Signature: __________________________________ Date: _________________________ Shanghai China March 15-17, 2011 Water and Compressed Air Deadline: January 21, 2011 Form 5 Please return form to: SEMI China Rm.201, 295 Zuchongzhi Road Zhangjiang Hi-tech Park, Pudong Shanghai, 201203, China Contact: Ms. May Pu Phone: +86.21.5027.0909*202 Fax: +86.21.5027.4829 E-mail: [email protected] Exhibitor Name: ___________________________________ ________________________Booth Number: ____________ Address: _________________________________________ Contact Person: ___________________________________ Phone: _____________________Fax: __________________ Email: ____________________________________________ Mobile: ___________________________________________ Item Unit Price(RMB) Quantity Total Price Water Supply and Drainage Water supply to booth with 10m pipe up & down. Ø 15mm, P. 4kg/cm 2 3,200 Water supply to machine with 10m pipe up & down. Ø 20mm, P. 4kg/cm 2 4,800 Water connection to booth, per point 450 Water connection to machine, per point 450 Compressed Air 0.5HP-5HP ( 0.4m3/Min & 8~10kgf/cm 2 ), Ø10mm 4,000 6HP-10HP ( 0.9m3/Min & 8~10kgf/cm 2 ), Ø19mm 4,800 10 Bar 1m 3 /Min, inner size 25mm 5,500 Compressed Air connection, per point 600 For water supply and air compressor services, exhibitors are required to bring along their adaptor to connect to their equipment. All water and compressed air orders must have a drawing indicating the location of the water and compressed air points. Please use Form 7 (Location Plan) to indicate the locations and fax this to SEMI China before January 21, 2011. Any relocating of the power points at show site will incur a 50% additional charge from SEMI China. Exhibitors with very sensitive equipment are advised to bring their own stabilizer. Exhibitors must bring their own special regulating units if they require very specific water temperature or water pressure. Payment must be made after receiving the invoice from SEMI China. Full cost of equipment or services will be applied for any cancellation of an order beginning January 21, 2011. Late order (after the deadline of January 21, 2011) will be surcharged 30%. Any order received after February 21, 2011 and any onsite order will be surcharged 50%.

Upload: semi-china

Post on 06-Mar-2016

212 views

Category:

Documents


0 download

DESCRIPTION

http://www.semiconchina.org/downloadFile/1291265334790.pdf

TRANSCRIPT

Page 1: Document

Signature: __________________________________ Date: _________________________

Shanghai China

March 15-17, 2011

Water and Compressed Air

Deadline: January 21, 2011

Form

5 Please return form to:

SEMI China

Rm.201, 295 Zuchongzhi Road

Zhangjiang Hi-tech Park, Pudong

Shanghai, 201203, China

Contact: Ms. May Pu

Phone: +86.21.5027.0909*202

Fax: +86.21.5027.4829

E-mail: [email protected]

Exhibitor Name: ___________________________________

________________________Booth Number: ____________

Address: _________________________________________

Contact Person: ___________________________________

Phone: _____________________Fax: __________________

Email: ____________________________________________

Mobile: ___________________________________________

Item Unit Price(RMB) Quantity Total Price

Water Supply and Drainage

Water supply to booth with 10m pipe up & down.

Ø 15mm, P. 4kg/cm2

3,200

Water supply to machine with 10m pipe up & down.

Ø 20mm, P. 4kg/cm2

4,800

Water connection to booth, per point 450

Water connection to machine, per point 450

Compressed Air

0.5HP-5HP (≤0.4m3/Min & 8~10kgf/cm2), Ø10mm 4,000

6HP-10HP (≤0.9m3/Min & 8~10kgf/cm2), Ø19mm 4,800

10 Bar 1m3/Min, inner size 25mm 5,500

Compressed Air connection, per point 600

� For water supply and air compressor services, exhibitors are required to bring along their adaptor to connect

to their equipment.

� All water and compressed air orders must have a drawing indicating the location of the water and compressed

air points. Please use Form 7 (Location Plan) to indicate the locations and fax this to SEMI China before

January 21, 2011. Any relocating of the power points at show site will incur a 50% additional charge from SEMI

China.

� Exhibitors with very sensitive equipment are advised to bring their own stabilizer.

� Exhibitors must bring their own special regulating units if they require very specific water temperature or

water pressure.

� Payment must be made after receiving the invoice from SEMI China.

� Full cost of equipment or services will be applied for any cancellation of an order beginning

January 21, 2011.

� Late order (after the deadline of January 21, 2011) will be surcharged 30%. Any order received after February