005
Using the above criteria, a hydrograph (Figure 3) for each of the three timeperiods (period 1 – 1911-1923, period 2 – 1963-1968, period 3 – 1996-2001) wascreated using the mean daily discharge for each time period. The mean dailydischarge data for period 1 suggested that the freshet period started on day 122(~ May 16). The mean daily discharge data for period 2 suggested that the startof the freshet occurred on day 116 (~ May 10). For period 3, the mean dailydischarge data suggested that the start of the freshet occurred on day 105 (~April 29), suggesting a trend in the advancement (i.e. freshet occurring earlierover time) of the start of the freshet period (refer to Appendix B for annualhydrographs).
Figure 3. Mean Daily Discharge by Period
4.3 Magnitude of the Peak Discharge
For station 08LE005, the maximum daily discharge typically occurred in May orJune, and only once in July. However for the current station, 08LE112, themaximum daily discharges have all occurred in May.
In order to compare the annual discharge data collected from the two differentstations, an adjustment to the maximum daily discharge was required based onwatershed area. Station 08LE112 has a drainage area of approximately 285km2
whereas station 08LE005 has a drainage area of approximately 279km2. Forstatistical comparison, the discharge data for station 08LE005 was adjusted toreflex the larger drainage area of station 08LE112. The adjustment factor basedon drainage area was 1.022. Creating a single data set for the current station will
0
2
4
6
8
10
12
14
01-Nov 21-Dec 09-Feb 31-Mar 20-May 09-Jul 28-Aug 17-Oct 06-Dec 25-JanDate
Dis
char
ge (m
3 /s)
Period 1 Daily Average (1911 - 1923) Period 2 Daily Average (1963 - 1968) Period 3 Daily Average (1996 - 2001)
Day 105, start of period 3 freshet
Day 116, start of period 2 freshet
Day 122, start of period 1 freshet
Hydrology of the Chase Creek Watershed Page 10
File:504-003 Project:22080 Date: March 2005
allow future data to be included. A review of the mean daily hydrographs for eachperiod indicates a trend of increasing peak flow over time (Figure 4).
Figure 4. Magnitude of Peak Discharge
4.4 Duration of Run-off Hydrograph
The 2m3/s threshold was used to calculate the duration of the run-off hydrograph.For Station 08LE005, the shortest freshet duration for period 1 lastedapproximately 32 days (i.e. in 1922 with a peak of 11.0m3/s) and the longestfreshet was 74 days (i.e. in 1916 with a peak of 7.22m3/s). The average length ofthe freshet for period 1 was 57 days. the shortest freshet duration for period 2lasted approximately 46 days (i.e. in 1964 with a peak of 16.0m3/s) and thelongest freshet was 69 days (i.e. in 1965 with a peak of 15m3/s). The averagelength of freshet for period 2 was 54 days. For station 08LE112, the shortestfreshet during period 3 was 37 days (i.e. in 1998 with a peak of 18.2m3/s) and thelongest was 90 days (i.e. in 1999 with a peak of 22.6m3/s). The average length ofthe freshet for period 3 was calculated at 64 days.
A review of the scatter plot of the data (Figure 5) did not identify a discernabletrend with regards to the length of the peak flow period.
0
2
4
6
8
10
12
14
01-Nov 21-Dec 09-Feb 31-Mar 20-May 09-Jul 28-Aug 17-Oct 06-Dec 25-JanDate
Dis
char
ge (m
3 /s)
Period 1 Daily Average (1911 - 1923) Period 2 Daily Average (1963 - 1968) Period 3 Daily Average (1996 - 2001)
Period 1 - Q=6.151 m3/s
Period 2 - Q = 10.148 m3/s
Period 3 - Q=11.982m3/s
Hydrology of the Chase Creek Watershed Page 11
File:504-003 Project:22080 Date: March 2005
Figure 5. Year Vs Duration of Peak Flow Period
4.5 Minimum Flows
For station 08LE005, the minimum daily discharge typically occurred in August orSeptember and twice in April prior to spring freshet. It should be noted that thiswas a seasonal station with data only collected from the period April throughSeptember. The minimum daily discharges recorded at station 08LE112 alsooccurred in August or September. A review of the data set does not suggest anypotential trends with regards to increasing or decreasing minimum flows overtime.
4.6 Mean Daily Discharge by Month
An analysis was completed for the mean daily discharge by month to identifypotential trends in discharge increasing or decreasing over time in any particularmonth. Unfortunately, for periods 1 and 2 the data is limited to the period fromApril to September only.
Analysis of the mean daily discharge for April (Figure 6) and May (Figure 7)identified potential increasing trends in discharge over the three time periods. Nodiscernable trends were identified in the months from July to September.
0
10
20
30
40
50
60
70
80
90
100
1910 1915 1920 1925 1930 1935 1940 1945 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000
Year of peak
Leng
th o
f pea
k flo
w p
erio
d (N
umbe
r of d
ays)
Length of Peak flow Period
Hydrology of the Chase Creek Watershed Page 12
File:504-003 Project:22080 Date: March 2005
Figure 6. Mean Daily Discharge for April
Figure 7. Mean Daily Discharge for May
Chase Creek - 1911 to 2002Mean Daily flows in April
0.00
1.00
2.00
3.00
4.00
5.00
6.00
1900 1920 1940 1960 1980 2000 2020
Year
Dis
char
ge (m
3 /s)
April Mean Daily Discharge
Chase Creek - 1911 to 2002Mean Daily flows in May
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
1900 1920 1940 1960 1980 2000 2020
Year
Dis
char
ge (m
3 /s)
May Mean Daily Discharge
Hydrology of the Chase Creek Watershed Page 13
File:504-003 Project:22080 Date: March 2005
4.7 Analysis of Water Levels at Station 08LE112 with upper Chase Creek andCharcoal Creek
The stage data (water levels) from station 08LE112 are plotted against stage datathat were recorded manually for upper Chase Creek and Charcoal Creek (refer toAppendix E for comparison plots). This comparison indicates, as expected, thatthe peak flows in upper Chase Creek and Charcoal Creek generally coincide withthe peak flows in Chase Creek at the Mouth. It is difficult to clearly define the dateof the maximum water level in some instances due to the fact that water levelswere recorded only once per day. The purpose for collecting stage data in theupper watershed was to determine the timing of the peak flows in upper ChaseCreek, Charcoal Creek, relative to Chase Creek at the mouth. It was hypothesizedthat the peak flows from upper Chase Creek and Charcoal Creek may bedesynchronized, which might suggest that snowmelt in only one of the sub-basinsdrives peak flows in Chase Creek at the Mouth. It is apparent that a single waterlevel reading is insufficient to accurately determine the synchronicity of the flows.
TABLE 4. Water Levels for Upper Chase/Charcoal Vs Discharge for ChaseCreek at the Mouth
Upper Chase Creek Stage Charcoal StageYear WSC
Date of PeakDate of Peak Days from
PeakDate of Peak Days from
Peak1999 May 25 May 25 0 May 25 0
2000 May 22 No data - No data -
2001 May 24 May 24 0 May 23 -12002 May 22 No data - May 21 -1
4.8 Climate Change
To investigate the issue of climate change, the climate data for the weatherstations #1166945 and #166R45 at Salmon Arm was examined. The period ofrecord for precipitation data is 1912 to 2001. Examination of the total annualprecipitation (Figure 8) indicated an increase in annual precipitation over theperiod of record. To illustrate the increase in total annual precipitation the data setwas plotted as 5-year moving averages.
Hydrology of the Chase Creek Watershed Page 14
File:504-003 Project:22080 Date: March 2005
Figure 8. Total Annual Precipitation as a five-year moving average
A literature review found only one study6 that addressed the effects of climatechange on hydrology of six streams in south central BC. All six streamsinvestigated showed changes in temporal pattern; earlier freshet, lower latesummer-early fall flows, and higher early winter flows, and were statisticallysignificant in three streams that were examined in detail. The journal article alsostates that the results are consistent with those predicted from climate changescenarios for hydrological changes.
Other studies regarding climate change also indicate increasing trends inprecipitation throughout the central and southern interior7. Statistically significantincreasing trends in minimum daily temperatures were also noted across BC, whilethe trend of increasing maximum daily temperatures is only statistically significantin southeast BC (Kamloops, Summerland, and Cranbrook).
6 Leith, Rory M.M. and Paul H. Whitfield. Accepted June, 1998. Evidence of Climate Change Effects on
the Hydrology of Streams in South-Central BC. Canadian Water Resources Journal. Vol. 23, No. 3, 1998,P. 219.
7 Environment Canada 2001
Five-Year Running Average Salmon Arm Total Precipitation (1912 - 2000)
0
100
200
300
400
500
600
700
800
900
1000
1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010
Year
5-ye
ar a
vera
ge T
otal
Ann
ual P
reci
pita
tion
(mm
)
Total Annual Precipitation - 5-year running average (mm)
Hydrology of the Chase Creek Watershed Page 15
File:504-003 Project:22080 Date: March 2005
5. DISCUSSION
There may be several reasons for the apparent increase in the size of peak flows. Mostlikely the apparent trend is due to the differences in the data collection methods(manual readings vs. automated station) and data collection standards. During period 1water levels were determined by recording a reading from a staff gauge once a day,typically in the morning but not always (for some years the time of reading was notreported). Because only one reading a day was recorded, it is likely that the maximumdaily flows were not captured (diurnal effect). This would result in significantly lowermean daily discharges for period 1.
Throughout period 2 water levels were recorded twice a day, typically at 7:00 a.m. and7:00 p.m. Because of the improved method of data collection, the average dailydischarge for period 2 is much closer in magnitude to that of period 3 (~10%difference). Water level recording techniques (manual vs automated) is one explanationfor the differences in the magnitude of peak flow between period 2 and 3.
Factors effecting the advancement of the start of freshet flows include climate change.Potential increasing trends for precipitation noted in April and May (refer to Figures 6and 7) may be one explanation. Increased minimum temperatures (that typically occurin the evening) may also be a main contributor to an earlier start to the freshet period.
Furthermore, it appears that the peak flow trends in Chase Creek are not significantlydifferent from those in other watersheds in south central BC6, and are consistent withexpected changes in hydrology that are predicted from climate change scenarios. Thissuggests that the Chase Creek trends are related primarily to climate change.
Of the several hydrology studies conducted to date (refer to summary in section 3),none were able to link forest harvesting activities directly to flooding experienced in themiddle and lower reaches of Chase Creek or any changes in timing of peak flows.Rather, the damaging flood events were caused by extreme hydrological conditions.Since the time that forest harvesting activities commenced (coupled with clearing ofagricultural/residential) in Chase Creek, runoff may have increased by as much as 10%(UBC model for computed flows with and without harvesting - SRK).
6. CONCLUSIONS
� Although there are 23 years of hydrometric records available it is difficult toaccurately determine trends. The reason for this is that the data was collected attwo stations at different locations in the watershed, some as manual once dailywater readings, some as twice daily water level readings, and some as continuousdata.
� It is apparent that the spring freshet usually occurs during the period April – June.� Using a threshold flow of 2 m3/s as the initiation of the spring freshet, the average
start day of the freshet is day 122 for period 1, day 116 for period 2, and day 105for period 3, suggesting a trend to an earlier freshet over the 1911-2001 period.
� Based on the published data the magnitude of the peak flow it would appear thatthere has been an increase in peak flow trend over the period of record, 1911-2001.The average peak flow for period 1 was 6.151 m3/s, for period 2 was 10.148 m3/s,
Hydrology of the Chase Creek Watershed Page 16
File:504-003 Project:22080 Date: March 2005
and for period 3 was 11.982 m3/s. However, due to the accuracy of the data(manual readings vs. continuous water level recording) it is not possible to concludewhether the trend is real or not.
� There was no discernable trend in the duration of the runoff over the period ofrecord. For period 1 the mean length of the freshet was 57 days, for period 2 it was54 days, and for period 3 it was 64 days.
� There was no discernable trend for the minimum flow period. Minimum flows usuallyoccurred in the August-September period for the period of record.
� There was an increasing trend in the mean daily discharges for the months of Apriland May but not for the months July through September.
� The manual water level data collected for upper Chase Creek and Charcoal Creek atthe Chase-Falkland Road was not adequate to detect whether the peak flows fromthese two sub-basins were synchronized or de-synchronized with the timing of thepeak flow for the Water Survey of Canada station Chase Creek near the Mouth.
� Assessment of the total annual precipitation recorded at Salmon Arm for the period1912-2001 indicated a well defined increasing trend in precipitation over the periodof record.
Brian GaucherProject Technologist
D.A. Dobson, P.Eng.Senior Reviewer
BG/dd
Chase Creek
Outline of Standards for Chase Creek Interpretive Report - FIA #2029021
Phase ITask: Review Streamflow and Components of StreamflowSources: Water Survey of Canada (available data is discontinuous)
City of Kamloops data summary Riverside Forest Products Limited stage date for Charcoal Creek and
upper Chase Creek
Summary: Streamflow [Q] and Components of Streamflow [S]:
1. Plot annual hydrographs using all available daily Water Survey of Canada dataprovided in the Chase Creek database
2. Review the hydrographs and summarize- any shifts in flow volumes and patterns over the
period of record- review station notes and local climate data to
identify the potential causes of any shifts observed in the record- for periods of record determined to be reliable,
summarise the data (max, mean, min) for key flow variablesincluding maximum daily discharge, peak flow volume, late seasonflow volumes, annual yield, timing of peak, duration of peak
- frequency of key streamflow events3. Obtain and plot stage data as recorded by Water Survey of Canada (include these
data in electronic format as part of the deliverables to the Chase Creek TechnicalSub-committee to be included in the Chase Creek database)
4. Compare stage at the Water Survey of Canada gauging station with stage measured atthe two upstream locations (Charcoal Creek at the Mouth and upper Chase Creek atChase-Falkland Road)
Phase IITask: Complete Preliminary ReportSource: Results from Phase I
Summary: Review and interpret streamflow [Q] and stage [S] data and preparepreliminary report for review by Chase Creek Technical Sub-committee.
4.6 Phase IIITask: Chase Watershed Committee – Technical Subcommittee MeetingSummary: Purpose of meeting: to present the results of the preliminary report onstreamflow and stage data (Phase II) and solicit direction on the interpretationmethodology for the next phase.
Note: Depending upon availability of the Technical Sub-committee members,this and the later phases may be deferred to 2003/04 fiscal year of FIAfunding.
4.6 Phase IVTask: Complete the DRAFT Interpretive Hydrology Report.Source: Comments and direction provided at Chase Creek Technical Sub-committee meeting.
Phases IV – VIIare scheduledfor 2003/04 (seenote Phase III)
Phase I, IIand IIIDelivery:March 14,2003
Summary: A comprehensive interpretive review of the available hydrometricrecord with recommendations for future data collection, if required. The goal isto provide an improved understanding of the hydrology of the watershed.
Phase VTask: Technical Review of the Final Interpretive Hydrology ReportSummary: Solicit feedback from the Chase Watershed Technical Sub-committeeon the Phase IV Report and prepare FINAL version of the InterpretiveHydrology Report
Phase VITask: Preparation of a Technical Note
Summary: Prepare a concise summary version of the Final InterpretiveHydrology ReportPhase VIITask: WAC MeetingPurpose of meeting: Present the Interpretive Report and Technical Note to theChase Creek Watershed Advisory Committee (possibly followed by theplacement of the data and Technical Note onto a website).
Note:Possible Additional Work in 2003/04 – Not included in this standardsagreement:What Role do forests play on snow accumulation – clearcut comparisons (simpleones). As there is not enough data, compare the snow and flow in Chase, andthis will help extrapolate from elsewhere.
Rev DD Feb4/03
1911-Chase Creek Daily Discharge - 08LE005
0
1
2
3
4
5
6
7
8
9
10
1/01/1
911
1/15/1
911
1/29/1
911
2/12/1
911
2/26/1
911
3/12/1
911
3/26/1
911
4/09/1
911
4/23/1
911
5/07/1
911
5/21/1
911
6/04/1
911
6/18/1
911
7/02/1
911
7/16/1
911
7/30/1
911
8/13/1
911
8/27/1
911
9/10/1
911
9/24/1
911
10/08
/1911
10/22
/1911
11/05
/1911
11/19
/1911
12/03
/1911
12/17
/1911
12/31
/1911
Date
Dai
ly D
isch
arge
(m3 /s
)
June 2, 1911- 8.98m3/s
1912 Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
Dat
e
Janu
ary
10, 1
912
Janu
ary
20, 1
912
Janu
ary
30, 1
912
Febr
uary
9, 1
912
Febr
uary
19,
191
2
Febr
uary
29,
191
2
Mar
ch 1
0, 1
912
Mar
ch 2
0, 1
912
Mar
ch 3
0, 1
912
April
9, 1
912
April
19,
191
2
April
29,
191
2M
ay 9
, 191
2
May
19,
191
2
May
29,
191
2Ju
ne 8
, 191
2
June
18,
191
2
June
28,
191
2Ju
ly 8
, 191
2
July
18,
191
2
July
28,
191
2Au
gust
7, 1
912
Augu
st 1
7, 1
912
Augu
st 2
7, 1
912
Sept
embe
r 6, 1
912
Sept
embe
r 16,
191
2Se
ptem
ber 2
6, 1
912
Oct
ober
6, 1
912
Oct
ober
16,
191
2O
ctob
er 2
6, 1
912
Nov
embe
r 5, 1
912
Nov
embe
r 15,
191
2N
ovem
ber 2
5, 1
912
Dec
embe
r 5, 1
912
Dec
embe
r 15,
191
2
Dec
embe
r 25,
191
2
Date
Dai
ly D
isch
arge
(m3/
s) May 15, 1912 - 13.7m3/s
April 17 to June 19
1915-Chase Creek Daily Discharge - 08LE005
0
1
2
3
4
5
6
7
8
9
1/01/1
915
1/15/1
915
1/29/1
915
2/12/1
915
2/26/1
915
3/12/1
915
3/26/1
915
4/09/1
915
4/23/1
915
5/07/1
915
5/21/1
915
6/04/1
915
6/18/1
915
7/02/1
915
7/16/1
915
7/30/1
915
8/13/1
915
8/27/1
915
9/10/1
915
9/24/1
915
10/08
/1915
10/22
/1915
11/05
/1915
11/19
/1915
12/03
/1915
12/17
/1915
12/31
/1915
Date
Dai
ly D
isch
arge
(m3 /s
)
May 20, 1915 - 8.5m3/sJune 27, 1915 - 7.79m3/s
1916 Chas Creek Daily Discharge - 08LE005
0
5
10
15
20
Dat
eJa
nuar
y 10
, 191
6
Janu
ary
20, 1
916
Janu
ary
30, 1
916
Febr
uary
9, 1
916
Febr
uary
19,
191
6
Febr
uary
29,
191
6M
arch
10,
191
6M
arch
20,
191
6
Mar
ch 3
0, 1
916
April
9, 1
916
April
19,
191
6Ap
ril 2
9, 1
916
May
9, 1
916
May
19,
191
6M
ay 2
9, 1
916
June
8, 1
916
June
18,
191
6
June
28,
191
6Ju
ly 8
, 191
6Ju
ly 1
8, 1
916
July
28,
191
6Au
gust
7, 1
916
Augu
st 1
7, 1
916
Augu
st 2
7, 1
916
Sept
embe
r 6, 1
916
Sept
embe
r 16,
191
6Se
ptem
ber 2
6, 1
916
Oct
ober
6, 1
916
Oct
ober
16,
191
6
Oct
ober
26,
191
6N
ovem
ber 5
, 191
6
Nov
embe
r 15,
191
6N
ovem
ber 2
5, 1
916
Dec
embe
r 5, 1
916
Dec
embe
r 15,
191
6D
ecem
ber 2
5, 1
916
Date
Dai
ly D
isch
arge
(m3 /s
)
May 5, 1916 - 6.51m3/s July 2, 1916 - 7.22m3/s
April 26 to July 9
1917 Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
Dat
e
Janu
ary
10, 1
917
Janu
ary
20, 1
917
Janu
ary
30, 1
917
Febr
uary
9, 1
917
Febr
uary
19,
191
7
Mar
ch 1
, 191
7M
arch
11,
191
7
Mar
ch 2
1, 1
917
Mar
ch 3
1, 1
917
April
10,
191
7Ap
ril 2
0, 1
917
April
30,
191
7
May
10,
191
7M
ay 2
0, 1
917
May
30,
191
7Ju
ne 9
, 191
7
June
19,
191
7Ju
ne 2
9, 1
917
July
9, 1
917
July
19,
191
7Ju
ly 2
9, 1
917
Augu
st 8
, 191
7Au
gust
18,
191
7
Augu
st 2
8, 1
917
Sept
embe
r 7, 1
917
Sept
embe
r 17,
191
7Se
ptem
ber 2
7, 1
917
Oct
ober
7, 1
917
Oct
ober
17,
191
7
Oct
ober
27,
191
7N
ovem
ber 6
, 191
7N
ovem
ber 1
6, 1
917
Nov
embe
r 26,
191
7D
ecem
ber 6
, 191
7
Dec
embe
r 16,
191
7D
ecem
ber 2
6, 1
917
Date
Dai
ly D
isch
arge
(m3 /s
) May 29, 1917 - 11.9m3/s
May 10 to July 8
1918-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
918
1/15/1
918
1/29/1
918
2/12/1
918
2/26/1
918
3/12/1
918
3/26/1
918
4/09/1
918
4/23/1
918
5/07/1
918
5/21/1
918
6/04/1
918
6/18/1
918
7/02/1
918
7/16/1
918
7/30/1
918
8/13/1
918
8/27/1
918
9/10/1
918
9/24/1
918
10/08
/1918
10/22
/1918
11/05
/1918
11/19
/1918
12/03
/1918
12/17
/1918
12/31
/1918
Date
Dai
ly D
isch
arge
(m3 /s
)
June 1 and 10, 1918 - 7.79m3/s
April 23 to June 22
1919-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
919
1/15/1
919
1/29/1
919
2/12/1
919
2/26/1
919
3/12/1
919
3/26/1
919
4/09/1
919
4/23/1
919
5/07/1
919
5/21/1
919
6/04/1
919
6/18/1
919
7/02/1
919
7/16/1
919
7/30/1
919
8/13/1
919
8/27/1
919
9/10/1
919
9/24/1
919
10/08
/1919
10/22
/1919
11/05
/1919
11/19
/1919
12/03
/1919
12/17
/1919
12/31
/1919
Date
Dai
ly D
isch
arge
(m3 /s
)
May 28, 1919 - 7.22m3/s
May 14 to June 18
1920-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
920
1/15/1
920
1/29/1
920
2/12/1
920
2/26/1
920
3/11/1
920
3/25/1
920
4/08/1
920
4/22/1
920
5/06/1
920
5/20/1
920
6/03/1
920
6/17/1
920
7/01/1
920
7/15/1
920
7/29/1
920
8/12/1
920
8/26/1
920
9/09/1
920
9/23/1
920
10/07
/1920
10/21
/1920
11/04
/1920
11/18
/1920
12/02
/1920
12/16
/1920
12/30
/1920
Date
Dai
ly D
isch
arge
(m3 /s
)
June 8 and 16 - 7.65m3/s
May 6 to July 11
1921-Chase Creek Daily Discharge - 08LE005
0
1
2
3
4
5
6
7
1/01/1
921
1/15/1
921
1/29/1
921
2/12/1
921
2/26/1
921
3/12/1
921
3/26/1
921
4/09/1
921
4/23/1
921
5/07/1
921
5/21/1
921
6/04/1
921
6/18/1
921
7/02/1
921
7/16/1
921
7/30/1
921
8/13/1
921
8/27/1
921
9/10/1
921
9/24/1
921
10/08
/1921
10/22
/1921
11/05
/1921
11/19
/1921
12/03
/1921
12/17
/1921
12/31
/1921
Date
Dai
ly D
isch
arge
(m3 /s
)
June 8, 1921 - 6.31m3/s
1922-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
922
1/15/1
922
1/29/1
922
2/12/1
922
2/26/1
922
3/12/1
922
3/26/1
922
4/09/1
922
4/23/1
922
5/07/1
922
5/21/1
922
6/04/1
922
6/18/1
922
7/02/1
922
7/16/1
922
7/30/1
922
8/13/1
922
8/27/1
922
9/10/1
922
9/24/1
922
10/08
/1922
10/22
/1922
11/05
/1922
11/19
/1922
12/03
/1922
12/17
/1922
12/31
/1922
Date
Dai
ly D
isch
arge
(m3 /s
)
June 3, 1922 - 11.0m3/s
May 16 to June 17
1923-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
923
1/15/1
923
1/29/1
923
2/12/1
923
2/26/1
923
3/12/1
923
3/26/1
923
4/09/1
923
4/23/1
923
5/07/1
923
5/21/1
923
6/04/1
923
6/18/1
923
7/02/1
923
7/16/1
923
7/30/1
923
8/13/1
923
8/27/1
923
9/10/1
923
9/24/1
923
10/08
/1923
10/22
/1923
11/05
/1923
11/19
/1923
12/03
/1923
12/17
/1923
12/31
/1923
Date
Dai
ly d
isch
arge
(m3 /s
)
June 23, 1923 - 10.5m3/s
May 6 to July 10
1963-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
963
1/15/1
963
1/29/1
963
2/12/1
963
2/26/1
963
3/12/1
963
3/26/1
963
4/09/1
963
4/23/1
963
5/07/1
963
5/21/1
963
6/04/1
963
6/18/1
963
7/02/1
963
7/16/1
963
7/30/1
963
8/13/1
963
8/27/1
963
9/10/1
963
9/24/1
963
10/08
/1963
10/22
/1963
11/05
/1963
11/19
/1963
12/03
/1963
12/17
/1963
12/31
/1963
Date
Dai
ly D
isch
arge
(m3 /s
)
May 23, 1963 - 9.29m3/s
April 26 to June 16
1964-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
964
1/15/1
964
1/29/1
964
2/12/1
964
2/26/1
964
3/11/1
964
3/25/1
964
4/08/1
964
4/22/1
964
5/06/1
964
5/20/1
964
6/03/1
964
6/17/1
964
7/01/1
964
7/15/1
964
7/29/1
964
8/12/1
964
8/26/1
964
9/09/1
964
9/23/1
964
10/07
/1964
10/21
/1964
11/04
/1964
11/18
/1964
12/02
/1964
12/16
/1964
12/30
/1964
Date
Dai
ly D
isch
arge
(m3 /s
)
June 2 1964 -16m 3/s
May 9 to June 24
1965-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
965
1/15/1
965
1/29/1
965
2/12/1
965
2/26/1
965
3/12/1
965
3/26/1
965
4/09/1
965
4/23/1
965
5/07/1
965
5/21/1
965
6/04/1
965
6/18/1
965
7/02/1
965
7/16/1
965
7/30/1
965
8/13/1
965
8/27/1
965
9/10/1
965
9/24/1
965
10/08
/1965
10/22
/1965
11/05
/1965
11/19
/1965
12/03
/1965
12/17
/1965
12/31
/1965
Date
Dai
ly D
isch
arge
(m3 /s
)
June 1, 1965 - 15.0m3/s
April 13 to June 21
1966-Chase Creek Daily Discharge - 08LE005
0
5
10
15
20
1/01/1
966
1/15/1
966
1/29/1
966
2/12/1
966
2/26/1
966
3/12/1
966
3/26/1
966
4/09/1
966
4/23/1
966
5/07/1
966
5/21/1
966
6/04/1
966
6/18/1
966
7/02/1
966
7/16/1
966
7/30/1
966
8/13/1
966
8/27/1
966
9/10/1
966
9/24/1
966
10/08
/1966
10/22
/1966
11/05
/1966
11/19
/1966
12/03
/1966
12/17
/1966
12/31
/1966
Date
Dai
ly D
isch
arge
(m/s
)
May 7, 1966 - 9.2m3/sJune 1, 1966 - 7.28m3/s
May 4 to June 17
1967-Chase Creek Daily Discharge - 08LE005
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
1/01/1
967
1/15/1
967
1/29/1
967
2/12/1
967
2/26/1
967
3/12/1
967
3/26/1
967
4/09/1
967
4/23/1
967
5/07/1
967
5/21/1
967
6/04/1
967
6/18/1
967
7/02/1
967
7/16/1
967
7/30/1
967
8/13/1
967
8/27/1
967
9/10/1
967
9/24/1
967
10/08
/1967
10/22
/1967
11/05
/1967
11/19
/1967
12/03
/1967
12/17
/1967
12/31
/1967
Date
Dai
ly D
isch
arge
(m3 /s
)
1968-Chase Creek Daily Discharge - 08LE005
0
0.5
1
1.5
2
2.5
3
3.5
4
1/01/1
968
1/15/1
968
1/29/1
968
2/12/1
968
2/26/1
968
3/11/1
968
3/25/1
968
4/08/1
968
4/22/1
968
5/06/1
968
5/20/1
968
6/03/1
968
6/17/1
968
7/01/1
968
7/15/1
968
7/29/1
968
8/12/1
968
8/26/1
968
9/09/1
968
9/23/1
968
10/07
/1968
10/21
/1968
11/04
/1968
11/18
/1968
12/02
/1968
12/16
/1968
12/30
/1968
Date
Dai
ly D
isch
arge
(m3 /s
)
1996 Chase Creek Daily Discharge - 08LE112
0
1
2
3
4
5
6
7
8
9
10
1/01/1
996
1/15/1
996
1/29/1
996
2/12/1
996
2/26/1
996
3/11/1
996
3/25/1
996
4/08/1
996
4/22/1
996
5/06/1
996
5/20/1
996
6/03/1
996
6/17/1
996
7/01/1
996
7/15/1
996
7/29/1
996
8/12/1
996
8/26/1
996
9/09/1
996
9/23/1
996
10/07
/1996
10/21
/1996
11/04
/1996
11/18
/1996
12/02
/1996
12/16
/1996
12/30
/1996
Date
Dai
ly D
isch
arge
(m3 /s
)
1997 Chase Creek Daily Discharge - 08LE112
0
5
10
15
20
25
30
35
1/01/1
997
1/15/1
997
1/29/1
997
2/12/1
997
2/26/1
997
3/12/1
997
3/26/1
997
4/09/1
997
4/23/1
997
5/07/1
997
5/21/1
997
6/04/1
997
6/18/1
997
7/02/1
997
7/16/1
997
7/30/1
997
8/13/1
997
8/27/1
997
9/10/1
997
9/24/1
997
10/08
/1997
10/22
/1997
11/05
/1997
11/19
/1997
12/03
/1997
12/17
/1997
12/31
/1997
Date
Dai
ly D
isch
arge
(m3 /s
)
May 15, 1997 - 33.3m3/s
July 12, 1997 - 14.9m3/s
April 16 to June 14
1998 Chase Creek Daily Discharge - 08LE112
0
5
10
15
20
1/01/1
998
1/15/1
998
1/29/1
998
2/12/1
998
2/26/1
998
3/12/1
998
3/26/1
998
4/09/1
998
4/23/1
998
5/07/1
998
5/21/1
998
6/04/1
998
6/18/1
998
7/02/1
998
7/16/1
998
7/30/1
998
8/13/1
998
8/27/1
998
9/10/1
998
9/24/1
998
10/08
/1998
10/22
/1998
11/05
/1998
11/19
/1998
12/03
/1998
12/17
/1998
12/31
/1998
Date
Dai
ly D
isch
arge
(m3 /s
)
May 3, 1998 - 18.2m3/s
April 21 to May 28
1999 Chase Creek Daily Discharge - 08LE112
0
5
10
15
20
25
1/01/1
999
1/15/1
999
1/29/1
999
2/12/1
999
2/26/1
999
3/12/1
999
3/26/1
999
4/09/1
999
4/23/1
999
5/07/1
999
5/21/1
999
6/04/1
999
6/18/1
999
7/02/1
999
7/16/1
999
7/30/1
999
8/13/1
999
8/27/1
999
9/10/1
999
9/24/1
999
10/08
/1999
10/22
/1999
11/05
/1999
11/19
/1999
12/03
/1999
12/17
/1999
12/31
/1999
Date
Dai
ly D
isch
arge
(m3 /s
)
May 25, 1999 - 22.6m3/s
April 18 to July 17
2000 Chase Creek Daily Discharge - 08LE112
0
5
10
15
1/01/2
000
1/15/2
000
1/29/2
000
2/12/2
000
2/26/2
000
3/11/2
000
3/25/2
000
4/08/2
000
4/22/2
000
5/06/2
000
5/20/2
000
6/03/2
000
6/17/2
000
7/01/2
000
7/15/2
000
7/29/2
000
8/12/2
000
8/26/2
000
9/09/2
000
9/23/2
000
10/07
/2000
10/21
/2000
11/04
/2000
11/18
/2000
12/02
/2000
12/16
/2000
12/30
/2000
Date
Dai
ly D
isch
arge
(m3 /s
)
May 21, 2000 - 12.6m3/s
April 22 to June 28
2001 Chase Creek Daily Discharge - 08LE112
0
5
10
15
20
1/01/2
001
1/15/2
001
1/29/2
001
2/12/2
001
2/26/2
001
3/12/2
001
3/26/2
001
4/09/2
001
4/23/2
001
5/07/2
001
5/21/2
001
6/04/2
001
6/18/2
001
7/02/2
001
7/16/2
001
7/30/2
001
8/13/2
001
8/27/2
001
9/10/2
001
9/24/2
001
10/08
/2001
10/22
/2001
11/05
/2001
11/19
/2001
12/03
/2001
12/17
/2001
12/31
/2001
Date
Dai
ly D
isch
arge
(m3 /s
)
May 15, 2001 - 8.4m3/sMay 24, 2001 - 8.55m3/s
April 25 to June 19
2002 Chase Creek Daily Discharge - 08LE112
0
5
10
15
20
25
30
35
40
1/01/2
002
1/15/2
002
1/29/2
002
2/12/2
002
2/26/2
002
3/12/2
002
3/26/2
002
4/09/2
002
4/23/2
002
5/07/2
002
5/21/2
002
6/04/2
002
6/18/2
002
7/02/2
002
7/16/2
002
7/30/2
002
8/13/2
002
8/27/2
002
9/10/2
002
9/24/2
002
10/08
/2002
10/22
/2002
11/05
/2002
11/19
/2002
12/03
/2002
12/17
/2002
12/31
/2002
Date
Dai
ly D
isch
arge
(m3 /s
)
May 22, 2002 - 37.2m3/s
April 12 to June 24
CHASE CREEKMaximum Monthly Discharge
Year jan Feb March April May June July August September October November December1911 - - - - - 8.98 3.88 0.368 0.159 0.142 - -1912 - - 0.595 4.47 13.7 4.47 1.53 0.269 0.963 0.311 0.227 -1915 - - - - 8.5 7.79 3.54 1.16 0.453 - - -1916 - - - - 6.51 6.23 7.22 1.3 0.396 0.255 - -1917 - - - 0.595 11.9 9.63 4.25 1.13 0.311 - - -1918 - - - - - 7.79 1.22 1.02 0.566 - - -1919 - - - 2.27 7.22 3.54 0.85 0.028 0.014 - - -1920 - - - 1.61 6.23 7.65 3.91 0.793 0.9006 - - -1921 - - - - - - 2.15 0.34 0.17 - - -1922 - - - 0.566 8.44 11 0.566 0.227 0.227 - - -1923 - - - 2.18 5.38 10.5 3.48 0.566 0.227 - - -1963 - - - - 9.29 5.21 1.78 0.951 0.578 - - -1964 - - - 1 10.6 16 5.21 1.08 4.05 - - -1965 - - - - 12.7 15 1.84 0.211 1.17 - - -1966 - - - 2.52 9.2 7.28 2.09 0.583 0.215 - - -1967 - - - - - - 0.83 0.263 0.227 - - -1968 - - - - - - 1.7 1.12 1.94 - - -
1996 - - - - - - - - 1.18 2 3.1 1.11997 0.636 0.592 2.32 10.3 33.3 11.4 14.9 1.24 1.94 3.2 4.33 0.951998 0.65 0.786 3.43 12.7 18.2 1.41 1.37 0.265 0.252 0.464 0.867 0.441999 8.44 - - 9.33 21.5 12.2 - - - - - -2000 0.539 0.426 0.722 11 12.6 8.14 2.25 0.843 - - - -2001 0.374 1.47 0.654 5.33 8.55 4.2 0.997 - - - 1.59 9.032002 0.453 0.393 0.595 8.03 37.2 9.52 1.58 0.05 0.212 0.829 0.205 0.139
Site 08LE005
Site 08LE112
CHASE CREEKMinimum Monthly Discharge
Year jan Feb March April May June July August September October November December1911 - - - - - 1.27 0.351 0.079 0.057 0.057 - -1912 - - 0.142 0.204 4.16 0.504 0.269 0.076 0.076 0.099 0.142 -1915 - - - - - 1.16 1.16 0.311 0.311 - - -1916 - - - - 1.98 2.27 1.53 0.396 0.255 0.255 - -1917 - - - 0.142 0.736 3.03 0.453 0.198 0.198 - - -1918 - - - - - 1.22 0.425 0.425 0.255 - - -1919 - - - 0.142 1.13 0.85 0.028 0.014 0.014 - - -1920 - - - 0 1.36 2.38 0.283 0.283 0.283 - - -1921 - - - - - - 0.34 0.142 0.17 - - -1922 - - - 0.085 0.878 0.651 0.17 0.085 0.028 - - -1923 - - - 0.283 1.25 1.44 0.354 0.227 0.127 - - -1963 - - - - 2.69 0.855 0.453 0.204 0.193 - - -1964 - - - 0.416 0.855 2.18 0.799 0.371 0.433 - - -1965 - - - - 2.94 1.05 0.484 0.413 0.47 - - -1966 - - - 1.27 1.19 0.929 0.45 0.204 0.156 - - -1967 - - - - - - 0.156 0.102 0.088 - - -1968 - - - - - - 0.28 0.215 0.261 - - -
1996 - - - - - - - - 0.175 0.424 0.754 0.361997 0.26 0.32 0.44 1.71 7 2.01 1.24 0.516 0.308 0.657 0.968 0.51998 0.14 0.395 0.594 1.59 1.42 0.663 0.088 0.004 0.004 0.185 0.354 0.031999 0.295 - - 1.09 3.37 3.72 - - - - - -2000 0.18 0.24 0.378 0.731 4.4 1.66 0.598 0.159 - - - -2001 0.246 0.219 0.269 0.521 3.15 0.902 0.128 - - - 0.295 0.3432002 0.16 0.175 0.16 0.608 2.68 1.42 0.028 0.005 0.055 0.101 0.098 0.09
Site 08LE005
Site 08LE112
CHASE CREEKMean Monthly Discharge
Year jan Feb March April May June July August September October November December1911 - - - - 3.5 1.29 0.244 0.098 0.105 - -1912 - - 0.358 1.82 7.66 2.55 0.678 0.128 0.344 0.18 0.187 -1915 - - - - 2.44 1.88 0.545 0.325 - - -1916 - - - 3.57 4.02 2.68 0.777 0.279 0.255 - -1917 - - - 0.287 6.01 5.98 1.39 0.429 0.206 - - -1918 - - - - 4.12 0.735 0.61 0.315 - - -1919 - - - 0.487 3.62 2.15 0.304 0.019 0.014 - - -1920 - - - 0.462 3.55 5.09 1.58 0.316 0.565 - - -1921 - - - - - 0.765 0.204 0.17 - - -1922 - - - 0.31 2.77 3.75 0.305 0.118 0.07 - - -1923 - - - 1.1 3.02 3.91 1.52 0.315 0.177 - - -1963 - - - 5.09 2.23 1 0.398 0.267 - - -1964 - - - 0.688 4.17 7.41 1.85 0.626 1.72 - - -1965 - - - 6.08 4.11 0.887 0.923 0.657 - - -1966 - - - 1.66 4.89 2.71 0.848 0.352 0.18 - - -1967 - - - - - 0.388 0.167 0.135 - - -1968 - - - - - 0.689 0.358 0.631 - - -
1996 - - - - - - - - 0.5 0.681 1.31 0.7171997 0.475 0.484 1.04 4.31 13.9 3.91 2.86 0.814 0.633 1.59 1.55 0.6361998 0.361 0.609 1.51 3.91 7.8 0.935 0.431 0.097 0.067 0.286 0.487 0.2231999 1.24 - - 3.21 8.75 7.17 - - - - - -2000 0.338 0.326 0.538 4.72 7.85 4.62 1.26 0.338 - - - -2001 0.323 0.389 0.485 1.53 5.36 2.19 0.499 - - - 0.517 2.332002 0.273 0.266 0.288 3.18 10.8 4.46 0.459 0.02 0.117 0.42 0.152 0.114
Site 08LE112
Site 08LE005
CHASE CREEKTotal Monthly Discharge
Year jan Feb March April May June July August September October November December1911 - - - - 105.03 40.001 7.553 2.945 3.244 - -1912 - - 11.109 54.742 237.48 76.474 21.025 3.959 10.318 5.576 5.606 -1915 - - - - - 73.17 58.43 16.898 9.756 - - -1916 - - - - 110.7 120.66 83 24.088 8.355 7.905 - -1917 - - - 8.609 186.302 179.45 43.008 13.299 6.166 - - -1918 - - - - - 123.57 22.773 18.919 9.453 - - -1919 - - - 14.601 112.16 64.42 9.43 0.574 0.42 - - -1920 - - - 13.858 109.96 152.69 48.948 9.793 6.938 - - -1921 - - - - - - 23.72 6.324 5.1 - - -1922 - - - 9.287 85.902 112.401 9.462 3.653 2.097 - - -1923 - - - 32.951 93.68 117.41 47.109 9.754 5.313 - - -1963 - - - - 157.65 66.922 31.043 12.34 8.005 - - -1964 - - - 20.645 129.343 222.39 57.465 19.404 51.737 - - -1965 - - - - 188.61 123.44 27.498 28.603 19.699 - - -1966 - - - 49.71 151.49 81.369 26.28 10.907 5.408 - - -1967 - - - - - - 12.035 5.191 4.045 - - -1968 - - - - - - 21.373 11.096 18.921 - - -
1996 - - - - - - - - 14.986 21.1 39.242 22.2291997 14.712 13.551 32.214 129.28 430.36 117.34 88.69 25.219 18.976 49.183 46.587 19.7241998 11.189 17.045 46.828 117.39 241.77 28.04 13.368 3.005 2.005 8.858 14.615 6.91999 38.543 - - 96.26 271.17 214.98 - - - - - -2000 10.468 9.441 16.67 141.487 243.25 138.57 39.169 10.491 - - - -2001 10.003 10.901 15.023 45.783 166.3 65.742 15.478 - - - 15.51 72.2942002 8.461 7.444 8.941 95.311 335 133.85 14.222 0.616 3.514 13.01 4.548 3.52
Site 08LE005
Site 08LE112
Chase Creek - 1911 - 2002 Maximum Daily Discharge - Station 08LE005 (adjusted) and 08LE112
0
5
10
15
20
25
30
35
40
1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010
Year
Adj
uste
d D
isch
arge
(m3 /s
)
Max Flow = -262.65 + 0.14 YearP-Value = 0.005
Chase Creek - 1911 - 2002 Minimum Daily Discharge - Station 08LE005 (adjusted) and 08LE112
0.00
0.10
0.20
0.30
0.40
0.50
1900 1920 1940 1960 1980 2000 2020
Year
Adj
uste
d D
isch
arge
(m3 /s
)
Min Flow = 0.71 - 0.0003 YearP-Value = 0.71
Chase Creek 1911 - 2002(Day of Peak flow)
0
40
80
120
160
200
1910 1920 1930 1940 1950 1960 1970 1980 1990 2000Year
Day
of P
eak
Flow
(# o
f day
s in
year
)
Date = 581.99 - 0.22 YearP-Value = 0.016
Chase Creek 1911 - 2002 (Duration of Peak flow Period)
0
20
40
60
80
100
1910 1920 1930 1940 1950 1960 1970 1980 1990 2000
Year
Dura
tiono
f pea
k flo
w (N
umbe
r of d
ays)
Length = -91.62 + 0.08 YearP-Value = 0.45
Salmon Arm - 1912 - 1997 Total Annual Precipitation
0
200
400
600
800
1000
1900 1910 1920 1930 1940 1950 1960 1970 1980 1990 2000 2010
Year
Prec
ipita
tion
(mm
)
Precip = -3856.37 + 2.25 YearP-Value < 0.001
1999 Chase Creek Freshet Stage Data
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
5/24/1
999
5/25/1
999
5/26/1
999
5/27/1
999
5/28/1
999
5/29/1
999
5/30/1
999
5/31/1
999
6/01/1
999
6/02/1
999
6/03/1
999
6/04/1
999
6/05/1
999
6/06/1
999
6/07/1
999
6/08/1
999
6/09/1
999
6/10/1
999
6/11/1
999
6/12/1
999
6/13/1
999
6/14/1
999
6/15/1
999
6/16/1
999
6/17/1
999
Date
Wat
er le
vel (
m)
1999 Upper Chase stream level 1999 Charcoal stream level 1999 Chase stream level - 08LE1112
2000 Chase Creek Freshet - Stage Data
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.64/
18/2
000
4/20
/200
0
4/22
/200
04/
24/2
000
4/26
/200
0
4/28
/200
04/
30/2
000
5/02
/200
0
5/04
/200
05/
06/2
000
5/08
/200
0
5/10
/200
05/
12/2
000
5/14
/200
0
5/16
/200
05/
18/2
000
5/20
/200
0
5/22
/200
05/
24/2
000
5/26
/200
0
5/28
/200
05/
30/2
000
6/01
/200
0
6/03
/200
06/
05/2
000
6/07
/200
0
6/09
/200
06/
11/2
000
6/13
/200
06/
15/2
000
6/17
/200
0
6/19
/200
06/
21/2
000
6/23
/200
0
6/25
/200
0
Date
Wat
er L
evel
(m)
2000 Upper Chase stream level 2000 Charcoal stream level 2000 Chase stream level - 08LE1112
2001 Chase Creek Freshet Stage Data
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
4/27/2
001
4/29/2
001
5/01/2
001
5/03/2
001
5/05/2
001
5/07/2
001
5/09/2
001
5/11/2
001
5/13/2
001
5/15/2
001
5/17/2
001
5/19/2
001
5/21/2
001
5/23/2
001
5/25/2
001
5/27/2
001
5/29/2
001
5/31/2
001
6/02/2
001
6/04/2
001
6/06/2
001
Date
Wat
er L
evel
(m)
2001 Upper Chase stream level 2001 Charcoal stream level 2001 Chase stream level - 08LE1112
2002 Chase Creek Freshet Stage Data
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
5/01/2
001
5/03/2
001
5/05/2
001
5/07/2
001
5/09/2
001
5/11/2
001
5/13/2
001
5/15/2
001
5/17/2
001
5/19/2
001
5/21/2
001
5/23/2
001
5/25/2
001
5/27/2
001
5/29/2
001
5/31/2
001
6/02/2
001
6/04/2
001
6/06/2
001
6/08/2
001
6/10/2
001
6/12/2
001
6/14/2
001
6/16/2
001
6/18/2
001
6/20/2
001
6/22/2
001
6/24/2
001
6/26/2
001
6/28/2
001
6/30/2
001
Date
Wat
er L
evel
s (m
)
2002 Upper Chase stream level 2002 Charcoal stream level 2002 Chase stream level - 08LE1112
1915 Chase Creek Water Level - 08LE005
0.00
0.20
0.40
0.60
0.80
1.00
1.205/09/1915
5/16/1915
5/23/1915
5/30/1915
6/06/1915
6/13/1915
6/20/1915
6/27/1915
7/04/1915
7/11/1915
7/18/1915
7/25/1915
8/01/1915
8/08/1915
8/15/1915
Date
Gau
ge le
vel (
m)
1916 Chase Creek Water Level - 08LE005
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
4/05/1
915
4/12/1
915
4/19/1
915
4/26/1
915
5/03/1
915
5/10/1
915
5/17/1
915
5/24/1
915
5/31/1
915
6/07/1
915
6/14/1
915
6/21/1
915
6/28/1
915
7/05/1
915
7/12/1
915
7/19/1
915
7/26/1
915
8/02/1
915
8/09/1
915
8/16/1
915
8/23/1
915
8/30/1
915
Date
Wat
er L
evel
(m)
1919 Chase Creek Water Level - 08LE005
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
4/01/1
919
4/08/1
919
4/15/1
919
4/22/1
919
4/29/1
919
5/06/1
919
5/13/1
919
5/20/1
919
5/27/1
919
6/03/1
919
6/10/1
919
6/17/1
919
6/24/1
919
7/01/1
919
7/08/1
919
7/15/1
919
7/22/1
919
7/29/1
919
8/05/1
919
8/12/1
919
8/19/1
919
8/26/1
919
Date
Wat
er L
evel
(m)
1963 Chase Creek Water Level - 08LE005
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
4/11/1
963
4/18/1
963
4/25/1
963
5/02/1
963
5/09/1
963
5/16/1
963
5/23/1
963
5/30/1
963
6/06/1
963
6/13/1
963
6/20/1
963
6/27/1
963
7/04/1
963
7/11/1
963
7/18/1
963
7/25/1
963
8/01/1
963
8/08/1
963
8/15/1
963
8/22/1
963
8/29/1
963
Date
Wat
er L
evel
(m)
1964 Chase Creek Water Level - 08LE005
0.00
0.20
0.40
0.60
0.80
1.00
1.20
4/01/1
964
4/08/1
964
4/15/1
964
4/22/1
964
4/29/1
964
5/06/1
964
5/13/1
964
5/20/1
964
5/27/1
964
6/03/1
964
6/10/1
964
6/17/1
964
6/24/1
964
7/01/1
964
7/08/1
964
7/15/1
964
7/22/1
964
7/29/1
964
8/05/1
964
8/12/1
964
8/19/1
964
8/26/1
964
9/02/1
964
9/09/1
964
9/16/1
964
9/23/1
964
9/30/1
964
Date
Wat
er L
evel
(m)
1965 Chase Creek Water Level - 08LE005
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
4/05/1
965
4/12/1
965
4/19/1
965
4/26/1
965
5/03/1
965
5/10/1
965
5/17/1
965
5/24/1
965
5/31/1
965
6/07/1
965
6/14/1
965
6/21/1
965
6/28/1
965
7/05/1
965
7/12/1
965
7/19/1
965
7/26/1
965
8/02/1
965
8/09/1
965
8/16/1
965
8/23/1
965
8/30/1
965
9/06/1
965
9/13/1
965
9/20/1
965
9/27/1
965
Date
Wat
er L
evel
(m)
1966 Chase Creek Water Level - 08LE005
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
4/01/1
966
4/08/1
966
4/15/1
966
4/22/1
966
4/29/1
966
5/06/1
966
5/13/1
966
5/20/1
966
5/27/1
966
6/03/1
966
6/10/1
966
6/17/1
966
6/24/1
966
7/01/1
966
7/08/1
966
7/15/1
966
7/22/1
966
7/29/1
966
8/05/1
966
8/12/1
966
8/19/1
966
8/26/1
966
9/02/1
966
9/09/1
966
9/16/1
966
9/23/1
966
9/30/1
966
Date
Wat
er L
evel
(m)
1967 Chase Creek Water Level - 08LE005
0.00
0.05
0.10
0.15
0.20
0.25
0.30
7/01/1
967
7/08/1
967
7/15/1
967
7/22/1
967
7/29/1
967
8/05/1
967
8/12/1
967
8/19/1
967
8/26/1
967
9/02/1
967
9/09/1
967
9/16/1
967
9/23/1
967
9/30/1
967
Date
Wat
er L
evel
(m)