hvac design verfication during commisisoning

Upload: rsahay

Post on 04-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    1/22

    R. SAHAY

    FOUNDER & CEO

    DESIGN VERIFICATION DURING

    COMMISSIOING OF HVAC SYSTEM

    Nov 7-8, 2012 Acreserve India 2012, Bangalore

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    2/22

    Design Verification During

    Commissioning

    When does the design verification forcommissioning start?

    After end user occupies and complains.

    After commissioning and testing. After completion of erection when

    commissioning team comes to site.

    After approval of drawings & data sheets

    After completion of tender documents After freezing of Design and BOQ

    After completion of concept design.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    3/22

    Design Verification During

    Commissioning

    Process of design verification should start from thecompletion of design scheme and operating logic.

    CxA should get involved in the design presentation.

    CxA should then create the results that needs to beachieved to meet the design and scheme intent.

    These then should be co-ordinated with the designerto have the testing points/ testing provisions

    incorporated in the design to enable thecommissioning team to take the proper data forevaluation.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    4/22

    Commissioning Team - Specialist

    Involve the commissioning team during thedesign review meeting or data sheet approval.

    The control logic and reasoning should be part

    of the review/ briefing. The commissioning team should inform the

    execution team about the requirement of

    provisions for measurements. Final check at site, before the completion of

    erection and pre-commissioning activity.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    5/22

    Tips

    Plan for the pre-commissioning, then testing and then balancing.

    Start the performance evaluation after all of above has beensatisfactorily completed by respective experts.

    Break down the whole performance testing activity into small parts.

    LOW SIDE

    AIR

    Area/Unit, conditions, control wise- WATER

    Zone, AHU, Shaft, Plant.

    EQUIPMENT

    REMEMBER -

    For every AHU/ Area, separate commissioning test report sheetsshould be used.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    6/22

    Conditioned Space Commissioning

    The design data for the room/ area to be the start

    point.

    Data to be included

    - Area with the drawing highlighted.

    - Conditions required.

    - Time of the day operations.

    - Load bifurcation without occupancy/ equipment.

    - Control system and logic of operation.

    Acreserve India 2012, Bangalore

    Nov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    7/22

    Water Side

    While taking the equipment CFM and DB and WBtemperatures, it is important to take the waterside reading simultaneously.

    Thus you can compare the enthlapy difference ofair across coil to the water temperaturedifference across coil with mass flow rates.

    Correct the same for the seasonal variation.

    Compare the same with design data given indesign sheet for load w/o equipment andoccupants.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    8/22

    EQUIPMENT SIDE

    AHU

    SPECIALISED AHU

    PUMPS COOLING TOWERS

    CHILLERS

    BMS CONTROL LOGIC

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    9/22

    AHU

    Parameters

    Chilled water flow rates,

    Chilled water temperature in/ out,

    Air flow rates,

    Air temperature in/ out DBT & WBT/ RH,

    Fan Static Pressure,

    Fan RPM, Motor RPM, Motor power,

    Noise.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    10/22

    SPECIALISED AHU

    Any other parameter involved CFMs at various sides of heat/ enthalpy

    exchangers.

    DBT & WBT at each inter-phase/ section, Any water/ brine flow rates and temperatures

    measurement IN/OUT.

    Static pressure across each of the sections.

    Fan motor power for each of the fans.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    11/22

    PUMPS

    Inlet and outlet pressures.

    Flow rates.

    Position of valves

    Power consumption.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    12/22

    COOLING TOWERS

    Water Flow rate

    Air Flow Rate

    Water temperatures In/Out Air Temperatures DBT & WBT In/ Out

    Fan RPM,

    Fan Power. Noise

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    13/22

    CHILLERS

    Water flow rates Chilled & Condenser water

    Water Temperatures IN/ OUT

    If Air Cooled Air flow rates Air Temperatures - In/ Out

    Power consumption for condenser fans

    Power consumption for the chiller package.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    14/22

    TIPS

    Acreserve India 2012, BangaloreNov 7-8, 2012

    Remember the design verification exercise is nota fault finding exercise,

    Nor is it a manipulation and handing overexercise.

    Take genuine readings and do not enterinformation to match data sheets.

    A correctly measured and verified plant willminimise your site revisits in guarantee/

    warrantee periods, minimising your costs andtime.

    Example of a design verification process -

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    15/22

    TIPS

    Highlight the parameters which will bemeasured from the approved data

    sheets.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    16/22

    TIPS Highlighted Data Sheet

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    17/22

    TIPS

    Create formats prior to the

    commissioning process, include the

    approved data sheets.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    18/22

    VOLTAGE R 402

    Y 402

    B 401

    AMPS R 19.6Y 19.6

    B 19

    POWER R 11.5

    Y 11.1

    B 11POWER FACTOR R 0.8

    Y 0.8

    B 0.8

    FLOW (USGPM) 757.666

    FLOW (M3

    /HR) 172.197PRESSURE AT DISCHARGE (KG/CM2) 3.6

    PRESSURE AT SUCTION (KG/CM2) 2

    TOTAL HEAD, M 16

    POWER TO MOTOR (KW) 11.20

    PUMP EFFICIENCY 84.59Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    19/22

    TIPS

    List the instruments to be used.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    20/22

    TIPS Instruments

    Pump pressure Glycerine filled pressure

    gauge at suction and discharge.

    Pump Flow Ultrasonic flow meter at header.

    Pump Power Three Phase Clamp type power

    meter

    Calculation -

    Pump Efficiency

    (Flow M3/Hr x head M/ (367.2 x IKWx 0.96x0.92)

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    21/22

    TIPS - General

    Ensure that the calibration is done in time so

    that the expiry is not around the corner.

    Visit the site and inform well in advance the

    locations wherein the data needs to be taken.

    Do not take the performance readings in

    temporary/ construction power supply.

    Acreserve India 2012, BangaloreNov 7-8, 2012

  • 7/30/2019 HVAC Design Verfication During Commisisoning

    22/22

    THANK YOU

    Question

    R.Sahay

    eQube