hsm 2nd july schedule -all activity

81
Activity ID Activity Name emaining Duration Start Finish Hot Strip Mill 249 03-Jun-11 A 07-Mar-15 6. HOT STRIP MILL 249 03-Jun-11 A 07-Mar-15 HSM-10000 Issue LOI of Main Mill Package 0 03-Jun-11 A HSM-10010 Start Milestone 0 01-Nov-11 A INPUT MILESTONES 147 01-Jul-14 A 26-Nov-14 From Utility & Water System 72 01-Jul-14 A 01-Nov-14 A162202 Requirement of Dry Compressed air for HSM 0 01-Jul-14 A A162180 Requirement of Chilled Water to HSM 0 20-Aug-14* A162160 Requirement of LP Ni trogen to HSM from ASU (Alternate to be in position till ASU is in opn 0 30-Sep-14* A162172 Requirement of Make-up Water to HSM 0 30-Sep-14* A162190 Requirement of Mixed Gas to HSM 0 20-Oct-14* A162210 Requirement of Propane 0 01-Nov-14* From PDS 0 02-Jul-14 02-Jul-14 A162150 Requirement of Power from MSDS to HSM 0 02-Jul-14* From SMS 0 26-Nov-14 26-Nov-14 A162140 SLAB to HSM 0 26-Nov-14* OUTPUT MILESTONE S 73 01-Nov-11 A 27-Nov-14 HSM-10110 Start of HSM 0 01-Nov-11 A HSM-10090 Mill Line readiness 0 17-Oct-14* HSM-10095 Cold test 35 15-Sep-14 30-Oct-14* HSM-10100 Mill Integrated trail 26 31-Oct-14 26-Nov-14* HSM-10080 1st coil from HSM - Target date 0 27-Nov-14* Furnace +Roll shop + ECR1+ Slab Yard + Rolls + Saddles 208 07-Dec-11 A 25-Jan-15 Furnace-L1, L2 interface, process model finalisation, Refrac. SYMS, Pulpit, Saddles & Shop Piping 124 10-May-12 A 02-Nov-14 Civil Building & Foundation Works 91 10-May-12 A 30-Sep-14 Slab Yard-QR /26-14 0 10-May-12 A 20-Apr-13 A SY-10000 Drawing Inputs (Building Column) 0 10-May-12 A 31-Oct-12 A SY-10010 Building Column 0 09-Aug-12 A 20-Apr-13 A Slab Yard-QR/14-9 60 10-May-12 A 31-Aug-14 SY-10020 Drawing Inputs (Building Column) 0 10-May-12 A 28-Sep-12 A SY-10030 Building Column 0 18-Feb-13 A 30-Apr-14 A SY-10100 Equipment Foundation 60 31-May-14 A 31-Aug-14 Heavy Spares Storage Area- A/7-13 91 24-Sep-12 A 30-Sep-14 HSS-10000 Drawing Inputs (Building Column) 0 24-Sep-12 A 31-Dec-12 A HSS-10010 Building Column 0 17-Sep-13 A 15-Feb-14 A HSS-10020 Flooring & Misc Works 91 01-May-14 A 30-Sep-14* May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr 2014 2015 Tata Steel - Odisha Project Hot Strip Mill Schedule As on: 02.07.14 Actual Work Remaining Work Critical Remaining Work Milestone Page 1 of 81 Filter: All Activity

Upload: roumik-mukherjee

Post on 17-Jul-2015

155 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Hot Strip MillHot Strip Mill 249 03-Jun-11 A 07-Mar-15

6. HOT STRIP MILL6. HOT STRIP MILL 249 03-Jun-11 A 07-Mar-15

HSM-10000 Issue LOI of Main Mill Package 0 03-Jun-11 A

HSM-10010 Start Milestone 0 01-Nov-11 A

INPUT MILESTONESINPUT MILESTONES 147 01-Jul-14 A 26-Nov-14

From Utility & Water SystemFrom Utility & Water System 72 01-Jul-14 A 01-Nov-14

A162202 Requirement of Dry Compressed air for HSM 0 01-Jul-14 A

A162180 Requirement of Chilled Water to HSM 0 20-Aug-14*

A162160 Requirement of LP Ni trogen to HSM from ASU (Alternate to be in position till ASU is in opn.) 0 30-Sep-14*

A162172 Requirement of Make-up Water to HSM 0 30-Sep-14*

A162190 Requirement of Mixed Gas to HSM 0 20-Oct-14*

A162210 Requirement of Propane 0 01-Nov-14*

From PDSFrom PDS 0 02-Jul-14 02-Jul-14

A162150 Requirement of Power from MSDS to HSM 0 02-Jul-14*

From SMSFrom SMS 0 26-Nov-14 26-Nov-14

A162140 SLAB to HSM 0 26-Nov-14*

OUTPUT MILESTONESOUTPUT MILESTONES 73 01-Nov-11 A 27-Nov-14

HSM-10110 Start of HSM 0 01-Nov-11 A

HSM-10090 Mill Line readiness 0 17-Oct-14*

HSM-10095 Cold test 35 15-Sep-14 30-Oct-14*

HSM-10100 Mill Integrated trail 26 31-Oct-14 26-Nov-14*

HSM-10080 1st coil from HSM - Target date 0 27-Nov-14*

Furnace +Roll shop + ECR1+ Slab Yard + Rolls + SaddlesFurnace +Roll shop + ECR1+ Slab Yard + Rolls + Saddles 208 07-Dec-11 A 25-Jan-15

Furnace-L1, L2 interface, process model finalisation, Refrac. SYMS, Pulpit, Saddles & Shop PipingFurnace-L1, L2 interface, process model finalisation, Refrac. SYMS, Pulpit, Saddles & Shop Piping 124 10-May-12 A 02-Nov-14

Civil Building & Foundation WorksCivil Building & Foundation Works 91 10-May-12 A 30-Sep-14Slab Yard-QR /26-14Slab Yard-QR /26-14 0 10-May-12 A 20-Apr-13 ASY-10000 Drawing Inputs (Building Column) 0 10-May-12 A 31-Oct-12 A

SY-10010 Building Column 0 09-Aug-12 A 20-Apr-13 A

Slab Yard-QR/14-9Slab Yard-QR/14-9 60 10-May-12 A 31-Aug-14SY-10020 Drawing Inputs (Building Column) 0 10-May-12 A 28-Sep-12 A

SY-10030 Building Column 0 18-Feb-13 A 30-Apr-14 A

SY-10100 Equipment Foundation 60 31-May-14 A 31-Aug-14

Heavy Spares Storage Area- A/7-13Heavy Spares Storage Area- A/7-13 91 24-Sep-12 A 30-Sep-14HSS-10000 Drawing Inputs (Building Column) 0 24-Sep-12 A 31-Dec-12 A

HSS-10010 Building Column 0 17-Sep-13 A 15-Feb-14 A

HSS-10020 Flooring & Misc Work s 91 01-May-14 A 30-Sep-14*

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 1 of 81 Filter: All Activity

Page 2: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Structural Building & Technological WorksStructural Building & Technological Works 124 13-Oct-12 A 02-Nov-14SLAB Yard PQR /26-14SLAB Yard PQR /26-14 101 05-Nov-12 A 10-Oct-14SY-10040 Drawing Inputs 0 05-Nov-12 A 17-Dec-13 A

SY-10050 Fabrication 0 11-Jan-13 A 23-May-14 A

SY-10120 Structural work complition to give front to EOT Erection 20 09-Mar-13 A 26-Jul-14

SY-10060 Complition of structural work & sheeting 101 09-Mar-13 A 10-Oct-14*

Slab Yard-PQR/14-9Slab Yard-PQR/14-9 109 05-Nov-12 A 18-Oct-14SY-10070 Drawing Inputs 0 05-Nov-12 A 28-Feb-13 A

SY-10080 Fabrication 0 15-Mar-13 A 14-Mar-14 A

SY-10090 Erection (including sheeting) 109 08-Apr-13 A 18-Oct-14*

Heavy Spares Storage Area A/ 7-13Heavy Spares Storage Area A/ 7-13 81 13-Oct-12 A 23-Oct-14HSS-10030 Drawing Inputs 0 13-Oct-12 A 05-Jul-13 A

HSS-10040 Fabrication 0 03-Sep-13 A 28-Mar-14 A

HSS-10050 Erection (including sheeting) 81 28-Sep-13 A 23-Oct-14

EOT CRANESEOT CRANES 99 14-Dec-13 A 02-Nov-14Heavy Spare Storage Area (Axis 13 to 7)EOTHeavy Spare Storage Area (Axis 13 to 7)EOT 33 01-Oct-14 02-Nov-14Crane (20T Bay A-B)Crane (20T Bay A-B) 33 01-Oct-14 02-Nov-14HSS-EOT-10000 Bldg readiness for crane erection 0 01-Oct-14

HSS-EOT-10010 EOT Erecti on 30 01-Oct-14 30-Oct-14

HSS-EOT-10020 Test & Commisioning 3 31-Oct-14 02-Nov-14

16T Crane at C-E Bay16T Crane at C-E Bay 0 14-Dec-13 A 11-Mar-14 AEOT-10030 Strl building readiness for crane erection 0 14-Dec-13 A

EOT-10040 EOT Erecti on & Testing of crane 0 16-Dec-13 A 11-Mar-14 A

2 nos 120t(on tong)/16 Cranes at P-Q and Q-R bays2 nos 120t(on tong)/16 Cranes at P-Q and Q-R bays 96 27-Jul-14 30-Oct-14HSS-EOT-10050 Strl building readiness for crane erection 0 27-Jul-14

HSS-EOT-10060 EOT Erecti on & Testing of crane (Required during operation) 77 15-Aug-14 30-Oct-14*

Slab Charging EquipmentSlab Charging Equipment 59 16-Aug-14 30-Oct-14SY-10110 Erection and alingment of Slab Charging Equipment 59 16-Aug-14* 30-Oct-14

Furnace (Electrics, Engineering & Erection), Rollshop Electrics and B&S for FurnaceFurnace (Electrics, Engineering & Erection), Rollshop Electrics and B&S for Furnace 61 12-Apr-12 A 31-Aug-14

Civil Building & Foundation WorksCivil Building & Foundation Works 27 12-Apr-12 A 28-Jul-14B-E/13-10 (Furnace - 1 area)B-E/13-10 (Furnace - 1 area) 0 12-Apr-12 A 10-Dec-13 AFCE-10020 Excavation by Blasting 0 13-Jul-12 A 31-Jan-13 A

FCE-10030 Building Column 0 16-Oct-12 A 25-Mar-13 A

FCE-10010 Drawing Inputs incl. Equipment foundation 0 12-Apr-12 A 31-May-13 A

FCE-10040 Furnace Raft, Wall, Pedestral & Beam 0 30-Oct-12 A 10-Dec-13 A

B-E/10-8 (Furnace - 2 area)B-E/10-8 (Furnace - 2 area) 21 09-May-12 A 28-Jul-14FCE-10060 Excavation by Blasting 0 08-Aug-12 A 29-Nov-12 A

FCE-10070 Building Column 0 15-Nov-12 A 25-Mar-13 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 2 of 81 Filter: All Activity

Page 3: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FCE-10050 Drawing Inputs incl. Equipment foundation 0 09-May-12 A 31-May-13 A

FCE-10080 Furnace Raft, Wall, Pedestral & Beam 21 08-Aug-12 A 28-Jul-14

Structural Building & Technological WorksStructural Building & Technological Works 61 20-Aug-12 A 31-Aug-14B-E/14-8 (Furnace - 1 &2 area)B-E/14-8 (Furnace - 1 &2 area) 40 20-Aug-12 A 10-Aug-14FCE-10090 Drawing Inputs 0 20-Aug-12 A 24-Oct-12 A

FCE-10100 Fabrication 0 15-Dec-12 A 09-Jan-14 A

FCE-10110 Erection (including sheeting) 40 02-Jan-13 A 10-Aug-14*

B-E/8-4 (Furnace - 3&4 area)B-E/8-4 (Furnace - 3&4 area) 61 27-Sep-12 A 31-Aug-14FCE-10120 Drawing Inputs 0 27-Sep-12 A 31-Oct-12 A

FCE-10160 Structural erection to give front for EOT erect ion 0 05-Apr-13 A 12-Dec-13 A

FCE-10130 Fabrication 0 01-Jan-13 A 03-Mar-14 A

FCE-10140 Erection (including sheeting) 61 05-Apr-13 A 31-Aug-14*

Furnace (Mechanical Equipment incl Hydraulics, lubrication & piping)Furnace (Mechanical Equipment incl Hydraulics, lubrication & piping) 208 20-Jan-14 A 25-Jan-15

Mechanical & RefractoryMechanical & Refractory 208 20-Jan-14 A 25-Jan-15

Furnace -1--Eqpt Erection by TenovaFurnace -1--Eqpt Erection by Tenova 145 20-Jan-14 A 24-Nov-14

FCE-10650 Clearence after Fdn & Building constn for Eqpt erection 0 20-Jan-14 A

Furnace Equipment ErectionFurnace Equipment Erection 118 12-Mar-14 A 28-Oct-14

Furnace Box and mechanismFurnace Box and mechanism 89 12-Mar-14 A 29-Sep-14FCE1-10670 Inclined ramps 0 12-Mar-14 A 25-Mar-14 A

FCE1-10680 Lifting and travelling cylinders supports 0 15-Apr-14 A 20-Apr-14 A

FCE1-10690 Lifting frame cylinders and centering device 14 20-May-14 A 16-Jul-14

FCE1-10700 Travell ing frame and cylinder 15 12-May-14 A 17-Jul-14

FCE1-10730 Side platforms and walkways level - 2250 mm 17 08-Jul-14* 25-Jul-14

FCE1-10720 Erection of Water seals 25 02-Jul-14 27-Jul-14

FCE1-10750 Erection of Fixed skid upright 7 20-Jul-14* 27-Jul-14

FCE1-10710 Erection of Moving skids uprights 29 02-Jul-14* 31-Jul-14

FCE1-10760 Lay down horizontal skids on the fixed hearth 5 27-Jul-14 01-Aug-14

FCE1-10770 Side and front, walls 10 28-Jul-14 07-Aug-14

FCE1-10740 Hearth frames and scale hoppers 14 25-Jul-14 08-Aug-14

FCE1-10800 Roof IPE 100 8 07-Aug-14* 15-Aug-14

FCE1-10790 Roof main beams 10 07-Aug-14* 17-Aug-14

FCE1-10810 Horizontal skids (Charge section) alignment & levelling 15 20-Aug-14 04-Sep-14

FCE1-10640 Side platforms and walkways Level +500 mm 25 15-Aug-14 09-Sep-14

FCE1-10820 Horizontal skids (Middle section) alignment & levelling 12 31-Aug-14 12-Sep-14

FCE1-10620 Horizontal skids (Discharge section) alignment & levelling 12 01-Sep-14 13-Sep-14

FCE1-10630 Final setting of water seals and paddles 15 03-Sep-14 18-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 3 of 81 Filter: All Activity

Page 4: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FCE1-10780 Side doors 46 07-Aug-14 22-Sep-14

FCE1-10650 Roof stairs and walkways 20 09-Sep-14 29-Sep-14

FCE1-10660 Completion of Furnace box and Mechanism 0 29-Sep-14*

Waste Gas Duct & StacksWaste Gas Duct & Stacks 46 10-Aug-14 25-Sep-14WG-10150 Downtake 3 10-Aug-14* 13-Aug-14

WG-10160 Waste gas ducts upsteam recuperator 25 13-Aug-14 07-Sep-14

WG-10170 Recuperator casing 9 01-Sep-14 10-Sep-14

WG-10180 Waste gas ducts downs team recuperator & pressure valve 15 01-Sep-14 16-Sep-14

WG-10190 Stack (lot no-1,2,3) 8 17-Sep-14 25-Sep-14

Handling EquipmentHandling Equipment 68 13-Jun-14 A 08-Sep-14HE-10060 Discharge machine 11 13-Jun-14 A 13-Jul-14

HE-10070 Charging machine 30 15-Jul-14* 14-Aug-14

HE-10080 Charging and discharging doors mechanism and doors 5 03-Sep-14 08-Sep-14

Refractory & InsulationRefractory & Insulation 112 05-Jul-14 25-Oct-14REF-10310 Side doors lining 6 25-Aug-14* 31-Aug-14

REF-10320 Charging and discharging doors lining 6 25-Aug-14* 31-Aug-14

REF-10360 Recu casing - lining 20 25-Aug-14* 14-Sep-14

REF-10340 Skids-lining 30 25-Aug-14* 24-Sep-14

REF-10390 Piping insulation 40 25-Aug-14* 04-Oct-14

REF-10350 Down take and waste gas duct upstream recu lining 30 16-Sep-14 16-Oct-14

REF-10370 Waste gas duct downstream recu lining 30 24-Sep-14 24-Oct-14

REF-10330 Furnace box - lining 60 25-Aug-14* 24-Oct-14

REF-10380 Stack refractory ining 30 25-Sep-14 25-Oct-14

REF-10400 Complete insulation & lining 0 25-Oct-14

Equipment & PipingEquipment & Piping 100 05-Jul-14 13-Oct-14EQP-10570 Combustion air fans (3 nos with scilencer & connecting pipe) 8 05-Jul-14* 13-Jul-14

EQP-10500 Hydraulic station and valve stand 10 15-Jul-14* 25-Jul-14

EQP-10490 Water sealing piping 15 27-Jul-14 11-Aug-14

EQP-10530 Lubricating piping system 20 25-Jul-14 14-Aug-14

EQP-10560 Burners (lateral & roof) 15 05-Aug-14* 20-Aug-14

EQP-10580 Combustion air piping & support 40 13-Jul-14 22-Aug-14

EQP-10510 Hydraulic Piping 30 25-Jul-14 24-Aug-14

EQP-10620 Compressed air system 30 02-Aug-14* 01-Sep-14

EQP-10520 Hydraulic piping flushing 15 24-Aug-14 08-Sep-14

EQP-10480 Skids cooling water piping and supports 45 02-Aug-14 16-Sep-14*

EQP-10550 Recuperators 10 14-Sep-14 24-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 4 of 81 Filter: All Activity

Page 5: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EQP-10590 Mixed gas piping and support 45 13-Aug-14 27-Sep-14

EQP-10600 Nitrogen piping and supports 20 19-Sep-14 09-Oct-14

EQP-10610 Pilot and frame control system 15 27-Sep-14 12-Oct-14*

EQP-10540 Pressure test 30 13-Sep-14 13-Oct-14

Electrical SystemsElectrical Systems 93 27-Jul-14 28-Oct-14EE-10410 MCC boards and local panels 15 16-Aug-14* 31-Aug-14

EE-10420 Erection of cable trays 30 01-Aug-14 31-Aug-14

EE-10430 Field instruments 45 27-Jul-14 10-Sep-14

EE-10440 Cable laying 45 06-Aug-14 20-Sep-14

EE-10450 Cable termination 30 26-Aug-14 25-Sep-14

EE-10460 CCTV system 15 13-Oct-14 28-Oct-14

EE-10470 Complete installation of electrical & instrumentation 0 28-Oct-14

Testing & CommissioningTesting & Commissioning 30 25-Oct-14 24-Nov-14

TEST-12430 Cold test & commissioning 17 25-Oct-14 11-Nov-14

TEST-12440 Heating and dry up 12 11-Nov-14 23-Nov-14

TEST-12450 1st Hot slab 0 24-Nov-14*

Furnace-2--Eqpt Erection by TenovaFurnace-2--Eqpt Erection by Tenova 205 05-Jul-14 25-Jan-15

FCE-10000 Clearence after Fdn & Building constn for Eqpt erection 0 29-Jul-14

Equipment Receipt at site (Furnace 2)Equipment Receipt at site (Furnace 2) 60 05-Jul-14 02-Sep-14FCE-10250 Receipt at site (Furnace 2) 60 05-Jul-14* 02-Sep-14

Furnace Box and MechanismFurnace Box and Mechanism 119 30-Jul-14 25-Nov-14FCE-10260 Equipment Erection 119 30-Jul-14 25-Nov-14

Waste gas ducts & StackWaste gas ducts & Stack 63 23-Aug-14 24-Oct-14FCE-10270 Equipment Erection 63 23-Aug-14 24-Oct-14

Refractory and InsulationRefractory and Insulation 67 18-Oct-14 23-Dec-14FCE-10280 Refractory work 67 18-Oct-14 23-Dec-14

Furnace Electrical systemFurnace Electrical system 70 21-Sep-14 29-Nov-14FCE-10290 Equipment Erection 70 21-Sep-14 29-Nov-14

Test & CommissioningTest & Commissioning 56 01-Dec-14 25-Jan-15FCE-10300 Individual trial 30 01-Dec-14 30-Dec-14

FCE-10310 Integrated trial 19 31-Dec-14 18-Jan-15

FCE-10320 Furnace Dry out 7 19-Jan-15 25-Jan-15

FCE-10330 Furnace-2 Ready 0 25-Jan-15*

Piping WorksPiping Works 100 23-Aug-14 30-Nov-14

Furnace-2Furnace-2 100 23-Aug-14 30-Nov-14FCE-10350 Piping Erection 100 23-Aug-14 30-Nov-14

ECR-1 & FCE area Auxiliary Electrical System incl tunnelsECR-1 & FCE area Auxiliary Electrical System incl tunnels 80 07-Dec-11 A 20-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 5 of 81 Filter: All Activity

Page 6: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Civil Building & Foundation WorksCivil Building & Foundation Works 0 07-Dec-11 A 31-Mar-14 AECR1-10000 Civil clearance ground floor 0 17-Nov-13 A

ECR1-10010 Base ment availability 0 14-Dec-13 A

ECR-1ECR-1 0 07-Dec-11 A 31-Mar-14 AECR1-10030 Base Raft 0 07-Mar-12 A 23-May-12 A

ECR1-10040 Basement Wall & Col umn 0 23-May-12 A 07-Oct-12 A

ECR1-10050 Ground Floor Slab 0 08-Aug-12 A 25-Oct-12 A

ECR1-10020 Drawing Inputs 0 07-Dec-11 A 28-Nov-12 A

ECR1-10060 Columns 0 20-Dec-12 A 31-Jan-13 A

ECR1-10070 Roof Slab 0 11-Feb-13 A 31-May-13 A

ECR1-10080 Other Finishing Work 0 13-Feb-13 A 16-Mar-14 A

ECR1-10130 Tranformer Foundation 0 22-Feb-14 A 31-Mar-14 A

Structural Building & Technological WorksStructural Building & Technological Works 0 02-Mar-14 A 19-Apr-14 ACrane LCSS-1Crane LCSS-1 0 02-Mar-14 A 19-Apr-14 ALCSS1-10000 LCSS panels(3) 0 02-Mar-14 A 11-Mar-14 A

LCSS1-10010 Transformer(3sets) 0 11-Apr-14 A 19-Apr-14 A

Cable Tunnel ECR1 to ECR2Cable Tunnel ECR1 to ECR2 0 15-Apr-13 A 25-May-14 AECR1-10090 Drawing availabilty 0 15-Apr-13 A 08-Jul-13 A

ECR1-10100 Civil Works 0 02-Dec-13 A 25-May-14 A

Electrical & Automation WorksElectrical & Automation Works 80 24-Feb-14 A 20-Sep-14RTDBsRTDBs 0 02-May-14 A 19-May-14 ARTDB-10000 Slab RTDB 1 0 02-May-14 A 02-May-14 A

RTDB-10010 Slab RTDB 2 0 02-May-14 A 03-May-14 A

RTDB-10020 Slab RTDB 3 0 03-May-14 A 05-May-14 A

RTDB-10030 Slab RTDB 4 0 05-May-14 A 05-May-14 A

RTDB-10040 Slab RTDB 5 0 05-May-14 A 06-May-14 A

RTDB-10050 Slab RTDB 6 0 06-May-14 A 07-May-14 A

RTDB-10060 Slab RTDB 7 0 07-May-14 A 07-May-14 A

RTDB-10070 Fce RTDB 1 0 08-May-14 A 08-May-14 A

RTDB-10080 Fce RTDB 2 0 08-May-14 A 09-May-14 A

RTDB-10090 Fce RTDB 3 0 09-May-14 A 10-May-14 A

RTDB-10100 Fce RTDB 4 0 10-May-14 A 10-May-14 A

RTDB-10110 Fce RTDB 5 0 10-May-14 A 12-May-14 A

RTDB-10120 Fce RTDB 6 0 12-May-14 A 13-May-14 A

RTDB-10130 Fce RTDB 7 0 13-May-14 A 14-May-14 A

RTDB-10140 Fce RTDB 8 0 14-May-14 A 14-May-14 A

RTDB-10150 RTDB1 0 14-May-14 A 15-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 6 of 81 Filter: All Activity

Page 7: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RTDB-10160 RTDB2 0 15-May-14 A 16-May-14 A

RTDB-10170 RTDB3 0 16-May-14 A 16-May-14 A

RTDB-10180 RTDB4 0 17-May-14 A 17-May-14 A

RTDB-10190 RTDB24 0 17-May-14 A 19-May-14 A

Other WorksOther Works 80 24-Feb-14 A 20-Sep-14EE-10010 LCSS 0 19-May-14 A 20-May-14 A

EE-10020 PDB2 0 20-May-14 A 20-May-14 A

EE-10030 MLDB 0 20-May-14 A 21-May-14 A

EE-10040 ELDB 0 21-May-14 A 22-May-14 A

EE-10050 Converter transformer room 0 22-May-14 A 23-May-14 A

EE-10060 Converter 0 23-May-14 A 23-May-14 A

EE-10070 Inverter 0 23-May-14 A 24-May-14 A

EE-10080 UPS 0 24-May-14 A 26-May-14 A

EE-10090 Battery 0 26-May-14 A 26-May-14 A

EE-10100 Slab transfer car drive 0 27-May-14 A 27-May-14 A

EE-10110 Ventilation MCC 0 27-May-14 A 28-May-14 A

EE-10120 SYMS room 0 28-May-14 A 29-May-14 A

EE-10130 AHU room 0 29-May-14 A 29-May-14 A

EE-10140 Earthing pits(14) 0 29-May-14 A 30-May-14 A

EE-10150 RIO 0 30-May-14 A 31-May-14 A

EE-10160 Amenities 0 31-May-14 A 02-Jun-14 A

EE-10000 tray support fabrication & erection 0 24-Feb-14 A 30-Jun-14 A

EE-10170 cable tray erection 36 30-Jun-14 A 07-Aug-14

EE-10180 cable laying & termination 30 28-Jul-14 27-Aug-14

EE-10190 Trial & Testing 10 08-Sep-14 20-Sep-14

Roll shop (Mechanical Equipment incl Hydraulics, lubrication & piping)Roll shop (Mechanical Equipment incl Hydraulics, lubrication & piping) 141 16-Jun-12 A 19-Nov-14

Civil Building & Foundation WorksCivil Building & Foundation Works 29 24-Sep-12 A 30-Jul-14Roll Shop-A/45-14Roll Shop-A/45-14 29 24-Sep-12 A 30-Jul-14RS-10000 Drawing Inputs 0 24-Sep-12 A 17-Jul-13 A

RS-10010 Building Columns 0 12-Apr-13 A 04-Apr-14 A

RS-10020 Equipment Foundations 14a-24 18 10-Apr-14 A 19-Jul-14

RS-10040 Equipment Foundations 32-45 29 30-Apr-14 A 30-Jul-14

RS-10030 Equipment Foundations 24-32 29 10-May-14 A 30-Jul-14*

Structural Building & Technological WorksStructural Building & Technological Works 120 16-Jun-12 A 30-Oct-14Roll Shop-A/45-14Roll Shop-A/45-14 84 16-Jun-12 A 23-Sep-14RS-10050 Drawing Inputs 0 16-Jun-12 A 11-Oct-12 A

RS-10060 Erection32-45 to give front for EOT erection 0 07-Jan-14 A 27-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 7 of 81 Filter: All Activity

Page 8: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RS-10080 Fabrication 0 01-Jul-13 A 20-May-14 A

RS-10070 Erection 14a-24 (including sheeting) 30 20-Sep-13 A 31-Jul-14*

RS-10090 Erection 24-31 (including sheeting) 65 13-Jul-13 A 23-Sep-14

RS-10065 Complition Erection32-45 (including sheeting) 65 07-Jan-14 A 23-Sep-14*

EOT CraneEOT Crane 120 11-Mar-14 A 30-Oct-14120 T EOT Crane (Roll Shop)120 T EOT Crane (Roll Shop) 15 11-Mar-14 A 16-Jul-14RS-EOT-10000 Erection of crane 0 11-Mar-14 A

RS-EOT-10010 Test & Commisioning 15 04-Apr-14 A 16-Jul-14

37.5+37.5/32 T EOT Crane (A-B Bay Roll Shop)37.5+37.5/32 T EOT Crane (A-B Bay Roll Shop) 68 02-Aug-14 30-Oct-14RS-EOT-10020 EOT Erecti on 38 02-Aug-14* 20-Sep-14

RS-EOT-10030 Test & Commisioning 30 20-Sep-14 30-Oct-14*

ROLL SHOPROLL SHOP 30 04-Jul-13 A 08-Aug-14RS-10100 Delivery of Equipment at Site of-Roll Shop 30 04-Jul-13 A 08-Aug-14

Mechanical & Piping WorksMechanical & Piping Works 96 15-Aug-14 19-Nov-14Equipment ErectionEquipment Erection 96 15-Aug-14 19-Nov-14RS-10110 Front readiness by Civil/ Strl & Crane for mechanical erection 0 15-Aug-14

RS-10130 Erection of priority Roll Grinders 46 16-Aug-14 30-Sep-14*

RS-10120 Erection of Roll Shop equipment (other than priority grinders) 60 01-Sep-14 30-Oct-14

RS-10150 Roll grinding 0 19-Nov-14

Roll shop layout, RSMS, WR, BUR, Pulpit and B&S coordination for Roll shopRoll shop layout, RSMS, WR, BUR, Pulpit and B&S coordination for Roll shop 115 05-Sep-14 29-Dec-14

Roll Shop - Test & TrialsRoll Shop - Test & Trials 60 31-Oct-14 29-Dec-14RS-10140 Test & Commissioning of priority Roll Grinders 20 31-Oct-14 19-Nov-14

RS-10160 Test & Commissioning Roll Shop Eqpt (other than priority grinders) 60 31-Oct-14 29-Dec-14

Roll Shop-Pulpit Area:Roll Shop-Pulpit Area: 42 05-Sep-14 30-Oct-14RS-10170 clearance 0 05-Sep-14 05-Sep-14

RS-10200 Equipment availablity & Drawing 1 06-Sep-14 08-Sep-14

RS-10180 Fabrication & erection of cable tray & supports 15 05-Sep-14 25-Sep-14

RS-10190 Installation of I/O Panels and HMI, Network cabinet, etc. 15 06-Sep-14 25-Sep-14

RS-10210 Cable Laying up to field equipment 15 25-Sep-14 15-Oct-14

RS-10220 Panel Earthing 27 20-Sep-14 27-Oct-14

RS-10230 Cable Glanding & Termination 10 17-Oct-14 30-Oct-14

Edger cum Roughing Mill (PD, RMs, discharge RT, All table Rolls)+ Shop Piping + LabEdger cum Roughing Mill (PD, RMs, discharge RT, All table Rolls)+ Shop Piping + Lab 121 01-Nov-11 A 30-Oct-14

FCE Charging & Discharge Table, Primary Descalar, R1 ( incl R1 Ent Table to R1 Del Table)FCE Charging & Discharge Table, Primary Descalar, R1 ( incl R1 Ent Table to R1 Del Table) 108 31-Mar-12 A 17-Oct-14

Civil Building & Foundation WorksCivil Building & Foundation Works 47 31-Mar-12 A 30-Aug-14Charging Aisle &Stack-E-F/ 1-14Charging Aisle &Stack-E-F/ 1-14 47 31-Mar-12 A 30-Aug-14FCE-10360 Drawing Inputs incl. Equipment foundation 0 31-Mar-12 A 29-Sep-12 A

FCE-10370 Building Column - Furnace Bay (B-C-E-F/2-13) 0 02-Jul-12 A 26-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 8 of 81 Filter: All Activity

Page 9: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FCE-10390 Stack Foundation 0 05-Mar-14 A 15-Apr-14 A

FCE-10380 Charging Roller Table Equip Foundation 13-10 0 28-Mar-13 A 17-Apr-14 A

FCE-10400 Charging Roller Table Equip Foundation 10-4 47 15-Jul-13 A 30-Aug-14

Structural Building & Technological WorksStructural Building & Technological Works 42 11-Sep-12 A 12-Aug-14Charging Aisle &Stack-E-F/ 1-13Charging Aisle &Stack-E-F/ 1-13 33 11-Sep-12 A 12-Aug-14FCE-10410 Drawing Inputs 0 11-Sep-12 A 17-Dec-12 A

FCE-10420 Fabrication 0 15-Dec-12 A 01-Mar-14 A

FCE-10440 Erection 8-1 to give front to EOT erection 0 10-Sep-13 A 31-Mar-14 A

FCE-10430 Erection 13-8 (including sheeting) 7 15-Jul-13 A 10-Jul-14

FCE-10445 Erection 8-1 (including sheeting) 33 15-Jul-13 A 12-Aug-14

40 (on tong)/16T Crane at E-F Bay40 (on tong)/16T Crane at E-F Bay 20 31-Mar-14 A 21-Jul-14FCE-EOT-10000 Strl building readiness for crane erection 0 31-Mar-14 A

FCE-EOT-10010 EOT Erecti on & Testing of crane 20 10-Apr-14 A 21-Jul-14

Receipt of Equipment at siteReceipt of Equipment at site 0 05-Jul-13 A 26-May-14 ARM-10000 Receipt at site (Sojitz scope) 0 05-Jul-13 A 10-Mar-14 A

FCE-10450 Receipt at site (TGS scope) 0 19-Jul-13 A 23-Apr-14 A

RM-10010 Receipt at site (TGS scope) 0 15-Jul-13 A 26-May-14 A

Mechanical & Piping WorksMechanical & Piping Works 108 15-Feb-14 A 17-Oct-14MILL MAIN EQUIPMENT ERECTIONMILL MAIN EQUIPMENT ERECTION 108 15-Feb-14 A 17-Oct-14FRONT#1 (FURNACE ENTRY SIDE)FRONT#1 (FURNACE ENTRY SIDE) 88 27-Apr-14 A 17-Oct-14FCE-10460 SLAB WEIGHER 8 22-Jul-14 29-Jul-14

FURNACE ENTRY TABLE + SLAB CHARGING TABLE (36 TABLES, 169 ROLLS)FURNACE ENTRY TABLE + SLAB CHARGING TABLE (36 TABLES, 169 ROLLS) 88 27-Apr-14 A 17-Oct-14FCE-10470 MOTOR ALLIGNMENT (169 MOTORS) 19 02-Sep-14 20-Sep-14

FCE-10480 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 11 15-Sep-14 25-Sep-14

PREPARATIONPREPARATION 6 27-Apr-14 A 27-Jul-14RM-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 27-Apr-14 A 01-May-14 A

RM-10030 ERECTION OF TABLE BEAM 1 22-Jul-14 22-Jul-14

RM-10040 INSTALLATION OF MOTOR FRAME 1 23-Jul-14 23-Jul-14

RM-10050 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE1 24-Jul-14 24-Jul-14

RM-10060 INSTALLATION OF MOTOR 1 25-Jul-14 25-Jul-14

RM-10070 SETTING THE ANCHOR BOLTS AND NUTS 1 26-Jul-14 26-Jul-14

RM-10080 ANCHOR GROUTING AND CURING. 1 27-Jul-14 27-Jul-14

ALLIGNMENTALLIGNMENT 6 28-Jul-14 02-Aug-14RM-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 2 28-Jul-14 29-Jul-14

RM-10100 CHECK THE LEVELNESS 2 30-Jul-14 31-Jul-14

RM-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 2 01-Aug-14 02-Aug-14

e.REMAINING WORKSe.REMAINING WORKS 22 25-Sep-14 17-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 9 of 81 Filter: All Activity

Page 10: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM-10120 INSTALLATION OF MOTOR COVER 1 25-Sep-14 26-Sep-14

RM-10130 INSTALLATION OF SPLASH GUARD 1 26-Sep-14 27-Sep-14

RM-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 27-Sep-14 28-Sep-14

RM-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 20 27-Sep-14 17-Oct-14

FRONT#2 (FURNACE DELIVERY SIDE)FRONT#2 (FURNACE DELIVERY SIDE) 83 05-May-14 A 28-Sep-14FURNACE DELIVERY TABLE (34 TABLES, 86 ROLLS)FURNACE DELIVERY TABLE (34 TABLES, 86 ROLLS) 55 05-May-14 A 02-Sep-14FCE-10490 MOTOR ALLIGNMENT (86 MOTORS) 1 10-Jul-14* 10-Jul-14

FCE-10500 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 1 11-Jul-14 11-Jul-14

a. PREPARATIONa. PREPARATION 0 05-May-14 A 10-Jun-14 AFCE-10510 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 05-May-14 A 05-May-14 A

FCE-10520 ERECTION OF TABLE BEAM 0 06-May-14 A 06-May-14 A

FCE-10530 INSTALLATION OF MOTOR FRAME 0 06-Jun-14 A 06-Jun-14 A

FCE-10540 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE0 07-Jun-14 A 07-Jun-14 A

FCE-10550 INSTALLATION OF MOTOR 0 08-Jun-14 A 08-Jun-14 A

FCE-10560 SETTING THE ANCHOR BOLTS AND NUTS 0 09-Jun-14 A 09-Jun-14 A

FCE-10570 ANCHOR GROUTING AND CURING. 0 10-Jun-14 A 10-Jun-14 A

b.ALLIGNMENT b.ALLIGNMENT 0 11-Jun-14 A 13-Jun-14 AFCE-10580 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 11-Jun-14 A 11-Jun-14 A

FCE-10590 CHECK THE LEVELNESS 0 12-Jun-14 A 12-Jun-14 A

FCE-10600 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 13-Jun-14 A 13-Jun-14 A

e.REMAINING WORKSe.REMAINING WORKS 53 12-Jul-14 02-Sep-14FCE-10610 INSTALLATION OF MOTOR COVER 5 12-Jul-14 16-Jul-14

FCE-10620 INSTALLATION OF SPLASH GUARD 15 17-Jul-14 31-Jul-14

FCE-10630 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 3 01-Aug-14 03-Aug-14

FCE-10640 ATTACHED PIPING AND OTHER REMAINING WORKS. 30 04-Aug-14 02-Sep-14

HSB ROLLER TABLE (3 TABLES, 18 ROLLS)HSB ROLLER TABLE (3 TABLES, 18 ROLLS) 62 29-Jul-14 28-Sep-14HSB-10000 MOTOR ALLIGNMENT (18 MOTORS) 10 07-Sep-14 16-Sep-14

HSB-10010 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 10 12-Sep-14 21-Sep-14

a. PREPARATIONa. PREPARATION 25 29-Jul-14 22-Aug-14HSB-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 1 29-Jul-14 29-Jul-14

HSB-10030 ERECTION OF TABLE BEAM 2 30-Jul-14 31-Jul-14

HSB-10040 INSTALLATION OF MOTOR FRAME 5 01-Aug-14 05-Aug-14

HSB-10050 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE5 06-Aug-14 10-Aug-14

HSB-10060 INSTALLATION OF MOTOR 5 11-Aug-14 15-Aug-14

HSB-10070 SETTING THE ANCHOR BOLTS AND NUTS 4 16-Aug-14 19-Aug-14

HSB-10080 ANCHOR GROUTING AND CURING. 3 20-Aug-14 22-Aug-14

b.ALLIGNMENT b.ALLIGNMENT 15 23-Aug-14 06-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 10 of 81 Filter: All Activity

Page 11: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

HSB-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 5 23-Aug-14 27-Aug-14

HSB-10100 CHECK THE LEVELNESS 5 28-Aug-14 01-Sep-14

HSB-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 5 02-Sep-14 06-Sep-14

e.REMAINING WORKSe.REMAINING WORKS 7 22-Sep-14 28-Sep-14HSB-10120 INSTALLATION OF MOTOR COVER 1 22-Sep-14 22-Sep-14

HSB-10130 INSTALLATION OF SPLASH GUARD 1 23-Sep-14 23-Sep-14

HSB-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 24-Sep-14 24-Sep-14

HSB-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 4 25-Sep-14 28-Sep-14

HYDRAULIC SCALE BREAKERHYDRAULIC SCALE BREAKER 11 25-Jul-14 04-Aug-14HSB-10160 INSTALLATION OF DESCALING BOX 2 26-Jul-14* 27-Jul-14

HSB-10170 INSTALLATION OF SPLASH GUARD 1 28-Jul-14 28-Jul-14

HSB-10180 ATTACHED PIPING 5 29-Jul-14 02-Aug-14

HSB-10190 INSTALLTION OF PX SENSOR 1 03-Aug-14 03-Aug-14

a. PREPARATIONa. PREPARATION 0 25-Jul-14 25-Jul-14HSB-10200 PREPARATION 0 25-Jul-14

HSB-10210 CONFIRM THE COMPLETION OF ALIGNMENT OF HSB TABLE 0 25-Jul-14*

HSB-10220 CONFIRM THE COMPLETION OF APRON INSTALLATION OF HSB TABLE 0 25-Jul-14

b. INSTALLATION OF BOTTOM HEADERb. INSTALLATION OF BOTTOM HEADER 1 25-Jul-14 25-Jul-14HSB-10230 INSTALL BOTTOM HEADER (CONFIRM THE POSITON OF LINE CENTER AND NOZZLE OF HEADER)1 25-Jul-14 25-Jul-14

g. INSTALLTION OF DESCALING NOZZLEg. INSTALLTION OF DESCALING NOZZLE 1 04-Aug-14 04-Aug-14HSB-10240 INSTALL THE NOZZLE AFTER COMPLETING THE WATER BLOW OF PIPE 1 04-Aug-14 04-Aug-14

ROUGHING MILL#2 APPROACH TABLE (8 TABLE, 62 ROLLS)ROUGHING MILL#2 APPROACH TABLE (8 TABLE, 62 ROLLS) 63 02-Jun-14 A 08-Sep-14RM2-10000 MOTOR ALLIGNMENT (62 MOTORS) 20 08-Jul-14* 27-Jul-14

RM2-10010 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 35 28-Jul-14 31-Aug-14

a. PREPARATIONa. PREPARATION 0 02-Jun-14 A 14-Jun-14 ARM2-10020 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 02-Jun-14 A 03-Jun-14 A

RM2-10030 ERECTION OF TABLE BEAM 0 03-Jun-14 A 04-Jun-14 A

RM2-10040 INSTALLATION OF MOTOR FRAME 0 05-Jun-14 A 06-Jun-14 A

RM2-10050 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE0 07-Jun-14 A 08-Jun-14 A

RM2-10060 INSTALLATION OF MOTOR 0 09-Jun-14 A 10-Jun-14 A

RM2-10070 SETTING THE ANCHOR BOLTS AND NUTS 0 11-Jun-14 A 12-Jun-14 A

RM2-10080 ANCHOR GROUTING AND CURING. 0 13-Jun-14 A 14-Jun-14 A

b.ALLIGNMENT b.ALLIGNMENT 0 15-Jun-14 A 19-Jun-14 ARM2-10090 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 15-Jun-14 A 15-Jun-14 A

RM2-10100 CHECK THE LEVELNESS 0 16-Jun-14 A 17-Jun-14 A

RM2-10110 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 18-Jun-14 A 19-Jun-14 A

e.REMAINING WORKSe.REMAINING WORKS 8 01-Sep-14 08-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 11 of 81 Filter: All Activity

Page 12: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM2-10120 INSTALLATION OF MOTOR COVER 2 01-Sep-14 02-Sep-14

RM2-10130 INSTALLATION OF SPLASH GUARD 2 03-Sep-14 04-Sep-14

RM2-10140 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 2 05-Sep-14 06-Sep-14

RM2-10150 ATTACHED PIPING AND OTHER REMAINING WORKS. 2 07-Sep-14 08-Sep-14

FRONT#3 (DELAY TABLE)FRONT#3 (DELAY TABLE) 91 15-Feb-14 A 30-Sep-14DT-10000 COBBLE PUSHER 91 31-Mar-14 A 30-Sep-14

DELAY TABLE (9 TABLE, 58 ROLLS)DELAY TABLE (9 TABLE, 58 ROLLS) 0 15-Feb-14 A 03-May-14 ADT-10010 MOTOR ALLIGNMENT (58 MOTORS) 0 27-Mar-14 A 10-Apr-14 A

DT-10020 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 10-Apr-14 A 13-Apr-14 A

a. PREPARATIONa. PREPARATION 0 15-Feb-14 A 18-Mar-14 ADT-10030 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 15-Feb-14 A 16-Feb-14 A

DT-10040 ERECTION OF TABLE BEAM 0 18-Feb-14 A 19-Feb-14 A

DT-10050 INSTALLATION OF MOTOR FRAME 0 07-Mar-14 A 08-Mar-14 A

DT-10060 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE0 09-Mar-14 A 10-Mar-14 A

DT-10070 INSTALLATION OF MOTOR 0 11-Mar-14 A 13-Mar-14 A

DT-10080 SETTING THE ANCHOR BOLTS AND NUTS 0 14-Mar-14 A 15-Mar-14 A

DT-10090 ANCHOR GROUTING AND CURING. 0 16-Mar-14 A 18-Mar-14 A

b.ALLIGNMENT b.ALLIGNMENT 0 20-Mar-14 A 24-Mar-14 ADT-10100 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 20-Mar-14 A 20-Mar-14 A

DT-10110 CHECK THE LEVELNESS 0 21-Mar-14 A 22-Mar-14 A

DT-10120 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 23-Mar-14 A 24-Mar-14 A

e.REMAINING WORKSe.REMAINING WORKS 0 13-Apr-14 A 03-May-14 ADT-10130 INSTALLATION OF MOTOR COVER 0 13-Apr-14 A 14-Apr-14 A

DT-10140 INSTALLATION OF SPLASH GUARD 0 15-Apr-14 A 16-Apr-14 A

DT-10150 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 17-Apr-14 A 18-Apr-14 A

DT-10160 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 19-Apr-14 A 03-May-14 A

MILL AUXILIARY EQUIPMENT (CELLAR EQUIP) ERECTIONMILL AUXILIARY EQUIPMENT (CELLAR EQUIP) ERECTION 90 15-Apr-14 A 29-Sep-14ERECTION OF G2ERECTION OF G2 53 01-Aug-14 22-Sep-14MILL-AUX-10000 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14* 01-Aug-14

MILL-AUX-10010 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14

MILL-AUX-10020 FLUSHING OF GREASE PIPES 2 21-Sep-14 22-Sep-14

ERECTION OF G3ERECTION OF G3 53 01-Aug-14 22-Sep-14MILL-AUX-10030 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14 01-Aug-14

MILL-AUX-10040 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14

MILL-AUX-10050 FLUSHING OF GREASE PIPES 2 21-Sep-14 22-Sep-14

ERECTION OF G4ERECTION OF G4 51 01-Aug-14 20-Sep-14MILL-AUX-10060 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 1 01-Aug-14 01-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 12 of 81 Filter: All Activity

Page 13: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MILL-AUX-10080 FLUSHING OF GREASE PIPES 4 02-Aug-14 05-Aug-14

MILL-AUX-10070 ERECTION OF GREASE PIPING 50 02-Aug-14 20-Sep-14

ERECTION OF G5ERECTION OF G5 55 01-Aug-14 24-Sep-14MILL-AUX-10100 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14

MILL-AUX-10090 ERECTION OF GREASE PIPING 50 01-Aug-14 19-Sep-14

MILL-AUX-10110 FLUSHING OF GREASE PIPES 5 20-Sep-14 24-Sep-14

ERECTION OF G6ERECTION OF G6 60 01-Aug-14 29-Sep-14MILL-AUX-10120 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14

MILL-AUX-10130 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14

MILL-AUX-10140 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14

ERECTION OF G7ERECTION OF G7 60 01-Aug-14 29-Sep-14MILL-AUX-10150 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14

MILL-AUX-10160 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14

MILL-AUX-10170 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14

ERECTION OF G8ERECTION OF G8 60 01-Aug-14 29-Sep-14MILL-AUX-10180 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14

MILL-AUX-10190 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14

MILL-AUX-10200 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14

ERECTION OF G9ERECTION OF G9 60 01-Aug-14 29-Sep-14MILL-AUX-10210 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14

MILL-AUX-10220 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14

MILL-AUX-10230 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14

ERECTION OF G10ERECTION OF G10 60 01-Aug-14 29-Sep-14MILL-AUX-10240 ERECTION OF FILLING PUMP & GREASE PUMP UNIT 5 01-Aug-14 05-Aug-14

MILL-AUX-10250 ERECTION OF GREASE PIPING 50 06-Aug-14 24-Sep-14

MILL-AUX-10260 FLUSHING OF GREASE PIPES 5 25-Sep-14 29-Sep-14

ERECTION OF RL1 (R1 GEAR LUB) SYSTEMERECTION OF RL1 (R1 GEAR LUB) SYSTEM 55 02-Jul-14 25-Aug-14MILL-AUX-10350 Electrical Work (Sensor Erec tion & Termination) 30 02-Jul-14 31-Jul-14

MILL-AUX-10270 Lowering of the tank and placing at the pedestal 1 01-Aug-14* 01-Aug-14

MILL-AUX-10280 Lowering of the pump unit and placing at the pedestal 1 02-Aug-14 02-Aug-14

MILL-AUX-10290 Alignment of tank unit 2 03-Aug-14 04-Aug-14

MILL-AUX-10300 Alignment of pump unit 2 05-Aug-14 06-Aug-14

MILL-AUX-10310 Installation of centrifuge 1 07-Aug-14 07-Aug-14

MILL-AUX-10320 Installation of Strainer and heat exchanger 10 08-Aug-14 17-Aug-14

MILL-AUX-10330 Installation of instruments at pump and tank unit 8 18-Aug-14 25-Aug-14

ERECTION OF ML1 (R1 WR BEARING LUB) SYSTEMERECTION OF ML1 (R1 WR BEARING LUB) SYSTEM 47 02-Jul-14 17-Aug-14MILL-AUX-10440 Electrical Work (Sensor Erec tion & Termination) 20 02-Jul-14 21-Jul-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 13 of 81 Filter: All Activity

Page 14: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MILL-AUX-10370 Lowering of the pump unit and placing at the pedestal 1 31-Jul-14 31-Jul-14

MILL-AUX-10360 Lowering of the tank and placing at the pedestal 1 01-Aug-14 01-Aug-14

MILL-AUX-10380 Alignment of tank unit 2 01-Aug-14 02-Aug-14

MILL-AUX-10390 Alignment of pump unit 2 03-Aug-14 04-Aug-14

MILL-AUX-10400 Installation of centrifuge 1 05-Aug-14 05-Aug-14

MILL-AUX-10410 Installation of Strainer and heat exchanger 7 06-Aug-14 12-Aug-14

MILL-AUX-10420 Installation of instruments at pump and tank unit 15 03-Aug-14 17-Aug-14

ERECTION OF RL2 (R2 GEAR LUB) SYSTEMERECTION OF RL2 (R2 GEAR LUB) SYSTEM 51 02-Jul-14 21-Aug-14MILL-AUX-10530 Electrical Work (Sensor Erec tion & Termination) 30 02-Jul-14 31-Jul-14

MILL-AUX-10450 Lowering of the tank and placing at the pedestal 1 01-Aug-14 01-Aug-14

MILL-AUX-10460 Lowering of the pump unit and placing at the pedestal 1 02-Aug-14 02-Aug-14

MILL-AUX-10470 Alignment of tank unit 2 03-Aug-14 04-Aug-14

MILL-AUX-10480 Alignment of pump unit 3 05-Aug-14 07-Aug-14

MILL-AUX-10490 Installation of centrifuge 2 08-Aug-14 09-Aug-14*

MILL-AUX-10500 Installation of Strainer and heat exchanger 2 10-Aug-14 11-Aug-14

MILL-AUX-10510 Installation of instruments at pump and tank unit 10 12-Aug-14 21-Aug-14

ERECTION OF ML2 (R2 BUR BEARING LUB) SYSTEMERECTION OF ML2 (R2 BUR BEARING LUB) SYSTEM 23 19-May-14 A 24-Jul-14MILL-AUX-10540 Lowering of the tank and placing at the pedestal 0 19-May-14 A 19-May-14 A

MILL-AUX-10550 Lowering of the pump unit and placing at the pedestal 0 20-May-14 A 21-May-14 A

MILL-AUX-10560 Alignment of tank unit 0 22-May-14 A 23-May-14 A

MILL-AUX-10570 Alignment of pump unit 0 24-May-14 A 25-May-14 A

MILL-AUX-10580 Installation of centrifuge 0 26-May-14 A 27-May-14 A

MILL-AUX-10590 Installation of Strainer and heat exchanger 0 28-May-14 A 01-Jun-14 A

MILL-AUX-10600 Installation of instruments at pump and tank unit 0 02-Jun-14 A 09-Jun-14 A

MILL-AUX-10620 Electrical Work (Sensor Erec tion & Termination) 23 30-Jun-14 A 24-Jul-14

ERECTION OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEMERECTION OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEM 38 30-Jul-14 05-Sep-14MILL-AUX-10640 Lowering of the pump unit and placing at the pedestal 1 03-Aug-14 03-Aug-14

MILL-AUX-10650 Alignment of tank unit 1 04-Aug-14 04-Aug-14

MILL-AUX-10660 Alignment of pump unit (Oil booster,metering pump) 1 05-Aug-14 05-Aug-14

MILL-AUX-10670 Installation of centrifuge 1 05-Aug-14 05-Aug-14

MILL-AUX-10680 Installation of Strainer and heat exchanger 1 06-Aug-14 06-Aug-14

MILL-AUX-10690 Installation of instruments at pump and tank unit 2 07-Aug-14 08-Aug-14

MILL-AUX-10700 Installation of valve Stands 10 30-Jul-14 08-Aug-14

MILL-AUX-10710 Electrical Work (Sensor Erec tion & Termination) 28 09-Aug-14 05-Sep-14

ERECTION OF DE-SCALING SYSTEMERECTION OF DE-SCALING SYSTEM 34 18-Jun-14 A 15-Sep-14MILL-AUX-10720 Erection of Surge Tank 0 18-Jun-14 A 20-Jun-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 14 of 81 Filter: All Activity

Page 15: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MILL-AUX-10730 Erection of Accumulator stands 2 23-Aug-14 24-Aug-14

MILL-AUX-10740 Erection of Descaling Pump units 2 25-Aug-14 26-Aug-14

MILL-AUX-10750 Erection of valve stands 10 27-Aug-14 05-Sep-14

MILL-AUX-10760 Electrical Work (Sensor Erec tion & Termination) 34 13-Aug-14 15-Sep-14

ERECTION OF HA1 (RM AUX HYD) SYSTEMERECTION OF HA1 (RM AUX HYD) SYSTEM 34 15-Apr-14 A 12-Aug-14MILL-AUX-10830 Installation of accumulator stand 0 15-Apr-14 A 16-Apr-14 A

MILL-AUX-10770 Lowering of the tank and placing at the pedestal 0 16-May-14 A 18-May-14 A

MILL-AUX-10780 Lowering of the pump unit and placing at the pedestal 0 19-May-14 A 22-May-14 A

MILL-AUX-10790 Alignment of tank unit 0 22-May-14 A 27-May-14 A

MILL-AUX-10800 Alignment of pump unit 0 27-May-14 A 01-Jun-14 A

MILL-AUX-10810 Installation of filter circulation unit 0 01-Jun-14 A 06-Jun-14 A

MILL-AUX-10840 Installation of instruments at pump and tank unit 4 21-Jul-14* 24-Jul-14

MILL-AUX-10850 Installation of valve Stands 15 10-Jul-14* 24-Jul-14

MILL-AUX-10820 Installation of return filter l ine 4 01-Aug-14 04-Aug-14

MILL-AUX-10860 Electrical Work (Sensor Erec tion & Termination) 19 25-Jul-14 12-Aug-14

ERECTION OF HS1 (RM SERVO HYD) SYSTEMERECTION OF HS1 (RM SERVO HYD) SYSTEM 45 02-Jul-14 15-Aug-14MILL-AUX-10870 Lowering of the tank and placing at the pedestal 3 02-Jul-14* 04-Jul-14

MILL-AUX-10880 Lowering of the pump unit and placing at the pedestal 1 05-Jul-14 05-Jul-14

MILL-AUX-10890 Alignment of tank unit 1 06-Jul-14 06-Jul-14

MILL-AUX-10900 Alignment of pump unit 1 07-Jul-14 07-Jul-14

MILL-AUX-10910 Installation of filter circulation unit 1 08-Jul-14 08-Jul-14

MILL-AUX-10920 Installation of return filter l ine 1 09-Jul-14 09-Jul-14

MILL-AUX-10930 Installation of accumulator stand 1 10-Jul-14 10-Jul-14

MILL-AUX-10940 Installation of instruments at pump and tank unit 10 11-Jul-14 20-Jul-14

MILL-AUX-10950 Installation of valve Stands (Incl servo valve) 10 21-Jul-14 30-Jul-14

MILL-AUX-10960 Electrical Work (Sensor Erec tion & Termination) 16 31-Jul-14 15-Aug-14*

Mill Elect portion & Local ElectricsMill Elect portion & Local Electrics 66 11-Jul-14 06-Oct-14Electrical & Automation WorksElectrical & Automation Works 66 11-Jul-14 06-Oct-14ELECTRICAL WORK (FRONT#1--> FURNACE ENTRY SIDE)ELECTRICAL WORK (FRONT#1--> FURNACE ENTRY SIDE) 60 11-Jul-14 27-Sep-14B&S-10000 POWER CABLE GLANDING 20 11-Jul-14 06-Aug-14

B&S-10010 POWER CABLE SOCKETING & TERMINATION 40 06-Aug-14 27-Sep-14

ELECTRICAL WORK (FRONT#2--> FURNACE DELIVERY SIDE)ELECTRICAL WORK (FRONT#2--> FURNACE DELIVERY SIDE) 20 08-Sep-14 04-Oct-14B&S-10020 INSTRUMENT INSTALLATION 9 08-Sep-14 19-Sep-14

B&S-10030 CABLE DUCTING LAYING & TERMINATION 5 27-Sep-14 04-Oct-14*

ELECTRICAL WORK (FRONT#3--> ROUGHING MILL#1)ELECTRICAL WORK (FRONT#3--> ROUGHING MILL#1) 28 29-Aug-14 04-Oct-14B&S-10040 INSTRUMENT INSTALLATION 20 29-Aug-14 24-Sep-14

B&S-10050 CABLE DUCTING LAYING & TERMINATION 23 04-Sep-14 04-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 15 of 81 Filter: All Activity

Page 16: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

ELECTRICAL WORK (FRONT#4--> ROUGHING MILL#2)ELECTRICAL WORK (FRONT#4--> ROUGHING MILL#2) 30 06-Aug-14 15-Sep-14B&S-10060 INSTRUMENT INSTALLATION 7 06-Aug-14 16-Aug-14

B&S-10070 CABLE DUCTING LAYING & TERMINATION 23 16-Aug-14 15-Sep-14

ELECTRICAL WORK (FRONT#5--> DELAY TABLE)ELECTRICAL WORK (FRONT#5--> DELAY TABLE) 43 09-Aug-14 06-Oct-14B&S-10080 INSTRUMENT INSTALLATION 30 09-Aug-14 18-Sep-14

B&S-10090 CABLE DUCTING LAYING & TERMINATION 10 22-Sep-14 06-Oct-14*

ELECTRICAL WORK (FRONT#6--> CROP SHEAR)ELECTRICAL WORK (FRONT#6--> CROP SHEAR) 43 09-Aug-14 06-Oct-14B&S-10100 INSTRUMENT INSTALLATION 28 09-Aug-14 15-Sep-14

B&S-10110 CABLE DUCTING LAYING & TERMINATION 12 19-Sep-14 06-Oct-14*

INDIVIDUAL TRIALSINDIVIDUAL TRIALS 85 24-Jul-14 17-Oct-14B&S-10150 FRONT#2 (FURNACE DELIVERY SIDE) INDIVIDUAL TRIAL 10 05-Oct-14 15-Oct-14

B&S-10130 FRONT#6 (CROP SHEAR) INDIVIDUAL TRIAL 6 08-Oct-14 16-Oct-14

B&S-10120 FRONT#5 (DELAY TABLE) INDIVIDUAL TRIAL 6 08-Oct-14 16-Oct-14

B&S-10140 FRONT#1 (FURNACE ENTRY SIDE) INDIVIDUAL TRIAL 7 09-Oct-14 17-Oct-14

Online FlushingOnline Flushing 58 24-Jul-14 08-Oct-14B&S-10170 ONLINE FLUSHING OF ML2 (R2 BUR BEARING LUB) SYSTEM 11 24-Jul-14 07-Aug-14

B&S-10210 ONLINE FLUSHING OF HA1 (RM AUX HYD) SYSTEM 4 12-Aug-14 18-Aug-14

B&S-10190 ONLINE FLUSHING OF HS1 (RM SERVO HYD) SYSTEM 11 08-Sep-14 22-Sep-14*

B&S-10230 ONLINE FLUSHING OF RL1 (R1 GEAR LUB) SYSTEM 10 09-Sep-14 22-Sep-14*

B&S-10160 ONLINE FLUSHING OF ML1 (R1 WR BEARING LUB) SYSTEM 10 09-Sep-14 22-Sep-14*

B&S-10220 ONLINE FLUSHING OF RL2 (R2 GEAR LUB) SYSTEM 10 09-Sep-14 22-Sep-14*

B&S-10200 ONLINE FLUSHING OF DE-SCALING SYSTEM 16 17-Sep-14 08-Oct-14*

B&S-10180 ONLINE FLUSHING OF RO1 (E1, E2 HOT ROLLING OIL) SYSTEM 10 25-Sep-14 08-Oct-14*

R2 (Incl R2 Entry Table to CS Entry Table) and TGS equipmentR2 (Incl R2 Entry Table to CS Entry Table) and TGS equipment 6 01-Nov-11 A 07-Jul-14

Civil Building & Foundation WorksCivil Building & Foundation Works 0 01-Nov-11 A 10-May-14 ARoughing-AreaRoughing-Area 0 01-Nov-11 A 10-May-14 ARM2-11880 Blasting 0 08-Aug-12 A 15-Sep-12 A

RM2-11860 Scale Flume 0 04-Feb-12 A 31-Oct-12 A

RM2-11850 Building Column 0 01-Feb-12 A 31-Jan-13 A

RM2-11840 Drawing Inputs incl. Equipment foundation 0 01-Nov-11 A 31-Jul-13 A

RM2-11870 Roughing Mill Equip Foundation-R2 incl. scale flume wall upto top 0 29-Apr-12 A 12-Feb-14 A

RM2-11890 Roughing Mill Equip Foundation-R1 incl. scale flume wall upto top 0 02-Nov-12 A 10-May-14 A

STRUCTURAL - RM 1 & 2 - B-C /14a - 32STRUCTURAL - RM 1 & 2 - B-C /14a - 32 5 25-Aug-12 A 07-Jul-14RM2-11900 Drawing Inputs 0 25-Aug-12 A 31-Oct-12 A

RM2-11910 Fabrication 0 15-Jan-13 A 25-Dec-13 A

RM2-11930 Erection B-C/24-32 0 15-Sep-12 A 27-Feb-14 A

RM2-11920 Erection B-C/14-24 0 16-Feb-13 A 30-Mar-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 16 of 81 Filter: All Activity

Page 17: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM2-11940 Sheeting B-C/14-32 5 18-Jan-14 A 07-Jul-14*

RM Pulpits, LAB & Roll bite lub systemRM Pulpits, LAB & Roll bite lub system 83 03-Jan-14 A 17-Oct-14

R1-Pulpit Area:R1-Pulpit Area: 83 03-Jan-14 A 17-Oct-14RM1-PUL-10000 Equipment availablity & Drawing 0 03-Jan-14 A 20-Jan-14 A

RM1-PUL-10010 Fabrication & erection of cable tray & supports 0 03-Feb-14 A 19-May-14 A

RM1-PUL-10050 Panel Erection & Earthing 5 19-May-14 A 08-Jul-14

RM1-PUL-10030 Installation of I/O Panels and HMI, Network cabinet, etc. 10 15-Sep-14 27-Sep-14

RM1-PUL-10040 Cable Laying up to field equipment 50 13-Aug-14 17-Oct-14

RM1-PUL-10060 Cable Glanding & Termination 15 27-Sep-14 17-Oct-14

R2-Pulpit Area:R2-Pulpit Area: 61 03-Jan-14 A 27-Sep-14RM2-PUL-10080 Equipment availablity & Drawing 0 03-Jan-14 A 24-Jan-14 A

RM2-PUL-10070 Fabrication & erection of cable tray & supports 0 03-Feb-14 A 14-Apr-14 A

RM2-PUL-10110 Panel Earthing 0 14-Apr-14 A 05-Jun-14 A

RM2-PUL-10100 Installation of I/O Panels and HMI, Network cabinet, etc. 25 11-Jul-14 12-Aug-14

RM2-PUL-10120 Cable Laying up to field equipment 20 02-Sep-14 27-Sep-14

RM2-PUL-10130 Cable Glanding & Termination 20 02-Sep-14 27-Sep-14

Structural Building & Technological WorksStructural Building & Technological Works 58 23-Jun-14 A 15-Sep-14RM2-PUL-10140 Structural & Interior Woks -R-2-Pulpits 8 23-Jun-14 A 11-Jul-14*

RM2-PUL-10150 Structural & Interior Woks -R-1-Pulpits 35 31-Jul-14* 15-Sep-14

Civil Building & Foundation WorksCivil Building & Foundation Works 17 10-May-14 A 31-Jul-14RM2-PUL-10160 Civil Works-R-2-Pulpits 0 10-May-14 A 21-Jun-14 A

RM2-PUL-10170 Civil Works-R-1-Pulpits 17 09-Jul-14* 31-Jul-14

LABORATORY EQUIPMENT -SAMPLE PREPARATION & ANALYTICAL INSTRUMENTSLABORATORY EQUIPMENT -SAMPLE PREPARATION & ANALYTICAL INSTRUMENTS 79 03-Feb-14 A 13-Oct-14LAB-10000 Issue LOI/Order of LABORATORY EQUIPMENT 0 03-Feb-14 A

LAB-10010 Receipt of Equipment at Site of LABORATORY EQUIPMENT 0 03-Feb-14 A 09-May-14 A

LAB-10020 Equipment Erection Work of- LABORATORY EQUIPMENT 59 09-May-14 A 16-Sep-14

LAB-10030 Cold Tes t of- LABORATORY EQUIPMENT 20 16-Sep-14 13-Oct-14

R1 & R2 Hyd & Lub systems, RM area grease system & Fire fighting systemR1 & R2 Hyd & Lub systems, RM area grease system & Fire fighting system 108 18-Jan-14 A 17-Oct-14

Mechanical & Piping WorksMechanical & Piping Works 108 18-Jan-14 A 17-Oct-14

FRONT#4 (ROUGHING MILL#1)FRONT#4 (ROUGHING MILL#1) 98 21-Apr-14 A 07-Oct-14

HYDRAULIC SCALE BREAKERHYDRAULIC SCALE BREAKER 87 02-Jul-14 26-Sep-14

FSB-10000 INSTALLATION OF DESCALING BOX 2 12-Jul-14 13-Jul-14

FSB-10010 INSTALLATION OF SPLASH GUARD 10 04-Jul-14 13-Jul-14

FSB-10020 ATTACHED PIPING 70 02-Jul-14 09-Sep-14

FSB-10030 INSTALLTION OF PX SENSOR 10 31-Aug-14 09-Sep-14

PREPARATIONPREPARATION 7 02-Jul-14 08-Jul-14FSB-10040 PREPARATION 1 02-Jul-14 02-Jul-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 17 of 81 Filter: All Activity

Page 18: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FSB-10050 CONFIRM THE ERECTION & ALIGNMENT OF HSB TABLE 5 03-Jul-14 07-Jul-14

FSB-10060 CONFIRM THE COMPLETION OF APRON INSTALLATION OF HSB TABLE 1 08-Jul-14 08-Jul-14

INSTALLATION OF BOTTOM HEADERINSTALLATION OF BOTTOM HEADER 3 09-Jul-14 11-Jul-14FSB-10070 INSTALL BOTTOM HEADER (CONFIRM THE POSITON OF LINE CENTER AND NOZZLE OF HEADER)3 09-Jul-14 11-Jul-14

INSTALLTION OF DESCALING NOZZLEINSTALLTION OF DESCALING NOZZLE 77 12-Jul-14 26-Sep-14FSB-10080 INSTALL THE NOZZLE AFTER COMPLETING THE WATER BLOW OF PIPE 38 12-Jul-14 18-Aug-14

FSB-10090 Individual Trial of HSB 5 20-Sep-14 26-Sep-14*

RM SHOE PLATERM SHOE PLATE 0 21-Apr-14 A 16-May-14 A

RM1-10010 FOUNDATION CHECKING 0 21-Apr-14 A 21-Apr-14 A

RM1-10020 FOUNDATION CHIPPING AND PADDING 0 22-Apr-14 A 23-Apr-14 A

RM1-10040 INSTALLATION AND ALLIGNMENT OF SHOE PLATE 0 15-May-14 A 15-May-14 A

RM1-10050 GROUTING & CURING 0 16-May-14 A 16-May-14 A

RM HOUSINGRM HOUSING 32 07-Jun-14 A 02-Aug-14

RM1-10060 FINAL MEASUREMENT OF HSG WITH PIANNO WIRE AND TIGHTENING OF HSG AND SEPARATOR BOLT.0 07-Jun-14 A 15-Jun-14 A

RM1-10070 INSTALLATION OF SIMPLE PARTS (PLATFORMS & STAIRS ETC) 32 16-Jun-14 A 02-Aug-14

DS HSG ERECTION AND ALLIGNMENTDS HSG ERECTION AND ALLIGNMENT 0 07-Jun-14 A 07-Jun-14 A

RM1-10140 ERECTION OF DS HOUSING 0 07-Jun-14 A 07-Jun-14 A

WS HSG ERECTION AND ALLIGNMENTWS HSG ERECTION AND ALLIGNMENT 0 08-Jun-14 A 08-Jun-14 A

RM1-10180 ERECTION OF WS HOUSING 0 08-Jun-14 A 08-Jun-14 A

BOTTOM SEPARATOR INSTALLATIONBOTTOM SEPARATOR INSTALLATION 0 09-Jun-14 A 09-Jun-14 A

RM1-10240 ERECTION OF BOTTOM SEPARATOR 0 09-Jun-14 A 09-Jun-14 A

TOP SEPARATOR INSTALLATIONTOP SEPARATOR INSTALLATION 0 10-Jun-14 A 12-Jun-14 A

RM1-10280 ERECTION OF TOP SEPARATOR 0 10-Jun-14 A 10-Jun-14 A

RM1-10290 ALLIGNMENT OF RM-1 HOUSING 0 10-Jun-14 A 12-Jun-14 A

E1 HOUSING & PROPERE1 HOUSING & PROPER 12 02-Jul-14 13-Jul-14

EDG1-10000 E1 HOUSNG ERECTION & ASSEMBLY. 2 02-Jul-14 03-Jul-14

EDG1-10010 AWC & PULL BACK CYLINDER 1 04-Jul-14 04-Jul-14

EDG1-10020 REDUCER & MOTOR ERECTION AND ALLIGNMENT 1 08-Jul-14 08-Jul-14

EDG1-10030 INSTALLATION OF SIMPLE PARTS (PLATFORM,STAIRS ETC) 1 13-Jul-14 13-Jul-14

ROLL ADJUST FRAME AND POWER TRUCKROLL ADJUST FRAME AND POWER TRUCK 3 05-Jul-14 07-Jul-14

EDG1-10080 INSERT ROLL ADJUST FRAME IN HSG 1 05-Jul-14 05-Jul-14

EDG1-10090 CONNECT ROLL ADJUST FRAME WITH PULL BACK CYLINDER 1 06-Jul-14 06-Jul-14

EDG1-10100 INSTALL DRAG CHAIN 1 07-Jul-14 07-Jul-14

ROLL DRIVE FRAMEROLL DRIVE FRAME 1 08-Jul-14 08-Jul-14

EDG1-10110 ASSEMBLE THE DRIVE FRAME AND MOTOR BRACKET 1 08-Jul-14 08-Jul-14

EDG1-10120 INSTALL DRIVE ASSEMBLY ON R1 HSG. 1 08-Jul-14 08-Jul-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 18 of 81 Filter: All Activity

Page 19: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EDG1-10130 TIGHTEN BOLT BY REGULATED TORQUE 1 08-Jul-14 08-Jul-14

EDG1-10140 CONNECT SUPPORT FOR DRIVE. 1 08-Jul-14 08-Jul-14

SPINDLE INSTALLATIONSPINDLE INSTALLATION 1 08-Jul-14 08-Jul-14

EDG1-10150 CONNECT SPINDLE AFTER ALLIGNMENT OF REDUCER AND MOTOR 1 08-Jul-14 08-Jul-14

RM SCREW DOWNRM SCREW DOWN 7 13-Jul-14 19-Jul-14

RM1-10370 INSTALLATION AND ALLIGNMENT OF CASING 1 13-Jul-14 13-Jul-14

RM1-10340 INSTALL MOTOR BRACKET ON HOUSING 1 13-Jul-14 13-Jul-14

RM1-10350 REMOVE THE COTTER PIN THAT WE FIXED THE LOCATING KEY FOR THE CASING ON THE TOP OF HOUSING.1 13-Jul-14 13-Jul-14

RM1-10360 FIX THE STUD BOLT FOR MOUNTING THE CASING 1 13-Jul-14 13-Jul-14

RM1-10380 FASTENING OF CASING BOLTS. 1 14-Jul-14 14-Jul-14

RM1-10390 ALLIGNMENT OF MOTOR,AIR BRAKE AND MAGNET CLUTCH. 1 15-Jul-14 15-Jul-14

RM1-10400 SENSOR ASSEMBLY AND REMAINING WORKS. 1 16-Jul-14 16-Jul-14

RM1-10410 INSTALLATION OF O/S SCREW & NUT ASSEMBLY 1 17-Jul-14 17-Jul-14

RM1-10420 INSTALLATION OF D/S SCREW & NUT ASSEMBLY 1 18-Jul-14 18-Jul-14

RM1-10430 INSTALLATION OF O/S & D/S BREAKER BLOCK ASSEMBLY 1 19-Jul-14 19-Jul-14

R1 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERSR1 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERS 1 19-Jul-14 19-Jul-14

RM1-10460 ENTRY AND DELIVERY BOTTOM STRIPPER AND FEED ROLLER ASSEMBLY. 1 19-Jul-14 19-Jul-14

RM1-10470 ENTRY AND DELIVERY TOP STRIPPER. 1 19-Jul-14 19-Jul-14

RM1-10480 TOP WR COOLANT HEADER AND HOSE 1 19-Jul-14 19-Jul-14

RM1-10490 ATTACHED DESCALING & ROLL COOLANT PIPES 1 19-Jul-14 19-Jul-14

RM1-10500 FEED ROLLER DRIVE UNIT 1 19-Jul-14 19-Jul-14

RM1-10510 ENRTY & DELIVERY STRIPPER CYLINDERS 1 19-Jul-14 19-Jul-14

RM1-10520 DELIVERY TOP & BOTTOM DESCALING HEADER 1 19-Jul-14 19-Jul-14

RM1-10530 INSTALLATION OF LOADING CYLINDERS 1 19-Jul-14 19-Jul-14

RM1-10540 REMAINING ASSEMBLIES (Inside rails) 1 19-Jul-14 19-Jul-14

RM1-10440 ENTRY & DELIVERY/TOP & BOTTOM STRIPPER BASE. 1 19-Jul-14 19-Jul-14

RM1-10450 ENTRY AND DELIVERY BOTTOM WR COLLANT HEADER 1 19-Jul-14 19-Jul-14

R1 SPINDLE CARRIERR1 SPINDLE CARRIER 1 20-Jul-14 20-Jul-14

RM1-10590 FIXING OF BOTTOM SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 20-Jul-14

RM1-10600 FIXING OF TOP SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 20-Jul-14

RM1-10610 ATTACHED PIPING 0 20-Jul-14*

RM1-10550 INSTALLATION OF CARRIER STAND 1 20-Jul-14 20-Jul-14

RM1-10560 ALLIGNMENT OF CARRIER STAND 1 20-Jul-14 20-Jul-14

RM1-10570 BASE GROUT (including cur ing) 1 20-Jul-14 20-Jul-14

RM1-10580 ASSEMBLING OF SPINDLE BEARING (Off iline) 1 20-Jul-14 20-Jul-14

R1 ENT TABLE (4-Tables, 22 Ro lls)R1 ENT TABLE (4-Tables, 22 Ro lls) 23 02-Jul-14 24-Jul-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 19 of 81 Filter: All Activity

Page 20: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM1-10620 MOTOR ALLIGNMENT (22 MOTORS) 8 11-Jul-14 18-Jul-14

RM1-10630 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 2 18-Jul-14 20-Jul-14

PREPARATIONPREPARATION 6 02-Jul-14 07-Jul-14

RM1-10640 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 1 02-Jul-14 02-Jul-14

RM1-10650 ERECTION OF TABLE BEAM 1 03-Jul-14 03-Jul-14

RM1-10660 INSTALLATION OF MOTOR FRAME 1 03-Jul-14 03-Jul-14

RM1-10670 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE1 04-Jul-14 04-Jul-14

RM1-10680 INSTALLATION OF MOTOR 1 05-Jul-14 05-Jul-14

RM1-10690 SETTING THE ANCHOR BOLTS AND NUTS 1 06-Jul-14 06-Jul-14

RM1-10700 ANCHOR GROUTING AND CURING. 1 07-Jul-14 07-Jul-14

ALLIGNMENTALLIGNMENT 2 08-Jul-14 09-Jul-14

RM1-10710 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 1 08-Jul-14 08-Jul-14

RM1-10720 CHECK THE LEVELNESS 1 09-Jul-14 09-Jul-14

RM1-10730 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 1 09-Jul-14 09-Jul-14

REMAINING WORKSREMAINING WORKS 4 20-Jul-14 24-Jul-14

RM1-10740 INSTALLATION OF MOTOR COVER 1 20-Jul-14 20-Jul-14

RM1-10750 INSTALLATION OF SPLASH GUARD 1 21-Jul-14 21-Jul-14

RM1-10760 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 21-Jul-14 22-Jul-14

RM1-10770 ATTACHED PIPING AND OTHER REMAINING WORKS. 1 22-Jul-14 23-Jul-14

RM1-10780 INSTALLATION OF E1 ENTRY DESCALING HEADERS & ITS FRAME 1 23-Jul-14 24-Jul-14

R1 DEL TABLE (3 TABLES, 17 ROLLS)R1 DEL TABLE (3 TABLES, 17 ROLLS) 92 02-Jul-14 01-Oct-14

RM1-10790 MOTOR ALLIGNMENT (17 MOTORS) 34 10-Jul-14 12-Aug-14

RM1-10800 BASE GROUTING AFTER TAPER LINER AND FLAT LINER 47 13-Aug-14 28-Sep-14

PREPARATIONPREPARATION 6 02-Jul-14 07-Jul-14

RM1-10810 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 1 02-Jul-14 02-Jul-14

RM1-10820 ERECTION OF TABLE BEAM 1 03-Jul-14 03-Jul-14

RM1-10830 INSTALLATION OF MOTOR FRAME 1 03-Jul-14 03-Jul-14

RM1-10840 TEMPORARY INSTALLATION AND TEMPORARY ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE.1 04-Jul-14 04-Jul-14

RM1-10850 INSTALLATION OF MOTOR 1 05-Jul-14 05-Jul-14

RM1-10860 SETTLING THE ANCHOR BOLTS AND NUTS 1 06-Jul-14 06-Jul-14

RM1-10870 ANCHOR GROUTING AND CURING. 1 07-Jul-14 07-Jul-14

ALLIGNMENTALLIGNMENT 2 08-Jul-14 09-Jul-14

RM1-10880 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 1 08-Jul-14 08-Jul-14

RM1-10890 CHECK THE LEVELNESS 1 09-Jul-14 09-Jul-14

RM1-10900 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE. 1 09-Jul-14 09-Jul-14

REMAINING WORKSREMAINING WORKS 3 29-Sep-14 01-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 20 of 81 Filter: All Activity

Page 21: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM1-10910 INSTALLATION OF MOTOR COVER 1 29-Sep-14 29-Sep-14

RM1-10920 INSTALLATION OF SPLASH GUARD 1 29-Sep-14 29-Sep-14

RM1-10930 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 1 30-Sep-14 30-Sep-14

RM1-10940 ATTACHED PIPING AND OTHER REMAINING WORKS. 1 01-Oct-14 01-Oct-14

R1 ENT SIDE GUIDER1 ENT SIDE GUIDE 36 24-Jul-14 29-Aug-14

RM1-10950 PREPARATION (Measurement of foundation bolt position, Ins tallation liner position and height & Installation of bench m2 24-Jul-14 26-Jul-14

RM1-10960 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 26-Jul-14 28-Jul-14

RM1-10970 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 01-Aug-14 02-Aug-14

RM1-10980 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)1 02-Aug-14 03-Aug-14

RM1-10990 CONNECTION OF GEAR COUPLING 1 03-Aug-14 04-Aug-14

ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 2 28-Jul-14 30-Jul-14

PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 1 28-Jul-14 29-Jul-14RM1-11000 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 28-Jul-14 28-Jul-14

RM1-11010 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 28-Jul-14 28-Jul-14

RM1-11020 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 29-Jul-14 29-Jul-14

RM1-11030 REMOVE FITTING FOR GREASE TUBE OF GEAR FRAME, REMOVE THE UPPER COVER AND PINION0 29-Jul-14 29-Jul-14

MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 29-Jul-14 30-Jul-14RM1-11040 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 29-Jul-14 29-Jul-14

RM1-11050 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 29-Jul-14 29-Jul-14

RM1-11060 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER ©1 30-Jul-14 30-Jul-14

ASSEMBLY OF RACK BARASSEMBLY OF RACK BAR 2 30-Jul-14 01-Aug-14

RM1-11070 ASSEMBLE BOTTOM RACK BAR & CONFIRM THE MARK POSITION OF THE RACK BAR 0 30-Jul-14 30-Jul-14

RM1-11080 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 30-Jul-14 30-Jul-14

RM1-11090 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACK AND PINION 0 31-Jul-14 31-Jul-14

RM1-11100 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 31-Jul-14 31-Jul-14

RM1-11110 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 31-Jul-14 31-Jul-14

RM1-11120 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 01-Aug-14 01-Aug-14

MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 25 04-Aug-14 29-Aug-14

RM1-11130 PULL BOTTOM RACK BAR(ENTRY & DELIVERY TOGETHER) WITH CHAIN BLOCK 1 04-Aug-14 05-Aug-14

RM1-11140 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERY AT DIFFERENT POSITIONS TO CHECK PARALLEL1 05-Aug-14 05-Aug-14

RM1-11150 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 29-Aug-14 29-Aug-14

R1 DEL SIDE GUIDER1 DEL SIDE GUIDE 45 04-Aug-14 17-Sep-14

RM1-11160 PREPARATION (Measurement of foundation bolt position, Ins tallation liner position and height & Installation of bench m4 04-Aug-14* 07-Aug-14

RM1-11170 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 07-Aug-14 09-Aug-14

RM1-11180 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 3 12-Aug-14 15-Aug-14

RM1-11190 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)3 15-Aug-14 18-Aug-14*

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 21 of 81 Filter: All Activity

Page 22: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 2 09-Aug-14 11-Aug-14

PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 1 09-Aug-14 10-Aug-14

RM1-11200 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 09-Aug-14 09-Aug-14

RM1-11210 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 09-Aug-14 09-Aug-14

RM1-11220 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 10-Aug-14 10-Aug-14

RM1-11230 REMOVE FITTING FOR GREASE TUBE OF GEAR FRAME, REMOVE THE UPPER COVER AND PINION0 10-Aug-14 10-Aug-14

MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 10-Aug-14 11-Aug-14

RM1-11240 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 10-Aug-14 10-Aug-14

RM1-11250 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 10-Aug-14 10-Aug-14

RM1-11260 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER (C)1 11-Aug-14 11-Aug-14

ASSEMBLY OF RACK BARASSEMBLY OF RACK BAR 2 10-Aug-14 12-Aug-14

RM1-11270 ASSEMBLE BOTTOM RACK BAR & CONFIRM THE MARK POSITION OF THE RACK BAR 0 10-Aug-14 10-Aug-14

RM1-11280 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 10-Aug-14 10-Aug-14

RM1-11290 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACK AND PINION 0 11-Aug-14 11-Aug-14

RM1-11300 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 11-Aug-14 11-Aug-14

RM1-11310 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 11-Aug-14 11-Aug-14

RM1-11320 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 12-Aug-14 12-Aug-14

MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 30 18-Aug-14 17-Sep-14

RM1-11330 PULL BOTTOM RACK BAR(ENTRY & DELIVERY TOGETHER) WITH CHAIN BLOCK 1 18-Aug-14 19-Aug-14

RM1-11340 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERY AT DIFFERENT POSITIONS TO CHECK PARALLEL1 19-Aug-14 19-Aug-14

RM1-11350 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 17-Sep-14 17-Sep-14

R1 WR CHANGING DEVICER1 WR CHANGING DEVICE 80 20-Jul-14 07-Oct-14

RM1-11360 INSTALLATION OF AIR CYLINDER 2 05-Aug-14* 06-Aug-14

RM1-11370 ALLIGNMENT OF AIR CYLINDER 2 07-Aug-14 08-Aug-14

PREPARATIONPREPARATION 20 20-Jul-14 08-Aug-14

RM1-11380 SHIFTING,CLEANNING AND POSITIONING OF EQUIPMENT 8 20-Jul-14 27-Jul-14

RM1-11390 CHECKING OF FOUNDATION 3 28-Jul-14 30-Jul-14

RM1-11400 CHIPPING AND PADDING 3 06-Aug-14 08-Aug-14

INSTALLATION OF RAIL AND HYDRAULIC CYLINDERINSTALLATION OF RAIL AND HYDRAULIC CYLINDER 12 09-Aug-14 20-Aug-14

RM1-11410 INSTALL RAIL AND HYD. CYLINDER FOR THE SIDE SHIFT CAR 6 09-Aug-14 14-Aug-14

RM1-11420 INSTALL RAIL,HYD. CYLINDER BASE AND RAIL BASE FOR FOR THE ROLL TRASVERSE. 6 15-Aug-14 20-Aug-14

ALLIGNMENT OF RAIL FOR ROLL TRAVERSEALLIGNMENT OF RAIL FOR ROLL TRAVERSE 20 21-Aug-14 09-Sep-14

RM1-11430 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 4 21-Aug-14 24-Aug-14

RM1-11440 POSITIONING FROM R1 MILL CENTRE LINE 4 25-Aug-14 28-Aug-14

RM1-11450 ADJUSTING THE TOP OF RAIL AND ALLIGNMENT OF CYLINDER BASE. 4 29-Aug-14 01-Sep-14

RM1-11460 WELDING THE RAIL STOPPER PLATE. 8 02-Sep-14 09-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 22 of 81 Filter: All Activity

Page 23: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

ALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CARALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CAR 6 10-Sep-14 15-Sep-14

RM1-11470 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 1 10-Sep-14 10-Sep-14

RM1-11480 POSITIONING FROM CENTRE OF DATUM RAIL 1 11-Sep-14 11-Sep-14

RM1-11490 POSITIONING FROM R1 MILL CENTRE LINE 1 12-Sep-14 12-Sep-14

RM1-11500 ADJUSTING THE TOP OF RAIL FROM BENCHMARK 1 13-Sep-14 13-Sep-14

RM1-11510 WELDING THE RAIL STOPPER PLATE 1 14-Sep-14 14-Sep-14

RM1-11520 ADJUSTING THE CYLINDER CENTRE 1 15-Sep-14 15-Sep-14

ALLIGNMENT OF HYDRAULLIC CYLINDERALLIGNMENT OF HYDRAULLIC CYLINDER 5 16-Sep-14 20-Sep-14

RM1-11530 INSTALL HYD CYLINDER AFTER ALLIGNMENT OF RAIL 2 16-Sep-14 17-Sep-14

RM1-11540 POSITIONING FROM SIDE SHIFT CAR CENTRE 1 18-Sep-14 18-Sep-14

RM1-11550 POSITIONING FROM MILL CENTRE 1 19-Sep-14 19-Sep-14

RM1-11560 WELDING THE CYLINDER STOPPER PLATE 1 20-Sep-14 20-Sep-14

INSTALLATION OF SIDE SHIFT CARINSTALLATION OF SIDE SHIFT CAR 17 21-Sep-14 07-Oct-14

RM1-11570 INSTALL SIDE SHIFT CAR ON RAIL SLOWLY 1 21-Sep-14 21-Sep-14

RM1-11580 CONFIRM THE CLEARANCE BETWEEN DATUM RAIL AND THE WHEEL 1 22-Sep-14 22-Sep-14

RM1-11590 CONNECT CYLINDER WITH SIDE SHIFT CAR 1 23-Sep-14 23-Sep-14

RM1-11600 INSTALL THE FLOOR PLATES 14 24-Sep-14 07-Oct-14

FRONT#4 (ROUGHING MILL#1) INDIVIDUAL TRIALFRONT#4 (ROUGHING MILL#1) INDIVIDUAL TRIAL 30 17-Sep-14 17-Oct-14

B&S-10240 ROUGHING MILL TRIAL 30 17-Sep-14* 17-Oct-14

FRONT#5 (ROUGHING MILL#2)FRONT#5 (ROUGHING MILL#2) 80 15-Feb-14 A 24-Sep-14

RM2-10160 SAFETY SCAFFOLDING INSTALLATION 0 28-Feb-14 A 02-Mar-14 A

RM SHOE PLATERM SHOE PLATE 0 15-Feb-14 A 22-Feb-14 ARM2-10170 FOUNDATION CHECKING 0 15-Feb-14 A 16-Feb-14 A

RM2-10180 FOUNDATION CHIPPING AND PADDING 0 17-Feb-14 A 18-Feb-14 A

RM2-10190 PREPARATION OF INSTALLATION 0 17-Feb-14 A 18-Feb-14 A

RM2-10200 INSTALLATION AND ALLIGNMENT OF SHOE PLATE 0 19-Feb-14 A 20-Feb-14 A

RM2-10210 GROUTING 0 21-Feb-14 A 22-Feb-14 A

RM HOUSINGRM HOUSING 0 23-Feb-14 A 24-Mar-14 ARM2-10220 FINAL MEASUREMENT OF HSG WITH PIANNO WIRE AND TIGHTENING OF HSG AND SEPARATOR BOLT.0 22-Mar-14 A 22-Mar-14 A

RM2-10230 INSTALLATION OF SIMPLE PARTS (PLATFORMS & STAIRS ETC) 0 23-Mar-14 A 24-Mar-14 A

PREPARATIONPREPARATION 0 23-Feb-14 A 23-Feb-14 ARM2-10280 HSG SURFACE TRIMMING 0 23-Feb-14 A 23-Feb-14 A

RM2-10290 SETUP OF HSG VERTICALLITY MEASUREMENT JIGS AND SCALFOLDING 0 23-Feb-14 A 23-Feb-14 A

RM2-10240 ASSEMBLY OF HOUSING LIFTING BEAM & TRIAL OF THE SAME WITH BOTH THE 120 TON CRANE0 23-Feb-14 A 23-Feb-14 A

RM2-10250 TRANSPORTING AND POSITIONING HSG AS REFERED IN MANUAL 0 23-Feb-14 A 23-Feb-14 A

RM2-10260 INSTALLATION OF MILL ATTACHED PIPING WHICH EVER POSIBLE 0 23-Feb-14 A 23-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 23 of 81 Filter: All Activity

Page 24: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM2-10270 INSTALLATION OF TEMPORARY SCALFOLDING AND LADDER FOR THE ACCESS TO THE MILL TOP0 23-Feb-14 A 23-Feb-14 A

DS HSG ERECTION AND ALLIGNMENTDS HSG ERECTION AND ALLIGNMENT 0 26-Feb-14 A 26-Feb-14 ARM2-10300 LIFTING THE DS HSG BY LIFTING BEAM AND TRANSFER FROM LIFTING AREA TO INSTALL POSITION0 26-Feb-14 A 26-Feb-14 A

RM2-10310 PUTTING HSG ON SHOE PLATE AND VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF HSG TO THE TOP OF SHOE PLATE0 26-Feb-14 A 26-Feb-14 A

RM2-10320 TEMPORARY BOLTING OF HSG WITH SHOE PLATE BY FOOT BOLT AND ADJUST THE HSG POSITIONING FROM LINE CENTERE SAME AS DRAWING0 26-Feb-14 A 26-Feb-14 A

RM2-10330 PUSH THE HSG TO THE DELIVERY SIDE SHOE PLATE AND VERIFY THE ZERO GAPS BETWEEN HSG AND SHOE PLATES AND TIGHTEN THE FOO0 26-Feb-14 A 26-Feb-14 A

WS HSG ERECTION AND ALLIGNMENTWS HSG ERECTION AND ALLIGNMENT 0 04-Mar-14 A 09-Mar-14 ARM2-10340 LIFTING THE WS HSG BY LIFTING BEAM AND TRANSFER FROM LIFTING AREA TO INSTALL POSITION0 04-Mar-14 A 04-Mar-14 A

RM2-10350 PUTTING HSG ON SHOE PLATE AND VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF HSG TO THE TOP OF SHOE PLATE0 05-Mar-14 A 05-Mar-14 A

RM2-10360 TEMPORARY BOLTING OF HSG WITH SHOE PLATE BY FOOT BOLT AND ADJUST THE HSG POSITIONING FROM LINE CENTERE SAME AS DRAWING0 06-Mar-14 A 06-Mar-14 A

RM2-10370 PUSH THE HSG TO THE ENTRY SIDE SHOE PLATE AND VERIFY THE ZERO GAPS BETWEEN THE HSG AND SHOE PLATES AND TIGHTEN THE FOO0 07-Mar-14 A 07-Mar-14 A

RM2-10380 INSTALL LINER BETWEEN ENTRY SIDE SHOE PLATE AND HSG. 0 08-Mar-14 A 08-Mar-14 A

RM2-10390 VERIFY THE FINAL CLEARANCE. 0 09-Mar-14 A 09-Mar-14 A

BOTTOM SEPARATOR INSTALLATIONBOTTOM SEPARATOR INSTALLATION 0 10-Mar-14 A 13-Mar-14 ARM2-10400 PULL IN THE BOTTOM SEPARATOR BOLTS IN HSG AND TEMPORARY SETTING BOTTOM SEPARATOR INTO THE HSG0 10-Mar-14 A 11-Mar-14 A

RM2-10410 VERIFY THE ZERO GAPS FOR CONTACT SURFACE OF SEPARATOR TO DS HSG. 0 12-Mar-14 A 12-Mar-14 A

RM2-10420 VERIFYING THE ZERO GAPS FOR CONTACT SURFACE OF WS HSG TO SHOE PLATE. 0 12-Mar-14 A 12-Mar-14 A

RM2-10430 FINAL TIGHTNING OF HSG FOOT BOLTS AND SEPARATOR BOLTS AFTER COMPLETING THE ALLIGNMENT OF MILL HOUSING0 13-Mar-14 A 13-Mar-14 A

TOP SEPARATOR INSTALLATIONTOP SEPARATOR INSTALLATION 0 14-Mar-14 A 21-Mar-14 ARM2-10440 ASSEMBLING THE TEMPORARY SCALFOLDING FOT THE INSTALLATION AREA 0 14-Mar-14 A 14-Mar-14 A

RM2-10450 SETTING THE JACK BETWEEN DS HSG AND WS HSG 0 15-Mar-14 A 15-Mar-14 A

RM2-10460 INSTALL THE TOP SEPARATOR TO THE HSG STEPPED SURFACE 0 16-Mar-14 A 16-Mar-14 A

RM2-10470 INSERT THE BOLT AND REMOVE THE JACK 0 17-Mar-14 A 17-Mar-14 A

RM2-10480 ALLIGN THE CENTRE OF THE COTTER PIN SLOTS OF THE DS AND WS HSG 0 18-Mar-14 A 19-Mar-14 A

RM2-10490 FINAL TIGHTNING OF HSG FOOT BOLTS AND SEPARATOR BOLTS AFTER COMPLETING THE ALLIGNMENT OF MILL HOUSING0 20-Mar-14 A 21-Mar-14 A

E2 PROPERE2 PROPER 0 08-Apr-14 A 05-May-14 AEDG1-10160 E1 HOUSNG ASSEMBLY (Offline) 0 08-Apr-14 A 09-Apr-14 A

EDG1-10170 AWC & PULL BACK CYLINDER 0 14-Apr-14 A 15-Apr-14 A

EDG1-10190 INSTALLATION OF SIMPLE PARTS (PLATFORM,STAIRS ETC) 0 30-Apr-14 A 03-May-14 A

EDG1-10180 REDUCER & MOTOR ERECTION AND ALLIGNMENT 0 05-May-14 A 05-May-14 A

E2 HOUSING ERECTIONE2 HOUSING ERECTION 0 10-Apr-14 A 13-Apr-14 AEDG1-10200 INSTALL & VERIFY THE ZERO GAPS FOR CONTACT SURFACE OF HSG TO TOP OF INSTALATION LINER0 10-Apr-14 A 10-Apr-14 A

EDG1-10210 PUSH THE HSG TO DELIVERY SIDE AND CONTACT TO R1 HSG. 0 11-Apr-14 A 11-Apr-14 A

EDG1-10220 MEASURE THE RAIL TOP SURFACE WITH STRAIGHT EDGE AND PRECISION LEVEL. 0 12-Apr-14 A 12-Apr-14 A

EDG1-10230 FINAL TIGHTENING THE HSG FOOT BOLTS AND JOINT BOLTS AFTER COMPLETING THE ALIGNMENT OF E1.0 13-Apr-14 A 13-Apr-14 A

ROLL ADJUST FRAME AND POWER TRUCKROLL ADJUST FRAME AND POWER TRUCK 0 16-Apr-14 A 18-Apr-14 AEDG1-10240 INSERT ROLL ADJUST FRAME IN HSG 0 16-Apr-14 A 16-Apr-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 24 of 81 Filter: All Activity

Page 25: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EDG1-10250 CONNECT ROLL ADJUST FRAME WITH PULL BACK CYLINDER 0 17-Apr-14 A 17-Apr-14 A

EDG1-10260 INSTALL DRAG CHAIN 0 18-Apr-14 A 18-Apr-14 A

ROLL DRIVE FRAMEROLL DRIVE FRAME 0 20-Apr-14 A 23-Apr-14 AEDG1-10270 ASSEMBLE THE DRIVE FRAME AND MOTOR BRACKET 0 20-Apr-14 A 20-Apr-14 A

EDG1-10280 INSTALL DRIVE ASSEMBLY ON R1 HSG. 0 21-Apr-14 A 21-Apr-14 A

EDG1-10290 TIGHTEN BOLT BY REGULATED TORQUE 0 22-Apr-14 A 22-Apr-14 A

EDG1-10300 CONNECT SUPPORT FOR DRIVE. 0 23-Apr-14 A 23-Apr-14 A

SPINDLE INSTALLATIONSPINDLE INSTALLATION 0 28-Apr-14 A 29-Apr-14 AEDG1-10310 CONNECT SPINDLE AFTER ALLIGNMENT OF REDUCER AND MOTOR 0 28-Apr-14 A 29-Apr-14 A

RM SCREW DOWNRM SCREW DOWN 0 31-Mar-14 A 19-Apr-14 ARM2-10500 INSTALL MOTOR BRACKET ON HOUSING 0 31-Mar-14 A 31-Mar-14 A

RM2-10510 REMOVE THE COTTER PIN THAT WE FIXED THE LOCATING KEY FOR THE CASING ON THE TOP OF HOUSING.0 07-Apr-14 A 07-Apr-14 A

RM2-10520 FIX THE STUD BOLT FOR MOUNTING THE CASING 0 07-Apr-14 A 07-Apr-14 A

RM2-10530 INSTALLATION AND ALLIGNMENT OF CASING 0 08-Apr-14 A 09-Apr-14 A

RM2-10540 FASTENING OF CASING BOLTS. 0 10-Apr-14 A 10-Apr-14 A

RM2-10550 ALLIGNMENT OF MOTOR,AIR BRAKE AND MAGNET CLUTCH. 0 11-Apr-14 A 12-Apr-14 A

RM2-10560 SENSOR ASSEMBLY AND REMAINING WORKS. 0 13-Apr-14 A 13-Apr-14 A

RM2-10570 INSTALLATION OF O/S SCREW & NUT ASSEMBLY 0 14-Apr-14 A 15-Apr-14 A

RM2-10580 INSTALLATION OF D/S SCREW & NUT ASSEMBLY 0 16-Apr-14 A 17-Apr-14 A

RM2-10590 INSTALLATION OF O/S & D/S BREAKER BLOCK ASSEMBLY 0 18-Apr-14 A 19-Apr-14 A

R2 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERSR2 STRIPPER, FEEDER ROLLS, DESCALING & ROLL COOLING HEADERS 0 20-Apr-14 A 13-May-14 ARM2-10600 ENTRY & DELIVERY/TOP & BOTTOM STRIPPER BASE. 0 20-Apr-14 A 21-Apr-14 A

RM2-10610 ENTRY AND DELIVERY BOTTOM WR COLLANT HEADER 0 22-Apr-14 A 23-Apr-14 A

RM2-10620 ENTRY AND DELIVERY BOTTOM STRIPPER AND FEED ROLLER ASSEMBLY. 0 24-Apr-14 A 25-Apr-14 A

RM2-10630 ENTRY AND DELIVERY TOP STRIPPER. 0 26-Apr-14 A 28-Apr-14 A

RM2-10640 TOP WR COOLANT HEADER AND HOSE 0 29-Apr-14 A 30-Apr-14 A

RM2-10650 ATTACHED DESCALING & ROLL COOLANT PIPES 0 01-May-14 A 03-May-14 A

RM2-10660 FEED ROLLER DRIVE UNIT 0 04-May-14 A 05-May-14 A

RM2-10670 ENRTY & DELIVERY STRIPPER CYLINDERS 0 06-May-14 A 07-May-14 A

RM2-10680 DELIVERY TOP & BOTTOM DESCALING HEADER 0 08-May-14 A 09-May-14 A

RM2-10690 INSTALLATION OF LOADING CYLINDERS 0 10-May-14 A 11-May-14 A

RM2-10700 REMAINING ASSEMBLIES (Inside rails) 0 12-May-14 A 13-May-14 A

R2 SPINDLE CARRIERR2 SPINDLE CARRIER 0 14-May-14 A 26-May-14 ARM2-10710 INSTALLATION OF CARRIER STAND 0 14-May-14 A 15-May-14 A

RM2-10720 ALLIGNMENT OF CARRIER STAND 0 16-May-14 A 18-May-14 A

RM2-10730 BASE GROUT (including cur ing) 0 19-May-14 A 20-May-14 A

RM2-10740 ASSEMBLING OF SPINDLE BEARING (Off iline) 0 21-May-14 A 25-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 25 of 81 Filter: All Activity

Page 26: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM2-10750 FIXING OF BOTTOM SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 26-May-14 A

RM2-10760 FIXING OF TOP SPINDLE (Precondition:- R1 MOTOR TESTING OVER) 0 26-May-14 A

RM2-10770 ATTACHED PIPING 0 26-May-14 A

R2 ENT TABLE (4-Tables, 22 Ro lls)R2 ENT TABLE (4-Tables, 22 Ro lls) 0 25-Mar-14 A 24-May-14 ARM2-10780 MOTOR ALLIGNMENT (22 MOTORS) 0 19-Apr-14 A 12-May-14 A

RM2-10790 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 12-May-14 A 20-May-14 A

PREPARATIONPREPARATION 0 25-Mar-14 A 06-May-14 ARM2-10800 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 0 25-Mar-14 A 26-Mar-14 A

RM2-10810 ERECTION OF TABLE BEAM 0 28-Mar-14 A 11-Apr-14 A

RM2-10820 INSTALLATION OF MOTOR FRAME 0 25-Apr-14 A 02-May-14 A

RM2-10830 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE0 02-May-14 A 03-May-14 A

RM2-10840 INSTALLATION OF MOTOR 0 03-May-14 A 04-May-14 A

RM2-10850 SETTING THE ANCHOR BOLTS AND NUTS 0 04-May-14 A 05-May-14 A

RM2-10860 ANCHOR GROUTING AND CURING. 0 05-May-14 A 06-May-14 A

ALLIGNMENTALLIGNMENT 0 06-May-14 A 08-May-14 ARM2-10870 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 06-May-14 A 07-May-14 A

RM2-10880 CHECK THE LEVELNESS 0 07-May-14 A 07-May-14 A

RM2-10890 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 08-May-14 A 08-May-14 A

REMAINING WORKSREMAINING WORKS 0 20-May-14 A 24-May-14 ARM2-10900 INSTALLATION OF MOTOR COVER 0 20-May-14 A 20-May-14 A

RM2-10910 INSTALLATION OF SPLASH GUARD 0 21-May-14 A 21-May-14 A

RM2-10920 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 21-May-14 A 22-May-14 A

RM2-10930 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 22-May-14 A 23-May-14 A

RM2-10940 INSTALLATION OF E1 ENTRY DESCALING HEADERS & ITS FRAME 0 23-May-14 A 24-May-14 A

R2 DEL TABLE (3 TABLES, 17 ROLLS)R2 DEL TABLE (3 TABLES, 17 ROLLS) 0 20-Mar-14 A 31-May-14 ARM2-10950 MOTOR ALLIGNMENT (17 MOTORS) 0 23-Apr-14 A 20-May-14 A

RM2-10960 BASE GROUTING AFTER TAPER LINER AND FLAT LINER 0 20-May-14 A 28-May-14 A

PREPARATIONPREPARATION 0 20-Mar-14 A 06-May-14 ARM2-10970 FOUNDATION CHECKING AND CHIPPING AND PADDING (Major job is parallel) 0 20-Mar-14 A 22-Mar-14 A

RM2-10980 ERECTION OF TABLE BEAM 0 26-Mar-14 A 16-Apr-14 A

RM2-10990 INSTALLATION OF MOTOR FRAME 0 25-Apr-14 A 02-May-14 A

RM2-11000 TEMPORARY INSTALLATION AND TEMPORARY ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE.0 02-May-14 A 03-May-14 A

RM2-11010 INSTALLATION OF MOTOR 0 03-May-14 A 04-May-14 A

RM2-11020 SETTLING THE ANCHOR BOLTS AND NUTS 0 04-May-14 A 05-May-14 A

RM2-11030 ANCHOR GROUTING AND CURING. 0 05-May-14 A 06-May-14 A

ALLIGNMENTALLIGNMENT 0 06-May-14 A 08-May-14 ARM2-11040 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 06-May-14 A 07-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 26 of 81 Filter: All Activity

Page 27: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM2-11050 CHECK THE LEVELNESS 0 07-May-14 A 07-May-14 A

RM2-11060 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE. 0 08-May-14 A 08-May-14 A

REMAINING WORKSREMAINING WORKS 0 28-May-14 A 31-May-14 ARM2-11070 INSTALLATION OF MOTOR COVER 0 28-May-14 A 28-May-14 A

RM2-11080 INSTALLATION OF SPLASH GUARD 0 29-May-14 A 29-May-14 A

RM2-11090 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 29-May-14 A 30-May-14 A

RM2-11100 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 30-May-14 A 31-May-14 A

R2 ENT SIDE GUIDER2 ENT SIDE GUIDE 9 28-May-14 A 15-Jul-14RM2-11110 PREPARATION (Measurement of foundation bolt position, Ins tallation liner position and height & Installation of bench m2 07-Jul-14* 08-Jul-14

RM2-11120 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 09-Jul-14 10-Jul-14

RM2-11130 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 11-Jul-14 11-Jul-14

RM2-11140 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)2 12-Jul-14 13-Jul-14

RM2-11150 CONNECTION OF GEAR COUPLING 2 14-Jul-14 15-Jul-14*

ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 0 28-May-14 A 30-May-14 APREPARATION FOR CENTERINGPREPARATION FOR CENTERING 0 28-May-14 A 29-May-14 ARM2-11160 REMOVE UPPER PART COVER OF SUPPORT FRAME 0 28-May-14 A 28-May-14 A

RM2-11170 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 0 28-May-14 A 28-May-14 A

RM2-11180 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 0 29-May-14 A 29-May-14 A

RM2-11190 REMOVE FITTING FOR GREASE TUBE OF GEAR FRAME, REMOVE THE UPPER COVER AND PINION0 29-May-14 A 29-May-14 A

MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 0 29-May-14 A 30-May-14 ARM2-11200 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 29-May-14 A 29-May-14 A

RM2-11210 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 29-May-14 A 29-May-14 A

RM2-11220 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER ©0 30-May-14 A 30-May-14 A

ASSEMBLY OF RACK BARASSEMBLY OF RACK BAR 0 30-May-14 A 01-Jun-14 ARM2-11230 ASSEMBLE BOTTOM RACK BAR & CONFIRM THE MARK POSITION OF THE RACK BAR 0 30-May-14 A 30-May-14 A

RM2-11240 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 30-May-14 A 30-May-14 A

RM2-11250 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACK AND PINION 0 31-May-14 A 31-May-14 A

RM2-11260 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME0 31-May-14 A 31-May-14 A

RM2-11270 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 31-May-14 A 31-May-14 A

RM2-11280 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 0 01-Jun-14 A 01-Jun-14 A

MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 0 06-Jun-14 A 08-Jun-14 ARM2-11290 PULL BOTTOM RACK BAR(ENTRY & DELIVERY TOGETHER) WITH CHAIN BLOCK 0 06-Jun-14 A 07-Jun-14 A

RM2-11300 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERY AT DIFFERENT POSITIONS TO CHECK PARALLEL0 07-Jun-14 A 07-Jun-14 A

RM2-11310 CONNECT THE TOP RACK BARS WITH CYLINDERS 0 08-Jun-14 A 08-Jun-14 A

R2 DEL SIDE GUIDER2 DEL SIDE GUIDE 79 08-Jul-14 24-Sep-14RM2-11320 PREPARATION (Measurement of foundation bolt position, Ins tallation liner position and height & Installation of bench m2 08-Jul-14* 09-Jul-14

RM2-11330 INSTALLATION OF SUPPORT ROLL AND GEAR FRAME 2 10-Jul-14 11-Jul-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 27 of 81 Filter: All Activity

Page 28: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM2-11340 ASSEMBLY OF SIDE GUIDE (DS, WS SIDE GUIDE & ENTRY SIDE GUIDE PLATE) 1 18-Sep-14 19-Sep-14

RM2-11350 CONNECTION OF GEAR COUPLING (CHECK FOR MARK MATCH AND CONNECT GEAR COUPLING)3 19-Sep-14 22-Sep-14

ALLIGNMENT OF SUPPORT ROLL AND GEAR FRAMEALLIGNMENT OF SUPPORT ROLL AND GEAR FRAME 47 02-Aug-14 17-Sep-14PREPARATION FOR CENTERINGPREPARATION FOR CENTERING 46 02-Aug-14 16-Sep-14RM2-11360 REMOVE UPPER PART COVER OF SUPPORT FRAME 1 02-Aug-14* 02-Aug-14

RM2-11370 REMOVE WIPER COVER, WIPER BRACKET AND MIDDLE COVER 1 03-Aug-14 03-Aug-14

RM2-11380 REMOVE SUPPORT ROLL (MARK) FROM INSIDE OF SIDE GUIDE 1 04-Aug-14 04-Aug-14

RM2-11390 REMOVE FITTING FOR GREASE TUBE OF GEAR FRAME, REMOVE THE UPPER COVER AND PINION4 12-Sep-14 16-Sep-14*

MEASURE CENTERING BASED ON SUPPORT ROLLMEASURE CENTERING BASED ON SUPPORT ROLL 1 16-Sep-14 17-Sep-14RM2-11400 MEASURE THE SUPPORT ROLL FROM LINE CENTER (A) 0 16-Sep-14 17-Sep-14

RM2-11410 MEASURE THE SUPPORT ROLL FROM RIGHT ANGLED CENTER (B) 0 17-Sep-14 17-Sep-14

RM2-11420 MEASURE THE HEIGHT FROM UPPER SURFACE OF SUPPORT ROLL AND THE TRUNNION PIN CENTER (C)1 17-Sep-14 17-Sep-14

ASSEMBLY OF RACK BARASSEMBLY OF RACK BAR 2 16-Sep-14 18-Sep-14RM2-11430 ASSEMBLE BOTTOM RACK BAR & CONFIRM THE MARK POSITION OF THE RACK BAR 0 16-Sep-14 17-Sep-14

RM2-11440 ASSEMBLE PINION & CONFIRM MARK POSITION w.r.t RACK MARK 0 17-Sep-14 17-Sep-14

RM2-11450 ASSEMBLE TOP RACK BAR & CONFIRM THE MATCH MARK w.r.t BOTTOM RACK AND PINION 0 17-Sep-14 17-Sep-14

RM2-11460 MEASURE AND ADJUST THE DISTANCE BETWEEN RACK EGDE SIDE FROM SUPPORT ROLL CENTER OF GEAR FRAME1 17-Sep-14 18-Sep-14

RM2-11470 INSTALL WIPER COVER, WIPER BRACKET & MIDDLE COVER 0 18-Sep-14 18-Sep-14

RM2-11480 INSTALL UPPER PART COVER OF SUPPORT FRAME, GEAR FRAME 1 18-Sep-14 18-Sep-14

MEASUREMENT OF PARRALEL.MEASUREMENT OF PARRALEL. 2 22-Sep-14 24-Sep-14RM2-11490 PULL BOTTOM RACK BAR(ENTRY & DELIVERY TOGETHER) WITH CHAIN BLOCK 1 22-Sep-14 23-Sep-14

RM2-11500 MEASURE WIDTH OF GUIDE BETWEEN ENTRY & DELIVERY AT DIFFERENT POSITIONS TO CHECK PARALLEL1 23-Sep-14 24-Sep-14

RM2-11510 CONNECT THE TOP RACK BARS WITH CYLINDERS 1 24-Sep-14 24-Sep-14

R2 WR CHANGING DEVICER2 WR CHANGING DEVICE 0 20-May-14 A 13-Jun-14 ARM2-11520 INSTALLATION OF AIR CYLINDER 0 12-Jun-14 A 12-Jun-14 A

RM2-11530 ALLIGNMENT OF AIR CYLINDER 0 13-Jun-14 A 13-Jun-14 A

PREPARATIONPREPARATION 0 20-May-14 A 22-May-14 ARM2-11540 SHIFTING,CLEANNING AND POSITIONING OF EQUIPMENT 0 20-May-14 A 20-May-14 A

RM2-11550 CHECKING OF FOUNDATION 0 21-May-14 A 21-May-14 A

RM2-11560 CHIPPING AND PADDING 0 22-May-14 A 22-May-14 A

INSTALLATION OF RAIL AND HYDRAULIC CYLINDERINSTALLATION OF RAIL AND HYDRAULIC CYLINDER 0 23-May-14 A 24-May-14 ARM2-11570 INSTALL RAIL AND HYD. CYLINDER FOR THE SIDE SHIFT CAR 0 23-May-14 A 23-May-14 A

RM2-11580 INSTALL RAIL,HYD. CYLINDER BASE AND RAIL BASE FOR FOR THE ROLL TRASVERSE. 0 24-May-14 A 24-May-14 A

ALLIGNMENT OF RAIL FOR ROLL TRAVERSEALLIGNMENT OF RAIL FOR ROLL TRAVERSE 0 25-May-14 A 28-May-14 ARM2-11590 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 0 25-May-14 A 25-May-14 A

RM2-11600 POSITIONING FROM R1 MILL CENTRE LINE 0 26-May-14 A 26-May-14 A

RM2-11610 ADJUSTING THE TOP OF RAIL AND ALLIGNMENT OF CYLINDER BASE. 0 27-May-14 A 27-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 28 of 81 Filter: All Activity

Page 29: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

RM2-11620 WELDING THE RAIL STOPPER PLATE. 0 28-May-14 A 28-May-14 A

ALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CARALIGNMENT OF RAIL AND HYDRAULLIC CYLINDER FOR SIDE SHIFT CAR 0 29-May-14 A 03-Jun-14 ARM2-11630 POSITIONING FROM SIDE SHIFT CYLINDER CENTRE LINE 0 29-May-14 A 29-May-14 A

RM2-11640 POSITIONING FROM CENTRE OF DATUM RAIL 0 30-May-14 A 30-May-14 A

RM2-11650 POSITIONING FROM R1 MILL CENTRE LINE 0 31-May-14 A 31-May-14 A

RM2-11660 ADJUSTING THE TOP OF RAIL FROM BENCHMARK 0 01-Jun-14 A 01-Jun-14 A

RM2-11670 WELDING THE RAIL STOPPER PLATE 0 02-Jun-14 A 02-Jun-14 A

RM2-11680 ADJUSTING THE CYLINDER CENTRE 0 03-Jun-14 A 03-Jun-14 A

ALLIGNMENT OF HYDRAULLIC CYLINDERALLIGNMENT OF HYDRAULLIC CYLINDER 0 04-Jun-14 A 07-Jun-14 ARM2-11690 INSTALL HYD CYLINDER AFTER ALLIGNMENT OF RAIL 0 04-Jun-14 A 04-Jun-14 A

RM2-11700 POSITIONING FROM SIDE SHIFT CAR CENTRE 0 05-Jun-14 A 05-Jun-14 A

RM2-11710 POSITIONING FROM MILL CENTRE 0 06-Jun-14 A 06-Jun-14 A

RM2-11720 WELDING THE CYLINDER STOPPER PLATE 0 07-Jun-14 A 07-Jun-14 A

INSTALLATION OF SIDE SHIFT CARINSTALLATION OF SIDE SHIFT CAR 0 08-Jun-14 A 11-Jun-14 ARM2-11730 INSTALL SIDE SHIFT CAR ON RAIL SLOWLY 0 08-Jun-14 A 08-Jun-14 A

RM2-11740 CONFIRM THE CLEARANCE BETWEEN DATUM RAIL AND THE WHEEL 0 09-Jun-14 A 09-Jun-14 A

RM2-11750 CONNECT CYLINDER WITH SIDE SHIFT CAR 0 10-Jun-14 A 10-Jun-14 A

RM2-11760 INSTALL THE FLOOR PLATES 0 11-Jun-14 A 11-Jun-14 A

R2 BUR CHANGING DEVICER2 BUR CHANGING DEVICE 0 12-May-14 A 19-May-14 ASLED BASE RAIL INSTALLATIONSLED BASE RAIL INSTALLATION 0 12-May-14 A 15-May-14 ARM2-11770 POSITIONING FROM PASS LINE CENTRE 0 12-May-14 A 12-May-14 A

RM2-11780 POSITIONING FROM MILL CENTRE 0 13-May-14 A 13-May-14 A

RM2-11790 ADJUST AND MEASURE THE TOP OF RAIL WRT BENCH MARK 0 14-May-14 A 14-May-14 A

RM2-11800 WELDING THE RAIL BASE PLATE 0 15-May-14 A 15-May-14 A

SLED TRAVERCE CYLINDERSLED TRAVERCE CYLINDER 0 17-May-14 A 19-May-14 ARM2-11810 POSITION FROM LINE CENTRE 0 17-May-14 A 17-May-14 A

RM2-11820 POSITION FROM MILL CENTRE 0 18-May-14 A 18-May-14 A

RM2-11830 MEASURE AND ADJUST THE CENTRE OF TRUNION FROM BENCH MARK. 0 19-May-14 A 19-May-14 A

FRONT#5 (ROUGHING MILL#2) INDIVIDUAL TRIALFRONT#5 (ROUGHING MILL#2) INDIVIDUAL TRIAL 30 15-Sep-14 15-Oct-14

B&S-10250 ROUGHING MILL TRIAL 30 15-Sep-14* 15-Oct-14

FRONT#6 (CROP SHEAR)FRONT#6 (CROP SHEAR) 46 18-Jan-14 A 16-Aug-14

CROP SHEARCROP SHEAR 46 18-Jan-14 A 16-Aug-14CS-10000 INSTALLATION AND ALIGNMENT OF GEAR, REDUCER & MOTOR 0 22-Feb-14 A 23-Apr-14 A

CS-10010 INSTALLTION OF COUPLING SUPPORT & COUPLING 0 23-Apr-14 A 03-Jun-14 A

CS-10020 REMAINING WORKS AND ATTACHED PIPING 46 02-Jul-14 16-Aug-14

SHOE PLATE ALIGNMENTSHOE PLATE ALIGNMENT 0 18-Jan-14 A 18-Feb-14 ASafety measure for openingSafety measure for opening 0 18-Jan-14 A 18-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 29 of 81 Filter: All Activity

Page 30: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

CS-10030 Since the lower part is crop chute, install a scaffolding with enough strength. 0 18-Jan-14 A

CS-10040 Lashing of scaffolding board s hould use the annealing wire. 0 18-Feb-14 A

Foundation checkFoundation check 0 19-Jan-14 A 25-Jan-14 ACS-10050 Check foundation and anchor bolts according to JIMS and " Instruction Manual for Erection (10065148-2002072-WP001)"0 19-Jan-14 A 19-Jan-14 A

CS-10060 Measure the position of foundation bolts from Line center and Crop Shear center. 0 20-Jan-14 A 20-Jan-14 A

CS-10070 Measure the height of foundation bolts from reference level. 0 22-Jan-14 A 23-Jan-14 A

CS-10080 Measure the clearance of Crop Shear Assembly installing area. Verify the no interference foundation to crop s hear0 24-Jan-14 A 25-Jan-14 A

Foundation Chipping (Roughing Foundation) and PaddingFoundation Chipping (Roughing Foundation) and Padding 0 12-Feb-14 A 14-Feb-14 ACS-10090 Chipping whole surface of grouting area. 0 12-Feb-14 A 13-Feb-14 A

CS-10100 Sprinkle water and avoid dust. 0 14-Feb-14 A

CS-10110 Cleaning the chipping surface (ex. dust, water, etc.) after completion of the chipping. 0 14-Feb-14 A

PaddingPadding 0 14-Feb-14 A 15-Feb-14 ACS-10120 Execute padding according to Work Procedure by " Grouting Pad method" in "Instruction Manual for Erection (10065148-20 14-Feb-14 A 15-Feb-14 A

Preparation of InstallationPreparation of Installation 0 28-Jan-14 A 28-Jan-14 ACS-10130 Remove the rust-preventive coating of the surface, which is contacted on the concrete grouting and required for insta0 28-Jan-14 A

CS-10140 Pre-assembly and disassembly, if any. Assembly or remove the parts required for installation. When removing the parts0 28-Jan-14 A

CS-10150 Taper liner should be set and adjusted the upper surface level. (4 points or more) 0 28-Jan-14 A 28-Jan-14 A

Installtion and Alignment for Shoe PlateInstalltion and Alignment for Shoe Plate 0 28-Jan-14 A 28-Jan-14 ACS-10160 Shoe plate temporary placing 0 28-Jan-14 A 28-Jan-14 A

CS-10170 After confirming the accuracy of the liner, install the delivery side shoe plate and check the center match mark is a0 28-Jan-14 A 28-Jan-14 A

Installation and alignment of Shoe PlateInstallation and alignment of Shoe Plate 0 28-Jan-14 A 28-Jan-14 ACS-10210 Install the foundation bolt cover. Apply sufficient grease to the foundation bolts and fit the foundation bolts then0 28-Jan-14 A 28-Jan-14 A

CS-10180 After verify the accuracy of the delivery side shoe plate, to be confirmed inside the entry side shoe plate using th0 28-Jan-14 A 28-Jan-14 A

CS-10190 Ensure that the upper surface (machined surface) of the shoe plate is covered with plastic sheet to protect from dirt0 28-Jan-14 A

CS-10200 Cut the foundation bolts, if any. 0 28-Jan-14 A 28-Jan-14 A

GroutingGrouting 0 28-Jan-14 A 29-Jan-14 ACS-10260 Check and ensure that grouting shall be poured successively from one direction so as not to leave air pockets and ens0 28-Jan-14 A

CS-10220 Set wooden frame and check its rigidity can support the grout load, and the depth shall conforms to the specification0 28-Jan-14 A 29-Jan-14 A

CS-10230 Clear the surface area to be grouted from dust/foreign particle and clean with compressed air. Wipe out dry any oil s0 28-Jan-14 A 29-Jan-14 A

CS-10240 Check if surface is properly saturated with water. Remove excess water. 0 28-Jan-14 A 29-Jan-14 A

CS-10250 Check grouting materials and its mixing ratio if according to the specification or otherwise shall conform to JIMS D-0 28-Jan-14 A 29-Jan-14 A

CS-10270 After finishing curing, check hardness. 0 28-Jan-14 A 29-Jan-14 A

ERECTION OF CROP SHEARERECTION OF CROP SHEAR 0 30-Jan-14 A 02-Feb-14 APreparationPreparation 0 30-Jan-14 A 30-Jan-14 ACS-10280 Preparation 0 30-Jan-14 A

CS-10290 Before erecting the Crop Shear Assembly, ins tall its par ts to be installed dur ing erection per iod, listed as fol lows :0 30-Jan-14 A

CS-10300 HSG surface trimming. Clean and remove the damage portion of HSG machined surfaces that will contact with the shoe pl0 30-Jan-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 30 of 81 Filter: All Activity

Page 31: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

CS-10310 Work prior to Crop Shear Assembly erection. A) Complete installation of shoe plates b) Prepare the foot bolts and nut0 30-Jan-14 A

Crop shear Erection and AlignmentCrop shear Erection and Alignment 0 31-Jan-14 A 02-Feb-14 ACS-10320 When erecting Crop Shear Assembly onto the shoe plates, lower the As sembly into positi on slowly, and carefully obser0 31-Jan-14 A

Crop Shear Assembly onto the shoe plateCrop Shear Assembly onto the shoe plate 0 02-Feb-14 A 02-Feb-14 ACS-10330 Lifting Crop Shear Assembly by lifting beam with overhead cranes. b) HSG surface trimming 0 02-Feb-14 A 02-Feb-14 A

CS-10340 Crop shear assembly onto the shoe plates. 0 02-Feb-14 A 02-Feb-14 A

CS-10350 Verify the zero gaps for contact surface of HSG to top of shoe plate. 0 02-Feb-14 A 02-Feb-14 A

CS-10360 Temporary bolting HSG with shoe plate by foot bolts. (Don't use hammer, only soft tighten by hand) 0 02-Feb-14 A 02-Feb-14 A

CS-10370 Adjust the Assembly position from line center same as drawing dimension. 0 02-Feb-14 A 02-Feb-14 A

CS-10380 Positioning Crop Shear Assembly. The Assembly push to the delivery s ide and verify the zero gaps between HSG and s0 02-Feb-14 A 02-Feb-14 A

MEASURE THE ITEMS IN PARAGRAPH-21 OF INSTALLATION ACCURACYMEASURE THE ITEMS IN PARAGRAPH-21 OF INSTALLATION ACCURACY 0 02-Feb-14 A 02-Feb-14 ACS-10390 Prepare the scaffolding, if any, and piano wire according to the drawing on the right and the measurement procedure.0 02-Feb-14 A 02-Feb-14 A

CS-10400 Final tighten the foot bolts after completion the alignment of Crop Shear Assembly. 0 02-Feb-14 A 02-Feb-14 A

CROP SHEAR ENTRY TABLE (1 TABLE, 6 ROLLS)CROP SHEAR ENTRY TABLE (1 TABLE, 6 ROLLS) 0 20-Mar-14 A 12-Apr-14 ACS-10410 MOTOR ALLIGNMENT (6 MOTORS) 0 05-Apr-14 A 10-Apr-14 A

CS-10420 BASE GROUTING & CURING AFTER TAPER LINER AND FLAT LINER WELDING 0 10-Apr-14 A 10-Apr-14 A

PREPARATIONPREPARATION 0 20-Mar-14 A 03-Apr-14 ACS-10430 FOUNDATION CHECKING AND CHIPPING AND PADDING 0 20-Mar-14 A 21-Mar-14 A

CS-10440 ERECTION OF TABLE BEAM 0 22-Mar-14 A 23-Mar-14 A

CS-10450 INSTALLATION OF MOTOR FRAME 0 24-Mar-14 A 25-Mar-14 A

CS-10460 PRELIMINARY LEVELING & ALLIGNMENT IS PERFORMED WITH TENSIONING OF PIANNO WIRE TO LINE CENTRE0 26-Mar-14 A 29-Mar-14 A

CS-10470 INSTALLATION OF MOTOR 0 02-Apr-14 A 02-Apr-14 A

CS-10480 SETTING THE ANCHOR BOLTS AND NUTS 0 02-Apr-14 A 02-Apr-14 A

CS-10490 ANCHOR GROUTING AND CURING. 0 03-Apr-14 A 03-Apr-14 A

ALLIGNMENTALLIGNMENT 0 03-Apr-14 A 04-Apr-14 ACS-10500 CONFIRM THE DIRECTION OF PASS LINE ROLLER CENTRE ON THE BASIS OF PIANO WIRE 0 03-Apr-14 A 03-Apr-14 A

CS-10510 CHECK THE LEVELNESS 0 04-Apr-14 A 04-Apr-14 A

CS-10520 MEASURE THE DIRECTION AT RIGHT ANGLED CENTRE (FOR VERIFICATION). 0 04-Apr-14 A 04-Apr-14 A

REMAINING WORKSREMAINING WORKS 0 10-Apr-14 A 12-Apr-14 ACS-10530 INSTALLATION OF MOTOR COVER 0 10-Apr-14 A 11-Apr-14 A

CS-10540 INSTALLATION OF SPLASH GUARD 0 11-Apr-14 A 11-Apr-14 A

CS-10550 TIGHTENING OF FOUNDATION BOLTS AFTER GROUTING 0 11-Apr-14 A 11-Apr-14 A

CS-10560 ATTACHED PIPING AND OTHER REMAINING WORKS. 0 11-Apr-14 A 12-Apr-14 A

Shop piping including water & UtilitiesShop piping including water & Utilities 94 19-Nov-12 A 30-Oct-14

Mechanical & Piping WorksMechanical & Piping Works 94 19-Nov-12 A 30-Oct-14UTILITY PIPING Works (Shop Piping)UTILITY PIPING Works (Shop Piping) 94 19-Nov-12 A 30-Oct-14Water SystemWater System 94 19-Nov-12 A 30-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 31 of 81 Filter: All Activity

Page 32: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

SP-10000 Drawing Inputs 0 19-Nov-12 A 10-May-14 A

SP-10010 Fabrication of Piping spools 12 04-Mar-13 A 17-Jul-14

SP-10030 Run out table Piping 30 03-Feb-14 A 08-Aug-14

SP-10070 Strip Cooling (WDS1) 32 02-Sep-13 A 11-Aug-14

SP-10110 Drainage Pumps. (WA1) 35 03-Feb-14 A 14-Aug-14

SP-10120 Drain for Down Coiler 25 30-Jul-14 01-Sep-14

SP-10080 High Pressure Water. (WH) 54 02-Sep-13 A 09-Sep-14

SP-10060 Direct Cooling Water 55 02-Sep-13 A 11-Sep-14

SP-10090 Indirect Cooling Water (W1) 59 02-Sep-13 A 16-Sep-14

SP-10050 Make up Water 60 02-Sep-13 A 17-Sep-14

SP-10040 Fire Fighting 63 02-Sep-13 A 20-Sep-14

SP-10020 Drinking Water. 94 02-Sep-13 A 30-Oct-14

Finishing Mill & ROT (including Crop shear, SD) + CFL + Transfer carFinishing Mill & ROT (including Crop shear, SD) + CFL + Transfer car 106 27-Dec-11 A 15-Oct-14

F1 to F7 (equipment), B&S coordination & Mechanical ErectionF1 to F7 (equipment), B&S coordination & Mechanical Erection 106 27-Dec-11 A 15-Oct-14Civil Building & Foundation WorksCivil Building & Foundation Works 0 27-Dec-11 A 16-Dec-13 AB-C/ 32-39 (Finishing Mill Area)B-C/ 32-39 (Finishing Mill Area) 0 27-Dec-11 A 20-Aug-13 AFM-10010 Building Column 0 27-Mar-12 A 31-Oct-12 A

FM-10020 Scale Sluice 0 08-May-12 A 31-Oct-12 A

FM-10000 Drawing Inputs incl. Equipment foundation 0 27-Dec-11 A 25-Jul-13 A

FM-10030 Finishing Mill Equip Foundation Including Scale flume wall 0 16-Jul-12 A 20-Aug-13 A

B-C/ 39- 45 (Laminar Cooling Area)B-C/ 39- 45 (Laminar Cooling Area) 0 03-Apr-12 A 16-Dec-13 AFM-10050 Building Column 0 02-Jul-12 A 15-Oct-12 A

FM-10040 Drawing Inputs incl. Equipment foundation 0 03-Apr-12 A 15-Jul-13 A

FM-10060 Run out table Equip foundation 0 31-Aug-12 A 16-Dec-13 A

Structural Building & Technological WorksStructural Building & Technological Works 0 03-Apr-12 A 25-Mar-14 AB-C/ 32-39 (Finishing Mill Area)B-C/ 32-39 (Finishing Mill Area) 0 15-Jun-12 A 04-Nov-13 AFM-10070 Drawing Inputs 0 15-Jun-12 A 03-Sep-12 A

FM-10080 Fabrication 0 17-Sep-12 A 30-Apr-13 A

FM-10090 Erection (including sheeting) 0 16-Oct-12 A 04-Nov-13 A

B-C/ 39- 45 (Laminar Cooling Area)B-C/ 39- 45 (Laminar Cooling Area) 0 03-Apr-12 A 25-Mar-14 AFM-LC-10000 Drawing Inputs 0 03-Apr-12 A 31-Oct-12 A

FM-LC10010 Fabrication 0 02-Jul-12 A 30-Apr-13 A

FM-LC-10020 Erection 0 17-Sep-12 A 13-Nov-13 A

FM-LC-10030 Sheeting 0 02-Aug-13 A 25-Mar-14 A

Mechanical & Piping WorksMechanical & Piping Works 56 15-Feb-13 A 26-Aug-14Mill Preconditions for ErectionMill Preconditions for Erection 0 23-May-13 A 03-Feb-14 AFM-10170 Avail ability of Fire extinguisher equipments 0 05-Jul-13 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 32 of 81 Filter: All Activity

Page 33: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM-10130 Sump pumps installed where necessary to keep ducts and cellar spaces free from rain water. 0 15-Jul-13 A

FM-10180 Access ways to erection site for movement of equipment 0 02-Aug-13 A

FM-10110 Temp. Bay lighting complete to facilitate erection 0 02-Aug-13 A

FM-10120 Adequate l ighting provided in utility cellars 0 02-Aug-13 A

FM-10160 Off ices & Restrooms for foreign s upervisors 0 02-Aug-13 A

FM-10100 Comisioning of 2x120 Tons Crane in BC Bay 0 23-May-13 A 14-Aug-13 A

FM-10190 Completion of equipment foundation and mill floor BC Bay 32-45 (FM & ROT) 0 19-Aug-13 A

FM-10200 Completion of equipment foundation Motor House CD Bay 32-39 0 03-Feb-14 A

FM-10140 Ready-to-operate extraction points for site power, compressed air and water supply in adequate volumes0 03-Feb-14 A

FM-10150 Adequate space for unpacking, cleaning and preassembling of equipment components in BC Bay 32-45 Work side0 03-Feb-14 A

EQPT RECEIPT AT SITEEQPT RECEIPT AT SITE 0 15-Feb-13 A 26-Jun-14 AFM-10210 Receipt at site (Sojitz scope) 0 15-Feb-13 A 05-Mar-14 A

FM-10220 Receipt at site (TGS scope) 0 02-Aug-13 A 26-Jun-14 A

Equipment Erection (Finishing Mill 1-7)Equipment Erection (Finishing Mill 1-7) 56 02-Sep-13 A 26-Aug-14FM-10230 Foundation Checking, Chipping, Padding & preparation of scaffolding for 7 stands 0 02-Sep-13 A

Finishing Mill 1Finishing Mill 1 55 01-Nov-13 A 25-Aug-14FM SHOE PLATEFM SHOE PLATE 0 22-Nov-13 A 17-Mar-14 AFM1-10950 Foundation chipping & Padding(including curing) 0 22-Nov-13 A 28-Nov-13 A

FM1-10960 Installation & alignment of Shoe plate 0 28-Nov-13 A 29-Nov-13 A

FM1-10970 Grouting of shoe plate(including curing time) 0 30-Nov-13 A 30-Nov-13 A

FM1-10980 Retightening of Anchor Bolts 0 13-Mar-14 A 17-Mar-14 A

FM HOUSINGFM HOUSING 0 18-Jan-14 A 27-Jan-14 AFM1-12790 Erection of work side housing with attached piping 0 18-Jan-14 A 18-Jan-14 A

FM1-12800 Erection of drive side housing with attached piping 0 18-Jan-14 A 18-Jan-14 A

FM1-12810 Erection of bottom separator 0 20-Jan-14 A 21-Jan-14 A

FM1-12820 Erection of top separator 0 22-Jan-14 A 23-Jan-14 A

FM1-12830 Erection of AGC bracket 0 25-Jan-14 A 26-Jan-14 A

FM1-12840 Allignment of FM-1 housing 0 27-Jan-14 A 27-Jan-14 A

FM Mill properFM Mill proper 55 02-Feb-14 A 25-Aug-14FM1-10910 Installation of WR Changing Rail 0 02-Feb-14 A 04-Feb-14 A

FM1-10860 Installation of bottom coupling support 0 13-Feb-14 A 14-Feb-14 A

FM1-10900 Installation of feed roller assembly 0 14-Feb-14 A 19-Mar-14 A

FM1-10920 Installation of AGC Cylinder assembly 0 02-Jun-14 A 06-Jun-14 A

FM1-10930 Installation of Step liner 0 06-Jun-14 A 08-Jun-14 A

FM1-10870 Instrumentation and installation 2 08-Jun-14 A 03-Jul-14

FM1-10880 Cable laying and termination 4 15-Jun-14 A 05-Jul-14

FM1-10890 Function test 45 11-Jul-14 25-Aug-14*

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 33 of 81 Filter: All Activity

Page 34: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM Pinion StandFM Pinion Stand 0 02-Nov-13 A 10-Mar-14 AFM1-12850 Foundation chipping. 0 02-Nov-13 A 04-Nov-13 A

FM1-12860 Fixing and allignment of liner plate. 0 04-Nov-13 A 06-Nov-13 A

FM1-12870 Padding & curing of liner plate. 0 07-Nov-13 A 09-Nov-13 A

FM1-12880 Installation & allignment of pinion gear box. 0 19-Nov-13 A 27-Feb-14 A

FM1-12890 Grouting of pinion gear box. 0 28-Feb-14 A 10-Mar-14 A

FM BUR Changing deviceFM BUR Changing device 0 03-Feb-14 A 23-Feb-14 AFM1-13160 Material availability at site. 0 03-Feb-14 A 06-Feb-14 A

FM1-13170 Foundation chipping,fixing & alignment of liner plate 0 03-Feb-14 A 06-Feb-14 A

FM1-13180 Padding of liner plate. 0 06-Feb-14 A 11-Feb-14 A

FM1-12900 Installation of sled base 0 11-Feb-14 A 14-Feb-14 A

FM1-12920 Installation of elevating base,rails & frame 0 14-Feb-14 A 18-Feb-14 A

FM1-12930 Grouting of base including curing time 0 18-Feb-14 A 21-Feb-14 A

FM1-12910 Installation of traversing cylinder 0 21-Feb-14 A 23-Feb-14 A

FM WR Changing DeviceFM WR Changing Device 0 01-Apr-14 A 19-Apr-14 AFM1-13040 Fixation of rails 0 01-Apr-14 A 02-Apr-14 A

FM1-13050 Installation of shifting rails 0 01-Apr-14 A 03-Apr-14 A

FM1-13060 Installation of shifting cylinders & base 0 02-Apr-14 A 05-Apr-14 A

FM1-13070 Installation of fixed rails 0 04-Apr-14 A 05-Apr-14 A

FM1-13030 Grouting including curing time 0 07-Apr-14 A 09-Apr-14 A

FM1-13190 Completion of WR Changing device 0 09-Apr-14 A 10-Apr-14 A

FM1-13020 Installation of Buggy & Side shift car 0 14-Apr-14 A 19-Apr-14 A

Side Guide & LooperSide Guide & Looper 0 02-Feb-14 A 18-Apr-14 AFM1-12940 Alignment & Installation of Guide Frame & Looper assembly 0 02-Feb-14 A 06-Feb-14 A

FM1-13150 Material availability at site 0 03-Feb-14 A 06-Feb-14 A

FM1-12950 Fixing of Delivery bottom stripper 0 06-Feb-14 A 08-Feb-14 A

FM1-12960 Installation of side guide 0 25-Feb-14 A 04-Mar-14 A

FM1-12970 Installation of Looper Table dr ive assembly 0 04-Mar-14 A 06-Mar-14 A

FM1-12980 Fixing of Entry top wiper 0 06-Mar-14 A 08-Mar-14 A

FM1-12990 Fixing of Delivery top stripper 0 08-Mar-14 A 10-Mar-14 A

FM1-13010 Erectiong of BUR Cooling headers 0 11-Mar-14 A 03-Apr-14 A

FM1-13000 Erection of attached piping 0 04-Apr-14 A 18-Apr-14 A

FM-1 balance erectionFM-1 balance erection 49 01-Nov-13 A 19-Aug-14FM1-13130 Installation of Attached Piping 0 01-Nov-13 A 20-Dec-13 A

FM1-13110 Simple Parts 0 26-Mar-14 A 30-Apr-14 A

FM1-13090 Installation of Sled 13 30-Apr-14 A 15-Jul-14

FM1-13100 Completiong of wiring & cabling 20 02-Jun-14 A 21-Jul-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 34 of 81 Filter: All Activity

Page 35: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM1-13140 Installation of Leading Spindle 1 18-Aug-14 18-Aug-14

FM1-13080 Installation of Mill spindle 1 18-Aug-14 18-Aug-14

FM1-13120 FM-1 Erection completion 0 19-Aug-14

Finishing Mill 2Finishing Mill 2 2 24-Sep-13 A 19-Aug-14FM SHOE PLATEFM SHOE PLATE 0 24-Sep-13 A 11-Feb-14 AFM2-10000 Foundation chipping & Padding(including curing) 0 24-Sep-13 A 28-Sep-13 A

FM2-10010 Installation & alignment of Shoe plate 0 07-Oct-13 A 16-Oct-13 A

FM2-10020 Grouting of shoe plate(including curing time) 0 02-Feb-14 A 06-Feb-14 A

FM2-10030 Retightening of Anchor Bolts 0 07-Feb-14 A 11-Feb-14 A

FM HOUSINGFM HOUSING 0 03-Feb-14 A 27-Feb-14 AFM2-10040 Erection of drive side housing with attached piping 0 03-Feb-14 A 06-Feb-14 A

FM2-10050 Erection of work side housing with attached piping 0 06-Feb-14 A 11-Feb-14 A

FM2-10060 Erection of bottom separator 0 11-Feb-14 A 14-Feb-14 A

FM2-10070 Erection of top separator 0 14-Feb-14 A 19-Feb-14 A

FM2-10080 Erection of AGC bracket 0 19-Feb-14 A 24-Feb-14 A

FM2-10090 Allignment of FM-2 housing 0 24-Feb-14 A 27-Feb-14 A

FM Mill properFM Mill proper 0 02-Feb-14 A 14-Feb-14 AFM2-10100 Installation of WR Changing Rail 0 02-Feb-14 A 04-Feb-14 A

FM2-10110 Installation of AGC Cylinder assembly 0 04-Feb-14 A 08-Feb-14 A

FM2-10120 Installation of Step liner 0 08-Feb-14 A 10-Feb-14 A

FM2-10130 Pass line adjustment 0 11-Feb-14 A 13-Feb-14 A

FM2-10140 Installation of bottom coupling support 0 13-Feb-14 A 14-Feb-14 A

FM Pinion StandFM Pinion Stand 0 02-Feb-14 A 20-Feb-14 AFM2-10190 Foundation chipping. 0 02-Feb-14 A 04-Feb-14 A

FM2-10200 Fixing and allignment of liner plate. 0 04-Feb-14 A 07-Feb-14 A

FM2-10210 Padding & curing of liner plate. 0 07-Feb-14 A 12-Feb-14 A

FM2-10220 Installation & allignment of pinion gear box. 0 12-Feb-14 A 17-Feb-14 A

FM2-10230 Grouting of pinion gear box. 0 17-Feb-14 A 20-Feb-14 A

FM BUR Changing deviceFM BUR Changing device 0 03-Feb-14 A 23-Feb-14 AFM2-10240 Material availability at site. 0 03-Feb-14 A 06-Feb-14 A

FM2-10250 Foundation chipping,fixing & alignment of liner plate 0 03-Feb-14 A 06-Feb-14 A

FM2-10260 Padding of liner plate. 0 06-Feb-14 A 11-Feb-14 A

FM2-10270 Installation of sled base 0 11-Feb-14 A 14-Feb-14 A

FM2-10280 Installation of elevating base,rails & frame 0 14-Feb-14 A 18-Feb-14 A

FM2-10290 Grouting of base including curing time 0 18-Feb-14 A 21-Feb-14 A

FM2-10300 Installation of traversing cylinder 0 21-Feb-14 A 23-Feb-14 A

FM WR Changing DeviceFM WR Changing Device 0 18-Apr-14 A 11-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 35 of 81 Filter: All Activity

Page 36: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM2-10310 Fixation of rails 0 18-Apr-14 A 22-Apr-14 A

FM2-10320 Installation of shifting rails 0 23-Apr-14 A 25-Apr-14 A

FM2-10330 Installation of shifting cylinders & base 0 26-Apr-14 A 29-Apr-14 A

FM2-10340 Installation of fixed rails 0 30-Apr-14 A 03-May-14 A

FM2-10350 Installation of Buggy & Side shift car 0 04-May-14 A 09-May-14 A

FM2-10360 Grouting including curing time 0 09-May-14 A 11-May-14 A

Side Guide & LooperSide Guide & Looper 0 02-Feb-14 A 04-Apr-14 AFM2-10370 Alignment & Installation of Guide Frame & Looper assembly 0 02-Feb-14 A 06-Feb-14 A

FM2-10380 Material availability at site 0 03-Feb-14 A 06-Feb-14 A

FM2-10390 Fixing of Delivery bottom stripper 0 06-Feb-14 A 08-Feb-14 A

FM2-10400 Installation of side guide 0 07-Feb-14 A 09-Feb-14 A

FM2-10410 Installation of Looper Table dr ive assembly 0 09-Feb-14 A 11-Feb-14 A

FM2-10420 Fixing of Entry top wiper 0 11-Feb-14 A 13-Feb-14 A

FM2-10430 Fixing of Delivery top stripper 0 13-Feb-14 A 15-Feb-14 A

FM2-10440 Erectiong of BUR Cooling headers 0 16-Feb-14 A 11-Mar-14 A

FM2-10450 Erection of attached piping 0 12-Mar-14 A 04-Apr-14 A

FM-2 balance erectionFM-2 balance erection 2 01-Nov-13 A 19-Aug-14FM2-10460 Installation of Attached Piping 0 01-Nov-13 A 20-Dec-13 A

FM2-10470 Installation of Mill spindle 0 02-Feb-14 A 03-Feb-14 A

FM2-10480 Installation of Sled 0 02-Feb-14 A 11-Apr-14 A

FM2-10500 Simple Parts 0 21-Nov-13 A 23-Apr-14 A

FM2-10520 FM-2 Erection completion 0 19-Aug-14

FM2-10490 Installation of Leading Spindle 2 18-Aug-14* 19-Aug-14

Finishing Mill 3Finishing Mill 3 56 24-Sep-13 A 26-Aug-14FM SHOE PLATEFM SHOE PLATE 0 24-Sep-13 A 06-Feb-14 AFM3-10000 Foundation chipping & Padding(including curing) 0 24-Sep-13 A 28-Sep-13 A

FM3-10010 Installation & alignment of Shoe plate 0 07-Oct-13 A 16-Oct-13 A

FM3-10020 Grouting of shoe plate(including curing time) 0 15-Nov-13 A 18-Nov-13 A

FM3-10030 Retightening of Anchor Bolts 0 02-Feb-14 A 06-Feb-14 A

FM HOUSINGFM HOUSING 0 27-Nov-13 A 31-Dec-13 AFM3-10420 Erection of drive side housing with attached piping 0 27-Nov-13 A 27-Nov-13 A

FM3-10410 Erection of work side housing with attached piping 0 27-Nov-13 A 28-Nov-13 A

FM3-10430 Erection of bottom separator 0 28-Nov-13 A 28-Nov-13 A

FM3-10450 Erection of top separator 0 29-Nov-13 A 29-Nov-13 A

FM3-10460 Erection of AGC bracket 0 30-Nov-13 A 30-Nov-13 A

FM3-10490 Allignment of FM-3 housing 0 30-Dec-13 A 31-Dec-13 A

FM Mill properFM Mill proper 56 02-Feb-14 A 26-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 36 of 81 Filter: All Activity

Page 37: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM3-10050 Installation of WR Changing Rail 0 02-Feb-14 A 04-Feb-14 A

FM3-10160 Installation of AGC Cylinder assembly 0 04-Feb-14 A 08-Feb-14 A

FM3-10220 Installation of Step liner 0 08-Feb-14 A 10-Feb-14 A

FM3-10250 Pass line adjustment 0 11-Feb-14 A 13-Feb-14 A

FM3-10280 Installation of bottom coupling support 0 13-Feb-14 A 14-Feb-14 A

FM3-10310 Instrumentation and installation 0 14-Feb-14 A 11-Mar-14 A

FM3-10320 Installation of feed roller assembly 0 14-Feb-14 A 19-Mar-14 A

FM3-10470 Cable ducting laying and termination 1 02-May-14 A 02-Jul-14

FM3-10510 I/O checking 55 02-Jul-14 26-Aug-14

FM Pinion StandFM Pinion Stand 0 02-Nov-13 A 20-Mar-14 AFM3-10060 Foundation chipping. 0 02-Nov-13 A 04-Nov-13 A

FM3-10150 Fixing and allignment of liner plate. 0 04-Nov-13 A 06-Nov-13 A

FM3-10190 Padding & curing of liner plate. 0 07-Nov-13 A 09-Nov-13 A

FM3-10370 Installation & allignment of pinion gear box. 0 19-Nov-13 A 27-Feb-14 A

FM3-10440 Grouting of pinion gear box. 0 28-Feb-14 A 20-Mar-14 A

FM BUR Changing deviceFM BUR Changing device 0 03-Feb-14 A 23-Feb-14 AFM3-10130 Material availability at site. 0 03-Feb-14 A 06-Feb-14 A

FM3-10140 Foundation chipping,fixing & alignment of liner plate 0 03-Feb-14 A 06-Feb-14 A

FM3-10180 Padding of liner plate. 0 06-Feb-14 A 11-Feb-14 A

FM3-10260 Installation of sled base 0 11-Feb-14 A 14-Feb-14 A

FM3-10330 Installation of elevating base,rails & frame 0 14-Feb-14 A 18-Feb-14 A

FM3-10350 Grouting of base including curing time 0 18-Feb-14 A 21-Feb-14 A

FM3-10390 Installation of traversing cylinder 0 21-Feb-14 A 23-Feb-14 A

FM WR Changing DeviceFM WR Changing Device 0 18-Apr-14 A 11-May-14 AFM3-10080 Fixation of rails 0 18-Apr-14 A 22-Apr-14 A

FM3-10210 Installation of shifting rails 0 23-Apr-14 A 25-Apr-14 A

FM3-10240 Installation of shifting cylinders & base 0 26-Apr-14 A 29-Apr-14 A

FM3-10300 Installation of fixed rails 0 30-Apr-14 A 03-May-14 A

FM3-10360 Installation of Buggy & Side shift car 0 04-May-14 A 09-May-14 A

FM3-10400 Grouting including curing time 0 09-May-14 A 11-May-14 A

Side Guide & LooperSide Guide & Looper 0 02-Feb-14 A 04-Apr-14 AFM3-10070 Alignment & Installation of Guide Frame & Looper assembly 0 02-Feb-14 A 06-Feb-14 A

FM3-10120 Material availability at site 0 03-Feb-14 A 06-Feb-14 A

FM3-10170 Fixing of Delivery bottom stripper 0 06-Feb-14 A 08-Feb-14 A

FM3-10200 Installation of side guide 0 07-Feb-14 A 09-Feb-14 A

FM3-10230 Installation of Looper Table dr ive assembly 0 09-Feb-14 A 11-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 37 of 81 Filter: All Activity

Page 38: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM3-10270 Fixing of Entry top wiper 0 11-Feb-14 A 13-Feb-14 A

FM3-10290 Fixing of Delivery top stripper 0 13-Feb-14 A 15-Feb-14 A

FM3-10340 Erectiong of BUR Cooling headers 0 16-Feb-14 A 11-Mar-14 A

FM3-10480 Erection of attached piping 0 12-Mar-14 A 04-Apr-14 A

FM-3 balance erectionFM-3 balance erection 49 01-Nov-13 A 19-Aug-14FM3-10040 Installation of Attached Piping 0 01-Nov-13 A 14-Jan-14 A

FM3-10090 Installation of Mill spindle 0 02-Feb-14 A 03-Feb-14 A

FM3-10380 Simple Parts 0 21-Nov-13 A 23-Apr-14 A

FM3-10100 Installation of Sled 0 02-Feb-14 A 09-May-14 A

FM3-10500 Completiong of wiring & cabling 9 22-May-14 A 10-Jul-14

FM3-10110 Installation of Leading Spindle 1 18-Aug-14* 18-Aug-14

FM3-10520 FM-3 Erection completion 0 19-Aug-14

Finishing Mill 4Finishing Mill 4 49 24-Sep-13 A 19-Aug-14FM SHOE PLATEFM SHOE PLATE 0 24-Sep-13 A 11-Feb-14 AFM4-10000 Foundation chipping & Padding(including curing) 0 24-Sep-13 A 28-Sep-13 A

FM4-10010 Installation & alignment of Shoe plate 0 07-Oct-13 A 16-Oct-13 A

FM4-10040 Grouting of shoe plate(including curing time) 0 02-Feb-14 A 06-Feb-14 A

FM4-10210 Retightening of Anchor Bolts 0 07-Feb-14 A 11-Feb-14 A

FM HOUSINGFM HOUSING 0 26-Nov-13 A 19-Feb-14 AFM4-10450 Erection of work side housing with attached piping 0 26-Nov-13 A 26-Nov-13 A

FM4-10460 Erection of drive side housing with attached piping 0 26-Nov-13 A 26-Nov-13 A

FM4-10050 Erection of bottom separator 0 03-Feb-14 A 06-Feb-14 A

FM4-10180 Erection of top separator 0 06-Feb-14 A 11-Feb-14 A

FM4-10280 Erection of AGC bracket 0 11-Feb-14 A 14-Feb-14 A

FM4-10370 Allignment of FM-7 housing 0 14-Feb-14 A 19-Feb-14 A

FM Mill properFM Mill proper 0 02-Feb-14 A 19-Mar-14 AFM4-10030 Installation of WR Changing Rail 0 02-Feb-14 A 04-Feb-14 A

FM4-10160 Installation of AGC Cylinder assembly 0 04-Feb-14 A 08-Feb-14 A

FM4-10240 Installation of Step liner 0 08-Feb-14 A 10-Feb-14 A

FM4-10270 Pass line adjustment 0 11-Feb-14 A 13-Feb-14 A

FM4-10310 Installation of bottom coupling support 0 13-Feb-14 A 14-Feb-14 A

FM4-10340 Instrumentation and installation 0 14-Feb-14 A 11-Mar-14 A

FM4-10350 Installation of feed roller assembly 0 14-Feb-14 A 19-Mar-14 A

FM Pinion StandFM Pinion Stand 0 02-Nov-13 A 03-Mar-14 AFM4-10060 Foundation chipping. 0 02-Nov-13 A 04-Nov-13 A

FM4-10150 Fixing and allignment of liner plate. 0 04-Nov-13 A 06-Nov-13 A

FM4-10200 Padding & curing of liner plate. 0 07-Nov-13 A 09-Nov-13 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 38 of 81 Filter: All Activity

Page 39: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM4-10410 Installation & allignment of pinion gear box. 0 19-Nov-13 A 27-Feb-14 A

FM4-10470 Grouting of pinion gear box. 0 28-Feb-14 A 03-Mar-14 A

FM BUR Changing deviceFM BUR Changing device 0 03-Feb-14 A 23-Feb-14 AFM4-10140 Foundation chipping,fixing & alignment of liner plate 0 03-Feb-14 A 06-Feb-14 A

FM4-10130 Material availability at site. 0 03-Feb-14 A 06-Feb-14 A

FM4-10190 Padding of liner plate. 0 06-Feb-14 A 11-Feb-14 A

FM4-10290 Installation of sled base 0 11-Feb-14 A 14-Feb-14 A

FM4-10360 Installation of elevating base,rails & frame 0 14-Feb-14 A 18-Feb-14 A

FM4-10390 Grouting of base including curing time 0 18-Feb-14 A 21-Feb-14 A

FM4-10430 Installation of traversing cylinder 0 21-Feb-14 A 23-Feb-14 A

FM WR Changing DeviceFM WR Changing Device 0 17-Mar-14 A 23-Apr-14 AFM4-10230 Installation of shifting rails 0 24-Mar-14 A 25-Mar-14 A

FM4-10260 Installation of shifting cylinders & base 0 08-Apr-14 A 11-Apr-14 A

FM4-10330 Installation of fixed rails 0 12-Apr-14 A 15-Apr-14 A

FM4-10080 Fixation of rails 0 17-Mar-14 A 18-Apr-14 A

FM4-10400 Installation of Buggy & Side shift car 0 16-Apr-14 A 21-Apr-14 A

FM4-10440 Grouting including curing time 0 21-Apr-14 A 23-Apr-14 A

Side Guide & LooperSide Guide & Looper 0 02-Feb-14 A 04-Apr-14 AFM4-10070 Alignment & Installation of Guide Frame & Looper assembly 0 02-Feb-14 A 06-Feb-14 A

FM4-10120 Material availability at site 0 03-Feb-14 A 06-Feb-14 A

FM4-10170 Fixing of Delivery bottom stripper 0 06-Feb-14 A 08-Feb-14 A

FM4-10220 Installation of side guide 0 07-Feb-14 A 09-Feb-14 A

FM4-10250 Installation of Looper Table dr ive assembly 0 09-Feb-14 A 11-Feb-14 A

FM4-10300 Fixing of Entry top wiper 0 11-Feb-14 A 13-Feb-14 A

FM4-10320 Fixing of Delivery top stripper 0 13-Feb-14 A 15-Feb-14 A

FM4-10380 Erectiong of BUR Cooling headers 0 16-Feb-14 A 11-Mar-14 A

FM4-10490 Erection of attached piping 0 12-Mar-14 A 04-Apr-14 A

FM-4 balance erectionFM-4 balance erection 49 01-Nov-13 A 19-Aug-14FM4-10020 Installation of Attached Piping 0 01-Nov-13 A 24-Dec-13 A

FM4-10090 Installation of Mill spindle 0 02-Feb-14 A 03-Feb-14 A

FM4-10100 Installation of Sled 0 02-Feb-14 A 11-Apr-14 A

FM4-10420 Simple Parts 0 21-Nov-13 A 23-Apr-14 A

FM4-10500 Completiong of wiring & cabling 8 21-May-14 A 09-Jul-14

FM4-10110 Installation of Leading Spindle 1 18-Aug-14* 18-Aug-14

FM4-10520 FM-4 Erection completion 0 19-Aug-14

Finishing Mill- 5Finishing Mill- 5 49 24-Sep-13 A 19-Aug-14FM SHOE PLATEFM SHOE PLATE 0 24-Sep-13 A 28-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 39 of 81 Filter: All Activity

Page 40: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM5-10000 Foundation chipping & Padding(including curing) 0 24-Sep-13 A 28-Sep-13 A

FM5-10160 Installation & alignment of Shoe plate 0 07-Nov-13 A 16-Nov-13 A

FM5-10320 Grouting of shoe plate(including curing time) 0 16-Nov-13 A 19-Nov-13 A

FM5-10400 Retightening of Anchor Bolts 0 23-Nov-13 A 28-Feb-14 A

FM HOUSINGFM HOUSING 0 22-Nov-13 A 19-Feb-14 AFM5-10390 Erection of drive side housing with attached piping 0 22-Nov-13 A 22-Nov-13 A

FM5-10410 Erection of work side housing with attached piping 0 23-Nov-13 A 23-Nov-13 A

FM5-10440 Erection of bottom separator 0 03-Feb-14 A 06-Feb-14 A

FM5-10450 Erection of top separator 0 06-Feb-14 A 11-Feb-14 A

FM5-10460 Erection of AGC bracket 0 11-Feb-14 A 14-Feb-14 A

FM5-10490 Allignment of FM-7 housing 0 14-Feb-14 A 19-Feb-14 A

FM Mill properFM Mill proper 0 02-Feb-14 A 19-Mar-14 AFM5-10020 Installation of WR Changing Rail 0 02-Feb-14 A 04-Feb-14 A

FM5-10130 Installation of AGC Cylinder assembly 0 04-Feb-14 A 08-Feb-14 A

FM5-10200 Installation of Step liner 0 08-Feb-14 A 10-Feb-14 A

FM5-10230 Pass line adjustment 0 11-Feb-14 A 13-Feb-14 A

FM5-10260 Installation of bottom coupling support 0 13-Feb-14 A 14-Feb-14 A

FM5-10290 Instrumentation and installation 0 14-Feb-14 A 11-Mar-14 A

FM5-10300 Installation of feed roller assembly 0 14-Feb-14 A 19-Mar-14 A

FM Pinion StandFM Pinion Stand 0 02-Nov-13 A 13-Mar-14 AFM5-10030 Foundation chipping. 0 02-Nov-13 A 04-Nov-13 A

FM5-10120 Fixing and allignment of liner plate. 0 04-Nov-13 A 06-Nov-13 A

FM5-10170 Padding & curing of liner plate. 0 07-Nov-13 A 09-Nov-13 A

FM5-10360 Installation & allignment of pinion gear box. 0 19-Nov-13 A 27-Feb-14 A

FM5-10430 Grouting of pinion gear box. 0 28-Feb-14 A 13-Mar-14 A

FM BUR Changing deviceFM BUR Changing device 0 03-Feb-14 A 23-Feb-14 AFM5-10100 Material availability at site. 0 03-Feb-14 A 06-Feb-14 A

FM5-10110 Foundation chipping,fixing & alignment of liner plate 0 03-Feb-14 A 06-Feb-14 A

FM5-10150 Padding of liner plate. 0 06-Feb-14 A 11-Feb-14 A

FM5-10240 Installation of sled base 0 11-Feb-14 A 14-Feb-14 A

FM5-10310 Installation of elevating base,rails & frame 0 14-Feb-14 A 18-Feb-14 A

FM5-10340 Grouting of base including curing time 0 18-Feb-14 A 21-Feb-14 A

FM5-10380 Installation of traversing cylinder 0 21-Feb-14 A 23-Feb-14 A

FM WR Changing DeviceFM WR Changing Device 0 24-Mar-14 A 25-Apr-14 AFM5-10190 Installation of shifting rails 0 26-Mar-14 A 27-Mar-14 A

FM5-10220 Installation of shifting cylinders & base 0 04-Apr-14 A 07-Apr-14 A

FM5-10280 Installation of fixed rails 0 08-Apr-14 A 11-Apr-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 40 of 81 Filter: All Activity

Page 41: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM5-10350 Installation of Buggy & Side shift car 0 12-Apr-14 A 17-Apr-14 A

FM5-10420 Grouting including curing time 0 17-Apr-14 A 19-Apr-14 A

FM5-10050 Fixation of rails 0 24-Mar-14 A 25-Apr-14 A

Side Guide & LooperSide Guide & Looper 0 02-Feb-14 A 04-Apr-14 AFM5-10040 Alignment & Installation of Guide Frame & Looper assembly 0 02-Feb-14 A 06-Feb-14 A

FM5-10090 Material availability at site 0 03-Feb-14 A 06-Feb-14 A

FM5-10140 Fixing of Delivery bottom stripper 0 06-Feb-14 A 08-Feb-14 A

FM5-10180 Installation of side guide 0 07-Feb-14 A 09-Feb-14 A

FM5-10210 Installation of Looper Table dr ive assembly 0 09-Feb-14 A 11-Feb-14 A

FM5-10250 Fixing of Entry top wiper 0 11-Feb-14 A 13-Feb-14 A

FM5-10270 Fixing of Delivery top stripper 0 13-Feb-14 A 15-Feb-14 A

FM5-10330 Erectiong of BUR Cooling headers 0 16-Feb-14 A 11-Mar-14 A

FM5-10480 Erection of attached piping 0 12-Mar-14 A 04-Apr-14 A

FM-5 balance erectionFM-5 balance erection 49 01-Nov-13 A 19-Aug-14FM5-10010 Installation of Attached Piping 0 01-Nov-13 A 31-Dec-13 A

FM5-10060 Installation of Mill spindle 0 02-Feb-14 A 03-Feb-14 A

FM5-10080 Installation of Leading Spindle 0 02-Feb-14 A 06-Feb-14 A

FM5-10070 Installation of Sled 0 02-Feb-14 A 11-Apr-14 A

FM5-10370 Simple Parts 0 21-Nov-13 A 23-Apr-14 A

FM5-10500 Completiong of wiring & cabling 5 18-May-14 A 06-Jul-14

FM5-10520 FM-5 Erection completion 0 19-Aug-14

Finishing Mill- 6Finishing Mill- 6 49 24-Sep-13 A 19-Aug-14FM SHOE PLATEFM SHOE PLATE 0 24-Sep-13 A 11-Feb-14 AFM6-10000 Foundation chipping & Padding(including curing) 0 24-Sep-13 A 28-Sep-13 A

FM6-10010 Installation & alignment of Shoe plate 0 07-Oct-13 A 16-Oct-13 A

FM6-10020 Grouting of shoe plate(including curing time) 0 02-Feb-14 A 06-Feb-14 A

FM6-10030 Retightening of Anchor Bolts 0 07-Feb-14 A 11-Feb-14 A

FM HOUSINGFM HOUSING 0 03-Feb-14 A 27-Feb-14 AFM6-10040 Erection of drive side housing with attached piping 0 03-Feb-14 A 06-Feb-14 A

FM6-10050 Erection of work side housing with attached piping 0 06-Feb-14 A 11-Feb-14 A

FM6-10060 Erection of bottom separator 0 11-Feb-14 A 14-Feb-14 A

FM6-10070 Erection of top separator 0 14-Feb-14 A 19-Feb-14 A

FM6-10080 Erection of AGC bracket 0 19-Feb-14 A 24-Feb-14 A

FM6-10090 Allignment of FM-7 housing 0 24-Feb-14 A 27-Feb-14 A

FM Mill properFM Mill proper 0 02-Feb-14 A 19-Mar-14 AFM6-10250 Installation of WR Changing Rail 0 02-Feb-14 A 04-Feb-14 A

FM6-10260 Installation of AGC Cylinder assembly 0 04-Feb-14 A 08-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 41 of 81 Filter: All Activity

Page 42: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM6-10270 Installation of Step liner 0 08-Feb-14 A 10-Feb-14 A

FM6-10280 Pass line adjustment 0 11-Feb-14 A 13-Feb-14 A

FM6-10290 Installation of bottom coupling support 0 13-Feb-14 A 14-Feb-14 A

FM6-10300 Instrumentation and installation 0 14-Feb-14 A 11-Mar-14 A

FM6-10310 Installation of feed roller assembly 0 14-Feb-14 A 19-Mar-14 A

FM Pinion StandFM Pinion Stand 0 02-Nov-13 A 03-Mar-14 AFM6-10100 Foundation chipping. 0 02-Nov-13 A 04-Nov-13 A

FM6-10130 Fixing and allignment of liner plate. 0 04-Nov-13 A 06-Nov-13 A

FM6-10150 Padding & curing of liner plate. 0 07-Nov-13 A 09-Nov-13 A

FM6-10190 Installation & allignment of pinion gear box. 0 19-Nov-13 A 27-Feb-14 A

FM6-10210 Grouting of pinion gear box. 0 28-Feb-14 A 03-Mar-14 A

FM BUR Changing deviceFM BUR Changing device 0 03-Feb-14 A 23-Feb-14 AFM6-10110 Material availability at site. 0 03-Feb-14 A 06-Feb-14 A

FM6-10120 Foundation chipping,fixing & alignment of liner plate 0 03-Feb-14 A 06-Feb-14 A

FM6-10140 Padding of liner plate. 0 06-Feb-14 A 11-Feb-14 A

FM6-10160 Installation of sled base 0 11-Feb-14 A 14-Feb-14 A

FM6-10170 Installation of elevating base,rails & frame 0 14-Feb-14 A 18-Feb-14 A

FM6-10180 Grouting of base including curing time 0 18-Feb-14 A 21-Feb-14 A

FM6-10200 Installation of traversing cylinder 0 21-Feb-14 A 23-Feb-14 A

FM WR Changing DeviceFM WR Changing Device 0 18-Mar-14 A 20-Apr-14 AFM6-10220 Fixation of rails 0 18-Mar-14 A 18-Mar-14 A

FM6-10230 Installation of shifting rails 0 20-Mar-14 A 22-Mar-14 A

FM6-10240 Installation of shifting cylinders & base 0 05-Apr-14 A 08-Apr-14 A

FM6-10450 Installation of fixed rails 0 09-Apr-14 A 12-Apr-14 A

FM6-10470 Installation of Buggy & Side shift car 0 13-Apr-14 A 18-Apr-14 A

FM6-10490 Grouting including curing time 0 18-Apr-14 A 20-Apr-14 A

Side Guide & LooperSide Guide & Looper 0 02-Feb-14 A 11-Mar-14 AFM6-10350 Alignment & Installation of Guide Frame & Looper assembly 0 02-Feb-14 A 06-Feb-14 A

FM6-10390 Material availability at site 0 03-Feb-14 A 06-Feb-14 A

FM6-10400 Fixing of Delivery bottom stripper 0 06-Feb-14 A 08-Feb-14 A

FM6-10410 Installation of side guide 0 07-Feb-14 A 09-Feb-14 A

FM6-10420 Installation of Looper Table dr ive assembly 0 09-Feb-14 A 11-Feb-14 A

FM6-10430 Fixing of Entry top wiper 0 11-Feb-14 A 13-Feb-14 A

FM6-10440 Fixing of Delivery top stripper 0 13-Feb-14 A 15-Feb-14 A

FM6-10500 Erection of attached piping 0 18-Feb-14 A 20-Feb-14 A

FM6-10460 Erectiong of BUR Cooling headers 0 16-Feb-14 A 11-Mar-14 A

FM-6 balance erectionFM-6 balance erection 49 01-Nov-13 A 19-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 42 of 81 Filter: All Activity

Page 43: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM6-10340 Installation of Attached Piping 0 01-Nov-13 A 20-Dec-13 A

FM6-10360 Installation of Mill spindle 0 02-Feb-14 A 03-Feb-14 A

FM6-10380 Installation of Leading Spindle 0 02-Feb-14 A 06-Feb-14 A

FM6-10370 Installation of Sled 0 02-Feb-14 A 11-Apr-14 A

FM6-10480 Simple Parts 0 21-Nov-13 A 23-Apr-14 A

FM6-10510 Completiong of wiring & cabling 7 17-May-14 A 08-Jul-14

FM6-10520 FM-6 Erection completion 0 19-Aug-14

Finishing Mill- 7Finishing Mill- 7 0 21-Sep-13 A 28-Jul-14FM SHOE PLATEFM SHOE PLATE 0 21-Sep-13 A 22-Oct-13 AFM7-10000 Foundation chipping & Padding(including curing) 0 21-Sep-13 A 25-Sep-13 A

FM7-10010 Installation & alignment of Shoe plate 0 07-Oct-13 A 16-Oct-13 A

FM7-10030 Retightening of Anchor Bolts 0 17-Oct-13 A 17-Oct-13 A

FM7-10020 Grouting of shoe plate(including curing time) 0 19-Oct-13 A 22-Oct-13 A

FM HOUSINGFM HOUSING 0 25-Oct-13 A 20-Nov-13 AFM7-10700 Erection of drive side housing with attached piping 0 25-Oct-13 A 25-Oct-13 A

FM7-10690 Erection of work side housing with attached piping 0 29-Oct-13 A 29-Oct-13 A

FM7-10710 Erection of bottom separator 0 06-Nov-13 A 06-Nov-13 A

FM7-10720 Erection of top separator 0 09-Nov-13 A 09-Nov-13 A

FM7-10730 Erection of AGC bracket 0 09-Nov-13 A 12-Nov-13 A

FM7-10740 Allignment of FM-7 housing 0 12-Nov-13 A 20-Nov-13 A

FM Mill properFM Mill proper 0 17-Dec-13 A 06-May-14 AFM7-10250 Installation of WR Changing Rail 0 17-Dec-13 A 17-Dec-13 A

FM7-10260 Installation of AGC Cylinder assembly 0 15-Apr-14 A 17-Apr-14 A

FM7-10270 Installation of Step liner 0 18-Apr-14 A 19-Apr-14 A

FM7-10280 Pass line adjustment 0 20-Apr-14 A 25-Apr-14 A

FM7-10290 Installation of bottom coupling support 0 26-Apr-14 A 26-Apr-14 A

FM7-10300 Installation of feed roller assembly 0 27-Apr-14 A 28-Apr-14 A

FM7-10310 Instrumentation and installation 0 27-Apr-14 A 06-May-14 A

FM Pinion StandFM Pinion Stand 0 02-Nov-13 A 13-Mar-14 AFM7-10390 Foundation chipping. 0 02-Nov-13 A 04-Nov-13 A

FM7-10400 Fixing and allignment of liner plate. 0 04-Nov-13 A 06-Nov-13 A

FM7-10410 Padding & curing of liner plate. 0 07-Nov-13 A 09-Nov-13 A

FM7-10420 Installation & allignment of pinion gear box. 0 19-Nov-13 A 27-Feb-14 A

FM7-10750 Grouting of pinion gear box. 0 28-Feb-14 A 13-Mar-14 A

FM BUR Changing deviceFM BUR Changing device 0 16-Nov-13 A 26-Feb-14 AFM7-10770 Foundation chipping,fixing & alignment of liner plate 0 16-Nov-13 A 23-Nov-13 A

FM7-10780 Padding of liner plate. 0 23-Nov-13 A 25-Nov-13 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 43 of 81 Filter: All Activity

Page 44: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM7-10760 Material availability at site. 0 03-Feb-14 A

FM7-10430 Installation of sled base 0 03-Feb-14 A 12-Feb-14 A

FM7-10450 Installation of elevating base,rails & frame 0 13-Feb-14 A 16-Feb-14 A

FM7-10460 Grouting of base including curing time 0 16-Feb-14 A 19-Feb-14 A

FM7-10440 Installation of traversing cylinder 0 19-Feb-14 A 21-Feb-14 A

FM7-13190 Complete completion of BUR changing device. 0 21-Feb-14 A 26-Feb-14 A

FM WR Changing DeviceFM WR Changing Device 0 18-Mar-14 A 23-Mar-14 AFM7-10470 Fixation of rails 0 18-Mar-14 A 18-Mar-14 A

FM7-10480 Installation of shifting rails 0 19-Mar-14 A 19-Mar-14 A

FM7-10490 Installation of shifting cylinders & base 0 20-Mar-14 A 20-Mar-14 A

FM7-10500 Installation of fixed rails 0 21-Mar-14 A 21-Mar-14 A

FM7-10510 Installation of Buggy & Side shift car 0 22-Mar-14 A 22-Mar-14 A

FM7-10520 Grouting including curing time 0 23-Mar-14 A 23-Mar-14 A

Side Guide & LooperSide Guide & Looper 0 03-Feb-14 A 28-Mar-14 AFM7-10610 Material availability at site 0 03-Feb-14 A 06-Feb-14 A

FM7-10550 Installation of side guide 0 07-Feb-14 A 09-Feb-14 A

FM7-10560 Installation of Looper Table dr ive assembly 0 09-Feb-14 A 11-Feb-14 A

FM7-10530 Alignment & Installation of Guide Frame & Looper assembly 0 07-Feb-14 A 11-Feb-14 A

FM7-10570 Fixing of Entry top wiper 0 11-Feb-14 A 13-Feb-14 A

FM7-10540 Fixing of Delivery bottom stripper 0 11-Feb-14 A 13-Feb-14 A

FM7-10580 Fixing of Delivery top stripper 0 13-Feb-14 A 15-Feb-14 A

FM7-10600 Erectiong of BUR Cooling headers 0 16-Feb-14 A 11-Mar-14 A

FM7-10590 Erection of attached piping 0 12-Mar-14 A 28-Mar-14 A

FM-7 balance erectionFM-7 balance erection 0 01-Nov-13 A 28-Jul-14FM7-10670 Installation of Attached Piping 0 01-Nov-13 A 10-Jan-14 A

FM7-10630 Installation of Mill spindle 0 02-Feb-14 A 03-Feb-14 A

FM7-10620 Installation of Leading Spindle 0 13-Mar-14 A 18-Mar-14 A

FM7-10640 Installation of Sled 0 02-Feb-14 A 11-Apr-14 A

FM7-10650 Simple Parts 0 21-Nov-13 A 23-Apr-14 A

FM7-10680 FM-7 Erection completion 0 28-Jul-14

Piping spool fabrication -> till flushingPiping spool fabrication -> till flushing 55 02-Feb-14 A 25-Aug-14FM-10240 Piping Spool fabrication->online flushing 55 02-Feb-14 A 25-Aug-14

ROTROT 44 03-Dec-13 A 14-Aug-14Table erection (25 Nos. of Table)Table erection (25 Nos. of Table) 44 03-Dec-13 A 14-Aug-14Table 1 - 25 TableTable 1 - 25 Table 32 03-Dec-13 A 03-Aug-14ROT-10110 Foundation chipping & padding including curing 0 07-Dec-13 A 21-Dec-13 A

ROT-10030 Tightening of foundation bolts 0 07-Jan-14 A 15-Jan-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 44 of 81 Filter: All Activity

Page 45: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

ROT-10040 Grouting of anchor followed by curing 0 15-Jan-14 A 30-Jan-14 A

ROT-10100 Measurement and checking of foundation bolts 0 03-Dec-13 A 16-Feb-14 A

ROT-10050 Precision alignment of roller assembly 0 20-Jan-14 A 16-Mar-14 A

ROT-10060 Motor erection & alignment 0 28-Jan-14 A 21-Mar-14 A

ROT-10070 Grouting of table base followed by curing 0 17-Feb-14 A 10-Apr-14 A

ROT-10120 Installation & allignment of table & table rollers 32 16-Dec-13 A 02-Aug-14

ROT-10080 Installation of attached piping & motor covers 0 22-Mar-14 A 03-Aug-14

Balance ROT equipmentBalance ROT equipment 12 24-Feb-14 A 14-Aug-14ROT-10000 Laminar strip cooling banks (Including side strip cooling)(mostly offline) 0 24-Feb-14 A 19-May-14 A

ROT-10010 Measuring House Structure 0 19-May-14 A 07-Jun-14 A

ROT-10020 Entry side guide for Down Coiler Area 12 03-Aug-14 14-Aug-14

Mill Cellar workMill Cellar work 33 25-Feb-14 A 11-Aug-14Erection of HA2 SystemErection of HA2 System 0 25-Feb-14 A 30-May-14 AMC-HA2-10000 Lowering of the tank and placing at the pedestal 0 25-Feb-14 A 25-Feb-14 A

MC-HA2-10010 Lowering of the pump unit and placing at the pedestal 0 26-Feb-14 A 26-Feb-14 A

MC-HA2-10020 Alignment of tank unit 0 27-Feb-14 A 28-Feb-14 A

MC-HA2-10030 Alignment of pump unit 0 02-Mar-14 A 03-Mar-14 A

MC-HA2-10040 Installation of filter circulation unit 0 04-Mar-14 A 13-Mar-14 A

MC-HA2-10050 Installation of return filter l ine 0 14-Mar-14 A 15-Mar-14 A

MC-HA2-10060 Installation of accumulator stand 0 15-Mar-14 A 16-Mar-14 A

MC-HA2-10070 Installation of instruments at pump and tank unit 0 16-Mar-14 A 28-Mar-14 A

MC-HA2-10080 Installation of valve Stands 0 28-Mar-14 A 30-May-14 A

Erection of HS2 SystemErection of HS2 System 0 03-Mar-14 A 31-May-14 AMC-HS2-10000 Lowering of the tank and placing at the pedestal 0 03-Mar-14 A 06-Mar-14 A

MC-HS2-10010 Lowering of the pump unit and placing at the pedestal 0 06-Mar-14 A 11-Mar-14 A

MC-HS2-10020 Alignment of tank unit 0 11-Mar-14 A 13-Mar-14 A

MC-HS2-10030 Alignment of pump unit 0 13-Mar-14 A 15-Mar-14 A

MC-HS2-10040 Installation of filter circulation unit 0 15-Mar-14 A 16-Mar-14 A

MC-HS2-10050 Installation of return filter l ine 0 16-Mar-14 A 18-Mar-14 A

MC-HS2-10060 Installation of accumulator stand 0 05-May-14 A 06-May-14 A

MC-HS2-10070 Installation of instruments at pump and tank unit 0 07-May-14 A 08-May-14 A

MC-HS2-10080 Installation of valve Stands (Incl servo valve) 0 22-Mar-14 A 31-May-14 A

Erection of FL1 SystemErection of FL1 System 2 15-May-14 A 27-Jul-14MC-FL1-10000 Lowering of the tank and placing at the pedestal 0 15-May-14 A 15-May-14 A

MC-FL1-10010 Lowering of the pump unit and placing at the pedestal 0 16-May-14 A 16-May-14 A

MC-FL1-10020 Alignment of tank unit 0 17-May-14 A 18-May-14 A

MC-FL1-10030 Alignment of pump unit 0 19-May-14 A 20-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 45 of 81 Filter: All Activity

Page 46: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MC-FL1-10060 Installation of instruments at pump and tank unit 0 23-May-14 A 31-May-14 A

MC-FL1-10040 Installation of centrifuge 1 25-Jul-14* 26-Jul-14

MC-FL1-10050 Installation of Strainer and heat exchanger 1 26-Jul-14 27-Jul-14

Erection of ML3 SystemErection of ML3 System 5 15-May-14 A 14-Jul-14MC-ML3-10000 Lowering of the tank and placing at the pedestal 0 15-May-14 A 15-May-14 A

MC-ML3-10010 Lowering of the pump unit and placing at the pedestal 0 16-May-14 A 16-May-14 A

MC-ML3-10030 Alignment of pump unit 0 18-May-14 A 18-May-14 A

MC-ML3-10060 Installation of instruments at pump and tank unit 0 23-May-14 A 30-May-14 A

MC-ML3-10070 Installation of valve Stands 0 16-May-14 A 30-May-14 A

MC-ML3-10020 Alignment of tank unit 1 10-Jul-14* 10-Jul-14

MC-ML3-10040 Installation of centrifuge 1 11-Jul-14 11-Jul-14

MC-ML3-10050 Installation of Strainer and heat exchanger 3 12-Jul-14 14-Jul-14

Erection of ML4 SystemErection of ML4 System 0 20-Apr-14 A 31-May-14 AMC-ML4-10000 Lowering of the tank and placing at the pedestal 0 20-Apr-14 A 20-Apr-14 A

MC-ML4-10010 Lowering of the pump unit and placing at the pedestal 0 07-May-14 A 07-May-14 A

MC-ML4-10020 Alignment of tank unit 0 08-May-14 A 16-May-14 A

MC-ML4-10030 Alignment of pump unit 0 16-May-14 A 18-May-14 A

MC-ML4-10040 Installation of centrifuge 0 18-May-14 A 19-May-14 A

MC-ML4-10050 Installation of Strainer and heat exchanger 0 19-May-14 A 21-May-14 A

MC-ML4-10060 Installation of instruments at pump and tank unit 0 21-May-14 A 26-May-14 A

MC-ML4-10070 Installation of valve Stands 0 01-May-14 A 31-May-14 A

Erection of RO2 SystemErection of RO2 System 27 03-May-14 A 11-Aug-14MC-RO2-10000 Lowering of the tank and placing at the pedestal 0 03-May-14 A 03-May-14 A

MC-RO2-10010 Lowering of the pump unit and placing at the pedestal 1 16-Jul-14* 16-Jul-14

MC-RO2-10020 Alignment of tank unit 8 17-Jul-14 24-Jul-14

MC-RO2-10030 Alignment of pump unit (Oil booster ,metering pump) 7 24-Jul-14 31-Jul-14

MC-RO2-10040 Installation of centrifuge 1 31-Jul-14 01-Aug-14

MC-RO2-10050 Installation of Strainer and heat exchanger 1 01-Aug-14 02-Aug-14

MC-RO2-10060 Installation of instruments at pump and tank unit 2 02-Aug-14 04-Aug-14

MC-RO2-10070 Installation of valve Stands 20 22-Jul-14 11-Aug-14

Electrical & Automation WorksElectrical & Automation Works 72 01-Jul-14 A 11-Sep-14FM-EE-10010 Electrical work(sensor erection and termination)-HA-2 27 01-Jul-14 A 28-Jul-14

FM-EE-10030 Electrical work(sensor erection and termination)-ML-3 20 15-Jul-14 03-Aug-14

FM-EE-10040 Electrical work(sensor erection and termination)-ML-4 20 15-Jul-14 03-Aug-14

FM-EE-10000 Electrical work(sensor erection and termination)-HS-2 20 15-Jul-14* 03-Aug-14

FM-EE-10020 Electrical work(sensor erection and termination)-FL-1 20 27-Jul-14 16-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 46 of 81 Filter: All Activity

Page 47: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM-EE-10050 Electrical work(sensor erection and termination)-RO 2 20 11-Aug-14 31-Aug-14

FM-EE-10060 Finish Electrical Works 0 11-Sep-14

TESTING & COMMISSIONING OF HSMTESTING & COMMISSIONING OF HSM 86 23-Jun-14 A 15-Oct-14Preconditions for individual trialPreconditions for individual trial 39 23-Jun-14 A 29-Aug-14FM-10270 Online flushing 0 23-Jun-14 A

FM-10260 Water system-ICW 0 21-Jul-14*

FM-10290 Equipment ready 0 20-Aug-14*

FM-10280 Water system-DCW 0 29-Aug-14

No Load Test of Finishing Mills and Laminar CoolingNo Load Test of Finishing Mills and Laminar Cooling 79 29-Jul-14 15-Oct-14FM-10310 Individual test of Finishing Mill Stands 64 29-Jul-14 30-Sep-14

FM-10320 Finishing Mill Stand Trials (With Motor) 15 01-Oct-14 15-Oct-14*

FM Hyd & Lub systems, FM area grease system, Descaling system, Dewatering pumpsFM Hyd & Lub systems, FM area grease system, Descaling system, Dewatering pumps 96 19-Oct-12 A 05-Oct-14Civil Building & Foundation WorksCivil Building & Foundation Works 91 19-Oct-12 A 30-Sep-14Central Oil Storage AreaCentral Oil Storage Area 91 19-Oct-12 A 30-Sep-14FM-10330 Drawing Inputs 0 19-Oct-12 A 05-Feb-14 A

FM-10350 Foundation 0 01-Jul-13 A 10-Feb-14 A

FM-10340 Column 0 29-Mar-13 A 19-Feb-14 A

FM-10360 Civil work Completion @ +8.00 M 60 21-Oct-13 A 30-Aug-14

FM-10370 Trenches & Equipment Foundation Completion 76 02-Feb-14 A 15-Sep-14

FM-10380 Flooring & Finishing Work 40 22-Aug-14 30-Sep-14*

Mechanical & Piping WorksMechanical & Piping Works 63 04-Aug-14 05-Oct-14Central Oil Storage Area-EquipmentCentral Oil Storage Area-Equipment 53 04-Aug-14 25-Sep-14FM-10390 Equipment works 53 04-Aug-14 25-Sep-14

Central Oil Storage Area-PipingCentral Oil Storage Area-Piping 48 19-Aug-14 05-Oct-14FM-10400 Piping Works 48 19-Aug-14 05-Oct-14

Grease System( area 3)Grease System( area 3) 60 02-Aug-14 30-Sep-14Erection of G10Erection of G10 60 02-Aug-14 30-Sep-14FM-10470 Erection of fi lling pump and grease pump unit 15 02-Aug-14* 16-Aug-14

FM-10480 Grease piping erection 30 17-Aug-14 15-Sep-14

FM-10490 Grease pipie flushing 15 16-Sep-14 30-Sep-14

Erection of G11Erection of G11 55 02-Aug-14 25-Sep-14FM-10500 Erection of fi lling pump and grease pump unit 15 02-Aug-14 16-Aug-14

FM-10510 Grease piping erection 30 17-Aug-14 15-Sep-14

FM-10520 Grease pipie flushing 10 16-Sep-14 25-Sep-14

Erection of G12Erection of G12 40 04-Aug-14 12-Sep-14FM-10530 Erection of fi lling pump and grease pump unit 15 04-Aug-14 18-Aug-14

FM-10540 Grease piping erection 28 06-Aug-14 02-Sep-14

FM-10550 Grease pipie flushing 10 03-Sep-14 12-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 47 of 81 Filter: All Activity

Page 48: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Erection of G13aErection of G13a 55 04-Aug-14 27-Sep-14FM-10560 Erection of fi lling pump and grease pump unit 15 04-Aug-14 18-Aug-14

FM-10570 Grease piping erection 10 08-Sep-14 17-Sep-14

FM-10580 Grease pipie flushing 10 18-Sep-14 27-Sep-14

Erection of G13Erection of G13 55 04-Aug-14 27-Sep-14FM-10590 Erection of fi lling pump and grease pump unit 15 04-Aug-14 18-Aug-14

FM-10600 Grease piping erection 30 19-Aug-14 17-Sep-14

FM-10610 Grease pipie flushing 10 18-Sep-14 27-Sep-14

Erection of G14Erection of G14 55 04-Aug-14 27-Sep-14FM-10620 Erection of fi lling pump and grease pump unit 15 04-Aug-14 18-Aug-14

FM-10630 Grease piping erection 30 19-Aug-14 17-Sep-14

FM-10640 Grease pipie flushing 10 18-Sep-14 27-Sep-14

FM Pulpits, ROT including Laminar Cooling System & SchedulingFM Pulpits, ROT including Laminar Cooling System & Scheduling 78 15-Jul-13 A 18-Sep-14Civil Building & Foundation WorksCivil Building & Foundation Works 46 15-Jul-13 A 29-Aug-14FM-10650 Civil Works-Finis hing Mill Pulpit 0 15-Jul-13 A 20-May-14 A

FM-10680 Civil Works-Roll Shop Pulpit 20 16-Jul-14 11-Aug-14

FM-10700 Civil Works-Furnac e Pulpit 30 14-Jul-14* 22-Aug-14

FM-10670 Civil Works-Coil Conveyor Pulpit 29 31-Jul-14* 28-Aug-14

FM-10660 Civil Works-Down Coiler Pulpit 30 30-Jul-14* 29-Aug-14

Structural Building & Technological WorksStructural Building & Technological Works 61 03-May-14 A 18-Sep-14FM-10710 Structural & Interior Woks -Finishing Mill Pulpit 23 03-May-14 A 30-Jul-14

FM-10730 Structural & Interior Woks -Coil Conveyor Pul pit 30 19-Jul-14 28-Aug-14

FM-10740 Structural & Interior Woks -Roll Shop Pulpit 20 11-Aug-14 05-Sep-14

FM-10760 Structural & Interior Woks -Furnace Pul pit 20 22-Aug-14* 16-Sep-14

FM-10720 Structural & Interior Woks -Down Coiler Pul pit 30 09-Aug-14* 18-Sep-14

FM-Pulpit Area:FM-Pulpit Area: 55 06-Jun-14 A 28-Aug-14FM-10780 Equipment availablity & Drawing 0 06-Jun-14 A 07-Jun-14 A

FM-10790 Fabrication & erection of cable tray & supports 22 07-Jun-14 A 01-Aug-14

FM-10770 clearance 1 31-Jul-14 01-Aug-14

FM-10820 Panel Earthing 20 12-Jul-14 07-Aug-14

FM-10810 Cable Laying up to field equipment 36 27-Jun-14 A 20-Aug-14

FM-10830 Cable Glanding & Termination 20 26-Jul-14 21-Aug-14

FM-10800 Installation of I/O Panels and HMI, Network cabinet, etc. 20 01-Aug-14* 27-Aug-14

FM-10840 Readiness Of Pulpit 0 28-Aug-14

DC's + Conveying system + Water system + Coil yards + ECR-3 + CablesDC's + Conveying system + Water system + Coil yards + ECR-3 + Cables 249 04-May-12 A 07-Mar-15

Offline inspection station, Inline shear, Pulpits, Marking ,Strapping & Weighing m/cOffline inspection station, Inline shear, Pulpits, Marking ,Strapping & Weighing m/c 107 06-Nov-13 A 25-Nov-14PulpitsPulpits 107 06-Nov-13 A 25-Nov-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 48 of 81 Filter: All Activity

Page 49: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Down Coiler-Pulpit Area:Down Coiler-Pulpit Area: 53 06-Nov-13 A 25-Nov-14DC-10020 Equipment availablity & Drawing 0 06-Nov-13 A 12-Dec-13 A

DC-10010 clearance 0 18-Sep-14 18-Sep-14

DC-10040 Installation of I/O Panels and HMI, Network cabinet, etc. 5 18-Sep-14 24-Sep-14

DC-10030 Fabrication & erection of cable tray & supports 15 18-Sep-14 08-Oct-14

DC-10060 Panel Earthing 10 08-Oct-14 21-Oct-14

DC-10050 Cable Laying up to field equipment 20 08-Oct-14 03-Nov-14

DC-10070 Cable Glanding & Termination 25 11-Oct-14 12-Nov-14

DC-10270 Panel Charging - Readiness of Pulpit 10 13-Nov-14 25-Nov-14

Coil Conveyor-Pulpit Area:Coil Conveyor-Pulpit Area: 96 11-Nov-13 A 11-Nov-14DC-10090 Equipment availablity & Drawing 0 11-Nov-13 A 16-Dec-13 A

DC-10100 Fabrication & erection of cable tray & supports 25 10-Jul-14* 11-Aug-14

DC-10080 clearance 1 28-Aug-14 29-Aug-14

DC-10130 Panel Earthing 40 12-Aug-14 04-Oct-14*

DC-10110 Installation of I/O Panels and HMI, Network cabinet, etc. 30 29-Aug-14 08-Oct-14

DC-10120 Cable Laying up to field equipment 30 05-Sep-14 14-Oct-14

DC-10140 Cable Glanding & Termination 30 19-Sep-14 28-Oct-14

DC-10310 Panel Charging - Readiness of Pulpit 10 28-Oct-14 11-Nov-14

Conveying System (Equipment incl Hydraulics, lubrication & piping)Conveying System (Equipment incl Hydraulics, lubrication & piping) 249 01-Mar-13 A 07-Mar-15Civil Building & Foundation Works-Coil Yard (Bays G-H-J / 47-60)Civil Building & Foundation Works-Coil Yard (Bays G-H-J / 47-60) 23 16-Sep-13 A 30-Jul-14Building column foundations (Under Area-II)Building column foundations (Under Area-II) 23 16-Sep-13 A 30-Jul-14CON-10000 Constn. of Column Fdns 23 16-Sep-13 A 30-Jul-14

Equipment foundations (Under Area-I & II)Equipment foundations (Under Area-I & II) 23 18-Jun-14 A 30-Jul-14CON-10010 Constn. of Eqpt Fdns 23 18-Jun-14 A 30-Jul-14

Civil Building & Foundation Work - Balance WorkCivil Building & Foundation Work - Balance Work 29 09-Apr-13 A 30-Jul-14CON-10050 Constn. of column foundation - (Required after Ist Coil Date.) 29 09-Apr-13 A 30-Jul-14

Structural Building & Technological Works-Coil Yard (Bays G-H-J/ 47-60)Structural Building & Technological Works-Coil Yard (Bays G-H-J/ 47-60) 78 01-Mar-13 A 07-Mar-15Structural work (Under Area-II)Structural work (Under Area-II) 78 01-Mar-13 A 07-Mar-15CON-10020 Fabrication 0 01-Mar-13 A 09-May-14 A

CON-10030 Erection (including sheeting) 78 31-Dec-13 A 07-Mar-15

ECR-3 & Conveying System, Cables, DC area Motors and General & special instrumentationECR-3 & Conveying System, Cables, DC area Motors and General & special instrumentation 71 23-Nov-12 A 10-Sep-14Civil Building & Foundation WorksCivil Building & Foundation Works 0 02-Aug-13 A 01-May-14 ACivil work (By TPL)Civil work (By TPL) 0 02-Aug-13 A 01-May-14 AECR3-10000 Drawing Inputs 0 02-Aug-13 A 20-Aug-13 A

ECR3-10010 Foundation 0 19-Aug-13 A 23-Dec-13 A

ECR3-10020 Column 0 08-Oct-13 A 07-Jan-14 A

ECR3-10030 Roof Slab 0 14-Jan-14 A 01-Apr-14 A

ECR3-10040 Wall and Finishing 0 01-Apr-14 A 01-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 49 of 81 Filter: All Activity

Page 50: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Mechanical & Piping WorksMechanical & Piping Works 45 23-Nov-12 A 29-Aug-14DG Room near MSDS #3DG Room near MSDS #3 45 23-Nov-12 A 29-Aug-14Installation (by others)Installation (by others) 45 23-Nov-12 A 29-Aug-14ECR3-10050 Order placement 0 23-Nov-12 A

ECR3-10060 Receipt at site 0 03-Feb-14 A 03-Feb-14 A

ECR3-10070 Installation and commissioning 45 15-Apr-14 A 29-Aug-14*

Electrical & Automation WorksElectrical & Automation Works 55 25-Apr-13 A 10-Sep-14Electrical Installation by other PDS AgenciesElectrical Installation by other PDS Agencies 55 25-Apr-13 A 10-Sep-14ECR 1ECR 1 0 02-Aug-13 A 28-May-14 AErection work at ECR 1Erection work at ECR 1 0 02-Aug-13 A 28-May-14 AECR1-10110 ECR 1 building ready for electr. erection 0 02-Aug-13 A

ECR1-10120 Electrical installation by Others (LCSSs), test & readiness LCSSs 0 03-Feb-14 A 28-May-14 A

ECR 3 (Under Area-II Civil Package)ECR 3 (Under Area-II Civil Package) 55 25-Apr-13 A 10-Sep-14Civil Work (Under Area-II Civil order)Civil Work (Under Area-II Civil order) 0 25-Apr-13 A 14-May-14 AECR3-10080 Construction of ECR-3 0 25-Apr-13 A 14-May-14 A

Erection work at ECR 3 (by others)Erection work at ECR 3 (by others) 55 07-Apr-14 A 10-Sep-14ECR3-10090 Electrical Installation 55 07-Apr-14 A 10-Sep-14

CABLE TUNNELCABLE TUNNEL 52 04-Feb-14 A 08-Sep-14Tunels ECR-1 TO ECR-2Tunels ECR-1 TO ECR-2 52 06-Feb-14 A 08-Sep-14ECR3-10100 Equipment availablity 0 06-Feb-14 A 07-Feb-14 A

ECR3-10110 Civil clearance 0 30-Apr-14 A 02-May-14 A

ECR3-10120 Tray fabrication and erection 52 02-May-14 A 08-Sep-14

Tunels ECR-2 TO Chiller PlantTunels ECR-2 TO Chiller Plant 27 02-Mar-14 A 05-Aug-14ECR3-10130 Civil clearance 0 02-Mar-14 A 03-Mar-14 A

ECR3-10140 Equipment availablity 0 10-Mar-14 A 11-Mar-14 A

ECR3-10150 Tray fabrication and erection 27 10-Apr-14 A 05-Aug-14*

Tunels MSDS3 TO ECR-2Tunels MSDS3 TO ECR-2 51 04-Feb-14 A 05-Sep-14ECR3-10160 Equipment availablity 0 15-Mar-14 A 16-Mar-14 A

ECR3-10170 Civil clearance 0 20-Mar-14 A 21-Mar-14 A

ECR3-10180 Tray fabrication and erection 51 04-Feb-14 A 05-Sep-14

Tunels ECR-2 TO WS-ECR (upto roll shop)Tunels ECR-2 TO WS-ECR (upto roll shop) 0 04-Feb-14 A 21-Jun-14 AECR3-10190 Equipment availablity 0 04-Feb-14 A 05-Feb-14 A

ECR3-10200 Civil clearance 0 15-May-14 A 15-May-14 A

ECR3-10210 Tray fabrication and erection including cabling 0 24-Mar-14 A 21-Jun-14 A

Down Coiler (Mechanical), Down Coiler Hydraulics, Grease & auxiliary system for DC area.Down Coiler (Mechanical), Down Coiler Hydraulics, Grease & auxiliary system for DC area. 212 04-May-12 A 29-Jan-15Civil Building & Foundation WorksCivil Building & Foundation Works 94 04-May-12 A 31-Oct-14B-C / 46 - 49 (Down Coiler Area)B-C / 46 - 49 (Down Coiler Area) 22 04-May-12 A 29-Jul-14DC-10150 Drawing Inputs incl. Equipment foundation 0 04-May-12 A 20-Nov-13 A

DC-10160 Building Column (B-C / 46-52) 0 02-Aug-12 A 28-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 50 of 81 Filter: All Activity

Page 51: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-10170 Equipment Fdns-DC1 22 15-Dec-12 A 29-Jul-14

DC-10180 Equipment Fdns-DC2 22 25-Dec-12 A 29-Jul-14

DC-10190 Equipment Fdns-DC3 22 03-Jan-13 A 29-Jul-14

B-C/49-52 Coil ConveyorB-C/49-52 Coil Conveyor 47 29-Mar-14 A 30-Aug-14DC-20000 Equipment Foundation - 1, 2 & 3 47 29-Mar-14 A 30-Aug-14

Area - II Civil WorkArea - II Civil Work 94 01-Sep-12 A 31-Oct-14DC-10200 Issue of LOI 0 01-Sep-12 A

DC-10210 Mobilization for Civil work 0 01-Dec-12 A 31-Dec-12 A

DC-10350 Roll Repair Shop 50 18-Jul-14* 20-Sep-14

DC-10290 33 kv Compensation Room 80 02-Jul-14* 14-Oct-14

DC-10300 HSM Laboratory 94 02-Jul-14* 31-Oct-14

Structural Building & Technological WorksStructural Building & Technological Works 174 06-Jul-12 A 23-Dec-14Area - II Structural WorkArea - II Structural Work 174 11-Sep-12 A 23-Dec-14DC-10370 LOI for Area - II Structural Work 0 11-Sep-12 A

FabricationFabrication 147 02-Aug-13 A 26-Nov-14DC-10430 Coil Yard No.1 0 02-Aug-13 A 07-Jun-14 A

DC-10450 Coil Yard No.2 & 3 90 02-Jul-14 27-Oct-14

DC-10440 TSPDL Scope 30 17-Sep-14 27-Oct-14

DC-10460 CPDY -1 (Part A) 50 07-Sep-14 27-Oct-14

DC-10470 CPDY-1 (Part B) 30 27-Oct-14 26-Nov-14

Structural ErectionStructural Erection 135 20-Feb-14 A 23-Dec-14DC-10500 Coil Yard No.1 78 20-Feb-14 A 11-Oct-14

DC-10520 TSPDL Scope 30 30-Sep-14 08-Nov-14*

DC-10560 CPDY -1 (Part A) 60 09-Sep-14 26-Nov-14

DC-10550 Coil Yard No.2 & 3 including sheeting 70 20-Sep-14 20-Dec-14

DC-10570 CPDY-1 (Part B) 45 27-Oct-14 23-Dec-14

B-C / 45 -52 (Down Coiler Area)B-C / 45 -52 (Down Coiler Area) 0 06-Jul-12 A 20-Jun-14 ADC-10580 Drawing Inputs 0 06-Jul-12 A 09-Oct-12 A

DC-10590 Fabrication 0 13-Dec-12 A 30-Dec-13 A

DC-10600 Erection (including sheeting) 0 07-Jan-13 A 20-Jun-14 A

EOT Crane (Coil Yard)EOT Crane (Coil Yard) 56 16-Aug-14 28-Oct-14EOT Crane 48/15 T (Bay G-H/43-52)EOT Crane 48/15 T (Bay G-H/43-52) 45 16-Aug-14 14-Oct-14DC-EOT-10000 EOT Erecti on 35 16-Aug-14* 30-Sep-14

DC-EOT-10010 Test & Commisioning 10 30-Sep-14 14-Oct-14

EOT Crane 48/15 T (Bay H-J/43-52)EOT Crane 48/15 T (Bay H-J/43-52) 53 16-Aug-14 24-Oct-14DC-EOT-10020 EOT Erecti on 43 16-Aug-14* 11-Oct-14

DC-EOT-10030 Test & Commisioning 10 11-Oct-14 24-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 51 of 81 Filter: All Activity

Page 52: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EOT Crane 48/15 T (Bay G-H/62-64)EOT Crane 48/15 T (Bay G-H/62-64) 40 01-Sep-14 22-Oct-14DC-EOT-10040 EOT Erecti on 20 01-Sep-14* 25-Sep-14

DC-EOT-10050 Test & Commisioning 20 25-Sep-14 22-Oct-14

EOT Crane 48/15 T (Bay H-J/62-64)EOT Crane 48/15 T (Bay H-J/62-64) 50 23-Aug-14 28-Oct-14DC-EOT-10060 EOT Erecti on 40 23-Aug-14 15-Oct-14

DC-EOT-10070 Test & Commisioning 10 15-Oct-14 28-Oct-14*

Mechanical & Piping Works-DCMechanical & Piping Works-DC 212 19-Nov-12 A 29-Jan-15EQPT RECEIPT AT SITEEQPT RECEIPT AT SITE 0 01-Jul-13 A 10-Jun-14 ADC-10610 Receipt at site (Sojitz scope) 0 01-Jul-13 A 18-Mar-14 A

DC-10620 Receipt at site (TGS scope) 0 01-Jul-13 A 10-Jun-14 A

PIPING & Auxiliary SystemsPIPING & Auxiliary Systems 60 19-Nov-12 A 16-Oct-14DC-10630 Drawing Inputs 0 19-Nov-12 A 10-Dec-13 A

DC-10640 Fabrication of Piping spools 0 01-Apr-13 A 13-Jun-14 A

DC-10650 No.1 Coil Conveyor Hydraulic System 38 30-Jul-14 17-Sep-14

DC-10660 No.2 Coil Conveyor Hydraulic System 38 07-Aug-14 26-Sep-14

DC-10670 No.1 Coil Conveyor Hydraulic System (Flushing) 15 25-Sep-14 15-Oct-14*

DC-10680 No.2 Coil Conveyor Hydraulic System (Flushing) 15 26-Sep-14 16-Oct-14*

Down Coiler AreaDown Coiler Area 212 31-May-14 A 29-Jan-15EnablersEnablers 115 31-May-14 A 25-Oct-14DC-10770 Coil Yard 1 WB conveyor Foundation 19 31-May-14 A 20-Jul-14

DC-10790 Coil Yard 2 WB conveyor Foundation 15 06-Jul-14* 20-Jul-14

DC-10690 Chain Conveyor Foundation 30 01-Aug-14 31-Aug-14

DC-10760 WB Conveyor 1 Foundation 30 08-Aug-14 07-Sep-14

DC-10780 Coil Yard 1 Crane 1 14-Oct-14 15-Oct-14

DC-10800 Coil Yard 2 Crane 1 24-Oct-14 25-Oct-14*

Safety measures For OpeningSafety measures For Opening 1 30-Jul-14 30-Jul-14DC-10810 Proper access and Preparation 1 30-Jul-14 30-Jul-14

Foundation PreparationFoundation Preparation 2 31-Jul-14 01-Aug-14DC-10820 Foundation Checking and chipping 1 31-Jul-14 31-Jul-14

DC-10830 Padding and curing 1 01-Aug-14 01-Aug-14

Down Coiler & Pinch RollDown Coiler & Pinch Roll 182 01-Aug-14 29-Jan-15No.1 Down Coiler proper - Phase - 1No.1 Down Coiler proper - Phase - 1 76 01-Aug-14 15-Oct-14DC-10840 Erection of Temporary Scaffolding & Ladder for Housing 1 01-Aug-14 01-Aug-14

DC-10860 Erection of base plate, levelling and alignment 1 02-Aug-14 02-Aug-14

DC-10970 Reducer installation 1 02-Aug-14 02-Aug-14

DC-10850 Mandrel Motor Installation 1 02-Aug-14 02-Aug-14

DC-10870 No 1 Down Coiler Delivery HSG Assembly Installation 1 03-Aug-14 03-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 52 of 81 Filter: All Activity

Page 53: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-10880 No 1 Down Coiler Delivery HSG Alignment 1 04-Aug-14 04-Aug-14

DC-10890 No 1 Down Coiler Entry HSG Assembly Installation 1 05-Aug-14 05-Aug-14

DC-10900 No 1 Down Coiler Entry HSG Alignment 1 06-Aug-14 06-Aug-14

DC-10910 Mandrel Stand Installation 1 07-Aug-14 07-Aug-14

DC-10920 Over Guide Installation 1 08-Aug-14 08-Aug-14

DC-10930 No.1 Unit Roll Frame Installation 1 09-Aug-14 09-Aug-14

DC-10940 Cylinders for unit rolls 1,2 & 3 installation 1 10-Aug-14 10-Aug-14

DC-10950 Mandrel & Mandrel Gear Unit Installation 1 11-Aug-14 11-Aug-14

DC-10960 Mandrel & Mandrel Gear Unit Alignment 1 12-Aug-14 12-Aug-14

DC-10980 Reducer alignment and grouting 1 13-Aug-14 13-Aug-14

DC-11000 Unit roll 1,2 &3 Motor Base Installation 1 14-Aug-14 14-Aug-14

DC-11010 Unit roll 1,2 &3 Motor Base Alignment and grouting 1 15-Aug-14 15-Aug-14

DC-10990 Mandrel Motor alignment and grouting 1 12-Sep-14 12-Sep-14

DC-11020 Gear Coupling Shaft Installation 1 13-Sep-14 13-Sep-14

DC-11030 Unit Roll 1,2&3 Motor Installation 1 14-Sep-14 14-Sep-14

DC-11040 Unit Roll 1,2&3 Motor Alignment 1 15-Sep-14 15-Sep-14

DC-11050 Sensor erection 1 16-Sep-14 16-Sep-14

DC-11060 Cable ducting, laying and termination 15 17-Sep-14 01-Oct-14

DC-11070 IO test 14 02-Oct-14 15-Oct-14

No.1 Pinch Roll - Phase - 1No.1 Pinch Roll - Phase - 1 56 06-Aug-14 30-Sep-14DC-11080 No.1 Pinch Roll Housing erection 3 06-Aug-14 08-Aug-14

DC-11090 No 1 Pinch Roll Housing Alignment 2 08-Aug-14 10-Aug-14

DC-11100 Erection and alignment of Spindle supports 2 10-Aug-14 12-Aug-14

DC-11110 No.1 Top-Bottom Pinc h Rolls and bottom spindle erection 3 12-Aug-14 15-Aug-14

DC-11120 Erection and alignment Top and bottom roll Motors 3 15-Aug-14 18-Aug-14

DC-11130 Top Spindle erection 1 18-Aug-14 19-Aug-14

DC-11140 Sensor erection 2 19-Aug-14 21-Aug-14

DC-11150 Cable ducting, laying and termination 15 21-Aug-14 05-Sep-14

DC-11160 IO test 25 05-Sep-14 30-Sep-14

No.2 Down Coiler proper - Phase - 1No.2 Down Coiler proper - Phase - 1 116 01-Aug-14 24-Nov-14DC-11170 Erection of Temporary Scaffolding & Ladder for Housing 1 01-Aug-14 01-Aug-14

DC-11180 Reducer installation 1 02-Aug-14 02-Aug-14

DC-11190 Mandrel Motor Installation 1 02-Aug-14 02-Aug-14

DC-11200 Erection of base plate, levelling and alignment 3 07-Aug-14 09-Aug-14

DC-11210 No 2 Down Coiler Delivery HSG Assembly Installation 3 10-Aug-14 12-Aug-14

DC-11220 No 2 Down Coiler Delivery HSG Alignment 3 13-Aug-14 15-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 53 of 81 Filter: All Activity

Page 54: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-11230 No 2 Down Coiler Entry HSG Assembly Installation 3 16-Aug-14 18-Aug-14

DC-11240 No 2 Down Coiler Entry HSG Alignment 3 19-Aug-14 21-Aug-14

DC-11250 Mandrel Stand Installation 1 15-Sep-14 15-Sep-14

DC-11260 Over Guide Installation 2 16-Sep-14 17-Sep-14

DC-11270 No.1 Unit Roll Frame Installation 2 18-Sep-14 19-Sep-14

DC-11280 Cylinders for unit rolls 1,2 & 3 installation 2 20-Sep-14 21-Sep-14

DC-11290 Mandrel & Mandrel Gear Unit Installation 3 22-Sep-14 24-Sep-14

DC-11300 Mandrel & Mandrel Gear Unit Alignment 4 25-Sep-14 28-Sep-14

DC-11310 Reducer alignment and grouting 4 29-Sep-14 02-Oct-14

DC-11330 Unit roll 1,2 &3 Motor Base Installation 2 03-Oct-14 04-Oct-14

DC-11320 Mandrel Motor alignment and grouting 4 03-Oct-14 06-Oct-14

DC-11340 Unit roll 1,2 &3 Motor Base Alignment and grouting 2 05-Oct-14 06-Oct-14

DC-11350 Gear Coupling Shaft Installation 1 07-Oct-14 07-Oct-14

DC-11360 Unit Roll 1,2&3 Motor Installation 2 11-Oct-14 12-Oct-14

DC-11370 Unit Roll 1,2&3 Motor Alignment 2 13-Oct-14 14-Oct-14

DC-11380 Sensor erection 1 15-Oct-14 15-Oct-14

DC-11390 Cable ducting, laying and termination 20 16-Oct-14 04-Nov-14

DC-11400 IO test 20 05-Nov-14 24-Nov-14*

No.2 Pinch Roll - Phase - 1No.2 Pinch Roll - Phase - 1 58 30-Aug-14 27-Oct-14DC-11410 No.2 Pinch Roll Housing erection 1 30-Aug-14 31-Aug-14

DC-11420 No 2 Pinch Roll Housing Alignment 1 31-Aug-14 01-Sep-14

DC-11430 Erection and alignment of Spindle supports 1 01-Sep-14 02-Sep-14

DC-11440 No.1 Top-Bottom Pinc h Rolls and bottom spindle erection 1 02-Sep-14 03-Sep-14

DC-11450 Erection and alignment Top and bottom roll Motors 1 03-Sep-14 04-Sep-14

DC-11460 Top Spindle erection 1 04-Sep-14 05-Sep-14

DC-11470 Sensor erection 2 20-Sep-14 22-Sep-14

DC-11480 Cable ducting, laying and termination 15 22-Sep-14 07-Oct-14

DC-11490 IO test 30 27-Sep-14 27-Oct-14

No.3 Down Coiler proper - Phase - 2No.3 Down Coiler proper - Phase - 2 167 16-Aug-14 29-Jan-15DC-11500 Erection of Temporary Scaffolding & Ladder for Housing 1 16-Aug-14 16-Aug-14

DC-11510 Reducer installation 1 17-Aug-14 17-Aug-14

DC-11520 Mandrel Motor Installation 1 17-Aug-14 17-Aug-14

DC-11530 Erection of base plate, levelling and alignment 1 22-Aug-14 22-Aug-14

DC-11540 No 3 Down Coiler Delivery HSG Assembly Installation 1 23-Aug-14 23-Aug-14

DC-11550 No 3 Down Coiler Entry HSG Assembly Installation 1 23-Aug-14 23-Aug-14

DC-11560 No 3 Down Coiler Delivery HSG Alignment 1 24-Aug-14 24-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 54 of 81 Filter: All Activity

Page 55: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-11570 No 3 Down Coiler Entry HSG Alignment 1 24-Aug-14 24-Aug-14

DC-11580 Mandrel Stand Installation 1 07-Nov-14 07-Nov-14

DC-11590 Over Guide Installation 1 08-Nov-14 08-Nov-14

DC-11600 No.1 Unit Roll Frame Installation 4 09-Nov-14 12-Nov-14

DC-11610 Cylinders for unit rolls 1,2 & 3 installation 2 13-Nov-14 14-Nov-14

DC-11620 Mandrel & Mandrel Gear Unit Installation 1 15-Nov-14 15-Nov-14

DC-11630 Mandrel & Mandrel Gear Unit Alignment 2 16-Nov-14 17-Nov-14

DC-11640 Reducer alignment and grouting 2 06-Dec-14 07-Dec-14

DC-11660 Unit roll 1,2 &3 Motor Base Installation 2 08-Dec-14 09-Dec-14

DC-11650 Mandrel Motor alignment and grouting 4 10-Dec-14 13-Dec-14

DC-11680 Gear Coupling Shaft Installation 1 14-Dec-14 14-Dec-14

DC-11670 Unit roll 1,2 &3 Motor Base Alignment and grouting 5 10-Dec-14 14-Dec-14

DC-11690 Unit Roll 1,2&3 Motor Installation 2 15-Dec-14 16-Dec-14

DC-11700 Unit Roll 1,2&3 Motor Alignment 3 17-Dec-14 19-Dec-14

DC-11710 Sensor erection 16 20-Dec-14 04-Jan-15

DC-11720 Cable ducting, laying and termination 18 05-Jan-15 22-Jan-15

DC-11730 IO test 7 23-Jan-15 29-Jan-15

No.3 Pinch Roll - Phase - 2No.3 Pinch Roll - Phase - 2 54 09-Nov-14 02-Jan-15DC-11740 No.3 Pinch Roll Housing erection 2 09-Nov-14 11-Nov-14

DC-11750 No 3 Pinch Roll Housing Alignment 2 11-Nov-14 13-Nov-14

DC-11760 Erection and alignment of Spindle supports 2 13-Nov-14 15-Nov-14

DC-11770 No.1 Top-Bottom Pinc h Rolls and bottom spindle erection 3 15-Nov-14 18-Nov-14

DC-11780 Erection and alignment Top and bottom roll Motors 3 18-Nov-14 21-Nov-14

DC-11790 Top Spindle erection 1 21-Nov-14 22-Nov-14

DC-11800 Sensor erection 16 22-Nov-14 08-Dec-14

DC-11810 Cable ducting, laying and termination 18 08-Dec-14 26-Dec-14

DC-11820 IO test 7 26-Dec-14 02-Jan-15

Attached Piping for DC proper & pinch rollAttached Piping for DC proper & pinch roll 145 19-Aug-14 11-Jan-15DC-11830 No1 DC proper and No1 PR piping 25 19-Aug-14 13-Sep-14

DC-11840 No2 DC proper and No2 PR piping 32 13-Sep-14 15-Oct-14

DC-11850 No3 DC proper and No1 PR piping 50 22-Nov-14 11-Jan-15

Coil Stripper Car And Delivery CarCoil Stripper Car And Delivery Car 97 19-Aug-14 24-Nov-14No1 Coil Stripper Car & Delivery CarNo1 Coil Stripper Car & Delivery Car 86 19-Aug-14 13-Nov-14DC-11860 Transverse Cylinder Install ation for Stripper Car 2 19-Aug-14 21-Aug-14

DC-11870 Rail and rack installation,levelling and alignment for stripper car & delivery car 2 21-Aug-14 23-Aug-14

DC-11880 Installation of Conveyor with track for stripper car and delivery car (1 each) 1 23-Aug-14 24-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 55 of 81 Filter: All Activity

Page 56: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-11890 Stripper car installation 2 24-Aug-14 26-Aug-14

DC-11900 Delivery car installation 2 26-Aug-14 28-Aug-14

DC-11910 Coil station installation and alignment 2 28-Aug-14 30-Aug-14

DC-11920 Sensor erection 15 14-Oct-14 29-Oct-14

DC-11930 Cable ducting, laying and termination 50 09-Sep-14 29-Oct-14

DC-11940 IO test 28 16-Oct-14 13-Nov-14

No2 Coil Stripper Car & Delivery CarNo2 Coil Stripper Car & Delivery Car 80 05-Sep-14 24-Nov-14DC-11950 Transverse Cylinder Install ation for Stripper Car 1 05-Sep-14 06-Sep-14

DC-11960 Rail and rack installation,levelling and alignment for stripper car & delivery car 6 06-Sep-14 12-Sep-14

DC-11970 Installation of Cableveyor with track for stripper car and delivery car (1 each) 2 12-Sep-14 14-Sep-14

DC-11980 Stripper car installation 1 14-Sep-14 15-Sep-14

DC-11990 Delivery car installation 2 15-Sep-14 17-Sep-14

DC-12000 Coil station installation and alignment 3 17-Sep-14 20-Sep-14

DC-12010 Sensor erection 15 04-Nov-14 19-Nov-14

DC-12020 Cable ducting, laying and termination 38 12-Oct-14 19-Nov-14

DC-12030 IO test 19 05-Nov-14 24-Nov-14*

No3 Coil Stripper Car & Delivery CarNo3 Coil Stripper Car & Delivery Car 28 22-Oct-14 19-Nov-14DC-12040 Transverse Cylinder Install ation for Stripper Car 2 22-Oct-14 24-Oct-14

DC-12050 Rail and rack installation,levelling and alignment for stripper car & delivery car 10 24-Oct-14 03-Nov-14

DC-12060 Installation of Conveyor with track for stripper car and delivery car (1 each) 3 03-Nov-14 06-Nov-14

DC-12070 Stripper car installation 2 06-Nov-14 08-Nov-14

DC-12080 Delivery car installation 2 08-Nov-14 10-Nov-14

DC-12090 Coil station installation and alignment 3 10-Nov-14 13-Nov-14

DC-12100 Sensor erection 5 14-Nov-14 19-Nov-14

DC-12110 Cable ducting, laying and termination 20 30-Oct-14 19-Nov-14

DC-12120 IO test 10 09-Nov-14 19-Nov-14

Coil Conveyor AreaCoil Conveyor Area 126 19-Jul-14 21-Nov-14DC-12130 Banding, Weighing and Marki ng Machines 2 19-Nov-14 21-Nov-14

Chain ConveyorChain Conveyor 61 31-Aug-14 30-Oct-14DC-12140 Foundation Checking and chipping 2 31-Aug-14 01-Sep-14

DC-12150 Padding and curing 4 02-Sep-14 05-Sep-14

DC-12160 Installation and alignment of driven frame , intermediate frame & drive frame(chain conveyor) 10 06-Sep-14 15-Sep-14

DC-12170 Installation of main rail & drive-driven shaft(chain conveyor) 5 16-Sep-14 20-Sep-14

DC-12180 Alignment of main rail & drive- driven shaft (chain conveyor) 4 21-Sep-14 24-Sep-14

DC-12190 Installation of return rail (chain conveyor) 5 25-Sep-14 29-Sep-14

DC-12200 Alignment of return rail (chain conveyor) 4 30-Sep-14 03-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 56 of 81 Filter: All Activity

Page 57: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-12210 Installation & alignment of reducer & motor 3 04-Oct-14 06-Oct-14

DC-12220 Installation of complete chain ass'y on main rail 2 07-Oct-14 08-Oct-14

DC-12230 Attached piping work 5 09-Oct-14 13-Oct-14

DC-12240 Installation of deck & sensor 2 14-Oct-14 15-Oct-14

DC-12250 Cable ducting, laying and termination 10 16-Oct-14 25-Oct-14

DC-12260 IO test 5 26-Oct-14 30-Oct-14

No.1 Walking Beam ConveyorNo.1 Walking Beam Conveyor 38 14-Sep-14 21-Oct-14DC-12270 Padding and curing 1 14-Sep-14 14-Sep-14

DC-12280 Installation and alignment of cable conveyor 1 15-Sep-14 15-Sep-14

DC-12290 Installation of equipment attached piping 1 16-Sep-14 16-Sep-14

DC-12300 Installation & alignment of top and bottom rails 1 17-Sep-14 17-Sep-14

DC-12310 Installation of supports and guides 1 18-Sep-14 18-Sep-14

DC-12320 Installation of walking beam 1 19-Sep-14 19-Sep-14

DC-12330 Installation and alignments of fixed coil skids (saddles) 1 20-Sep-14 20-Sep-14

DC-12340 Installation of stoppers 1 21-Sep-14 21-Sep-14

DC-12350 Sensor erection 5 22-Sep-14 26-Sep-14

DC-12360 Cable ducting, laying and termination 15 27-Sep-14 11-Oct-14

DC-12370 IO test 15 07-Oct-14 21-Oct-14

No.2 Walking Beam ConveyorNo.2 Walking Beam Conveyor 43 16-Sep-14 28-Oct-14DC-12380 Padding and curing 1 16-Sep-14 16-Sep-14

DC-12390 Installation and alignment of cable conveyor 1 17-Sep-14 17-Sep-14

DC-12400 Installation & alignment of top and bottom rails 4 18-Sep-14 21-Sep-14

DC-12410 Installation of supports and guides 3 22-Sep-14 24-Sep-14

DC-12420 Installation of walking beam 3 25-Sep-14 27-Sep-14

DC-12430 Installation and alignments of fixed coil skids (saddles) 2 28-Sep-14 29-Sep-14

DC-12440 Installation of stoppers 2 30-Sep-14 01-Oct-14

DC-12450 Installation of equipment attached piping 10 02-Oct-14 11-Oct-14

DC-12460 Sensor erection 15 03-Oct-14 18-Oct-14

DC-12470 Cable ducting, laying and termination 15 03-Oct-14 18-Oct-14

DC-12480 IO test 10 18-Oct-14 28-Oct-14

Shuttle CarShuttle Car 45 14-Sep-14 28-Oct-14DC-12490 Padding and curing 3 21-Sep-14 23-Sep-14

DC-12500 Installation and allignment of rail 7 24-Sep-14 30-Sep-14

DC-12510 Erection and allignment of car 7 01-Oct-14 07-Oct-14

DC-12520 Sensor erection 5 09-Oct-14 13-Oct-14

DC-12530 Cable ducting, laying and termination 30 14-Sep-14 13-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 57 of 81 Filter: All Activity

Page 58: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-12540 IO test 15 14-Oct-14 28-Oct-14

Inline Sample shearInline Sample shear 37 27-Sep-14 02-Nov-14DC-12550 Padding and curing 1 08-Oct-14 08-Oct-14

DC-12560 Installation Of Sample Shear Frame Assembly 1 09-Oct-14 09-Oct-14

DC-12570 Installation Of Sample Handling Device 1 10-Oct-14 10-Oct-14

DC-12580 Installlation of crop bucket system 1 11-Oct-14 11-Oct-14

DC-12590 Sensor erection 15 12-Oct-14 26-Oct-14

DC-12600 Cable ducting, laying and termination 30 27-Sep-14 26-Oct-14

DC-12610 IO test 7 27-Oct-14 02-Nov-14*

No.3A Walking Beam ConveyorNo.3A Walking Beam Conveyor 52 19-Jul-14 08-Sep-14DC-12620 Padding and curing 1 31-Jul-14 31-Jul-14

DC-12630 Installation and alignment of cable conveyor 1 01-Aug-14 01-Aug-14

DC-12640 Installation of equipment attached piping 1 02-Aug-14 02-Aug-14

DC-12660 Installation & alignment of top and bottom rails 1 03-Aug-14 03-Aug-14

DC-12670 Installation of supports and guides 2 04-Aug-14 05-Aug-14

DC-12680 Installation of walking beam 2 06-Aug-14 07-Aug-14

DC-12690 Installation and alignments of fixed coil skids (saddles) 2 08-Aug-14 09-Aug-14

DC-12700 Installation of stoppers 3 10-Aug-14 12-Aug-14

DC-12710 Sensor erection 5 13-Aug-14 17-Aug-14

DC-12720 Cable ducting, laying and termination 30 19-Jul-14 17-Aug-14

DC-12730 IO test 22 18-Aug-14 08-Sep-14*

No.3B Walking Beam ConveyorNo.3B Walking Beam Conveyor 76 01-Aug-14 15-Oct-14DC-12740 Foundation Checking & chipping 1 01-Aug-14 01-Aug-14

DC-12750 Padding and curing 2 01-Aug-14 04-Aug-14

DC-12760 Installation and alignment of cable conveyor 5 04-Aug-14 09-Aug-14

DC-12770 Installation of equipment attached piping 5 09-Aug-14 14-Aug-14

DC-12780 Installation & alignment of top and bottom rails 5 14-Aug-14 19-Aug-14

DC-12790 Installation of supports and guides 1 19-Aug-14 20-Aug-14

DC-12800 Installation of walking beam 1 19-Aug-14 20-Aug-14

DC-12810 Installation and alignments of fixed coil skids (saddles) 1 20-Aug-14 21-Aug-14

DC-12820 Installation of stoppers 1 20-Aug-14 21-Aug-14

DC-12830 Sensor erection 15 21-Aug-14 05-Sep-14

DC-12840 Cable ducting, laying and termination 30 05-Sep-14 05-Oct-14

DC-12850 IO test 10 05-Oct-14 15-Oct-14

No.4 Walking Beam ConveyorNo.4 Walking Beam Conveyor 76 14-Aug-14 29-Oct-14DC-12860 Foundation checking and chipping 3 14-Aug-14 20-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 58 of 81 Filter: All Activity

Page 59: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-12870 Padding and curing 3 20-Aug-14 23-Aug-14

DC-12880 Installation and alignment of cable conveyor 3 23-Aug-14 26-Aug-14

DC-12890 Installation & alignment of top and bottom rails 8 26-Aug-14 03-Sep-14

DC-12900 Installation of supports and guides 4 03-Sep-14 07-Sep-14

DC-12910 Installation of walking beam 5 07-Sep-14 12-Sep-14

DC-12920 Installation and alignments of fixed coil skids (saddles) 1 12-Sep-14 13-Sep-14

DC-12930 Installation of stoppers 1 12-Sep-14 13-Sep-14

DC-12940 Sensor erection 7 13-Sep-14 20-Sep-14

DC-12950 Installation of equipment attached piping 7 13-Sep-14 20-Sep-14

DC-12960 Cable ducting, laying and termination 20 20-Sep-14 10-Oct-14

DC-12970 IO test 20 10-Oct-14 29-Oct-14*

No.8 Walking Beam ConveyorNo.8 Walking Beam Conveyor 42 14-Aug-14 25-Sep-14DC-12980 Foundation checking and chipping 3 14-Aug-14 20-Aug-14

DC-12990 Padding and curing 3 20-Aug-14 23-Aug-14

DC-13000 Installation and alignment of cable conveyor 3 23-Aug-14 26-Aug-14

DC-13010 Installation & alignment of top and bottom rails 8 26-Aug-14 03-Sep-14

DC-13020 Installation of supports and guides 4 03-Sep-14 07-Sep-14

DC-13030 Installation of walking beam 5 07-Sep-14 12-Sep-14

DC-13040 Installation and alignments of fixed coil skids (saddles) 5 12-Sep-14 17-Sep-14

DC-13050 Installation of stoppers 3 17-Sep-14 20-Sep-14

DC-13070 Sensor erection 2 20-Sep-14 22-Sep-14

DC-13060 Installation of equipment attached piping 4 20-Sep-14 23-Sep-14

DC-13080 Cable ducting, laying and termination 4 22-Sep-14 25-Sep-14

DC-13090 IO test - not required in phase - 1 2 23-Sep-14 25-Sep-14*

No.5A Walking Beam ConveyorNo.5A Walking Beam Conveyor 63 21-Jul-14 22-Sep-14DC-13100 Foundation checking and chipping 1 21-Jul-14 22-Jul-14

DC-13110 Padding and curing 1 22-Jul-14 23-Jul-14

DC-13120 Installation and alignment of cable conveyor 1 23-Jul-14 24-Jul-14

DC-13130 Installation & alignment of top and bottom rails 1 24-Jul-14 25-Jul-14

DC-13140 Installation of supports and guides 1 25-Jul-14 26-Jul-14

DC-13150 Installation of walking beam 1 26-Jul-14 27-Jul-14

DC-13160 Installation and alignments of fixed coil skids (saddles) 1 27-Jul-14 28-Jul-14

DC-13170 Installation of stoppers 1 28-Jul-14 29-Jul-14

DC-13190 Sensor erection 2 29-Jul-14 31-Jul-14

DC-13180 Installation of equipment attached piping 5 29-Jul-14 03-Aug-14

DC-13200 Cable ducting, laying and termination 28 31-Jul-14 28-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 59 of 81 Filter: All Activity

Page 60: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-13210 IO test 25 28-Aug-14 22-Sep-14*

No.5B Walking Beam ConveyorNo.5B Walking Beam Conveyor 88 21-Jul-14 16-Oct-14DC-13220 Foundation checking and chipping 10 21-Jul-14 01-Aug-14

DC-13230 Padding and curing 10 02-Aug-14 11-Aug-14

DC-13240 Installation and alignment of cable conveyor 1 12-Aug-14 12-Aug-14

DC-13250 Installation & alignment of top and bottom rails 1 13-Aug-14 13-Aug-14

DC-13260 Installation of supports and guides 1 14-Aug-14 14-Aug-14

DC-13270 Installation of walking beam 1 15-Aug-14 15-Aug-14

DC-13280 Installation and alignments of fixed coil skids (saddles) 1 16-Aug-14 16-Aug-14

DC-13290 Installation of stoppers 1 17-Aug-14 17-Aug-14

DC-13310 Sensor erection 5 18-Aug-14 22-Aug-14

DC-13300 Installation of equipment attached piping 10 18-Aug-14 27-Aug-14

DC-13320 Cable ducting, laying and termination 10 28-Aug-14 06-Sep-14

DC-13330 IO test 21 26-Sep-14 16-Oct-14*

No.9 Walking Beam ConveyorNo.9 Walking Beam Conveyor 40 27-Aug-14 07-Oct-14DC-13340 Foundation checking and chipping 3 27-Aug-14 01-Sep-14

DC-13350 Padding and curing 3 01-Sep-14 04-Sep-14

DC-13360 Installation and alignment of cable conveyor 3 04-Sep-14 07-Sep-14

DC-13370 Installation & alignment of top and bottom rails 8 07-Sep-14 15-Sep-14

DC-13380 Installation of supports and guides 4 15-Sep-14 19-Sep-14

DC-13390 Installation of walking beam 5 19-Sep-14 24-Sep-14

DC-13400 Installation and alignments of fixed coil skids (saddles) 5 24-Sep-14 29-Sep-14

DC-13410 Installation of stoppers 3 29-Sep-14 02-Oct-14

DC-13430 Sensor erection 2 02-Oct-14 04-Oct-14

DC-13420 Installation of equipment attached piping 3 02-Oct-14 05-Oct-14

DC-13440 Cable ducting, laying and termination 2 04-Oct-14 06-Oct-14

DC-13450 IO test - Not Required in Phase - 1 1 06-Oct-14 07-Oct-14*

Down Coiler Hydraulic systemDown Coiler Hydraulic system 66 15-Aug-14 19-Oct-14Erection of Coiler Servo Hydraulic System (HS3)Erection of Coiler Servo Hydraulic System (HS3) 40 30-Aug-14 08-Oct-14DC-13460 Lowering of the tank and placing at the pedestal 1 30-Aug-14 30-Aug-14

DC-13470 Lowering of the pump unit and placing at the pedestal 1 31-Aug-14 31-Aug-14

DC-13480 Alignment of tank unit 2 01-Sep-14 02-Sep-14

DC-13490 Alignment of pump unit 2 03-Sep-14 04-Sep-14

DC-13500 Installation of filter circulation unit 2 05-Sep-14 06-Sep-14

DC-13510 Installation of return filter l ine 2 07-Sep-14 08-Sep-14

DC-13520 Installation of accumulator stand 2 09-Sep-14 10-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 60 of 81 Filter: All Activity

Page 61: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-13530 Installation of instruments at pump and tank unit 15 11-Sep-14 25-Sep-14

DC-13540 Installation of valve Stands (Incl servo valve) 20 09-Sep-14 28-Sep-14

DC-13550 Electrical work(sensor erection and termination) 10 29-Sep-14 08-Oct-14

Erection of Coiler Oil Lub System (DL)Erection of Coiler Oil Lub System (DL) 59 15-Aug-14 12-Oct-14DC-13560 Lowering of the tank and placing at the pedestal 1 15-Aug-14 15-Aug-14

DC-13570 Lowering of the pump unit and placing at the pedestal 1 16-Aug-14 16-Aug-14

DC-13580 Alignment of tank unit 2 17-Aug-14 18-Aug-14

DC-13590 Alignment of pump unit 2 19-Aug-14 20-Aug-14

DC-13600 Installation of centrifuge 1 21-Aug-14 21-Aug-14

DC-13610 Installation of Strainer and heat exchanger 1 22-Aug-14 22-Aug-14

DC-13620 Installation of instruments at pump and tank unit 2 23-Aug-14 24-Aug-14

DC-13630 Installation of valve Stands 15 25-Aug-14 08-Sep-14

DC-13640 Electrical work(sensor erection and termination) 34 09-Sep-14 12-Oct-14

Erection of No.1 Coil Conveyor Hydraulic System (HA3)Erection of No.1 Coil Conveyor Hydraulic System (HA3) 47 30-Aug-14 15-Oct-14DC-13650 Lowering of the tank and placing at the pedestal 1 30-Aug-14 30-Aug-14

DC-13660 Lowering of the pump unit and placing at the pedestal 1 31-Aug-14 31-Aug-14

DC-13670 Alignment of tank unit 5 01-Sep-14 05-Sep-14

DC-13680 Alignment of pump unit 1 06-Sep-14 06-Sep-14

DC-13690 Installation of filter circulation unit 1 07-Sep-14 07-Sep-14

DC-13700 Installation of return filter l ine 2 08-Sep-14 09-Sep-14

DC-13710 Installation of accumulator stand 1 10-Sep-14 10-Sep-14

DC-13720 Installation of instruments at pump and tank unit 2 11-Sep-14 12-Sep-14

DC-13730 Installation of valve Stands 18 13-Sep-14 30-Sep-14

DC-13740 Electrical work(sensor erection and termination) 15 01-Oct-14 15-Oct-14

Erection of NO.2 Coil Conveyor Hydraulic System (HA4)Erection of NO.2 Coil Conveyor Hydraulic System (HA4) 51 30-Aug-14 19-Oct-14DC-13750 Lowering of the tank and placing at the pedestal 1 30-Aug-14 30-Aug-14

DC-13760 Lowering of the pump unit and placing at the pedestal 2 31-Aug-14 01-Sep-14

DC-13770 Alignment of tank unit 2 02-Sep-14 03-Sep-14

DC-13780 Alignment of pump unit 1 04-Sep-14 04-Sep-14

DC-13790 Installation of filter circulation unit 1 05-Sep-14 05-Sep-14

DC-13800 Installation of return filter l ine 1 06-Sep-14 06-Sep-14

DC-13810 Installation of accumulator stand 1 07-Sep-14 07-Sep-14

DC-13820 Installation of instruments at pump and tank unit 2 08-Sep-14 09-Sep-14

DC-13830 Installation of valve Stands 20 10-Sep-14 29-Sep-14

DC-13840 Electrical work(sensor erection and termination) 20 30-Sep-14 19-Oct-14

Grease System (Area 4)Grease System (Area 4) 62 16-Aug-14 17-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 61 of 81 Filter: All Activity

Page 62: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-13850 Grease System (Area 4) 0 16-Aug-14*

DC-13860 Grease System (Area 4) 0 17-Oct-14

Erection of G15Erection of G15 62 16-Aug-14 17-Oct-14DC-13870 Erection of G15 0 16-Aug-14

DC-13880 Erection of fi lling pump and grease pump unit 5 16-Aug-14 20-Aug-14

DC-13890 Grease piping erection 10 21-Aug-14 30-Aug-14

DC-13900 Grease pipie flushing 10 31-Aug-14 09-Sep-14

DC-13910 Erection of G15 0 17-Oct-14*

Erection of G16Erection of G16 62 16-Aug-14 16-Oct-14DC-13920 Erection of fi lling pump and grease pump unit 5 16-Aug-14 20-Aug-14

DC-13930 Grease piping erection 10 21-Aug-14 30-Aug-14

DC-13940 Grease pipie flushing 10 07-Oct-14 16-Oct-14*

Erection of G17Erection of G17 57 21-Aug-14 16-Oct-14DC-13950 Erection of fi lling pump and grease pump unit 5 21-Aug-14 25-Aug-14

DC-13960 Grease piping erection 10 26-Aug-14 04-Sep-14

DC-13970 Grease pipie flushing 10 07-Oct-14 16-Oct-14*

Erection of G18Erection of G18 52 21-Aug-14 11-Oct-14DC-13980 Erection of fi lling pump and grease pump unit 10 21-Aug-14 30-Aug-14

DC-13990 Grease piping erection 10 31-Aug-14 09-Sep-14

DC-14000 Grease pipie flushing 5 07-Oct-14 11-Oct-14

Erection of G19Erection of G19 57 21-Aug-14 16-Oct-14DC-14010 Erection of fi lling pump and grease pump unit 25 21-Aug-14 14-Sep-14

DC-14020 Grease piping erection 20 15-Sep-14 04-Oct-14

DC-14030 Grease pipie flushing 10 07-Oct-14 16-Oct-14*

Erection of G20Erection of G20 57 21-Aug-14 16-Oct-14DC-14040 Erection of fi lling pump and grease pump unit 25 21-Aug-14 14-Sep-14

DC-14050 Grease piping erection 20 15-Sep-14 04-Oct-14

DC-14060 Grease pipie flushing 10 07-Oct-14 16-Oct-14*

Erection of G21Erection of G21 57 21-Aug-14 16-Oct-14DC-14070 Erection of fi lling pump and grease pump unit 25 21-Aug-14 14-Sep-14

DC-14080 Grease piping erection 20 15-Sep-14 04-Oct-14

DC-14090 Grease pipie flushing 10 07-Oct-14 16-Oct-14*

Erection of G22Erection of G22 57 21-Aug-14 16-Oct-14DC-14100 Erection of fi lling pump and grease pump unit 25 21-Aug-14 14-Sep-14

DC-14110 Grease piping erection 20 15-Sep-14 04-Oct-14

DC-14120 Grease pipie flushing 10 07-Oct-14 16-Oct-14*

Erection of G23Erection of G23 57 21-Aug-14 16-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 62 of 81 Filter: All Activity

Page 63: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DC-14130 Erection of fi lling pump and grease pump unit 25 21-Aug-14 14-Sep-14

DC-14140 Grease piping erection 20 15-Sep-14 04-Oct-14

DC-14150 Grease pipie flushing 10 07-Oct-14 16-Oct-14*

No Load Test : Down coiler areaNo Load Test : Down coiler area 15 16-Oct-14 30-Oct-14A163560 Coil conveyor individual test 5 16-Oct-14 20-Oct-14

A163550 Down coiler Individual & cold test 15 16-Oct-14 30-Oct-14

Water System to HSMWater System to HSM 57 15-Jun-14 A 08-Sep-14WS-10020 Readiness of ICW Circuit for Production 0 15-Jun-14 A

WS-10000 Avail ability of ICW MILL Water for Online Hydraulic Flushing 0 30-Jun-14 A

WS-10030 Avail ability of LCW Water for Individual Tri al 0 13-Jul-14*

WS-10050 Readiness of LCW Water for Production 0 02-Aug-14*

WS-10060 Readiness of ICW Furnace Water Circuit with EOHT for Reheating Furnace Light-up 0 03-Aug-14*

WS-10040 Avail ability of ICW Furnace Water for Cold Trial for Reheating Furnace 0 05-Aug-14*

WS-10010 Avail ability of DCW Water for Individual Tr ial 0 29-Aug-14

WS-10070 Readiness of DCW Circuit for Production 0 08-Sep-14

Motor house + Local electrics + DG + PulpitsMotor house + Local electrics + DG + Pulpits 106 05-Nov-11 A 15-Oct-14

Motor house (Electrics, L&T Engineering & Erection), Main Motors (HTC)Motor house (Electrics, L&T Engineering & Erection), Main Motors (HTC) 106 05-Nov-11 A 15-Oct-14

Civil Building & Foundation WorksCivil Building & Foundation Works 4 05-Nov-11 A 05-Jul-14C- D / 14-32 (Roughing Mill Motor area)C- D / 14-32 (Roughing Mill Motor area) 4 05-Nov-11 A 05-Jul-14MH-10010 Building Column 0 03-Feb-12 A 15-Jan-13 A

MH-10000 Drawing Inputs incl. Equipment foundation 0 05-Nov-11 A 31-Jul-13 A

MH-10020 Motor Equip foundation 4 02-May-13 A 05-Jul-14

C-D / 32-39 (Finishing Mill Motor area)C-D / 32-39 (Finishing Mill Motor area) 0 11-Jan-12 A 24-Jan-14 AMH-10040 Building Column 0 10-Apr-12 A 10-Jan-13 A

MH-10030 Drawing Inputs incl. Equipment foundation 0 11-Jan-12 A 31-Jul-13 A

MH-10060 Motor Equip foundation Grid 37-39 0 08-Apr-13 A 30-Nov-13 A

MH-10050 Motor Equip foundation Grid 32-37 0 05-Apr-13 A 24-Jan-14 A

Structural Building & Technological WorksStructural Building & Technological Works 11 16-Jun-12 A 15-Jul-14C-D / 32-39 (Finishing Mill Motor area)C-D / 32-39 (Finishing Mill Motor area) 0 16-Jun-12 A 23-May-14 AMH-10070 Drawing Inputs 0 16-Jun-12 A 27-Aug-12 A

MH-10080 Fabrication 0 15-Sep-12 A 30-Oct-13 A

MH-10090 Erection 0 12-Dec-12 A 30-Apr-14 A

MH-10240 Sheeting 0 02-Sep-13 A 23-May-14 A

EOT crane 185/25T-C-D / 32-39 (Finishing Mill Motor area)EOT crane 185/25T-C-D / 32-39 (Finishing Mill Motor area) 0 02-Aug-13 A 14-Feb-14 AMH-10100 Strl building readiness (39 - 32) for crane erection 0 02-Aug-13 A

MH-10130 Crane ready for erection 0 30-Sep-13 A

MH-10110 Erection of crane 0 30-Sep-13 A 17-Oct-13 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 63 of 81 Filter: All Activity

Page 64: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MH-10120 Test & Commisioning 0 03-Feb-14 A 14-Feb-14 A

C- D / 14-32 (Roughing Mill Motor area)C- D / 14-32 (Roughing Mill Motor area) 11 29-Aug-12 A 15-Jul-14MH-10140 Drawing Inputs 0 29-Aug-12 A 15-Jul-13 A

MH-10150 Fabrication 0 02-Feb-13 A 15-Nov-13 A

MH-10160 Erection 0 05-Mar-13 A 24-May-14 A

MH-10230 Sheeting 11 08-Jan-14 A 15-Jul-14

Mechanical & Piping WorksMechanical & Piping Works 106 02-Feb-14 A 15-Oct-14motor house erectionmotor house erection 106 02-Feb-14 A 15-Oct-14MH-10170 Installation & Comisioning of Motor house crane 1x185 Tons i n CD Bay 0 03-Feb-14 A

R1 ErectionR1 Erection 87 06-Jul-14 30-Sep-14R1 MOTOR 1R1 MOTOR 1 87 06-Jul-14 30-Sep-14MH-R1-10000 Foundation survey 1 06-Jul-14 06-Jul-14

MH-R1-10010 Padding 5 07-Jul-14 11-Jul-14

MH-R1-10020 Curing 2 12-Jul-14 13-Jul-14

MH-R1-10030 Motor assembly 10 15-Sep-14* 24-Sep-14

MH-R1-10040 Placement of rotor 1 25-Sep-14 25-Sep-14

MH-R1-10050 Rotor Alignment 2 26-Sep-14 27-Sep-14

MH-R1-10060 final grouting 1 28-Sep-14 28-Sep-14

MH-R1-10070 curing of the grouting 2 29-Sep-14 30-Sep-14

R1 Motor 2R1 Motor 2 86 06-Jul-14 29-Sep-14MH-R1-10080 Foundation survey 5 06-Jul-14 10-Jul-14

MH-R1-10090 Padding 5 11-Jul-14 15-Jul-14

MH-R1-10100 Curing 2 16-Jul-14 17-Jul-14

MH-R1-10110 motor assembly 12 10-Sep-14* 21-Sep-14

MH-R1-10120 Placement of rotor 1 22-Sep-14 22-Sep-14

MH-R1-10130 Rotor Alignment 5 23-Sep-14 27-Sep-14

MH-R1-10140 final grouting 1 28-Sep-14 28-Sep-14

MH-R1-10150 curing of the grouting 1 29-Sep-14 29-Sep-14

R2 ERECTIONR2 ERECTION 54 01-Mar-14 A 28-Aug-14R2 ERECTION MOTOR 1R2 ERECTION MOTOR 1 30 01-Mar-14 A 28-Aug-14MH-R2-10000 Foundation survey 0 01-Mar-14 A 13-Mar-14 A

MH-R2-10010 Padding 5 30-Jul-14* 03-Aug-14

MH-R2-10020 Curing 5 04-Aug-14 08-Aug-14

MH-R2-10030 MOTOR ASSEMBLY 5 09-Aug-14 13-Aug-14

MH-R2-10040 Placement of rotor 3 14-Aug-14 16-Aug-14

MH-R2-10050 rotor allignment 5 17-Aug-14 21-Aug-14

MH-R2-10060 final grouting 5 22-Aug-14 26-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 64 of 81 Filter: All Activity

Page 65: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MH-R2-10070 curing of the grouting 2 27-Aug-14 28-Aug-14

R2 ERECTION MOTOR 2R2 ERECTION MOTOR 2 42 06-Jul-14 16-Aug-14MH-R2-10080 Foundation survey 1 06-Jul-14 06-Jul-14

MH-R2-10090 Padding 2 07-Jul-14 08-Jul-14

MH-R2-10100 Curing 3 09-Jul-14 11-Jul-14

MH-R2-10110 MOTOR assembly 19 16-Jul-14 03-Aug-14

MH-R2-10120 Placement of rotor 5 04-Aug-14 08-Aug-14

MH-R2-10130 rotor allignment 2 09-Aug-14 10-Aug-14

MH-R2-10140 final grouting 3 11-Aug-14 13-Aug-14

MH-R2-10150 curing of the grouting 3 14-Aug-14 16-Aug-14

FM 1 ErectionFM 1 Erection 16 02-Feb-14 A 21-Jul-14MH-FM1-10000 Foundation survey 0 02-Feb-14 A 16-Feb-14 A

MH-FM1-10010 Padding 0 17-Feb-14 A 28-Mar-14 A

MH-FM1-10020 Curing 0 29-Mar-14 A 01-Apr-14 A

MH-FM1-10025 Placement & alignment of stator 0 10-Jun-14 A 14-Jun-14 A

MH-FM1-10030 Motor assembly 3 05-Jul-14* 07-Jul-14

MH-FM1-10040 Placement of Alignment rotor 3 08-Jul-14 10-Jul-14

MH-FM1-10050 rotor & Stator allignment 5 11-Jul-14 15-Jul-14

MH-FM1-10060 Installation of Lubrication unit 3 15-Jul-14 19-Jul-14

MH-FM1-10070 Compltion of F1 motor 1 19-Jul-14 21-Jul-14

FM 2 ERECTIONFM 2 ERECTION 22 02-Feb-14 A 26-Jul-14MH-FM2-10000 Foundation survey 0 02-Feb-14 A 16-Feb-14 A

MH-FM2-10010 Padding 0 17-Feb-14 A 14-Mar-14 A

MH-FM2-10020 Curing 0 14-Mar-14 A 25-Mar-14 A

MH-FM2-10030 Motor assembly 15 05-Jul-14 19-Jul-14

MH-FM2-10040 Placement of rotor 1 20-Jul-14 20-Jul-14

MH-FM2-10050 rotor allignment 2 21-Jul-14 22-Jul-14

MH-FM2-10060 final grouting 1 24-Jul-14 24-Jul-14

MH-FM2-10070 curing of the grouting 1 25-Jul-14 26-Jul-14

FM 3 ERECTIONFM 3 ERECTION 23 02-Feb-14 A 27-Jul-14MH-FM3-10000 Foundation survey 0 02-Feb-14 A 21-Feb-14 A

MH-FM3-10010 Padding 0 22-Feb-14 A 23-Mar-14 A

MH-FM3-10020 Curing 0 24-Mar-14 A 29-Mar-14 A

MH-FM3-10030 Motor assembly 15 05-Jul-14* 19-Jul-14

MH-FM3-10040 Placement of rotor 1 20-Jul-14 20-Jul-14

MH-FM3-10050 rotor allignment 2 21-Jul-14 22-Jul-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 65 of 81 Filter: All Activity

Page 66: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MH-FM3-10060 final grouting 1 24-Jul-14 25-Jul-14

MH-FM3-10070 curing of the grouting 2 25-Jul-14 27-Jul-14

FM 4 ERECTIONFM 4 ERECTION 44 02-Feb-14 A 17-Aug-14MH-FM4-10000 Foundation survey 0 02-Feb-14 A 14-Feb-14 A

MH-FM4-10010 Padding 0 15-Feb-14 A 06-Mar-14 A

MH-FM4-10020 Curing 0 07-Mar-14 A 26-Mar-14 A

MH-FM4-10030 motor assembly 15 05-Jul-14 19-Jul-14

MH-FM4-10040 Placement of rotor 1 23-Jul-14 24-Jul-14

MH-FM4-10050 rotor allignment 3 24-Jul-14 27-Jul-14

MH-FM4-10060 final grouting 1 13-Aug-14 14-Aug-14

MH-FM4-10070 curing of the grouting 3 14-Aug-14 17-Aug-14

FM 5ERECTIONFM 5ERECTION 23 02-Feb-14 A 27-Jul-14MH-FM5-10000 Foundation survey 0 02-Feb-14 A 17-Feb-14 A

MH-FM5-10010 Padding 0 18-Feb-14 A 17-Mar-14 A

MH-FM5-10020 Curing 0 18-Mar-14 A 16-Apr-14 A

MH-FM5-10030 motor assembly 15 05-Jul-14 19-Jul-14

MH-FM5-10040 Placement of rotor 1 20-Jul-14 20-Jul-14

MH-FM5-10050 rotor allignment 3 21-Jul-14 23-Jul-14

MH-FM5-10060 final grouting 2 24-Jul-14 25-Jul-14

MH-FM5-10070 curing of the grouting 2 26-Jul-14 27-Jul-14

FM 6 ERECTIONFM 6 ERECTION 0 02-Feb-14 A 28-Jun-14 AMH-FM6-10000 Foundation survey 0 02-Feb-14 A 16-Feb-14 A

MH-FM6-10010 Padding 0 17-Feb-14 A 08-Mar-14 A

MH-FM6-10020 Curing 0 09-Mar-14 A 07-Apr-14 A

MH-FM6-10030 motor assembly 0 05-Jun-14 A 19-Jun-14 A

MH-FM6-10040 Placement of rotor 0 21-Jun-14 A 22-Jun-14 A

MH-FM6-10050 rotor allignment 0 22-Jun-14 A 23-Jun-14 A

MH-FM6-10060 final grouting 0 25-Jun-14 A 26-Jun-14 A

MH-FM6-10070 curing of the grouting 0 27-Jun-14 A 28-Jun-14 A

FM 7 ERECTIONFM 7 ERECTION 0 15-Feb-14 A 18-Jun-14 AMH-FM7-10020 Padding 0 19-Feb-14 A 23-Feb-14 A

MH-FM7-10030 Curing 0 24-Feb-14 A 26-Feb-14 A

MH-FM7-10000 Foundation survey 0 15-Feb-14 A 01-Mar-14 A

MH-FM7-10040 Placement of rotor 0 20-May-14 A 24-May-14 A

MH-FM7-10050 rotor allignment 0 25-May-14 A 29-May-14 A

MH-FM7-10010 motor assembly 0 25-May-14 A 08-Jun-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 66 of 81 Filter: All Activity

Page 67: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

MH-FM7-10060 final grouting 0 01-Jun-14 A 17-Jun-14 A

MH-FM7-10070 curing of the grouting 0 17-Jun-14 A 18-Jun-14 A

Crop shearCrop shear 33 07-Apr-14 A 03-Aug-14MH-CS-10010 Foundation survey 0 07-Apr-14 A 09-Apr-14 A

MH-CS-10020 Padding 0 10-Apr-14 A 11-Apr-14 A

MH-CS-10030 Curing 0 12-Apr-14 A 14-Apr-14 A

MH-CS-10000 motor assembly 8 30-Jun-14 A 09-Jul-14

MH-CS-10040 Placement of rotor 8 10-Jul-14 17-Jul-14

MH-CS-10050 rotor allignment 5 18-Jul-14 23-Jul-14

MH-CS-10060 final grouting 5 24-Jul-14 29-Jul-14

MH-CS-10070 curing of the grouting 4 30-Jul-14 03-Aug-14

Individual TrialIndividual Trial 60 16-Aug-14 15-Oct-14MH-TEST-10040 Individual trials for FM 1-7 motors. 34 18-Aug-14 30-Sep-14

MH-TEST-10060 Individual trials for RM1 & RM2 motors. 35 16-Aug-14 30-Sep-14

MH-TEST-10010 Coupled Trials for Roughing Mill Main Motors 4 30-Sep-14 07-Oct-14

MH-TEST-10000 Coupled Trials for Finishing Mill Main Motors 4 12-Oct-14 15-Oct-14

Motor House Scheduling & Equipment storageMotor House Scheduling & Equipment storage 15 05-Sep-14 25-Sep-14

MH-10310 R2 delivery RTDB room 15 05-Sep-14 25-Sep-14

MH-10350 Furnace delivery RTDB room 13 08-Sep-14 25-Sep-14

MH-10320 R1 entry RTDB room 15 05-Sep-14 25-Sep-14

MH-10330 R1 delivery RTDB room 15 05-Sep-14 25-Sep-14

MH-10340 R2 entry RTDB room 15 05-Sep-14 25-Sep-14

ECR-2 + LCSS + Main & Aux Transformers + Construction PowerECR-2 + LCSS + Main & Aux Transformers + Construction Power 127 03-Jan-12 A 06-Nov-14

6.6 KV CRP, 33KV CRP & LCSS, ECR-2 (L&T Erection Engineering)6.6 KV CRP, 33KV CRP & LCSS, ECR-2 (L&T Erection Engineering) 127 03-Jan-12 A 06-Nov-14Civil Building & Foundation WorksCivil Building & Foundation Works 4 03-Jan-12 A 25-Jul-14Civil Work (L&T) for Power SystemCivil Work (L&T) for Power System 0 03-Jan-12 A 11-Jun-14 AECR 2ECR 2 0 03-Jan-12 A 11-Jun-14 ACIVILCIVIL 0 03-Jan-12 A 11-Jun-14 AEE-ECR2-10010 Base Raft 0 03-Apr-12 A 26-Oct-12 A

EE-ECR2-10000 Drawing Inputs 0 03-Jan-12 A 30-Jul-13 A

ECR Grid - 1 - 12ECR Grid - 1 - 12 0 01-Sep-12 A 20-May-14 AEE-ECR2-10020 Basement Wall & Col umn 0 01-Sep-12 A 31-Jan-13 A

EE-ECR2-10030 Ground Floor Slab 0 25-Feb-13 A 19-Jul-13 A

EE-ECR2-10040 Column 0 20-Jul-13 A 10-Feb-14 A

EE-ECR2-10050 Roof Slab 0 16-Dec-13 A 11-Mar-14 A

EE-ECR2-10060 Inside Finishing Works 0 10-Aug-13 A 20-May-14 A

Grid 22-31 (ECR Grid - 12 - 24)Grid 22-31 (ECR Grid - 12 - 24) 0 25-Jul-12 A 10-Feb-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 67 of 81 Filter: All Activity

Page 68: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-10070 Basement Wall & Col umn 0 25-Jul-12 A 31-Jan-13 A

EE-ECR2-10080 Ground Floor Slab 0 25-Jan-13 A 25-Apr-13 A

EE-ECR2-10090 Column 0 01-Jul-13 A 15-Jul-13 A

EE-ECR2-10100 Roof Slab 0 16-Jul-13 A 01-Nov-13 A

EE-ECR2-10110 Inside Finishing Works 0 25-Jul-12 A 10-Feb-14 A

Grid 31-37 (ECR Grid - 24 - 31)Grid 31-37 (ECR Grid - 24 - 31) 0 01-Sep-12 A 08-Feb-14 AEE-ECR2-10120 Basement Wall & Col umn 0 01-Sep-12 A 05-Jan-13 A

EE-ECR2-10130 Ground Floor Slab 0 02-Nov-12 A 31-Jan-13 A

EE-ECR2-10140 Column 0 22-Apr-13 A 30-Aug-13 A

EE-ECR2-10150 Roof Slab with inside Finishing 0 01-Sep-12 A 08-Feb-14 A

Grid 37-48 (ECR Grid - 31 - 47)Grid 37-48 (ECR Grid - 31 - 47) 0 01-Sep-12 A 21-May-14 AEE-ECR2-10160 Basement Wall & Col umn 0 01-Sep-12 A 15-Jan-13 A

EE-ECR2-10170 Ground Floor Slab 0 15-Mar-13 A 10-Feb-14 A

EE-ECR2-10180 Column 0 04-Sep-13 A 26-Feb-14 A

EE-ECR2-10190 Roof Slab 0 21-Oct-13 A 22-Mar-14 A

EE-ECR2-10200 Inside Finishing Works 0 01-Sep-12 A 21-May-14 A

Other Finishing WorkOther Finishing Work 0 21-May-14 A 11-Jun-14 AEE-ECR2-10210 Other Finishing Work 0 21-May-14 A 11-Jun-14 A

Cable Tunnel ECR2 to MSDS3Cable Tunnel ECR2 to MSDS3 0 16-Jan-13 A 15-Dec-13 AEE-ECR2-10220 Drawing availabilty 0 16-Jan-13 A 31-Jan-13 A

EE-ECR2-10230 Civil Works 0 05-Jul-13 A 15-Dec-13 A

Cable Tunnel ECR2 to Chiller PlantCable Tunnel ECR2 to Chiller Plant 0 02-Aug-13 A 20-Feb-14 AEE-ECR2-10240 Civil Works Drawing availabi lty 0 02-Aug-13 A 05-Dec-13 A

EE-ECR2-10250 Civil Works 0 10-Feb-14 A 20-Feb-14 A

Cable Tunnel ECR2 to WS-ECR (upto roll shop)Cable Tunnel ECR2 to WS-ECR (upto roll shop) 0 02-Aug-13 A 15-May-14 AEE-ECR2-10260 Drawing availabilty 0 02-Aug-13 A 05-Dec-13 A

EE-ECR2-10270 Civil Works 0 10-Feb-14 A 15-May-14 A

ECR 2 Civil ClearenecECR 2 Civil Clearenec 4 01-Jul-13 A 25-Jul-14EE-ECR2-10290 Civil clearance for 22 to 31 Basement - Mill Grid - 12 to 24 0 01-Jul-13 A

EE-ECR2-10280 Civil clearance for 31 to 37 Basement - Mill Grid - 24 to 31 0 02-Aug-13 A

EE-ECR2-10320 Civil clearance for 22 to 31 Ground Floor - Mill Grid - 12 to 24 0 12-Sep-13 A

EE-ECR2-10310 Civil clearance for 37 to 48 Basement - Mill Grid - 31 to 37 0 11-Feb-14 A

EE-ECR2-10330 Civil clearance for 31 to 37 Ground Floor - Mill Grid - 24 to 31 0 19-Feb-14 A

EE-ECR2-10300 Civil clearance for 14 to 22 Basement - Mill Grid - 1 to 12 0 26-Mar-14 A

EE-ECR2-10340 Civil clearance for 14 to 22 Ground Floor - Mill Grid - 1 to 12 0 20-Jul-14

EE-ECR2-10350 Civil clearance for 37 to 48 Ground Floor - Mill Grid - 31 to 37 0 25-Jul-14*

Electrical & Automation WorksElectrical & Automation Works 127 02-Aug-13 A 06-Nov-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 68 of 81 Filter: All Activity

Page 69: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Electrical automation in ECR 2Electrical automation in ECR 2 127 02-Aug-13 A 06-Nov-14Mill ECR 2 GRID 14 TO 22 (Mill Grid - 1 - 12)Mill ECR 2 GRID 14 TO 22 (Mill Grid - 1 - 12) 127 15-Sep-13 A 06-Nov-14SMALL DRIVESSMALL DRIVES 108 21-Jul-14 06-Nov-14EE-ECR2-10360 RM Section 1 Inverter MCCB 2 24-Jul-14 26-Jul-14

EE-ECR2-10370 RM Section 2 Inverter MCCB 6 09-Oct-14 16-Oct-14

RM Section 1 ConverterRM Section 1 Converter 4 21-Jul-14 24-Jul-14EE-ECR2-10380 RM Section 1 Converter (A-1, A-2 and distribution) 2 21-Jul-14 22-Jul-14

EE-ECR2-10390 RM Section 1 Converter (B-1, B-2) 2 23-Jul-14 24-Jul-14

R1 Entry table section-1,2,3, Incoming and R1 screw down (WS, DS, LS)R1 Entry table section-1,2,3, Incoming and R1 screw down (WS, DS, LS) 13 27-Jul-14 08-Aug-14EE-ECR2-10400 R1 Entry table section-1 2 27-Jul-14 28-Jul-14

EE-ECR2-10410 R1 Entry table section-2 2 29-Jul-14 30-Jul-14

EE-ECR2-10420 R1 Entry table section-3 2 31-Jul-14 01-Aug-14

EE-ECR2-10430 R1 screw down (WS) and Incoming 1 02-Aug-14 02-Aug-14

EE-ECR2-10440 R1 screw down (DS) 1 03-Aug-14 03-Aug-14

EE-ECR2-10450 R1 screw down (LS) 5 04-Aug-14 08-Aug-14

R1 Delivery table section-1,2, Incoming and R2 approach table section 1,2,3R1 Delivery table section-1,2, Incoming and R2 approach table section 1,2,3 50 09-Aug-14 27-Sep-14EE-ECR2-10460 R1 Delivery table section-1 10 09-Aug-14 18-Aug-14

EE-ECR2-10470 R1 Delivery table section-2 10 19-Aug-14 28-Aug-14

EE-ECR2-10480 R2 Approach table section-1 and Incoming 10 29-Aug-14 07-Sep-14

EE-ECR2-10490 R2 Approach table section-2 10 08-Sep-14 17-Sep-14

EE-ECR2-10500 R2 Approach table section-3 10 18-Sep-14 27-Sep-14

RM Section 2 ConverterRM Section 2 Converter 11 28-Sep-14 09-Oct-14EE-ECR2-10510 RM Section 2 Converter (A-1, A-2 and distribution) 5 28-Sep-14 02-Oct-14

EE-ECR2-10520 RM Section 2 Converter (B-1, B-2) 6 03-Oct-14 09-Oct-14

R2 Entry table section-1,2,3, Incoming and R2 screw down (WS, DS)R2 Entry table section-1,2,3, Incoming and R2 screw down (WS, DS) 5 16-Oct-14 21-Oct-14EE-ECR2-10530 R2 screw down (DS) 1 16-Oct-14 17-Oct-14

EE-ECR2-10540 R2 screw down (WS) 1 17-Oct-14 18-Oct-14

EE-ECR2-10550 R2 Entry table section-3 and Incoming 1 18-Oct-14 19-Oct-14

EE-ECR2-10560 R2 Entry table section-2 1 19-Oct-14 20-Oct-14

EE-ECR2-10570 R2 Entry table section-1 1 20-Oct-14 21-Oct-14

R2 approach table section 4,5,6,7,8,9 and IncomingR2 approach table section 4,5,6,7,8,9 and Incoming 6 21-Oct-14 27-Oct-14EE-ECR2-10580 R2 approach table section-9 1 21-Oct-14 22-Oct-14

EE-ECR2-10590 R2 approach table section-8 1 22-Oct-14 23-Oct-14

EE-ECR2-10600 R2 approach table section-7 1 23-Oct-14 24-Oct-14

EE-ECR2-10610 R2 approach table section-6 and Incoming 1 24-Oct-14 25-Oct-14

EE-ECR2-10620 R2 approach table section-5 1 25-Oct-14 26-Oct-14

EE-ECR2-10630 R2 approach table section-4 1 26-Oct-14 27-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 69 of 81 Filter: All Activity

Page 70: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Furnace delivery and SSP ConverterFurnace delivery and SSP Converter 2 27-Oct-14 29-Oct-14EE-ECR2-10640 Furnace delivery and SSP s ection converter A-1, A-2 and distribution 1 27-Oct-14 28-Oct-14

EE-ECR2-10650 Furnace delivery and SSP s ection converter B-1, B-2 1 28-Oct-14 29-Oct-14

Furnace delivery and SSP InverterFurnace delivery and SSP Inverter 8 29-Oct-14 06-Nov-14EE-ECR2-10660 Furnace delivery section-4 1 29-Oct-14 30-Oct-14

EE-ECR2-10670 Furnace delivery section-3 1 30-Oct-14 31-Oct-14

EE-ECR2-10680 Furnace delivery section-2 1 31-Oct-14 01-Nov-14

EE-ECR2-10690 Furnace delivery section-1 1 01-Nov-14 02-Nov-14

EE-ECR2-10700 HSB table and Incoming 1 02-Nov-14 03-Nov-14

EE-ECR2-10710 SSP area table 1 03-Nov-14 04-Nov-14

EE-ECR2-10720 SSP entry table 1 04-Nov-14 05-Nov-14

EE-ECR2-10730 SSP delivery fix table 1 05-Nov-14 06-Nov-14

MCCMCC 9 21-Jul-14 29-Jul-14MCC-2 (RM MCC)MCC-2 (RM MCC) 3 21-Jul-14 23-Jul-14EE-ECR2-10740 SS-1 1 21-Jul-14 21-Jul-14

EE-ECR2-10750 SS-2 1 22-Jul-14 22-Jul-14

EE-ECR2-10760 SS-3 1 23-Jul-14 23-Jul-14

MCC-3 (RM MCC) with interface panelMCC-3 (RM MCC) with interface panel 6 24-Jul-14 29-Jul-14EE-ECR2-10770 SS-1 2 24-Jul-14 25-Jul-14

EE-ECR2-10780 SS-2 1 26-Jul-14 26-Jul-14

EE-ECR2-10790 SS-3 1 27-Jul-14 27-Jul-14

EE-ECR2-10800 SS-4 1 28-Jul-14 28-Jul-14

EE-ECR2-10810 SS-5 1 29-Jul-14 29-Jul-14

EM MCCEM MCC 3 30-Jul-14 01-Aug-14EE-ECR2-10820 SS-1 1 30-Jul-14 30-Jul-14

EE-ECR2-10830 SS-2 1 31-Jul-14 31-Jul-14

EE-ECR2-10840 SS-3 1 01-Aug-14 01-Aug-14

Other Electrical equipmentsOther Electrical equipments 105 15-Sep-13 A 14-Oct-14EE-ECR2-10850 Cable tray support & Cable tray erection 0 15-Sep-13 A 21-Jun-14 A

EE-ECR2-10870 UPS 15 02-Aug-14 16-Aug-14

EE-ECR2-10880 DL (Furnace) 1 17-Aug-14 17-Aug-14

EE-ECR2-10860 Cable laying 47 10-May-14 A 18-Aug-14

EE-ECR2-10900 MAIN DS- 5 sets 7 12-Aug-14 18-Aug-14

EE-ECR2-10890 IF 1 18-Aug-14 18-Aug-14

EE-ECR2-10910 Cable termination 30 05-Sep-14 04-Oct-14

EE-ECR2-10920 Panel testing 20 25-Sep-14 14-Oct-14

Mill ECR 2 GRID 22 TO 31 (Mill Grid - 12 - 24)Mill ECR 2 GRID 22 TO 31 (Mill Grid - 12 - 24) 69 02-Aug-13 A 09-Sep-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 70 of 81 Filter: All Activity

Page 71: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

DIRECT INVERTER DRIVEDIRECT INVERTER DRIVE 47 03-Apr-14 A 17-Aug-14DIRECT INVERTER DRIVE 1DIRECT INVERTER DRIVE 1 0 03-Apr-14 A 02-May-14 AEE-ECR2-10930 Panel 1 0 03-Apr-14 A 17-Apr-14 A

EE-ECR2-10940 Panel 2 0 18-Apr-14 A 02-May-14 A

DIRECT INVERTER DRIVE 2DIRECT INVERTER DRIVE 2 0 03-May-14 A 11-Jun-14 AEE-ECR2-10950 Panel 1 0 03-May-14 A 27-May-14 A

EE-ECR2-10960 Panel 2 0 28-May-14 A 11-Jun-14 A

DIRECT INVERTER DRIVE 3DIRECT INVERTER DRIVE 3 27 12-Jun-14 A 28-Jul-14EE-ECR2-10970 Panel 1 2 12-Jun-14 A 03-Jul-14

EE-ECR2-10980 Panel 2 25 04-Jul-14 28-Jul-14

DIRECT INVERTER DRIVE 4DIRECT INVERTER DRIVE 4 10 29-Jul-14 07-Aug-14EE-ECR2-10990 Panel 1 5 29-Jul-14 02-Aug-14

EE-ECR2-11000 Panel 2 5 03-Aug-14 07-Aug-14

DIRECT INVERTER DRIVE 5DIRECT INVERTER DRIVE 5 10 08-Aug-14 17-Aug-14EE-ECR2-11010 Panel 1 5 08-Aug-14 12-Aug-14

EE-ECR2-11020 Panel 2 5 13-Aug-14 17-Aug-14

SMALL DRIVESSMALL DRIVES 2 10-Apr-14 A 20-Aug-14EE-ECR2-11030 RM Section 3 Inverter MCCB 2 18-Aug-14 20-Aug-14

RM Section 3 ConverterRM Section 3 Converter 0 10-Apr-14 A 19-Apr-14 AEE-ECR2-11040 RM Section 3 Converter (A-1, A-2 and distribution) 0 10-Apr-14 A 14-Apr-14 A

EE-ECR2-11050 RM Section 1 Converter (B-1, B-2) 0 15-Apr-14 A 19-Apr-14 A

R2 Delivery table section-1,2,3,5,6,7 and IncomingR2 Delivery table section-1,2,3,5,6,7 and Incoming 0 20-Apr-14 A 24-May-14 AEE-ECR2-11060 R2 Delivery table section-7 0 20-Apr-14 A 24-Apr-14 A

EE-ECR2-11070 R2 Delivery table section-6 0 25-Apr-14 A 29-Apr-14 A

EE-ECR2-11080 R2 Delivery table section-5 0 30-Apr-14 A 04-May-14 A

EE-ECR2-11090 R2 Delivery table section-4 and Incoming 0 05-May-14 A 09-May-14 A

EE-ECR2-11100 R2 Delivery table section-3 0 10-May-14 A 14-May-14 A

EE-ECR2-11110 R2 Delivery table section-2 0 15-May-14 A 19-May-14 A

EE-ECR2-11120 R2 Delivery table section-1 0 20-May-14 A 24-May-14 A

MCCMCC 0 02-Mar-14 A 19-May-14 AMCC-4 (RM MCC)MCC-4 (RM MCC) 0 02-Mar-14 A 10-Apr-14 AEE-ECR2-11150 SS-3 0 02-Mar-14 A 16-Mar-14 A

EE-ECR2-11130 SS-1 0 17-Mar-14 A 26-Mar-14 A

EE-ECR2-11140 SS-2 0 27-Mar-14 A 10-Apr-14 A

MCC-5 (RM MCC) with interface panelMCC-5 (RM MCC) with interface panel 0 17-Mar-14 A 19-May-14 AEE-ECR2-11160 SS-1 0 17-Mar-14 A 26-Mar-14 A

EE-ECR2-11170 SS-2 0 27-Mar-14 A 31-Mar-14 A

EE-ECR2-11180 SS-3 0 01-Apr-14 A 05-Apr-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 71 of 81 Filter: All Activity

Page 72: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-11190 SS-4 0 06-Apr-14 A 10-Apr-14 A

EE-ECR2-11200 SS-5 0 11-Apr-14 A 15-Apr-14 A

EE-ECR2-11210 SS-6 0 16-Apr-14 A 20-Apr-14 A

EE-ECR2-11220 SS-7 0 21-Apr-14 A 26-Apr-14 A

EE-ECR2-11230 SS-8 0 27-Apr-14 A 07-May-14 A

EE-ECR2-11240 SS-9 0 08-May-14 A 19-May-14 A

EM MCCEM MCC 0 28-Feb-14 A 05-May-14 AEE-ECR2-11250 SS-1 0 28-Feb-14 A 22-Mar-14 A

EE-ECR2-11260 SS-2 0 22-Mar-14 A 26-Mar-14 A

EE-ECR2-11270 SS-3 0 27-Mar-14 A 25-Apr-14 A

EE-ECR2-11280 UPS 0 26-Apr-14 A 05-May-14 A

PLC (RM)PLC (RM) 0 07-May-14 A 11-May-14 AEE-ECR2-11290 PLC-1 &2 0 07-May-14 A 09-May-14 A

EE-ECR2-11300 PLC-3,4 & 5 0 10-May-14 A 11-May-14 A

MV (RM)MV (RM) 0 15-May-14 A 26-May-14 AEE-ECR2-11310 Panel 1 0 15-May-14 A 15-May-14 A

EE-ECR2-11320 Panel 2 0 20-May-14 A 20-May-14 A

EE-ECR2-11330 Panel 3 0 21-May-14 A 21-May-14 A

EE-ECR2-11340 Panel 4 0 22-May-14 A 22-May-14 A

EE-ECR2-11350 Panel 5 0 23-May-14 A 23-May-14 A

EE-ECR2-11360 Panel 6 0 24-May-14 A 26-May-14 A

RY (RM)RY (RM) 0 15-May-14 A 17-May-14 AEE-ECR2-11370 Panel 1 0 15-May-14 A 15-May-14 A

EE-ECR2-11380 Panel 2 0 16-May-14 A 17-May-14 A

LV (RM)LV (RM) 0 18-May-14 A 24-May-14 AEE-ECR2-11390 Panel 1 0 18-May-14 A 18-May-14 A

EE-ECR2-11400 Panel 2 0 23-May-14 A 24-May-14 A

Other Electrical equipmentOther Electrical equipment 69 02-Aug-13 A 09-Sep-14EE-ECR2-11410 Cable tray support & Cable tray erection 0 02-Aug-13 A 02-May-14 A

EE-ECR2-11440 MAIN DS 5 sets 0 04-Jun-14 A 10-Jun-14 A

EE-ECR2-11450 DL (RM) 0 11-Jun-14 A 11-Jun-14 A

EE-ECR2-11460 IF (RM) 0 12-Jun-14 A 12-Jun-14 A

EE-ECR2-11420 Cable laying 57 03-May-14 A 27-Aug-14

EE-ECR2-11430 Cable termination 64 21-Jun-14 A 03-Sep-14

EE-ECR2-11470 Panel Testing 20 20-Aug-14 09-Sep-14

Mill ECR 2 grid 31 to 37 (Mill Grid - 24 - 31)Mill ECR 2 grid 31 to 37 (Mill Grid - 24 - 31) 20 10-Oct-13 A 22-Jul-14SMALL DRIVESSMALL DRIVES 0 19-Feb-14 A 08-Mar-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 72 of 81 Filter: All Activity

Page 73: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

FM Section ConverterFM Section Converter 0 19-Feb-14 A 23-Feb-14 AEE-ECR2-11480 FM Section Converter (A-1, A-2 and distribution) 0 19-Feb-14 A 21-Feb-14 A

EE-ECR2-11490 FM Section Converter (B-1, B-2) 0 21-Feb-14 A 23-Feb-14 A

FM Delay table section-1,2,3,4 and IncomingFM Delay table section-1,2,3,4 and Incoming 0 23-Feb-14 A 02-Mar-14 AEE-ECR2-11500 FM Delay table section-1 0 23-Feb-14 A 24-Feb-14 A

EE-ECR2-11510 FM Delay table section-2 0 24-Feb-14 A 25-Feb-14 A

EE-ECR2-11520 FM Delay table section-3 and Incoming 0 25-Feb-14 A 27-Feb-14 A

EE-ECR2-11530 FM Delay table section-4 0 27-Feb-14 A 02-Mar-14 A

FM section inverter (MCCB)FM section inverter (MCCB) 0 04-Mar-14 A 08-Mar-14 AEE-ECR2-11540 FM Section Inverter (MCCB)-5 0 04-Mar-14 A 04-Mar-14 A

EE-ECR2-11550 FM section inverter (MCCB)-4 0 05-Mar-14 A 05-Mar-14 A

EE-ECR2-11560 FM section inverter (MCCB)-3 0 06-Mar-14 A 06-Mar-14 A

EE-ECR2-11570 FM section inverter (MCCB)-2 0 07-Mar-14 A 07-Mar-14 A

EE-ECR2-11580 FM section inverter (MCCB)-1 0 08-Mar-14 A 08-Mar-14 A

MCCMCC 0 19-Feb-14 A 07-Apr-14 AMCC-6 (FM MCC)MCC-6 (FM MCC) 0 19-Feb-14 A 23-Mar-14 AEE-ECR2-11630 SS-1 0 19-Feb-14 A 03-Mar-14 A

EE-ECR2-11650 SS-2 0 03-Mar-14 A 13-Mar-14 A

EE-ECR2-11660 SS-3 0 13-Mar-14 A 23-Mar-14 A

MCC-7 (FM MCC) with interface panelMCC-7 (FM MCC) with interface panel 0 02-Mar-14 A 31-Mar-14 AEE-ECR2-11710 SS-4 0 02-Mar-14 A 05-Mar-14 A

EE-ECR2-11680 SS-1 0 22-Mar-14 A 26-Mar-14 A

EE-ECR2-11690 SS-2 0 26-Mar-14 A 30-Mar-14 A

EE-ECR2-11700 SS-3 0 30-Mar-14 A 31-Mar-14 A

MCC-8 (FM MCC)MCC-8 (FM MCC) 0 06-Mar-14 A 19-Mar-14 AEE-ECR2-11720 SS-1 0 06-Mar-14 A 08-Mar-14 A

EE-ECR2-11730 SS-2 0 09-Mar-14 A 12-Mar-14 A

EE-ECR2-11740 SS-3 0 13-Mar-14 A 14-Mar-14 A

EE-ECR2-11750 SS-4 0 15-Mar-14 A 16-Mar-14 A

EE-ECR2-11760 SS-5 0 17-Mar-14 A 19-Mar-14 A

MCC-9 (FM MCC) with interface panelMCC-9 (FM MCC) with interface panel 0 20-Mar-14 A 30-Mar-14 AEE-ECR2-11780 SS-1 0 20-Mar-14 A 20-Mar-14 A

EE-ECR2-11790 SS-2 0 21-Mar-14 A 21-Mar-14 A

EE-ECR2-11800 SS-3 0 22-Mar-14 A 22-Mar-14 A

EE-ECR2-11820 SS-4 0 23-Mar-14 A 23-Mar-14 A

EE-ECR2-11840 SS-5 0 24-Mar-14 A 24-Mar-14 A

EE-ECR2-11850 SS-6 0 25-Mar-14 A 26-Mar-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 73 of 81 Filter: All Activity

Page 74: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-11860 SS-7 0 26-Mar-14 A 27-Mar-14 A

EE-ECR2-11890 SS-8 0 27-Mar-14 A 30-Mar-14 A

MCC-10 (FM MCC) with interface panelMCC-10 (FM MCC) with interface panel 0 30-Mar-14 A 07-Apr-14 AEE-ECR2-11920 SS-1 0 30-Mar-14 A 31-Mar-14 A

EE-ECR2-11940 SS-2 0 31-Mar-14 A 01-Apr-14 A

EE-ECR2-11970 SS-3 0 01-Apr-14 A 02-Apr-14 A

EE-ECR2-11980 SS-4 0 02-Apr-14 A 03-Apr-14 A

EE-ECR2-11990 SS-5 0 03-Apr-14 A 04-Apr-14 A

EE-ECR2-12010 SS-6 0 04-Apr-14 A 07-Apr-14 A

EM MCCEM MCC 0 07-Apr-14 A 12-Apr-14 AEE-ECR2-12580 SS-1 0 07-Apr-14 A 08-Apr-14 A

EE-ECR2-12600 SS-2 0 08-Apr-14 A 09-Apr-14 A

EE-ECR2-12610 SS-3 0 09-Apr-14 A 12-Apr-14 A

PLC(FM)PLC(FM) 0 12-May-14 A 22-May-14 APLC 1 (FM)PLC 1 (FM) 0 12-May-14 A 16-May-14 AEE-ECR2-12890 Panel 1 &2 0 12-May-14 A 12-May-14 A

EE-ECR2-12910 Panel 3,4 & 5 0 13-May-14 A 14-May-14 A

EE-ECR2-12950 Panel 6 & 7 0 15-May-14 A 16-May-14 A

PLC 2 (FM)PLC 2 (FM) 0 17-May-14 A 22-May-14 AEE-ECR2-12980 Panel 1 &2 0 17-May-14 A 18-May-14 A

EE-ECR2-13020 Panel 3 & 4 0 19-May-14 A 20-May-14 A

EE-ECR2-13050 Panel 5 & 6 0 21-May-14 A 22-May-14 A

MV (FM)MV (FM) 0 28-May-14 A 08-Jun-14 AMV-1 (FM)MV-1 (FM) 0 28-May-14 A 03-Jun-14 AEE-ECR2-13150 Panel 1 0 28-May-14 A 28-May-14 A

EE-ECR2-13170 Panel 2 0 29-May-14 A 29-May-14 A

EE-ECR2-13190 Panel 3 0 30-May-14 A 30-May-14 A

EE-ECR2-13210 Panel 4 0 31-May-14 A 31-May-14 A

EE-ECR2-13230 Panel 5 0 01-Jun-14 A 01-Jun-14 A

EE-ECR2-13250 Panel 6 0 02-Jun-14 A 03-Jun-14 A

MV-2 (FM)MV-2 (FM) 0 04-Jun-14 A 08-Jun-14 AEE-ECR2-13290 Panel 1 0 04-Jun-14 A 04-Jun-14 A

EE-ECR2-13310 Panel 2 0 05-Jun-14 A 05-Jun-14 A

EE-ECR2-13330 Panel 3 0 06-Jun-14 A 06-Jun-14 A

EE-ECR2-13350 Panel 4 0 07-Jun-14 A 08-Jun-14 A

RY (FM)RY (FM) 0 02-May-14 A 25-May-14 AEE-ECR2-13410 Panel 2 0 02-May-14 A 02-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 74 of 81 Filter: All Activity

Page 75: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-13370 Panel 1 0 24-May-14 A 25-May-14 A

LV (FM)LV (FM) 0 02-May-14 A 27-May-14 AEE-ECR2-13790 Panel 2 0 02-May-14 A 02-May-14 A

EE-ECR2-13770 Panel 3 0 03-May-14 A 03-May-14 A

EE-ECR2-13780 Panel 1 0 26-May-14 A 27-May-14 A

Other Electrical equipmentOther Electrical equipment 20 10-Oct-13 A 22-Jul-14EE-ECR2-13420 BR (FM) 0 03-May-14 A 04-May-14 A

EE-ECR2-12660 UPS 0 02-Apr-14 A 06-May-14 A

EE-ECR2-11600 Cable tray support & Cable tray erection 0 10-Oct-13 A 22-May-14 A

EE-ECR2-13080 DL (FM) 0 23-May-14 A 24-May-14 A

EE-ECR2-13100 IF 0 25-May-14 A 26-May-14 A

EE-ECR2-11620 Cable laying 4 11-Feb-14 A 05-Jul-14

EE-ECR2-13750 MAIN DS-15 sets 7 29-Jun-14 A 09-Jul-14

EE-ECR2-13040 Cable termination 14 26-Apr-14 A 16-Jul-14

EE-ECR2-13630 Panel Testing 20 03-May-14 A 22-Jul-14

Mill ECR 2 grid 37 to 48 (Mill Grid - 31 - 37)Mill ECR 2 grid 37 to 48 (Mill Grid - 31 - 37) 104 11-Feb-14 A 14-Oct-14SMALL DRIVESSMALL DRIVES 16 25-Jul-14 10-Aug-14EE-ECR2-12020 DC section-1 inverter (MCCB) 1 04-Aug-14 05-Aug-14

DC section-1DC section-1 10 25-Jul-14 03-Aug-14EE-ECR2-12030 DC Section-1 Converter (A-1, A-2 and distribution) 5 25-Jul-14 29-Jul-14

EE-ECR2-12040 DC Section-1 Converter (B-1, B-2) 5 30-Jul-14 03-Aug-14

Run Out table section-1,2,3,4,5,6,7 and IncomingRun Out table section-1,2,3,4,5,6,7 and Incoming 0 10-Aug-14 10-Aug-14EE-ECR2-12440 Run Out table section-7 0 10-Aug-14 10-Aug-14

EE-ECR2-12380 Run Out table section-1 0 10-Aug-14 10-Aug-14

EE-ECR2-12390 Run Out table section-2 0 10-Aug-14 10-Aug-14

EE-ECR2-12400 Run Out table section-3 0 10-Aug-14 10-Aug-14

EE-ECR2-12410 Run Out table section-4 and Incoming 0 10-Aug-14 10-Aug-14

EE-ECR2-12420 Run Out table section-5 0 10-Aug-14 10-Aug-14

EE-ECR2-12430 Run Out table section-6 0 10-Aug-14 10-Aug-14

DC section-2DC section-2 0 10-Aug-14 10-Aug-14EE-ECR2-12510 DC Section-2 Converter (B-1, B-2) 0 10-Aug-14 10-Aug-14

EE-ECR2-12500 DC Section-2 Converter (A-1, A-2 and distribution) 0 10-Aug-14 10-Aug-14

Run Out and Carry over tableRun Out and Carry over table 0 10-Aug-14 10-Aug-14EE-ECR2-12520 Run Out table section-8 0 10-Aug-14 10-Aug-14

EE-ECR2-12530 Run Out table section-9 0 10-Aug-14 10-Aug-14

EE-ECR2-12540 Run Out table section-10 and Incoming 0 10-Aug-14 10-Aug-14

EE-ECR2-12550 Carry over table 1 0 10-Aug-14 10-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 75 of 81 Filter: All Activity

Page 76: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-12560 Carry over table 2 0 10-Aug-14 10-Aug-14

DC section-2 inverter (MCCB)DC section-2 inverter (MCCB) 0 10-Aug-14 10-Aug-14EE-ECR2-12480 DC Section-2 Inverter (MCCB)-4 0 10-Aug-14 10-Aug-14

EE-ECR2-12490 DC Section-2 Inverter (MCCB)-5 0 10-Aug-14 10-Aug-14

EE-ECR2-12450 DC Section-2 Inverter (MCCB)-1 0 10-Aug-14 10-Aug-14

EE-ECR2-12460 DC Section-2 Inverter (MCCB)-2 0 10-Aug-14 10-Aug-14

EE-ECR2-12470 DC Section-2 Inverter (MCCB)-3 0 10-Aug-14 10-Aug-14

MCCMCC 22 25-Jul-14 15-Aug-14MCC-11 (DC MCC)MCC-11 (DC MCC) 4 25-Jul-14 28-Jul-14EE-ECR2-12220 SS-1 1 25-Jul-14 25-Jul-14

EE-ECR2-12230 SS-2 1 26-Jul-14 27-Jul-14

EE-ECR2-12240 SS-3 1 27-Jul-14 28-Jul-14

MCC-12 (DC MCC) with interface panelMCC-12 (DC MCC) with interface panel 6 28-Jul-14 03-Aug-14EE-ECR2-12140 SS-1 1 28-Jul-14 29-Jul-14

EE-ECR2-12150 SS-2 1 29-Jul-14 30-Jul-14

EE-ECR2-12160 SS-3 1 30-Jul-14 31-Jul-14

EE-ECR2-12170 SS-4 1 31-Jul-14 01-Aug-14

EE-ECR2-12180 SS-5 1 01-Aug-14 02-Aug-14

EE-ECR2-12130 SS-6 1 02-Aug-14 03-Aug-14

MCC-13 (DC MCC)MCC-13 (DC MCC) 3 03-Aug-14 06-Aug-14EE-ECR2-12190 SS-1 1 03-Aug-14 04-Aug-14

EE-ECR2-12200 SS-2 1 04-Aug-14 05-Aug-14

EE-ECR2-12210 SS-3 1 05-Aug-14 06-Aug-14

MCC-14 (DC MCC)MCC-14 (DC MCC) 3 06-Aug-14 09-Aug-14EE-ECR2-12310 SS-1 1 06-Aug-14 07-Aug-14

EE-ECR2-12320 SS-2 1 07-Aug-14 08-Aug-14

EE-ECR2-12330 SS-3 1 08-Aug-14 09-Aug-14

MCC-15 (DC MCC)MCC-15 (DC MCC) 3 09-Aug-14 12-Aug-14EE-ECR2-12250 SS-1 1 09-Aug-14 10-Aug-14

EE-ECR2-12260 SS-2 1 10-Aug-14 11-Aug-14

EE-ECR2-12270 SS-3 1 11-Aug-14 12-Aug-14

MCC-16 (DC MCC)MCC-16 (DC MCC) 3 12-Aug-14 15-Aug-14EE-ECR2-12280 SS-1 1 12-Aug-14 13-Aug-14

EE-ECR2-12290 SS-2 1 13-Aug-14 14-Aug-14

EE-ECR2-12300 SS-3 1 14-Aug-14 15-Aug-14

EM MCCEM MCC 0 15-Aug-14 15-Aug-14EE-ECR2-12110 SS-1 0 15-Aug-14 15-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 76 of 81 Filter: All Activity

Page 77: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-12120 SS-2 0 15-Aug-14 15-Aug-14

PLC (DC)PLC (DC) 1 16-Aug-14 17-Aug-14EE-ECR2-12080 Panel 1 &2 0 16-Aug-14 16-Aug-14

EE-ECR2-12090 Panel 3 & 4 0 16-Aug-14 16-Aug-14

EE-ECR2-12100 Panel 5 & 6 1 16-Aug-14 17-Aug-14

MV (DC)MV (DC) 0 24-Aug-14 24-Aug-14MV-1 (DC)MV-1 (DC) 0 24-Aug-14 24-Aug-14EE-ECR2-12820 Panel 6 0 24-Aug-14 24-Aug-14

EE-ECR2-12830 Panel 7 0 24-Aug-14 24-Aug-14

EE-ECR2-12770 Panel 1 0 24-Aug-14 24-Aug-14

EE-ECR2-12780 Panel 2 0 24-Aug-14 24-Aug-14

EE-ECR2-12790 Panel 3 0 24-Aug-14 24-Aug-14

EE-ECR2-12800 Panel 4 0 24-Aug-14 24-Aug-14

EE-ECR2-12810 Panel 5 0 24-Aug-14 24-Aug-14

MV-2 (DC)MV-2 (DC) 0 24-Aug-14 24-Aug-14EE-ECR2-12710 Panel 1 0 24-Aug-14 24-Aug-14

EE-ECR2-12720 Panel 2 0 24-Aug-14 24-Aug-14

EE-ECR2-12730 Panel 3 0 24-Aug-14 24-Aug-14

EE-ECR2-12740 Panel 4 0 24-Aug-14 24-Aug-14

EE-ECR2-12750 Panel 5 0 24-Aug-14 24-Aug-14

EE-ECR2-12760 Panel 6 0 24-Aug-14 24-Aug-14

RY (DC)RY (DC) 0 24-Aug-14 24-Aug-14EE-ECR2-12840 Panel 1 0 24-Aug-14 24-Aug-14

EE-ECR2-12850 Panel 2 0 24-Aug-14 24-Aug-14

LV (DC)LV (DC) 0 24-Aug-14 24-Aug-14EE-ECR2-12680 Panel 1 0 24-Aug-14 24-Aug-14

EE-ECR2-12690 Panel 10 0 24-Aug-14 24-Aug-14

Other Electrical equipmentOther Electrical equipment 104 11-Feb-14 A 14-Oct-14EE-ECR2-11610 Cable tray support & Cable tray erection 0 11-Feb-14 A 20-Jun-14 A

EE-ECR2-12050 UPS 1 15-Aug-14 16-Aug-14

EE-ECR2-12060 DL (DC) 2 17-Aug-14 19-Aug-14

EE-ECR2-12070 IF 2 19-Aug-14 21-Aug-14

EE-ECR2-12700 BR (DC) 0 24-Aug-14 24-Aug-14

EE-ECR2-13270 MAIN DS 0 30-Sep-14 30-Sep-14

EE-ECR2-11670 Cable laying 91 17-May-14 A 30-Sep-14

EE-ECR2-11870 Cable Termination 29 30-Aug-14 07-Oct-14

EE-ECR2-13300 Panel Testing 30 14-Sep-14 14-Oct-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 77 of 81 Filter: All Activity

Page 78: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

Preconditions for individual trialPreconditions for individual trial 56 20-Aug-14 16-Oct-14EE-ECR2-13760 chiller unit 0 20-Aug-14*

EE-ECR2-13810 Last equipment ready and Individual Trails 20 24-Aug-14 13-Sep-14

EE-ECR2-13820 Integrated Trials 36 10-Sep-14 16-Oct-14*

LBSS, GIS (33Kv), Main Transformers & HHFLBSS, GIS (33Kv), Main Transformers & HHF 0 16-Jun-14 A 16-Jun-14 AElectrical & Automation WorksElectrical & Automation Works 0 16-Jun-14 A 16-Jun-14 AEE-ECR2-11640 Avail abilty of Power from PDS 0 16-Jun-14 A

Main Drive system, Lighting & Fitting and Condition Monitoring SystemMain Drive system, Lighting & Fitting and Condition Monitoring System 47 03-Feb-14 A 14-Sep-14Electrical & AutomationElectrical & Automation 47 03-Feb-14 A 14-Sep-14MAIN DRIVES-Mill ECR 2 GRID 14 TO 22 - Mill Grid - 1 to 12MAIN DRIVES-Mill ECR 2 GRID 14 TO 22 - Mill Grid - 1 to 12 34 12-Aug-14 14-Sep-14R1 Conv (TOP)R1 Conv (TOP) 7 12-Aug-14 18-Aug-14EE-ECR2-13130 R1 Main (TOP) Control and Incoming 5 13-Aug-14 18-Aug-14

EE-ECR2-13200 R1 Main (Top) Converter 1 & 2 7 12-Aug-14 18-Aug-14

R1 Conv (Bottom)R1 Conv (Bottom) 7 12-Aug-14 18-Aug-14EE-ECR2-13380 R1 Main (Bottom) Converter 1 & 2 7 12-Aug-14 18-Aug-14

EE-ECR2-13340 R1 Main (Bottom) Control and Incoming 3 16-Aug-14 18-Aug-14

R1 Inv (Top)R1 Inv (Top) 11 14-Aug-14 24-Aug-14EE-ECR2-13460 R1 Main (Top) Inverter 1,2,3 (A) 5 14-Aug-14 18-Aug-14

EE-ECR2-13520 R1 Main (Top) Control and Incoming 3 16-Aug-14 18-Aug-14

EE-ECR2-13540 R1 Main (Top) Inverter 1,2,3 (B) 6 19-Aug-14 24-Aug-14

R1 Inv (Bottom)R1 Inv (Bottom) 21 25-Aug-14 14-Sep-14EE-ECR2-13600 R1 Main (Bottom) Inverter 1,2,3 (A) 9 25-Aug-14 02-Sep-14

EE-ECR2-13660 R1 Main (Bottom) Control and Incoming 3 03-Sep-14 05-Sep-14

EE-ECR2-13680 R1 Main (Bottom) Inverter 1,2,3 (B) 9 06-Sep-14 14-Sep-14

MAIN DRIVES-Mill ECR 2 GRID 22 TO 31 - Mill Grid - 12 to 24MAIN DRIVES-Mill ECR 2 GRID 22 TO 31 - Mill Grid - 12 to 24 29 11-Jun-14 A 27-Aug-14R2 Conv/Inv (TOP A)R2 Conv/Inv (TOP A) 10 11-Jun-14 A 08-Aug-14EE-ECR2-12640 R2 Main(TOP) Converter 1,2 (A) 0 11-Jun-14 A 14-Jun-14 A

EE-ECR2-12870 R2 Main(TOP) Control 0 15-Jun-14 A 20-Jun-14 A

EE-ECR2-12940 R2 Main(TOP) Inverter 1,2,3 (A) 10 30-Jul-14 08-Aug-14*

R2 Conv/Inv (TOP B)R2 Conv/Inv (TOP B) 4 21-Jun-14 A 08-Aug-14EE-ECR2-12930 R2 Main(TOP) Converter 1,2 (B) 0 21-Jun-14 A 24-Jun-14 A

EE-ECR2-13000 R2 Main(TOP) Control 0 25-Jun-14 A 26-Jun-14 A

EE-ECR2-13060 R2 Main(TOP) Inverter 1,2,3 (B) 4 04-Aug-14 08-Aug-14

R2 Conv/Inv (BOTTOM A)R2 Conv/Inv (BOTTOM A) 13 08-Aug-14 21-Aug-14EE-ECR2-13140 R2 Main(TOP) Converter 1,2 (A) 4 08-Aug-14 12-Aug-14

EE-ECR2-13220 R2 Main(TOP) Control 2 12-Aug-14 14-Aug-14

EE-ECR2-13260 R2 Main(TOP) Inverter 1,2,3 (A) 7 14-Aug-14 21-Aug-14

R2 Conv/Inv (BOTTOM B)R2 Conv/Inv (BOTTOM B) 6 21-Aug-14 27-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 78 of 81 Filter: All Activity

Page 79: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-13390 R2 Main(TOP) Converter 1,2 (B) 2 21-Aug-14 23-Aug-14

EE-ECR2-13430 R2 Main(TOP) Control 2 23-Aug-14 25-Aug-14

EE-ECR2-13450 R2 Main(TOP) Inverter 1,2,3 (B) 2 25-Aug-14 27-Aug-14

MAIN DRIVES-Mill ECR 2 grid 31 to 37 - Mill Grid - 24 to 31MAIN DRIVES-Mill ECR 2 grid 31 to 37 - Mill Grid - 24 to 31 0 02-May-14 A 29-Jun-14 ACrop ShearCrop Shear 0 02-May-14 A 05-May-14 AEE-ECR2-11770 Crop Shear converter-1,2 0 02-May-14 A 02-May-14 A

EE-ECR2-11810 Crop Shear control 0 03-May-14 A 04-May-14 A

EE-ECR2-11830 Crop Shear inverter-1,2 0 04-May-14 A 05-May-14 A

F1 Main (A)F1 Main (A) 0 06-May-14 A 09-May-14 AEE-ECR2-11900 F1 Main converter-1(A),2(A) 0 06-May-14 A 07-May-14 A

EE-ECR2-11930 F1 Main control 0 07-May-14 A 08-May-14 A

EE-ECR2-11960 F1 Main inverter-1(A),2(A) 0 08-May-14 A 09-May-14 A

F1 Main (B)F1 Main (B) 0 09-May-14 A 12-May-14 AEE-ECR2-12000 F1 Main converter-1(B),2(B) 0 09-May-14 A 10-May-14 A

EE-ECR2-12570 F1 Main control 0 10-May-14 A 11-May-14 A

EE-ECR2-12590 F1 Main inverter-1(B),2(B) 0 11-May-14 A 12-May-14 A

F2 Main (A)F2 Main (A) 0 12-May-14 A 15-May-14 AEE-ECR2-12650 F2 Main converter-1(A),2(A) 0 12-May-14 A 13-May-14 A

EE-ECR2-12860 F2 Main control 0 13-May-14 A 14-May-14 A

EE-ECR2-12880 F2 Main inverter-1(A),2(A) 0 14-May-14 A 15-May-14 A

F2 Main (B)F2 Main (B) 0 15-May-14 A 18-May-14 AEE-ECR2-12960 F2 Main converter-1(B),2(B) 0 15-May-14 A 16-May-14 A

EE-ECR2-13010 F2 Main control 0 16-May-14 A 17-May-14 A

EE-ECR2-13030 F2 Main inverter-1(B),2(B) 0 17-May-14 A 18-May-14 A

F3 Main (A)F3 Main (A) 0 18-May-14 A 21-May-14 AEE-ECR2-13070 F3 Main converter-1(A),2(A) 0 18-May-14 A 19-May-14 A

EE-ECR2-13110 F3 Main control 0 19-May-14 A 20-May-14 A

EE-ECR2-13120 F3 Main inverter-1(A),2(A) 0 20-May-14 A 21-May-14 A

F3 Main (B)F3 Main (B) 0 21-May-14 A 24-May-14 AEE-ECR2-13180 F3 Main converter-1(B),2(B) 0 21-May-14 A 22-May-14 A

EE-ECR2-13240 F3 Main control 0 22-May-14 A 23-May-14 A

EE-ECR2-13280 F3 Main inverter-1(B),2(B) 0 23-May-14 A 24-May-14 A

F4 Main (A)F4 Main (A) 0 24-May-14 A 27-May-14 AEE-ECR2-13320 F4 Main converter-1(A),2(A) 0 24-May-14 A 25-May-14 A

EE-ECR2-13360 F4 Main control 0 25-May-14 A 26-May-14 A

EE-ECR2-13400 F4 Main inverter-1(A),2(A) 0 26-May-14 A 27-May-14 A

F4 Main (B)F4 Main (B) 0 28-May-14 A 31-May-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 79 of 81 Filter: All Activity

Page 80: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-13440 F4 Main converter-1(B),2(B) 0 28-May-14 A 29-May-14 A

EE-ECR2-13470 F4 Main control 0 29-May-14 A 30-May-14 A

EE-ECR2-13480 F4 Main inverter-1(B),2(B) 0 30-May-14 A 31-May-14 A

F5 Main (A)F5 Main (A) 0 31-May-14 A 03-Jun-14 AEE-ECR2-13490 F5 Main converter-1(A),2(A) 0 31-May-14 A 01-Jun-14 A

EE-ECR2-13500 F5 Main control 0 01-Jun-14 A 02-Jun-14 A

EE-ECR2-13510 F5 Main inverter-1(A),2(A) 0 02-Jun-14 A 03-Jun-14 A

F5 Main (B)F5 Main (B) 0 03-Jun-14 A 06-Jun-14 AEE-ECR2-13530 F5 Main converter-1(B),2(B) 0 03-Jun-14 A 04-Jun-14 A

EE-ECR2-13570 F5 Main control 0 04-Jun-14 A 05-Jun-14 A

EE-ECR2-13580 F5 Main inverter-1(B),2(B) 0 05-Jun-14 A 06-Jun-14 A

F6 Main (A)F6 Main (A) 0 06-Jun-14 A 11-Jun-14 AEE-ECR2-13590 F6 Main converter-1(A),2(A) 0 06-Jun-14 A 08-Jun-14 A

EE-ECR2-13610 F6 Main control 0 08-Jun-14 A 09-Jun-14 A

EE-ECR2-13620 F6 Main inverter-1(A),2(A) 0 09-Jun-14 A 11-Jun-14 A

F6 Main (B)F6 Main (B) 0 12-Jun-14 A 17-Jun-14 AEE-ECR2-13640 F6 Main converter-1(B),2(B) 0 12-Jun-14 A 14-Jun-14 A

EE-ECR2-13650 F6 Main control 0 14-Jun-14 A 15-Jun-14 A

EE-ECR2-13670 F6 Main inverter-1(B),2(B) 0 15-Jun-14 A 17-Jun-14 A

F7 Main (A)F7 Main (A) 0 18-Jun-14 A 23-Jun-14 AEE-ECR2-13690 F7 Main converter-1(A),2(A) 0 18-Jun-14 A 20-Jun-14 A

EE-ECR2-13700 F7 Main control 0 20-Jun-14 A 21-Jun-14 A

EE-ECR2-13710 F7 Main inverter-1(A),2(A) 0 21-Jun-14 A 23-Jun-14 A

F7 Main (B)F7 Main (B) 0 24-Jun-14 A 29-Jun-14 AEE-ECR2-13720 F7 Main converter-1(B),2(B) 0 24-Jun-14 A 26-Jun-14 A

EE-ECR2-13730 F7 Main control 0 26-Jun-14 A 27-Jun-14 A

EE-ECR2-13740 F7 Main inverter-1(B),2(B) 0 27-Jun-14 A 29-Jun-14 A

POWER, CONTROL AND INST. CABLES FOR HSMPOWER, CONTROL AND INST. CABLES FOR HSM 0 03-Feb-14 A 30-Apr-14 AEE-ECR2-11590 Receipt of Equipment at Site of POWER, CONTROLAND INST. CABLES FOR HSM 0 03-Feb-14 A 30-Apr-14 A

Aux Drive system, Aux Transformers, PA system, FDA & FP, VHF and CCTVAux Drive system, Aux Transformers, PA system, FDA & FP, VHF and CCTV 59 25-May-14 A 30-Sep-14Electrical & Automation WorksElectrical & Automation Works 59 25-May-14 A 30-Sep-14AUX DRIVES-Mill ECR 2 grid 37 to 48AUX DRIVES-Mill ECR 2 grid 37 to 48 59 02-Aug-14 30-Sep-14EE-ECR2-12620 No.1 DC Main Inverter, Inverter common and Incoming 6 02-Aug-14* 07-Aug-14

EE-ECR2-12900 No.2 DC Main Inverter, Inverter common and Incoming 4 11-Sep-14 15-Sep-14

EE-ECR2-13160 No.3 DC Main Inverter, Inverter common and Incoming 5 25-Sep-14 30-Sep-14

No.1 DC Conv/InvNo.1 DC Conv/Inv 21 10-Aug-14 30-Aug-14EE-ECR2-12350 No.1 DC Conv/Inv 0 10-Aug-14

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 80 of 81 Filter: All Activity

Page 81: HSM 2nd July Schedule -All activity

Activity ID Activity Name Remaining

Duration

Start Finish

EE-ECR2-12360 No. 1 DC Converter and Converter common 10 10-Aug-14 20-Aug-14

EE-ECR2-12370 No.1 DC Pinch Roll (Top and Bottom) Inverter, Incoming and common 11 20-Aug-14 30-Aug-14

No.2 DC Conv/InvNo.2 DC Conv/Inv 12 30-Aug-14 11-Sep-14EE-ECR2-12340 No. 2 DC Converter and Converter common 7 30-Aug-14 06-Sep-14

EE-ECR2-12630 No.2 DC Pinch Roll (Top and Bottom) Inverter, Incoming and common 5 06-Sep-14 11-Sep-14

No.3 DC Conv/InvNo.3 DC Conv/Inv 10 15-Sep-14 25-Sep-14EE-ECR2-12990 No.3 DC Converter and Converter common 5 15-Sep-14 20-Sep-14

EE-ECR2-13090 No.3 DC Pinch Roll (Top and Bottom) Inverter, Incoming and common 5 20-Sep-14 25-Sep-14

AUX DRIVES-Mill ECR 2 GRID 14 TO 22AUX DRIVES-Mill ECR 2 GRID 14 TO 22 4 15-Aug-14 18-Aug-14E1 Conv/InvE1 Conv/Inv 4 15-Aug-14 18-Aug-14EE-ECR2-12670 E1 Main Converter and Converter common 4 15-Aug-14 18-Aug-14

EE-ECR2-12920 E1 Main Converter (WS) Inverter 2 17-Aug-14 18-Aug-14

EE-ECR2-12970 E1 Main Inverter common, E1 Main Incoming and E1 Main (DS) Inverter 4 15-Aug-14 18-Aug-14

AUX DRIVES-Mill ECR 2 GRID 22 TO 31AUX DRIVES-Mill ECR 2 GRID 22 TO 31 0 25-May-14 A 03-Jun-14 AE2 Conv/InvE2 Conv/Inv 0 25-May-14 A 03-Jun-14 AEE-ECR2-11880 E2 Main Converter and Converter common 0 25-May-14 A 27-May-14 A

EE-ECR2-11910 E2 Main Converter (WS) Inverter 0 28-May-14 A 29-May-14 A

EE-ECR2-11950 E2 Main Inverter common, E1 Main Incoming and E1 Main (DS) Inverter 0 30-May-14 A 03-Jun-14 A

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr2014 2015

Tata Steel - Odisha Project Hot Strip Mill  Schedule As on: 02.07.14

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Page 81 of 81 Filter: All Activity