human-system interface design implementation plandps diverse protection system edg emergency diesel...
TRANSCRIPT
KEPCO & KHNP HSI Design Implementation Plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP
Human-System Interface Design
Implementation Plan
Technical Report
September 2013
Copyright ⓒ 2013
Korea Electric Power Corporation & Korea Hydro & Nuclear Power Co., Ltd
All Rights Reserved
Non-Proprietary
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP i
Revision History
Revision Page
(Section) Description
0 All Issue for Standard
This document was prepared for the design certification application to the U.S. Nuclear Regulatory Commission and contains technological information that constitutes intellectual property. Copying, using, or distributing the information in this document in whole or in part is permitted only by the U.S. Nuclear Regulatory Commission and its contractors for the purpose of reviewing design certification application materials. Other uses are strictly prohibited without the written permission of Korea Electric Power Corporation and Korea Hydro & Nuclear Power Co., Ltd.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP ii
ABSTRACT
The objective of this plan is to control the human-system interface (HSI) design process and scope,
including the translation of function and task requirements into the detailed design of alarms, displays,
controls, and other aspects of the HSI through the systematic application of human factors engineering
(HFE) principles and criteria.
The scope of HSI design includes the main control room (MCR), remote shutdown room, technical
support center, emergency operations facility, and local control stations associated with important human
actions, and the HSI resources. MCR design includes operator consoles, safety console, and large
display panel (LDP). HSI resources are controls, alarms, information displays, LDP, and computer-based
procedures. The critical function monitoring, success path monitoring, accident monitoring instrumentation,
and bypassed and inoperable status indication are implemented using the HSI resources as integrated
fashion.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP iii
TABLE OF CONTENTS
1.0 OVERVIEW 1
1.1 Purpose 1
1.2 Scope 1
2.0 METHOD 2
2.1 HSI Design Process 2
2.2 HSI Design Input 4
2.3 Concept of Use and HSI Design Overview 8
2.4 HFE Design Guidance for HSIs 17
3.0 IMPLEMENTATION 18
3.1 HSI Detailed Design and Integration 18
3.2 Degraded I&C and HSI Conditions 24
3.3 HSI Tests and Evaluations 25
4.0 RESULT 26
4.1 Results Summary Report 26
5.0 REFERENCES 27
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP iv
LIST OF FIGURES Figure 1. HSI Design Process Figure 2. Schematic for Main Control Room
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP v
List of Acronyms AFAS auxiliary feedwater actuation signal AFWS auxiliary feedwater system AMI accident monitoring instrumentation ANS American Nuclear Society ANSI American National Standards Institute APR1400 Advanced Power Reactor 1400 BISI bypassed and inoperable status indication BOP Balance of Plant C&ID control & instrumentation and diagram CBP computer-based procedure CCF common-cause failure CFM critical function monitoring CFR Code of Federal Regulations CIAS containment isolation actuation signal CLD control logic diagram COL combined license CPIAS containment purge isolation actuation signal CREVAS control room emergency ventilation actuation signal CSAS containment spray actuation signal CSF critical safety function DPS diverse protection system EDG emergency diesel generator EO electrical operator EOF emergency operating facility ESF engineered safety features ESF-CCS engineered safety feature-component control system ESFAS engineered safety features actuation system FHEVAS fuel handling area emergency ventilation actuation signal FPD flat panel display FRA functional requirements analysis FA function allocation HA human action HF human factor HFE human factors engineering HFEPP Human Factors Engineering Program Plan HSI human-system interface HSIDIP Human-System Interface Design Implementation Plan HVAC heating , ventilation, and air conditioning I&C instrumentation and control IHA important human action IPS information process system IRWST in-containment refueling water storage tank KHNP Korea Hydro & Nuclear Power Co., Ltd. LCS local control station LDP large display panel
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP vi
MCR main control room MSIS main steam isolation signal NRC U.S. Nuclear Regulatory Commission NSSS nuclear steam supply system OER operating experience review P-CCS process- component control system P&ID piping & instrumentation diagram POSRV pilot operated safety relief valve PPS plant protection system QIAS-N qualified indication and alarm system-non-safety QIAS-P qualified indication and alarm system-P RCPB reactor coolant pressure boundary RMS radiation monitoring system RO reactor operator RSC remote shutdown console RSR remote shutdown room S&Q staffing and qualifications SDC system design criteria SFA system functional analysis SFD system functional description SG steam generator SIAS safety injection actuation signal SPADES+ safety parameter display and evaluation system + SPDS safety parameter display system SPM success path monitoring SS shift supervisor STA shift technical advisor TA task analysis TO turbine operator TSC technical support center V&V verification and validation VDU visual display unit
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 1
1.0 Overview
1.1 Purpose
The systematic design of the APR1400 human-system interface (HSI) and incorporation of human factors
engineering (HFE) principles in the design are controlled by the Human Factors Engineering Program
Plan (HFEPP) (Reference 1).
The purpose of the HSI design implementation plan is to define the necessary and sufficient activities to
be performed to develop the HSI. This includes the development and incorporation of HFE design
guidance (e.g., Style Guide, HFE design process). This plan provides a systematic approach to integrate
this guidance and the results and evaluation methods defined in other HFE program elements into the
HSI design process. This integration helps assure that the resulting HSI resources and control and
monitoring facilities effectively support performance of operational functions and tasks.
1.2 Scope
The scope of HSI design includes the main control room (MCR), remote shutdown room (RSR), technical
support center (TSC), emergency operations facility (EOF), and local control stations (LCSs) associated
with important human actions (IHAs), and the HSI resources. MCR design includes operator consoles,
safety console, and large display panel (LDP). HSI resources are controls, alarms, information display
hierarchy, large display panel and procedure display. The computer-based procedures (CBPs), critical
function monitoring (CFM), success path monitoring (SPM), accident monitoring instrumentation (AMI),
and bypassed and inoperable status indication (BISI) are implemented in the HSI resources in integrated
fashion.
These resources constitute the basic design from which plant system specific designs will be
implemented.
The plan defines those activities directly related to creating and refining the HSI design based on the
other HFE program elements and their associated implementation plans. Activities defined in other HFE
program elements will be referenced in this plan to ensure their integration into the HSI design process.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 2
2.0 Method 2.1 HSI Design Process
The HSI design process are composed of five phases as follows and the structure of HSI design process
is shown in Figure 1:
Planning phase
Analysis phase
Design phase (Basic HSI Platform design, and HSI detail design)
Test and evaluation phase
HF V&V phase
Figure 1. HSI Design Process 2.1.1 Planning Phase
The HFEPP and HSI Design Implementation Plan (HSIDIP) are issued for HFE and HSI design during the
planning phase. They describe how the HFE elements are managed and define the activities to be
performed to develop the HSI.
TS
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 3
2.1.2 Analysis Phase
The Implementation Plan and Results Summary Report of functional requirements analysis (FRA) and
function allocation (FA) (Reference 2) and task analysis (TA) (Reference 3) are developed during the
analysis phase and provided as the design input for the HSI designer of each design entity. They provide
the basis for the Basic HSI Platform design of HSI resources and control and monitoring facilities (e.g.,
critical safety function (CSF) display for information flat panel display (FPD), critical function/success path
monitoring alarm for large display panel (LDP), minimum inventory for LDP, and safety console). The TA
Results Summary Report will be used in the detailed design phase.
The results of operating experience review (OER) (Reference 4) are incorporated in system design
criteria (SDC) and HSI detail design as shown in Figure 1.
The initial staffing and qualifications (S&Q) (Reference 5) provide an input for the layout of the control
room and allocating controls and displays to individual consoles, panels, and workstations.
The system requirements, regulatory requirements, and other requirements are incorporated in SDC and
Style Guide. Other requirements are described in subsection 2.2.4.
2.1.3 Design Phase
The major activities for the HSI design phase are Basic HSI Platform design and HSI detail design.
2.1.3.1 Basic HSI Platform Design
The SDC and system functional description (SFD) are developed to establish the Basic HSI Platform
design. The detailed design criteria and system descriptions are described in the Basic HSI Platform
design documents such as SDC, SFD, system requirement, design requirement and System Description.
The General Design Criteria (GDC) and Classification Criteria provide the high level goals and design
bases for the Basic HSI Platform design. The Project Engineering Guides or Engineering Procedure is
provided for the consistent development of the Basic HSI Platform design. It includes the index and
writing guide for the Basic HSI Platform design. The interface requirements between the HSI resources
and control and monitoring facilities are provided through the Basic HSI Platform design.
2.1.3.2 HSI Detail Design
The HSI Detail Design Report and HSI Design Specification are developed to support the component
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 4
design in the detailed design phase.
The HSI Detail Design Report includes HSI display drawings and system functional analysis (SFA). SFA is
the identification of system function to determine the composition of system mimic display. The HSI
designer can produce the integrated and consistent system mimic display by using the SFA.
The HSI Design Specification includes the design specification for qualified indication and alarm system-
non-safety (QIAS-N), engineered safety feature-component control system (ESF-CCS), distributed control
system (DCS), and Consoles. The CBP Design Specification and the nuclear steam supply system
(NSSS) I&C Design Specification implemented in HSI system BOP will be integrated in HSI system BOP
Design Specification.
The SDC and SFD provide the basis and design reference (e.g., inventory and function) for detail design.
The Style Guide was developed to guide the detail design. The Style Guide provides human factors
principles and detail design guidelines (e.g., visual information display and coding convention, display and
control hardware and software, alarm system, workspace environments).
The interface requirements among the HSI resources and control and monitoring facilities are provided
through the project design procedure and interface design meeting.
2.1.4 Test and Evaluation Phase
Tests and evaluations of concepts and detailed design features are conducted during the process of
developing HSIs to support design decisions through trade-off evaluation and performance-based tests.
2.1.5 HF V&V Phase
HF V&V is performed on the HSI Detailed design, which is the final HSI design using a dynamic simulator
that meets the criteria of ANSI/ANS 3.5 (Reference 5).
2.2 HSI Design Input
The HSI design process represents the application of the lessons learned from the OER and results of FA,
TA, treatment of IHAs and initial staffing assumption into a detailed HSI product.
The OER forms the bases of the design by identifying past, positive and negative, experience that is
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 5
accounted for in the APR1400 HSI. This includes nuclear experience, predecessor plant experience and
experience with the application of similar advanced technologies.
The HSI design reviews the output from the FA to assure that the HSI design supports the identified roles
of the human in the plant and that levels of automation are used to reduce operator burden, reduce the
chance for error and enhance the ability of the operator to recover from an error when one occurs. The
task analysis is used by the design to identify: the task needs to monitor and control the plant for a range
of operating conditions, the information and control requirements including display range, precision,
accuracy and units of measure, and the task support requirements.
The HSI includes cost effective and technology possible designs to assure that all identified important
human actions are limited by the design and when this is not achievable that other compensatory
measures (e.g., training, procedures, staffing) are identified.
The resulting staffing assumption levels and qualifications of the plant staff are used as inputs to the
control room layout and allocation of controls and displays to assure that the integrated HSI, staffing and
design, results in successfully meeting the function and task requirements.
The following sources provide input to the HSI design process.
2.2.1 Analysis of Personnel Task Requirements The analyses performed in the early stages of the design process are used to identify requirements for the HSIs. These analyses include the following:
Operational Experience Review – An input to the HSI design encompasses lessons learned from other complex human-machine systems, especially predecessor designs and those involving similar HSI technology.
Functional Requirements Analysis and Function Allocation – The HSIs supports the roles of
personnel in the plant, e.g., appropriate levels of automation.
Task Analysis – The set of requirements to support the role of personnel is provided by task analyses that should identify:
- tasks needed to control the plant during a range of operating conditions from normal through
accident conditions
- detailed information and control requirements (e.g., requirements for display range, precision, accuracy, and units of measurement)
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 6
- task support requirements (e.g., special lighting and ventilation requirements) - Important HAs that should be given special attention in the HSI design process
Staffing and Qualifications – The findings from analyses of S&Q provide input for deciding upon
the layout of the overall control room and allocating controls and displays to individual consoles, panels, and workstations. The S&Q analyses establish the basis for the number of personnel to be accommodated, and requirements for coordinating activities between them.
2.2.2 System Requirements Constraints on the HSI design imposed by the overall I&C system, (e.g., constraints on the information
that can be presented due to sensor data availability) are the inputs for the HSI design as follow.
Piping & instrumentation Diagrams (P&IDs)
Control & instrumentation and diagrams (C&IDs)
Control logic diagrams (CLDs)
System functional description (SFD)
2.2.3 Regulatory Requirements
The following regulatory requirements are applicable.
10 CFR 50.34(f)(2)(iv) Safety Parameter Display System
10 CFR 50.34(f)(2)(v) Bypassed and Inoperable Status
10 CFR 50.34(f)(2)(xi) Relief and Safety Valve Position Monitoring
10 CFR 50.34(f)(2)(xii) Manual Feedwater Control
10 CFR 50.34(f)(2)(xvii) Containment Monitoring
10 CFR 50.34(f)(2)(xviii) Core Cooling
10 CFR 50.34(f)(2)(xix) Post-accident Monitoring
10 CFR 50.34(f)(2)(xxvi) Leakage Control
10 CFR 50.34(f)(2)(xxvii) Radiation Monitoring
10 CFR 50 Appendix A GDC 19 General Design Criteria for Nuclear Power Plants
BTP 7-19, Point 4 Guidance for Evaluation of Diversity and Defense-in-Depth in Digital
Computer-Based Instrumentation and Control Systems
DI&C-ISG-5, Highly-Integrated Control Rooms-Human Factors Issues (NRC,2008)
Regulatory Guide 1.23, Meteorological Monitoring Programs for Nuclear Power Plants, (NRC,
2007)
Regulatory Guide 1.47, Bypassed and Inoperable Status Indication for Nuclear Power Plant
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 7
Safety Systems, Rev.1 (NRC, 2010)
Regulatory Guide 1.62, Manual Initiation of Protective Actions (NRC, 2010)
Regulatory Guide 1.97, Criteria For Accident Monitoring Instrumentation For Nuclear Power
Plants, Rev.4, (NRC, 2006)
NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response
Plans and Preparedness in Support of Nuclear Power Plants, (NRC,1980)
NUREG-0696, Functional Criteria for Emergency Response Facility, (NRC, 1981)
NUREG-0737, Clarification of TMI Action Plan Requirements, (NRC,1980)
NUREG-0700, Human-System Interface Design Review Guidelines (NRC, 2002)
NUREG-0711, Human Factors Engineering Program Review Model, Rev. 3, (NRC, 2012)
NUREG-0800, Standard Review Plan, Chapter 18 Human Factors Engineering (NRC, 2004)
NUREG-0835, Human Factors Acceptance Criteria for the Safety Parameter Display System,
(NRC, 1981)
NUREG-1342, A Status Report Regarding Industry Implementation of Safety Parameter Display
Systems, (NRC, 1989)
2.2.4 Other Requirements
As customer requirements are identified, the HSI design and the functional requirements documents will
be revised to include them.
The following codes and standards are applicable.
NUREG/CR-6393, Integrated System Validation: Methodology and Review Criteria (1997).
NUREG/CR-6633, Advanced Information Systems: Technical Basis and Human Factors Review
Guidance (2000).
NUREG/CR-6634, Computer-Based Procedure Systems: Technical Basis and Human Factors
Review Guidance (2000).
NUREG/CR-6635, Soft Controls: Technical Basis and Human Factors Review Guidance (2000).
NUREG/CR-6636, Maintenance of Digital Systems: Technical Basis and Human Factors Review
Guidance (2000).
NUREG/CR-6637, Human-System Interface and Plant Modernization Process: Technical Basis
and Human Factors Review Guidance (2000).
NUREG/CR-6684, Advance Alarm Systems: Guidance Development and Technical Basis (2000).
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 8
2.3 Concept of Use and HSI Design Overview
2.3.1 Concept of Use
The concept of use provides a high-level description of how personnel will work with HSI resources and
address the coordination of personnel activities, such as interactions with auxiliary operators and the
coordination of maintenance and operations.
2.3.1.1 High-level Description
Based on anticipated staffing levels, the operations personnel consist of reactor operator (RO), turbine
operator (TO), electrical operator (EO), shift supervisor (SS), and shift technical advisor (STA).
The RO is responsible for making all reactivity manipulations. The RO coordinates plant evolutions with
the TO as necessary to maintain control of the NSSS.
The TO is responsible for manipulating the controls for BOP and turbine systems. The TO coordinates
with the RO prior to making any control manipulations which will directly affect the heat balance or
reactivity control of the NSSS.
The EO is responsible for the operation of main generator, emergency diesel generator (EDG), electrical
distribution breaker, and other activities (for example, fire protection, heating ventilation and air
conditioning (HVAC), radiation monitoring system (RMS), contact with electric load dispatcher) assigned
by the technical & administrative procedure of the specific plant in the MCR.
The SS is responsible for coordinating all activities within the plant that may affect operations. This
includes direct supervision of the operators in the MCR as well as activities outside the control room
(including maintenance).
The STA advises the SS on plant safe operation and performs the tasks which are mandated from SS.
2.3.1.2 Coordination of Personnel Activities
The coordination of personnel activities, such as interactions with auxiliary operators and the coordination
of maintenance and operations is accomplished through voice communication, loudspeakers, paging
phone, evacuation alarm, sound powered telephone, and direct wire telephone.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 9
The voice communication is provided between plant personnel in all vital areas during normal and
accident conditions. Voice communication is provided to the MCR, RSR, TSC and EOF, and Nuclear
Emergency Response Center.
Loudspeakers are located and distributed such that the page is intelligible in all locations.
The paging phone system is designed so that it provides effective communication between plant
personnel in all vital areas during the full spectrum of accident or incident conditions under normal
operating noise levels. For operating purposes, a paging phone system provides communications through
handset stations and loudspeaker assemblies. The system provides two independent communication
modes, page and partyline consisting of five circuits. Intra-plant communication can be established by
using the page channel to call a particular party and then communicating through one of the five party
lines available, thus leaving the page channel open for others. This page-and-partyline system is
available for use during emergency shutdown operations outside the MCR and communication between
the remote shutdown area, control room, and other areas that may require operator action during this
period.
An evacuation alarm system is provided utilizing sirens located throughout the plant. The sirens and tone
generator are manually activated from the evacuation switch board. The audible alarm system is
supplemented by visual alarm in high-noise areas.
A sound powered telephone system is located throughout the plant at designated control points for plant
maintenance and testing and to serve as a backup communication system.
This direct wire telephone system consists of desk-type telephones and signal addition units located
throughout the plant and plant site. This system is connected to the commercial telephone system and
the combined license (COL) private network, which allows offsite communications for normal and
abnormal/accident conditions. This system operates as backup to the paging phone system.
The Basic HSI Platform (Reference 7) provides the detailed concept of operations and the detailed
description of the HSI design and the methodology used to develop that design.
2.3.2 HSI Design Overview
The HSI design overview includes a description of:
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 10
facility layouts, including workstations, large screen displays, and the nominal staff working
positions
key HSI resources and their functionality, such as alarms, displays, controls, CBPs, and other
support and job aids
technologies to support teamwork and communication within the MCR and between the MCR,
RSR, the TSC, EOF, and LCS associated with IHAs
the responsibilities of the crew for monitoring, interacting, and overriding automatic systems and
for interacting with computerized procedures systems and other computerized operator support
systems
2.3.2.1 MCR Layout
MCR design includes operator consoles, safety console, and LDP. The MCR design configuration is
depicted in Figure 2 and provides five redundant consoles, each of which has capability to control all
power plant processes. Redundant operator consoles and the LDP are the main means of operation
during normal and accident situations.
Figure 2. Schematic for Main Control Room
Each of the three front consoles is designed to be used by one operator and two rear consoles are
assigned to SS and STA respectively. Each operator console provides devices for access to all
information and controls necessary for one person to monitor and control all processes associated with
nuclear plant operation and maintaining the plant in a safe condition. The front operator consoles are
linked together to provide good communications for the normal staffing assignment of RO, TO, and EO.
TS
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 11
The two rear operator consoles assigned to the SS and STA who use the operator console features for
monitoring only. The rear operator consoles also serves as an alternate operator console to be used for
plant monitoring and control in the event of a failure of one of the front operator consoles (where
monitoring and control capability of a operator console was degraded).
Each operator console contains as follows:
Multiple FPDs that support process monitoring and control with pointing devices
Engineered safety features-component control system (ESF-CCS) soft control flat panel displays
(FPDs).
Laydown space for logs, drawings, documents, paper procedures, etc.
The safety console provides controls and displays with which a backup operation can be performed
during a failure of the operator consoles. The safety console is located in the main operating area as
shown in Figure 2. The mini-LDP installed on the safety console provides the same fixed position alarms
and displays included on the LDP.
The safety console contains the following equipment:
Multiple FPDs that are of a same type as that of operator console
qualified indication and alarm system-non-safety (QIAS-N) displays
qualified indication and alarm system-p (QIAS-P) displays
plant protection system (PPS)/ core protection calculator operator modules
Reactor trip and ESF system level actuation switches
Diverse manual actuation controls
Minimum inventory of fixed position switches
ESF-CCS soft control modules
The LDP is located in front of operator consoles as shown in Figure 2. It displays information that the
operator requires for quickly assessing overall plant status and is viewable from all MCR consoles and
the MCR offices.
The Large Display Panel is made up of eight separate display areas which are driven by workstations as
listed below:
Four Variable Display Sections
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 12
The CFM/BISI and System Group/Important Alarm Sections
The Reactor Operator Mimic Section
The Turbine Operator Mimic Section
2.3.2.2 Key HSI Resources and Functionality
Key HSI resources include soft control, LDP, information display hierarchy, CBP, alarm.
Soft control
Soft controls are used to provide control room operators with plant control capabilities, which replace
conventional dedicated pushbuttons and process controllers. The soft control consists of the ESF-CCS
soft control and the process-component control system (P-CCS) soft control. The ESF-CCS soft control is
used to control the safety-related control components through the ESF-CCS, and the P-CCS soft control
is used to control the non-safety related control components through the P-CCS.
The soft control allows the control of continuous process, discrete components, and other special
controllers such as control rods and turbine generators from the MCR and the remote shutdown console
(RSC).
The operator can control both safety and non-safety components using the ESF-CCS control or P-CCS
soft control on any one of operator console. The use of soft control is essential to achieve compact
operator consoles design.
The soft control emulates and replaces the various physical switches and analog control devices which
populate conventional plant control panels. The operator interacts with the ESF-CCS soft control via
touch screen, and interacts the P-CCS soft control via pointing device such as mouse. These soft controls,
which are software based, allow a standard interface device to assume the role of numerous control
switches and analog control devices via software configuration. The selection of components is possible
from the information displays.
The ESF-CCS soft control is implemented on the qualified touch screen-based FPD, and the P-CCS soft
control is implemented on each information FPD of the MCR and the RSC.
Also the ESF-CCS soft control and the P-CCS soft control are provided on the safety console to support
the operator task of a predesignated operator in post trip conditions as a means for controlling non-safety
related equipment.
Large display panel
The LDP provides two types of displays.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 13
One is a fixed display and the other is a variable display. The fixed display provides the rapid assessment
of plant conditions so that personnel are able to quickly extract status information from the display.
Therefore, the fixed displays are centrally located in the MCR.
The Variable Display Section of the LDP provides the operator with flexibility in specifying LDP display
information which will support varying information needs.
The LDP display is also available on any operator consoles in the MCR, TSC and EOF.
The LDP provides the operators with information that allows them to determine overall operational and
safety status of the plant.
The LDP presents high level process overview information by which an operator can:
Provide a selected set of high level function indicators, trend for key parameters, PPS actuation
status flags and alarms to support operators situation awareness of the plant.
Provide continuous display of critical function and success path alarms to meet SPDS
requirements.
Provide prioritized alarm presentation emphasizing important alarms to support operational
concerns.
Provide plant-wide system fixed mimic to alleviate display page navigation load and to support
crew coordination.
Provide flexible display areas in variable display section to meet the diverse information
requirements of different operators in different operational situations.
The LDP uses the same Style Guide for display design (i.e., dynamic symbols, color code, highlighting,
blinking, graphic layout and information coding features), that are used on the information display pages.
Information display hierarchy
The information display hierarchy in operator consoles provides dynamic display pages of plant
parameters and alarms using color graphic VDU so that an understanding of current plant conditions and
status is readily recognized. Information display pages provide information important to monitoring,
planning, controlling, and obtaining feedback on control actions. These display pages contain all the plant
information that is available to the operator, in a structured hierarchy. The information display pages are
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 14
useful for information presentation because they allow graphical layouts of the plant and process in
formats that are consistent with the operator's visualization of the plant. In addition information display
formats are designed to aid operational activities of the plant by providing trends, categorized listings,
messages, operational prompts, as well as alerts to abnormal process.
The MCR operator consoles use multiple display devices that allow simultaneous access to a variety of
display pages in information display hierarchy. Each operator console includes four VDUs, to each of
which any display page in the information display hierarchy can be assigned. Use of four VDUs also
provides a redundancy in the event of any VDU becoming unavailable. A pointing device such as mouse
is primary interface to navigate and access display pages in the hierarchy. Keyboards are not used for
information access to any of the control room operator consoles during normal operation. The information
display hierarchy is driven by the information process system (IPS).
Computer-based procedure
The CBP is a computerized operator support system that enables the operators to execute operation
procedural steps with much reduced secondary tasks. It presents an overview and instructions of a
procedure and related process information and controls that need to be cross-referenced to execute the
procedure. The procedure display is used by the operator in conjunction with other types of displays.
Basically the same operating process as conventional control room is maintained. SS has the overall
control over the execution of the procedure. RO and TO execute the procedural steps that are assigned
to them by SS. The emergency operating procedures is executed by the operating crew in coordination.
Some procedures such as system operating procedures can be executed by a single operator. The CBP
supports coordination among operators. When an operating crew executes a single procedure, the steps
that the other operators are currently working on are shown on the overview pane and SS who is in
charge of coordination issues verbal orders.
The CBP can be displayed in the following locations:
RO workstation
TO workstation
EO workstation
SS workstation
STA workstation
Switching the procedure display VDUs does not result in the loss of place keeping information. When an
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 15
operator does not use CBP, the operator can use all the workstation displays for other purpose.
Alarm
The purpose of the alarm system is to alert the operators by means of visual and audible signals of
abnormal conditions that require operator action.
The alarm system is designed to perform the following functions:
Alerting the operators to off-normal conditions that require the operator to take action
Guiding the operators to the appropriate response
Assisting the operators in determining and maintaining an awareness of the state of the plant
and its systems or functions
The alarm warning system consists of three major functions; an auditory alert function, a visual alarm
function, and an operator response function. Together, these three functions are designed to provide a
preferred operational sequence for alarm warnings. The alarm system follows Style Guide in order to be
immediately and correctly alert the operator, for the operator to accurately responded to in a timely
fashion, the alarms to be easily acknowledged, reset, and distinguished.
Alarms are presented and prioritized so that the operator's response can be based on their relative
importance or urgency and the time within which the operator must take action. Alarms are grouped into 3
priorities. In addition, there exists a separate category called "Flag". Flag provides operational guidance
information that is not representative of an undesirable process or component condition.
Shape coding on alarm tiles, alarm descriptor, mimic diagram component descriptors, process parameter
descriptors, and directory/display page option fields is used to help MCR operator identify each alarm.
The alarm system is implemented in both the IPS and QIAS-N. Alarms are presented or accessed with
various formats or methods on LDP, operator console displays and QIAS-N Display.
Alarm information is presented on the LDP with alarm tile representation to graphically mimic the
conventional alarm windows and parameter/component descriptor. Alarm tile representations are used for
critical function, success path alarms and system level alarm, and parameter/component descriptors are
used for process alarm on process mimic of the LDP. Each alarm representation can show either priority
1, 2, or 3 conditions. Each alarm can notify the operator of one or more possible alarm conditions relating
to a system, component, or major process problem. For the grouped alarms presented on LDP, specific
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 16
alarm information is provided on alarm list of operator console displays.
The alarm list of operator console displays presents all alarm information associated with activated priority
1, 2, and 3 alarms. This list provides various kind of lists including prioritized, operator established and
chronological alarm. The operator can acknowledge the alarm on this list.
The multiple methods of operator console displays alarm presentation allow the operators to utilize alarm
information in the most meaningful manner for a given function or task, and it also allows operators to
efficiently access, acknowledge, and diagnose any alarm condition. Alarm priority and status coding is
applied when alarms are present on component/parameter alarm descriptor, directory options, and
display page menu options. The menus located at the operator console displays screen in the alarm
design provides the operator with an overview of the existence of any unacknowledged alarm conditions
and a general overview of where they exist by plant sector. If an alarm exists in a particular plant sector,
the corresponding directory page menu option flashes. This is the sector of the hierarchy where the
display page can be found that would best allow the alarm to be acknowledged.
Important alarm list is shown on the QIAS-N displays located on the safety console. The QIAS-N displays
alarms related with NRC RG 1.97 (Reference 8) Type A, B, C, and selected sets of Type D and E
variables, minimum inventory and operating support information, which are mainly displayed on the LDP.
Alarm acknowledgment is accomplished on these displays by clicking the track ball.
The HSIs allow significant flexibility in alarm acknowledgment to accommodate varying numbers of
alarms (single and multiple) and various methods by which the operator can acknowledge them. Alarm
acknowledgment in either IPS or QIAS-N display will acknowledge the same alarm in the other system.
2.3.2.3 Technologies to Support Teamwork and Communication
LDP variable display area
Alarm lists, trend displays, etc., normally displayed on VDU screens can be projected on to the large
screen for a monitoring or discussion purposes amongst the operating crew. Operators are able to
choose any display format available on the operator console and have it displayed on the LDP variable
display area.
The communication technologies within MCR and between the MCR, RSR, TSC, EOF, and local control
stations are described in Section 2.3.1.2.
The Basic HSI Platform provides the overall HSI design concept and rationale.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 17
2.4 HFE Design Guidance for HSIs
The topics in Style Guide address the scope of HSIs, their form, function and operation, as well as the
environmental conditions in which they will be used that are relevant to human performance. The Style
Guide is provided in the Style Guide (Reference 9).
The Style Guide is developed for each of the HSI resources to facilitate the standard and consistent
application of HFE principles to the HSI design. The Style Guide contains a set of standards and
conventions that are produced by tailoring generic HFE guidance to the specific design of HSI and define
how those HFE principles are applied.
The HFE guidelines in NUREG-0700 (Reference 10) are included in the Style Guide.
The Style Guide provides:
Specification of accepted HFE standard, guideline, and principles to which HSI must conform
Statements of scope of the Style Guide
instructions for proper use of the Style Guide
Specification of design conventions to which HSI must conform
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 18
3.0 Implementation 3.1 HSI Detailed Design and Integration 3.1.1 General
The HSI Detailed Design will
Consider Important HAs
Base the layout of HSIs within consoles, panels, and workstations on analyses of personnel
roles (job analysis), and systematic strategies for organization, such as arrangement by
importance, and frequency and sequence of use.
Design the HSIs to support inspection, maintenance, test, and repair of (1) plant equipment, and
(2) the HSIs. The applicant should design the latter so that inspection, maintenance, test, and
repair of the HSIs do not interfere with other plant-control activities.
Support personnel task performance under conditions of S&Q assumption.
Account for using the HSIs over the duration of a shift where decrements in human performance
due to fatigue may be a concern.
Support human performance under the full range of environmental conditions, ranging from
normal to credible extreme conditions, such as loss of lighting and of ventilation. For the remote
shutdown facility and local control stations, the applicant’s HFE design should consider the
ambient environment (e.g., noise, temperature, contamination) and the need for and type of
protective clothing.
3.1.2 Main Control Room 3.1.2.1 Safety Parameter Display System
The safety parameter display and evaluation system + (SPADES+) application program in conjunction
with the continuous LDP display and the information display VDUs meets the safety parameter display
system (SPDS) requirements for the HSI without using stand-alone monitoring and display systems.
Since the main intended use of SPDS is during relatively rare occurrences, HFE suggests that the
operators will find that the use of data acquisition habits acquired and repeated during the normal
operation of the plant will be the most successful. The operator interface to the plant is improved by
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 19
integrating SPDS requirements into the overall HSI design to avoid the need for another system that is
infrequently used. The SPDS functions are implemented in the SPADES+. CSF and success path
(availability and performance) information is integrated throughout the HSI information hierarchy.
3.1.2.2 Bypassed and Inoperable Status Indication
The bypassed and inoperable status indication (BISI) status display at the system level provides a
continuous indication of the bypassed and inoperable status of the system. Deliberately induced
bypassed conditions typically occur during plant startup/shutdown and during routine testing activities.
The System level status indication of BISI is provided for the protection systems and auxiliary or
supporting systems which are required for safe operation of the plant.
Graphic information is presented on display page formats with hierarchical structure to aid in rapid
operator comprehension from LDP. The operator can select the proper menu on the information FPD for
confirming the BISI status from LDP in the MCR.
The bypassed and inoperable condition of ESF components is provided to the IPS which indicates the
system level bypassed and inoperable condition. The IPS also provides status information at the
component level. The operator has the ability to manually activate each ESF system level bypass
indication in the MCR. Inoperable indication is shown on the IPS displays and LDP.
3.1.2.3 Relief and Safety Valve Position Monitoring
The position indicators and temperature indicators downstream of each pressurizer pilot operated safety
relief valves (POSRVs) are provided to monitor each pressurizer POSRVs position and to detect leakage
from each pressurizer POSRVs. The LDP and IPS provide operators with monitoring function for POSRVs.
3.1.2.4 Manual Feedwater Control
The auxiliary feedwater system (AFWS) is actuated by an auxiliary feedwater actuation signal (AFAS)-1
for steam generator (SG) 1 and an AFAS-2 for SG 2. The AFWS is also actuated by the diverse
protection system (DPS).
The AFWS is started automatically on an AFAS. Both motor-driven and turbine-driven auxiliary
feedwater pumps aligned to the affected SG(s) are started simultaneously, and the auxiliary feedwater
modulating valves to the SG are automatically placed in the modulation mode. When an AFAS signal is
present, the auxiliary feedwater modulation valves are in a modulation mode and opened/closed
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 20
depending on SG level.
The AFAS is initiated by either low water level in the associated steam generator(s) or manual actuation
from the MCR. The AFAS is also initiated by loss of power to two or more channels.
The LDP and IPS display feedwater flows to control the flows.
3.1.2.5 Containment Monitoring
The LDP and information FPD display containment atmosphere pressure, containment water level,
containment hydrogen concentration, in-containment refueling water storage tank (IRWST) hydrogen
concentration, containment radiation intensity, and noble gas effluents.
3.1.2.6 Core Cooling
The QIAS-P and QIAS-N provide the operator in the control room with an unambiguous indication of
inadequate core cooling.
3.1.2.7 Post-accident Monitoring
The QIAS-P, QIAS-N, and IPS display accident monitoring variables.
The QIAS-P is dedicated to continuously monitor and display NRC RG 1.97 Type A, B, and C variables.
These displays are located on the MCR safety console.
The QIAS-N is designed to support continuous plant operation if the IPS becomes unavailable. The
function of QIAS-N also includes displaying NRC RG 1.97 Type A, B, C, and selected sets of Type D and
E variables. These displays are located on the MCR safety console and RSC.
The IPS provides displays for all NRC RG 1.97 variables. The IPS also has historical data storage,
retrieval and trending capability.
3.1.2.8 Leakage Control
MCR provides necessary control and displays for leakage control. The LDP and IPS provide monitoring
function for operators to mitigate leakage.
To minimize leakage from portions of systems outside containment that could contain highly radioactive
fluids during a serious transient or accident to levels as low as practicable, The systems include
containment spray system, safety injection system, and chemical and volume control system are used.
HSIs for monitoring and control are provided in the MCR.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 21
3.1.2.9 Radiation Monitoring
The QIAS-P, QIAS-N, and IPS display accident monitoring variables including in-plant radiation and
airborne radioactivity under a broad range of routine and accident conditions.
3.1.2.10 Manual Initiation of Protective Actions
Manual ESF system level actuation switches are provided on the safety console. The engineered safety
features actuation system (ESFAS) consists of follows:
Safety injection actuation signal (SIAS)
Containment spray actuation signal (CSAS)
Containment isolation actuation signal (CIAS)
Main steam isolation signal (MSIS)
Auxiliary feedwater actuation signal (AFAS)
Fuel handling area emergency ventilation actuation signal (FHEVAS)
Containment purge isolation actuation signal (CPIAS)
Control room emergency ventilation actuation signal (CREVAS)
3.1.2.11 Diversity and Defense-in-depth
The diverse manual ESF actuation switches are provided to permit the operator to actuate ESF systems
from the MCR after a postulated CCF of the PPS and ESF-CCS. Also, the diverse indication system
provides functions to monitor critical variables and control the heater power for proper heated junction
thermocouple output signal level, when the CCF of digital I&C safety systems occurs.
3.1.2.12 Important HAs
The minimum inventory on the safety console provides the controls, displays and alarms that ensure the
reliable performance of identified important HAs. The APR1400 Basic HSI Platform provides the minimum
inventory of HSIs.
3.1.2.13 Computer-Based Procedure Platform
The CBP system is designed to be consistent with the design review guidance in NUREG-0700, Section 8,
the CBP system and in Section 1 of DI&C-ISG-5 (NRC, 2008).
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 22
3.1.3 Technical Support Center
The TSC provides plant management and technical support to plant operating personnel during
emergency conditions.
The IPS provides the necessary interfaces with the TSC, EOF and ERDS to make the same information
that is available to the operating staff available to other interested personnel.
The SPADES+ is a computer applications program that is a part of the IPS and displays a primary safety
parameters directly monitoring critical plant functions on the FPD in the MCR, TSC, and EOF.
The Information FPDs and station including SPADES+ displays, keyboards and a hard copy device is
provided along with a minimum of 10 regular telephones, "hot-lines", and other communications
equipment as deemed necessary by the regulatory office to remain in contact with the control room and
other emergency facilities.
The TSC instrumentation consists of Information FPDs, keyboards, and hard copy devices necessary to
monitor plant data systems such as SPADES+. In addition, instrumentation or other TSC equipment such
as display boards and files is provided for data storage and retrieval. Instrumentation for display of
radiological, environmental, and meteorological data variables includes those specified in IEEE Std. 497
(Reference 11), NUREG-0737, Supplement 1 (Reference 12), and meteorological variables listed in
proposed RG 1.23 (Reference 13). These historical data are retrieval and available in the TSC for a
minimum of 2 hours prior to and 12 hours after the accident.
The TSC location, design and equipment meet the requirements of NUREG-0696 (Reference 14) and
NUREG-0737, Supplement 1 as applicable.
3.1.4 Emergency Operation Facility
The EOF is an owner controlled and operated offsite support center. Equipment is provided in the EOF
for the acquisition, display and evaluation of all radiological, meteorological, and plant system data
pertinent to determination of offsite protective measures.
The IPS provides the necessary interfaces with the TSC, EOF and ERDS to make the same information
that is available to the operating staff available to other interested personnel.
The SPADES+ is a computer applications program that is a part of the IPS and displays a primary safety
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 23
parameters directly monitoring critical plant functions on the FPD in the MCR, TSC, and EOF.
The EOF instrumentation consists of Information FPDs, keyboards, and hard copy devices necessary to
monitor plant data systems such as SPADES+. In addition, instrumentation or other EOF equipment such
as display boards and files is provided for data storage and retrieval. Instrumentation for display of
radiological, environmental, and meteorological data variables includes those specified in IEEE 497,
NUREG-0737, Supplement 1, and meteorological variables listed in proposed RG 1.23. These historical
data are retrieval and available in the EOF for a minimum of 2 hours prior to and 12 hours after the
accident.
3.1.5 Remote Shutdown Facility
The remote shutdown facility has an HSI that supports remote shutdown of the reactor that is consistent
with and outside of the MCR per 10 CFR 50, Appendix A, GDC 19.
3.1.6 Local Control Stations
The LCS and those LCS associated with risk-important and credited human actions are designed through
the same design process as the MCR and are consistent with those in the MCR. As the HSI design
matures the design documentation will describe how the final HSI design meets the above criteria.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 24
3.2 Degraded I&C and HSI Conditions
The HFE program and the HSI design process account for the effects on the plants performance in the
event of the failure or degradation of automated systems. Alarms and displays required for the timely
detection, and evaluation of significance, of degraded I&C and HSI conditions are identified and provided
in the HSI. Conditions where back-up systems are required are identified and designed into the HSI to
support important tasks can be accomplished. The need for specific compensatory actions, supporting
procedures and degraded I&C training will be evaluated and be supplied to ensure effective management
of degraded I&C and HSI conditions.
The goal of the HSI design for degraded I&C and HSI conditions is to ensure that personnel will
successfully transition to back up systems.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 25
3.3 HSI Tests and Evaluations
Tests and evaluations of concepts and detailed design features are conducted during the process of
developing HSIs to support design decisions.
HSI trade-off studies will rely on the following factors when selecting one design over another:
personnel-task requirements
human performance capabilities and limitations
HSI performance requirements
inspection, test and maintenance needs
application of proven technology, OER results and predecessor experience
application of advanced technologies to improve human performance
HSI performance-based tests are used to verify aspects of the HSI design meet performance criteria. The
following aspects of the tests will be described:
participants
testbed
design features or characteristics of the HSI being tested
tasks or scenarios used
performance measures
test procedures
data analyses
Both HSI trade-off studies and performance based tests will be performed under an approved and
documented test procedure. The conclusions from the tests and their impact on design decisions will be
described.
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 26
4.0 Result 4.1 Results Summary Report
The Results Summary Report incorporates the following contents:
SDC
SFD
Drawings
HSI display drawings
Design specification
KEPCO & KHNP HSI Design Implementation plan APR1400-E-J-NR-12008-NP, Rev.0
KEPCO & KHNP 27
5.0 References
1. KHNP, APR1400-E-J-NR-12002-P, “Human Factors Engineering Program Plan,” September,
2013.
2. KHNP, APR1400-E-J-NR-12001-P, “FRA/FA Implementation Plan,” September, 2013.
3. KHNP, APR1400-E-J-NR-12007-P, “Task Analysis Implementation Plan,” September, 2013.
4. KHNP, APR1400-E-J-NR-12003-P, “Operating Experience Review Implementation Plan,”
September, 2013.
5. KHNP, APR1400-K-J-NR-13001-P “Staffing and Qualifications Implementation Plan,” September,
2013.
6. ANSI/ANS 3.5, "Nuclear Power Plant Simulators for Use in Operator Training and Examination,”
2009.
7. KHNP, APR1400-E-J-NR-12009-P, “Basic HSI Platform,” September, 2013.
8. NRC RG 1.97 Revision 4, “Criteria for accident monitoring instrumentation for nuclear power
plants.”
9. KHNP, APR1400-E-J-NR-12005-P, “Style Guide,” September, 2013.
10. NUREG-0700, Revision 2, “Human-System Interface Design Review Guidelines,” U.S. NRC,
Washington, DC, May 2002.
11. IEEE Std. 497-2002, “Accident monitoring instrumentation for nuclear power generating stations.”
12. NUREG-0737, Supplement No. 1, “Clarification of TMI Action Plan Requirements,” 1982.
13. NRC RG 1.23, Revision 1, “Meteorological Monitoring Programs for Nuclear Power Plants.”
14. NUREG-0696, Functional Criteria for Emergency Response Facility, 1981.