hydrocloroflourocarbons (hcfc) phase out projects: case studies, lessons learnt grenada
DESCRIPTION
Hydrocloroflourocarbons (HCFC) Phase Out Projects: Case studies, lessons learnt Grenada. Overview:. HPMP preparation Project Work Plan Survey Design and Implementation National Consultations Preparation of Project document Review of Project Document –UNEP Review of Project Document-MLFS - PowerPoint PPT PresentationTRANSCRIPT
Overview:HPMP preparation Project
Work Plan Survey Design and Implementation National Consultations Preparation of Project document Review of Project Document –UNEP Review of Project Document-MLFS Submission to Ex-Com
WORK PLAN
CONSULTANCY SERVICE FOR GRENADA HPMP PROJECTWORKPLANMARCH 2009 TO AUGUST 2010PREPARED BY: JN TELESFORD - LEAD CONSULTANT and NOURE-SUBMITTED ON 17/03/2010
ACT # TASK ACTIVITIES START DATE END DATE Responsible RESULTS/REMARKS
50 First UNEP Country Mission
Meet with all stakeholders including Government Officials 3/16/2010 3/18/2010 UNEP, NOU Done
100 Developmement of survey tool 3/1/2010 3/19/2010 Lead Consultant Done
101 Develop draft 1 of survey tool 3/1/2010 3/19/2010 Lead Consultant Done
102 Submit to NOU/UNEP for comments 3/15/2010 3/19/2010 Lead, NOU, UNEP Done
103 Receive comments 3/15/2010 3/19/2010 NOU Done
104 Finalise Draft 3/15/2010 3/19/2010 NOU, UNEP
105 Deliver Final Survey tool 3/19/2010 Lead Consultant
200Planning, Design and Management of Survey 3/22/2010 5/31/2010 Lead Consultant
201 Planning and design of survey format 3/22/2010 3/31/2010 Lead Consultant
202 Piloting of survey tool/tool validation 3/22/2010 3/31/2010 Consultants
203 Finalise survey Format 3/31/2010 Lead Consultant
300 Conduct Survey 4/1/2010 5/31/2010 Consultants
GRENADA HCFC PHASE-OUT MANAGEMENT PLAN (HPMP)
HPMP Work Plan
National Consultation
GRENADA HCFC PHASE OUT AND MANAGEMENT PLAN (HPMP) PROJECT
SERVICE TECHNICIANS SURVEY FORM
INSTRUCTIONS
Please read all questions carefully and answer as accurately as possible. Your best estimates will also suffice.
########## QUESTIONS BEGIN HERE ##########
SECTION A COMPANY DATA
1. NAME OF COMPANY OR OWNER (if not a company): _____________________________________________________________________________________
Address: _____________________________________________________________________________
2. CONTACT DETAILS
Contact Person: ________________________ Telephone: _______________ (W) ______________ (M)
Fax: _________________ E-mail : __________________________________________________
SECTION B: EQUIPMENT SERVICE AND INSTALLATION
3. Can you please provide a list of your current and past clients and the average number of units serviced per year (i.e. persons for whom you have provided service for air conditioning and refrigeration)?
Name of client/Business activity Average number of units or installations serviced by type of unit Commercial
Refrigeration Domestic AC unit
Domestic Refrigeration
Commercial AC units
Industrial Refrigeration
Refrigerated Transport
Con
du
ct S
urv
ey
Review of Project with UNEP/ROLAC
Review with MLFS
Submission to Ex-Com
Approval of HPMP
THANK YOU!!