HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the Progress report on the HMPID LV System HMPID LV System Cabling and LV sectors Cabling and LV sectors The WIENER PS Low Voltage Solution The WIENER PS Low Voltage Solution System Improvements with the New System Improvements with the New A1676W R3.04 Firmware A1676W R3.04 Firmware Preliminary Test results Preliminary Test results Conclusions Conclusions

Upload: zachariah-mead

Post on 14-Dec-2015

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

Progress report on the Progress report on the HMPID LV SystemHMPID LV System

• Cabling and LV sectorsCabling and LV sectors• The WIENER PS Low Voltage SolutionThe WIENER PS Low Voltage Solution• System Improvements with the New System Improvements with the New

A1676W R3.04 FirmwareA1676W R3.04 Firmware• Preliminary Test resultsPreliminary Test results• ConclusionsConclusions

Page 2: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

Cabling and LV sectorsCabling and LV sectorsHMPID HV- FE/RO Sectors

FEE 1FEE 1 FEE 2FEE 2 FEE 3FEE 3 FEE 4FEE 4 FEE 5FEE 5 FEE 6FEE 6FEE 1

HV1 HV2 HV3 HV4 HV5 HV6

-5V 2.5A

FEE1-6; - 2.8V, 6.8A each

FEE1-6; + 2.8V 5.6A each

HV1-6; 2.1KV Im 2nACG ; 250V Im 2nA

CG

CAEN SY1527A1821P

ROR+DDL

-5V 2.5A

ROL+DDL

1 or 2 Ch’s for +5V 18+1 A (peak 28A)

1x 7.2 A Ret. line FEE/M

2x 16.5A Ret.- l’s RO/M

WIENER PL500F8

HV returning lines= shielding of cables

1 or 2 Ch’s for +5V 18+1 A (peak 28A)

Page 3: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

HV sectors 2.1KV

Sensors ws x Pt100And pressure sensors

1

7

Patch panelOn the cradle

TrDAQ

HV

1

2

RG XX ?

2 x Optic fibres ?

09.41.25.130.5-CRIMP CAB.PLUG.PEEK SHV 5kV

04.31.51.C- COAXIAL HIGH-VOLTAGE CABLE 5 kVdc - WITH PARTIAL DISCHARGE SCREENS HTC-50-1-1

Rack side

Siemens PLC118

,Tw

09.41.25.150.1-CEN.CHASS.PLUG TEFLON SHV 5kV

04.21.51.118.6- CAB.SIG.BL. 18x0,50mm2

,Tw

,Tw

,Tw

118118118

Cabling and LV sectorsCabling and LV sectors

Cable Scheme # : 04.08.61.336.5 16mm2 F 7.7mm

RO +- 5 Volt

FEE +- 2.8 Volt

Sensing w. FEE

Sensing w. RO

1

18

5

11

1

6

1

09.31.05.248.919 pins D 12.5mm

7

7

1 CABLE LUGS CRIMPED-TYPE04.76.21.040.1 OR 04.76.21.038.5

04.21.51.118.6- CAB.SIG.BL. 18x0,50mm2

Rack sideSensing wires connectors

Canbus connectorLV output connector !!

Sensing wires connectors

Canbus connectorLV output connector !!

Sw

ROLRFEEa FEEb

Sensing wires connectors

Canbus connectorLV output connector !!

Sensing wires connectors

Canbus connectorLV output connector !!

Patch panel on the cradle

LV Sensing wires

Sensor cables

Page 4: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

The LV System Setup with the The LV System Setup with the WIENER PL500 F8WIENER PL500 F8

Weiner PL500 Weiner PL500

Control Control FirmwareFirmware

CAEN CAEN A1676W A1676W

Control Control FirmwareFirmware

CAEN CAEN SY1527 SY1527

Control Control Software Software (Linux OS (Linux OS

based)based)

CAEN Wrapper CAEN Wrapper LibLib

CAEN OPC CAEN OPC ServerServer

ETM OPC Client ETM OPC Client SoftwareSoftware

ETM PVSSII GUI ETM PVSSII GUI and Control and Control

SoftwareSoftware

Page 5: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

Main goals of the PL500 F8 Main goals of the PL500 F8 remote controlremote control

Weiner PL500 Weiner PL500

Control Control FirmwareFirmware

CAEN CAEN A1676W A1676W

Control Control FirmwareFirmware

CAEN CAEN SY1527 SY1527

Control Control Software Software (Linux OS (Linux OS

based)based)

CAEN Wrapper CAEN Wrapper LibLib

CAEN OPC CAEN OPC ServerServer

ETM OPC Client ETM OPC Client SoftwareSoftware

ETM PVSSII GUI ETM PVSSII GUI and Control and Control

SoftwareSoftwareBest solutionBest solution

Slow response time (2 sec)

Low reliability

(Already implemented)

Slow response time (2 sec)

Low reliability

(Already implemented)Our solutionOur solution

Requirements of the remote control system: complete, fast and reliable.Requirements of the remote control system: complete, fast and reliable.

Complete: each LV channel has to be equipped with an exhaustive set of controlled parameters, including the power On/Off, the single channel Trip Off and the channel grouping for bipolar electronics that are missed in the present Wiener PS version.

Complete: each LV channel has to be equipped with an exhaustive set of controlled parameters, including the power On/Off, the single channel Trip Off and the channel grouping for bipolar electronics that are missed in the present Wiener PS version.

Fast: the remote control response time in case of OVV, OVC,… should be as fast as possible to prevent electronics' damaging.

Fast: the remote control response time in case of OVV, OVC,… should be as fast as possible to prevent electronics' damaging.

Reliable: the system safety has to be anyway ensured in case of: missing Ethernet and/or Can Bus connection, SY 1527 Power cut off and/or control software (PVSS) crash.

Reliable: the system safety has to be anyway ensured in case of: missing Ethernet and/or Can Bus connection, SY 1527 Power cut off and/or control software (PVSS) crash.

Page 6: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

A1676W Can Bus Branch Controller A1676W Can Bus Branch Controller

A1676W Interface

Board

A1676W Wiener PS Controller characteristics:

• The Model A1676W is a board, designed for the SY1527/2527/3527 System family, whichallows to control up to 8 W-IE-NE-R Mod. PL500 power supplies via CANBUS. The boardis single-width.

• The A1676W can handle 64 PS channels, since each PL500 can house up to 8 channels. All the channels are seen as Caen channels.

• The board allows to control the PS channels through a complete set of programmableparameters, such as output voltage, current limits, etc.

A1676W Wiener PS Controller characteristics:

• The Model A1676W is a board, designed for the SY1527/2527/3527 System family, whichallows to control up to 8 W-IE-NE-R Mod. PL500 power supplies via CANBUS. The boardis single-width.

• The A1676W can handle 64 PS channels, since each PL500 can house up to 8 channels. All the channels are seen as Caen channels.

• The board allows to control the PS channels through a complete set of programmableparameters, such as output voltage, current limits, etc.

Page 7: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

The improved features of theThe improved features of thePL500F8 via the PL500F8 via the NewNew A1676W A1676W

R3.04 FirmwareR3.04 Firmware

New Channel Features:

• Single Channel ON/OFF (CH PW)

• Single Channel TRIPOFF (CH TRIPOFF)

• Channel Grouping

New PL500 feature:

• Enable/disable the Bipolar Grouping Mode (CR GRP).

New Channel Features:

• Single Channel ON/OFF (CH PW)

• Single Channel TRIPOFF (CH TRIPOFF)

• Channel Grouping

New PL500 feature:

• Enable/disable the Bipolar Grouping Mode (CR GRP).

Page 8: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

Telnet Window

Telnet WindowTelnet WindowNewNew A1676W R3.04 Firmware A1676W R3.04 Firmware

Page 9: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

Measure of the Channel Tripoff Measure of the Channel Tripoff Response Time (TResponse Time (TRR))

A CH TRIPOFF has been induced (OVC on Ch#1), we measured the switch OFF time of the single channel (reaction time).

A CH TRIPOFF has been induced (OVC on Ch#1), we measured the switch OFF time of the single channel (reaction time).

CAEN SY 1527

A1676W WIENER PL500 F8 Power Supply

Can Bus

(speed 1 Mbps)

LECROY 9310AM Telnet connectionTelnet connection

Channel 1 probe

2

Channel 1 probe

2

Can Bus probe 1

Can Bus probe 1

Page 10: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

Statistical analysis of TStatistical analysis of TRR

Frequency Probability Plot of the Single Channel Tripoff Time

00.5

11.5

22.5

33.5

44.5

0 15 30 45 60 75 90 105

120

135

150

time [ms]

Fre

qu

en

cy

1 crate 8 crates

<TR> 64 [ms] 130 [ms]

TR Max 140 [ms] 240 [ms]

A1676W FW R. 3.04:

1 crate 8 crates

Status 110 [ms] 210 [ms]

Vmon, Imon 500 [ms] 1470 [ms]

PSOT, Temp.

48500 [ms] 123495 [ms]

Page 11: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

Measure of the Crate TripoffMeasure of the Crate TripoffResponse TimeResponse Time

When the crate TRIPOFF option is enabled, on the over-current occurrence, about 5 ms are requested to switch OFF the entire power box.

WIENER PL500 F8 Power Supply

LECROY 9310AM

Channel 1 probe

1

Channel 1 probe

1

Page 12: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

In case of CANbus controller power cut (SY1527 power cut) , an Interlock signal switches Off the connected PS’s.Recovering of the settings after a power cut is guaranteed since all the values are written in the E2PROM of the A1676A.

In case of CANbus controller power cut (SY1527 power cut) , an Interlock signal switches Off the connected PS’s.Recovering of the settings after a power cut is guaranteed since all the values are written in the E2PROM of the A1676A.

System reliabilitySystem reliability

CAEN SY 1527 WIENER PL500 F8

POWER SUPPLY

A 1676W

In case of CANbus disconnection, the occurrence of an over current can be limited by setting each channel Current Limit’ equal to the OVC. Is now under study the activation (via PVSS) of the the Interlock line to switch Off in a selective way the “unplugged” PS.

In case of CANbus disconnection, the occurrence of an over current can be limited by setting each channel Current Limit’ equal to the OVC. Is now under study the activation (via PVSS) of the the Interlock line to switch Off in a selective way the “unplugged” PS.

Can Bus

If the Ethernet connection is missed, the system still remains in its full operation.If the Ethernet connection is missed, the system still remains in its full operation.

Interlock

Ethernet Connection

Interlock

Page 13: HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari Progress report on the HMPID LV System Cabling and LV sectorsCabling and

HV-LV DCS Workshop – 16/03/2004 G. De Cataldo, A. Franco, A.Tauro - INFN Bari

ConclusionsConclusions

• The PL500F8 technical specifications fits the LV sector requirements but the control features.

• The prototype of the new project CAEN –WIENER (A1676W), with single channel ON⁄OFF, grouping,…, is now running! The test results on the reaction time, are in agreement with the expectations and are very encouraging!!

• The PVSS HMPID LV Control has been updated taking into account the new PS features