hydraulic control treatment system - …...ed system operation (n-3 licensed operator), process...

1
GWTT constructed a ground water extraction and treatment system in Kearny, New Jersey designed to remediate groundwater contaminated with hexavalent chromium (Cr VI), dense non-aqueous phase liquid (DNAPL), and volatile organic compounds (VOCs) from a total of 42 hydraulic control wells installed within the confines of a slurry wall. The treatment process utilized chromium reduction, metals precipitation, pH adjustment, and carbon/ organo-clay technologies to maintain the system effluent within limits of a NJPDES DSW permit. GWTT was responsible for the installation of all interior building treatment components and mechanical work including process piping, HVAC, electrical and instrumentation and controls. After project construction was complete, GWTT performed startup and commissioning services for the system and provid- ed system operation (N-3 licensed operator), process optimization, and maintenance for the initial 60 days of operation. Hydraulic Control Treatment System Ground/Water Treatment & Technology 627 Mt. Hope Road Wharton, NJ 07885 p: (973) 983-0901 f: (973) 983-0903 www.gwttllc.com © 2019 GROUND/WATER TREATMENT & TECHNOLOGY, LLC Connect with our Remediation Contracting experts now: 800-770-0901 PROJECT PROFILE Hydraulic Control Treatment System Project Narrative Project Location New Jersey Client Name WRS Compass GWTT Scope System Build, Startup, O&M Contract Value $1.6M Project Duration 11 Months Contaminants Hexavalent Chromium, DNAPL, VOCs System Components: 20-cubic foot Plate Filter Press & Platform 10,000-Gal Sludge Thickening Tank Two (2) 20-ft Tall x 18-ft Jib Cranes (2-ton) Transfer Pumps, Sludge Handling Pumps Process and Well Pump Controls Five (5) LPGAC Units Flash/Floc & Clarifier Tanks Elevated Steel Mezzanine and Stairways 42 Recovery Wells with Local Control Panels Instrumentation and Controls Two (2) Organo-Clay Units pH Adjustment System GAC Backwash System Main and Secondary Distribution Integrated Panels JOB# 1756

Upload: others

Post on 23-May-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hydraulic Control Treatment System - …...ed system operation (N-3 licensed operator), process optimization, and maintenance for the initial 60 days of operation. Hydraulic Control

GWTT constructed a ground water extraction and treatment system in Kearny, New Jersey designed to remediate groundwater contaminated with hexavalent chromium (Cr VI), dense non-aqueous phase liquid (DNAPL), and volatile organic compounds (VOCs) from a total of 42 hydraulic control wells installed within the confines of a slurry wall.

The treatment process utilized chromium reduction, metals precipitation, pH adjustment, and carbon/ organo-clay technologies to maintain the system effluent within limits of a NJPDES DSW permit.

GWTT was responsible for the installation of all interior building treatment components and mechanical work including process piping, HVAC, electrical and instrumentation and controls.

After project construction was complete, GWTT performed startup and commissioning services for the system and provid-ed system operation (N-3 licensed operator), process optimization, and maintenance for the initial 60 days of operation.

Hydraulic Control Treatment System

Ground/Water Treatment & Technology627 Mt. Hope RoadWharton, NJ 07885

p: (973) 983-0901f: (973) 983-0903www.gwttllc.com

© 2019 GROUND/WATER TREATMENT & TECHNOLOGY, LLC

Connect with our Remediation Contracting experts now: 800-770-0901

PROJECT PROFILE

Hydraulic Control Treatment System Project Narrative

Project Location New Jersey

Client Name WRS Compass

GWTT Scope System Build, Startup, O&M

Contract Value $1.6M

Project Duration 11 Months

Contaminants Hexavalent Chromium, DNAPL, VOCs

System Components:• 20-cubic foot Plate Filter Press & Platform• 10,000-Gal Sludge Thickening Tank• Two (2) 20-ft Tall x 18-ft Jib Cranes (2-ton) • Transfer Pumps, Sludge Handling Pumps• Process and Well Pump Controls• Five (5) LPGAC Units• Flash/Floc & Clarifier Tanks• Elevated Steel Mezzanine and Stairways• 42 Recovery Wells with Local Control Panels• Instrumentation and Controls• Two (2) Organo-Clay Units• pH Adjustment System• GAC Backwash System• Main and Secondary Distribution Integrated Panels

JOB# 1756