hvac design verfication during commisisoning
TRANSCRIPT
-
7/30/2019 HVAC Design Verfication During Commisisoning
1/22
R. SAHAY
FOUNDER & CEO
DESIGN VERIFICATION DURING
COMMISSIOING OF HVAC SYSTEM
Nov 7-8, 2012 Acreserve India 2012, Bangalore
-
7/30/2019 HVAC Design Verfication During Commisisoning
2/22
Design Verification During
Commissioning
When does the design verification forcommissioning start?
After end user occupies and complains.
After commissioning and testing. After completion of erection when
commissioning team comes to site.
After approval of drawings & data sheets
After completion of tender documents After freezing of Design and BOQ
After completion of concept design.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
3/22
Design Verification During
Commissioning
Process of design verification should start from thecompletion of design scheme and operating logic.
CxA should get involved in the design presentation.
CxA should then create the results that needs to beachieved to meet the design and scheme intent.
These then should be co-ordinated with the designerto have the testing points/ testing provisions
incorporated in the design to enable thecommissioning team to take the proper data forevaluation.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
4/22
Commissioning Team - Specialist
Involve the commissioning team during thedesign review meeting or data sheet approval.
The control logic and reasoning should be part
of the review/ briefing. The commissioning team should inform the
execution team about the requirement of
provisions for measurements. Final check at site, before the completion of
erection and pre-commissioning activity.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
5/22
Tips
Plan for the pre-commissioning, then testing and then balancing.
Start the performance evaluation after all of above has beensatisfactorily completed by respective experts.
Break down the whole performance testing activity into small parts.
LOW SIDE
AIR
Area/Unit, conditions, control wise- WATER
Zone, AHU, Shaft, Plant.
EQUIPMENT
REMEMBER -
For every AHU/ Area, separate commissioning test report sheetsshould be used.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
6/22
Conditioned Space Commissioning
The design data for the room/ area to be the start
point.
Data to be included
- Area with the drawing highlighted.
- Conditions required.
- Time of the day operations.
- Load bifurcation without occupancy/ equipment.
- Control system and logic of operation.
Acreserve India 2012, Bangalore
Nov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
7/22
Water Side
While taking the equipment CFM and DB and WBtemperatures, it is important to take the waterside reading simultaneously.
Thus you can compare the enthlapy difference ofair across coil to the water temperaturedifference across coil with mass flow rates.
Correct the same for the seasonal variation.
Compare the same with design data given indesign sheet for load w/o equipment andoccupants.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
8/22
EQUIPMENT SIDE
AHU
SPECIALISED AHU
PUMPS COOLING TOWERS
CHILLERS
BMS CONTROL LOGIC
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
9/22
AHU
Parameters
Chilled water flow rates,
Chilled water temperature in/ out,
Air flow rates,
Air temperature in/ out DBT & WBT/ RH,
Fan Static Pressure,
Fan RPM, Motor RPM, Motor power,
Noise.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
10/22
SPECIALISED AHU
Any other parameter involved CFMs at various sides of heat/ enthalpy
exchangers.
DBT & WBT at each inter-phase/ section, Any water/ brine flow rates and temperatures
measurement IN/OUT.
Static pressure across each of the sections.
Fan motor power for each of the fans.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
11/22
PUMPS
Inlet and outlet pressures.
Flow rates.
Position of valves
Power consumption.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
12/22
COOLING TOWERS
Water Flow rate
Air Flow Rate
Water temperatures In/Out Air Temperatures DBT & WBT In/ Out
Fan RPM,
Fan Power. Noise
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
13/22
CHILLERS
Water flow rates Chilled & Condenser water
Water Temperatures IN/ OUT
If Air Cooled Air flow rates Air Temperatures - In/ Out
Power consumption for condenser fans
Power consumption for the chiller package.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
14/22
TIPS
Acreserve India 2012, BangaloreNov 7-8, 2012
Remember the design verification exercise is nota fault finding exercise,
Nor is it a manipulation and handing overexercise.
Take genuine readings and do not enterinformation to match data sheets.
A correctly measured and verified plant willminimise your site revisits in guarantee/
warrantee periods, minimising your costs andtime.
Example of a design verification process -
-
7/30/2019 HVAC Design Verfication During Commisisoning
15/22
TIPS
Highlight the parameters which will bemeasured from the approved data
sheets.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
16/22
TIPS Highlighted Data Sheet
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
17/22
TIPS
Create formats prior to the
commissioning process, include the
approved data sheets.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
18/22
VOLTAGE R 402
Y 402
B 401
AMPS R 19.6Y 19.6
B 19
POWER R 11.5
Y 11.1
B 11POWER FACTOR R 0.8
Y 0.8
B 0.8
FLOW (USGPM) 757.666
FLOW (M3
/HR) 172.197PRESSURE AT DISCHARGE (KG/CM2) 3.6
PRESSURE AT SUCTION (KG/CM2) 2
TOTAL HEAD, M 16
POWER TO MOTOR (KW) 11.20
PUMP EFFICIENCY 84.59Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
19/22
TIPS
List the instruments to be used.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
20/22
TIPS Instruments
Pump pressure Glycerine filled pressure
gauge at suction and discharge.
Pump Flow Ultrasonic flow meter at header.
Pump Power Three Phase Clamp type power
meter
Calculation -
Pump Efficiency
(Flow M3/Hr x head M/ (367.2 x IKWx 0.96x0.92)
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
21/22
TIPS - General
Ensure that the calibration is done in time so
that the expiry is not around the corner.
Visit the site and inform well in advance the
locations wherein the data needs to be taken.
Do not take the performance readings in
temporary/ construction power supply.
Acreserve India 2012, BangaloreNov 7-8, 2012
-
7/30/2019 HVAC Design Verfication During Commisisoning
22/22
THANK YOU
Question
R.Sahay
eQube