hse directive 3 working at heights

10
HSE DIRECTIVE 3 WORKING AT HEIGHTS

Upload: akubestlah

Post on 28-Nov-2014

671 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: HSE Directive 3 Working at Heights

HSE DIRECTIVE 3WORKING AT HEIGHTS

Page 2: HSE Directive 3 Working at Heights

107HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011

1. GENERALPurposeThe purpose of this directive is to ensure that• allworkatheightsiscarriedoutsafely• therearenoaccidentsduetodroppedobjects• alluseofladderstakesplaceinasafemanner• allscaffoldingiserected,takendownandusedsafely• workabovetheseaiscarriedoutsafely

DomainThis directive applies to all BP-operated installations and contracted installations on the Norwegian continental shelf.Contractedmobileinstallationswhichhaveasystemthatsatisfiestherequirements in this directive, may use their own system provided this has been clarified upon implementation.By following this directive, all requirements in the “Working at Heights” section in the “BP 8 Golden Rules of Safety” are complied with.Onshore facilities or projects where BP Norge have a particular responsibility and which are assessed being part of the petroleum activities References• TheActivitiesRegulations,section§42 Use of work equipment • Regulationsrelatingtoscaffolding,laddersandworkonroofs,etc.• Regulationrelatingtouseofworkequipment The Norwegian Labour Inspection Authority’s regulations• OMSProcedure4.5ControlofWork• OMSRisk3.2PersonalSafety• 088Commonmodelforworkpermits The Norwegian Labour Inspection Authority’s regulations • NS-EN795Protectionagainstfallfromheights.Anchoringmethodes.• HSEDirectiveno.1–Workpermits• HSEDirectiveno.11Safejobanalysis• UseofWorkBasket-ref.HSEDirective4LiftingOperations• OLFGuideline113-Securingandrescuewhenworkinginheights(only in Norwegian)

Definitions and abbreviations• Working at heights means all work carried out standing with one’s feet two metres or more above deck level where there is no fixed platform or approved scaffolding• Work permit is a written permit to carry out a defined work task at a given place onboard an installation under given conditions and in a safe manner• Safe Job Analysis (SJA) is a systematic and step-by-step review of all elements of risk carried out prior to a specific task or operation so that measures can be taken to remove or control any elements of risk identified during the preparation for or performance of the said task or operation • First line MOB (Man overboard) preparedness includes o the platform’s MOB crew standing by in case of an emergency or o a standby vessel ready by the installation

Page 3: HSE Directive 3 Working at Heights

HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011108

2. WORKING AT HEIGHTS

Competence • CompleteBPfallarrestcourseoffshore

Use of safety devices • allworkcarriedoutstandingwithone’sfeet2metresormoreabove the deck requires: o fixed platform with handrail, or o scaffolding with green scafftag, or o use of approved safety harness secured in a suitable anchor point which limits free fall to 2 metres from the footing, normally by use of a fall block, and ofilledinandsigned“ChecklistforWorkAtHeights/UseofHarness”.• Whenmovingatheightoutsideafixedplatform,scaffoldingorladder an approved safety harness with fallblock (or, alternatively, a Y-line) shall be used. When relocating the fallblock, the person involved must be secured with a fall arrest line.• Whenusingfallarrestequipment • atleastonepersonshallbepresentintheareanearbyatalltimesin order to alert and start basic rescue work in case of a fall • priortocommencementofwork,arealisticandsaferescueplan shall exist. The plan shall take the time for a safe rescue into consideration in order to be able to rescue a person within sufficient time (i.e. prevent blood circulation injuries). • Thereshallbeasitespecificinstructiononhowrequiredcompetent personnel are organized (for instance a rescue team)

Securing underlaying area• Toolsandequipmentshall,asfaraspractical,besecuredwithsuitable means to prevent them from being dropped • Ifthereisapotentialfordroppedobjectstheunderlayingareashallbe secured either with a guard person or roped off in co-ooperation with the area technician. • Ifdroppedobjectscandamagepressurisedequipment,theareashall be physically protected or de-pressurised in co-operation with the area techncian. • Uponcompletionofworktheareashallbecheckedtosecurethatno potential dropped objects are left.

Inspection of fall arrest harness• Theusershallalwaysvisuallycheckhis/hersafetyharness,-systemand anchor point and also have it checked by a co-worker. If there is any doubt contact the scaffolding foreman or inspection re. anchor points. • Defectharnessesorharnessesthatlackthecontroltag (yearly control) for approved lifting device shall not be used and handed in for repair

Page 4: HSE Directive 3 Working at Heights

109HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011

Use of fall lifeline• Theanchoragepointforthelifelineshallstandaloadof1000kgandthe anchorage point should be above the user• Thelifelineshallbeconnectedtotheanchoragepointattheapproved fall Harness. The rear anchorage point should be used but depending on the work the front anchorage can be used.• Normallyaselfretractinglifelineshallbeused• Restraintlanyardshallnotbeusedaslifeline• Compositionofthefallarrestsystemshallbebasedonidentifiedrisks like: potential pendulum movement, horizontal movement

3. USE OF LADDERS

Use• Laddersmayonlybeusedforaccessorworkofshortduration,like installing temporary chain hoists, control and cleaning of F & G detectors

Which ladders can be used• LaddersshallbeinaccordancewithChapterVIintheRegulations relating to scaffolding, ladders, work on roofs, etc. • Laddersmusthaverubberknotsatbothendsandhavenovisual deformation• Onlysingleladdersmaybeused.• Stepladdersupto3.5m,maybeusedonfirmandevenfoundations when there is no potential for fall to a lower level/ sea. Maximum climb height in the ladder is 2m. The 2m shall be clearly marked on the ladder• Inelectricalswitchrooms,laddersshallbeofnon-conductingmaterial

Inspection• Theuserisresponsibleforcheckingtheladderbeforeuse• Defectiveladdersmustbediscarded

Safety measures• Laddersmustbesecuredtopreventthemfromslidingortippingover when used, by a person securing at the bottom until it is secured at the top. • Duringmovementinaladdernothingmustbecarriedinthehands.• Duringworkinaladderthree-pointcontactmustbemaintained(e.g.2 feet and one hand) • Whenworkingstandingabove2metersfallarrestharnessshallbe used.

Page 5: HSE Directive 3 Working at Heights

HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011110

4. SCAFFOLDING

Approval of work• Erecting/dismantlingscaffoldinghigherthan2mrequiresaWorkPermit level 2. • Erecting/dismantlingscaffoldinglowerthan2mrequiresageneral platform/area Work Permit level 2.• Erecting/dismantlingscaffoldingoversearequiresapprovalaccordingto section 6 of this directive.

Erecting/dismantling scaffolding• Scaffoldingshallbeerected/movedanddismantledbyauthorised scaffolders only• ScaffoldingshallbeinaccordancewithChapterIIIoftheRegulations relating to scaffolding, ladders, work on roofs, etc.• Aworkplatform(includingaccessplatforms)shallbesecuredwith handrails and kick plates and other required covering/ securing to prevent dropped objects. If this is not possible the green scafftag shall be marked with necessary safety precautions, such as use of harness and closing of underlaying area.

Erecting/dismantling scaffolding over seaWhen scaffolding is erected/dismantled over sea:• therulesforWorkoverseashallapply.• aToolboxTalkorJobSafetyAnalysisshallbeperformed.• alwaysbe2scaffolders.

Scaffolding approval• Approvalofscaffoldingforuseshallonlybeperformedbyauthorised approval personnel. Ref. competency requirements, section 1. • Approvedscaffoldingisshownwithagreenscafftagwithdateand signature. The scafftag must be at the scaffolding entrance• Thescaffoldingforemanmustensurescaffoldsareinspected/approved at least once every 14 days, as well as after spells of strong wind or other conditions that may damage the scaffolding

Use of scaffolding• Onlyscaffoldinghavingagreenscafftag is approved for use• Scaffoldingmustbeusedinaccordancewithlimitationsgivenonthe green scafftag.

Page 6: HSE Directive 3 Working at Heights

111HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011

5. ROPE ACCESS (RA)

Standard and trainingThe following standards shall be used:• 0901SOFTStandardforropeaccesspart1: Requirements for company and personnel• 0904SOFTStandardforropeaccesspart4: Implementation of courses

Routin and methodesThe following standards shall be used:• 0902SOFTStandardforropeaccesspart2: Requirements for routines• 0903SOFTStandardforropeaccesspart3: Recommended methode

Approval• RAworkrequireapprovedworkpermitlevel1 •Workshallbeplannedandexiqutedaccordingtosection4 Operative routines in SOFT standard 0902 •RescueplanshallbeattachedtotheWorkPermitform

6. WORK OVER OPEN SEA

Introduction• Workoverseameansworktakingplaceoutsidepermanentrailing where there is a risk of a person/persons falling into the sea.

• UseofRopeAssess(RA)isnotdefinedasworkoverseawhenitis performed in complains with RA requirements in section 5.

• Workinhydraulicbasketin“moonpool”andonapprovedscaffoldingis not defined as work over sea when extra barriers such as •fallarrestequipment •man-ridingbelt •net •Scaffoldingbuildasaclass3andtobecertifiedandusedasaclass2 scaffolding with extra heighten hand rail (railing). The scaffolding shall be certified every week and inspected after external influence e.g. strong wind

Note: Use of fall arrest equipment, man-riding belt or net requires independent securing. (not attached to the scaffolding).

Approval• Workoversearequiresanapprovedworkpermitlevel1

Page 7: HSE Directive 3 Working at Heights

HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011112

RestrictionsWork over sea is permitted provided:• Thewindspeedismaximum30knots,measuredata10mlevel• Thewaveheightismaximum5m(correspondsto3msignificantwave height)

• Standbyvesselinnear-standbymodeorMOBinextrapreparedness mode

• TheMOBboatonboardoronthestandbyvesselisoperativeandcan be launched/retrieved in case a person falls into the sea

• Thelightandviewisgoodenoughtoperformtheworkandrescueany person that may fall into the sea

• Consenthasbeenobtainedfromthedivingsupervisorifthereisdiving activity near the work site

Safety precautions• Whenworkingoversea,asafetyguardmustbepresentandmonitor the personnel located over sea at all times. The safety guard shall be familiar with and carry out tasks stated in the Safety guard’s duties in connection with work over sea

• Alifebuoywithlineandlightshallbeeasilyavailable

• Theperformingpersonnelshallbefamiliarwithallprocedures, preconditions, risks and safety precautions relating to the work

• Everyoneworkingoveropenseashallwearalifevest

• Whenworkingbelowthecellardeck,considerwhethertosecurespills, overflow, etc. from e.g. fire water

• Considertheneedforimplementingmeasurestoavoidobjectsfalling to lower levels or down on vessels.

HSE DIRECTIVE 3WORKING AT HEIGHTS

ATTACHMENTS

Page 8: HSE Directive 3 Working at Heights

HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011

Attachment 1:Duties for the safety guard during work over sea

Attachment 2:SafetyCriticalWorkProcedureBP

HSE DIRECTIVE 3WORKING AT HEIGHTS

ATTACHMENTS

Page 9: HSE Directive 3 Working at Heights

115HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011

ATTACHMENT 1: DUTIES FOR THE SAFETY GUARD DURING WORK OVER SEAThe Safety Guard shall be clearly marked with “sikkerhetsvakt”

Before commencing the workThe Safety Guard shall:• participateintheworkplanning,includingSJA/pre-jobtalks• locatethenearestfirecallpoint/telephone• ensurethattheagreedMOBfunction(Standbyboatortheinstallation’s MOB crew) is informed and operational• establishandcheckradiocommunicationwiththeworkplace,SCRand MOB function. (Standby boat or the installation’s Radio room when usingtheinstallation’sMOBboat.CheckthattheradiointheMOB boad can communicate with the Safety guard).• ensureescaperoutesareknownbyinvolvedpersonnel• befamiliarwiththeweatherlimitationsforworkoversea• perform“comradeshipcheck”uponfallarresterequipmentandlifevest

During work The Safety Guard shall:• informSCRandMOBfunctionatstart,interruptionandcompletionof work• belocatedatapermanentdeckoftheinstallationandhavean unhindered view of the personnel working over sea• nottakepartinworkthatmayinterferewithhis/herdutyassafetyguard• monitorchangesinweatherconditions/visibilityandlightandstopthe work if the preconditions and limitations for the work are exceeded• monitortheworkandsurroundingsandstopworkshouldasituation arise that calls for such action• facilitateagooddialoguewiththestand-byvesselregardinglightand weather conditions, if and when any limitations should occur

Interruptions/ completion of work The Safety Guard shall:• informSCRandMOBfunction• secureequipment/workplace

If ”man over board” The Safety Guard shall:• notifycolleaguesCCRandMOBfunction• activatealarm• throwoutalifebuoy• maintainvisualcontactwithpersoninsea• secureequipment/workplace

Alarm situations The Safety Guard shall:• notifypersonneloverseaandstopwork• securethatallpersonnelreturntoapermanentdeckoftheinstallation• secureequipment/workplace

Page 10: HSE Directive 3 Working at Heights

HEALTH, SAFETY & ENVIRONMENT HANDBOOK 2011116

ATTACHMENT 2: SAFETY CRITICAL WORK PROCEDURE BP

HSE DIRECTIVE 4 LIFTING OPERATIONS

Safety Critical Work Procedure BP

Task / Title:

USE OF FALL ARREST HARNESS / WORKING IN HEIGHT

TAG no.: N/A

Con

sequ

ence

1

2 SiKAP No.:

1.70.076 Field:

BPN Offshore Discipline:

ALL Validated by: B.Skulstad, S.G.Hellevik, A.Hide, G.Lied Date: 03.11.2011

3 4 5

Verified by: OTL-V Mech/Utility Date: 01.01.2011

Approved by; Owner HSSE Directive no 3 Working in Height Date: 01.01.2011

Rev. No.: 02 Expire: 01/2014

D C B A

Probability

ARKIVERT: Eustvs2/BPN Info Vol//Templates/BP Norge Templates 1 av 2

The objective for the work procedure (ref. classification sheet no,): K 1.70.076 Prevent personnel injury from using fall arrest harness and associated equipment.

Identified dangers (ref. classification sheet no,): K 1.70.076 1. Lack of competence in inspection, control and use of fall arrest harness and lines. 2. Uses anchor points of less strength than 1000kg load bearing capacity. 3. Incorrect limitation in use of equipment in relation to fall distance to protruding equipment or swinging

can result in collision and hurt oneself. 4. If hanging for a long time in fall protection harness one can get circulation failure if one does not get to

use relief (leg) strap. (Hang trauma) References: (Refers to relevant laws, regulations and BP’s directives, manuals, HMS-instructions, vendor’s documents, datasheet for chemicals and other dangerous substances,) Governing documents: 8 Golden Safety Rules – Permit to Work, Working at Hights; HSE directive 1

Work Permits, HSE directive 3 – Working at Hights. Vendor documents: Users Guide Drawings: Users Guide HSE data sheet, (LogiChem):

N/A

Planning / Preparation: WP Level 1 when working over sea, otherwise Level 2 Work Permit (WP) no.: Level 1 Class ”A” Class ”B” Level 2 Class ”B”

Direct involved roles (number): 2+

Performing technician, one person/safety guard

Gassfree /Access / Scaffolding:

Ref WP

Requirement for service by vendor:

N/A

Tools / Equipment / Chemicals: (Refers to special personal protective equipment, tools listings, special equipment and expected state of equipment / systems, in excess of WP, in advance to allow start of work) Equipment/system state: Ref WP Special personal protective equipment:

Fall arrest harness and associated line(s)

Special tools & equipment: N/A Special lifting equipment: N/A Special position of valves: N/A Step no.:

Description of the activity: (step number gives the sequence of actions; bullets indicates that the actions can be performed in any chosen order)

Comments: (especially critical steps and warning about adjacent activities are marked with underlined BOLD letters and eventual risk reducing measures are noted, ref to Tr@ction no. and SJA as relevant.)

Evt.k

vitte

r

Plan for working at hights: - Consider the need for WP - Follow check list and tick off each step - Step 7, see identified danger no. 4

NOTE! It is vital to initiate rescue immediately after a fall. To be hanging in the harness without being able to use the relief strap may indulge hang trauma to the person and stop the blood from circulating.

Safety Critical Work Procedure BP

Task / Title:

USE OF FALL ARREST HARNESS / WORKING IN HEIGHT

TAG no.: N/A

Con

sequ

ence

1

2 SiKAP No.:

1.70.076 Field:

BPN Offshore Discipline:

ALL Validated by: B.Skulstad, S.G.Hellevik, A.Hide, G.Lied Date: 03.11.2011

3 4 5

Verified by: OTL-V Mech/Utility Date: 01.01.2011

Approved by; Owner HSSE Directive no 3 Working in Height Date: 01.01.2011

Rev. No.: 02 Expire: 01/2014

D C B A

Probability

ARKIVERT: Eustvs2/BPN Info Vol//Templates/BP Norge Templates 2 av 2

Check list for use of fall arrest harness / working in height Check points N/A YES NO Comments

1. Are you using a full body harness with double latch self-locking snap hooks and equipment with relief strap / foot strap?

2. Has a proper anchor point for the safety line been located?

3. Is fall arrest equipment in use that will limit the free fall to 2 meters or less?

4. Has the fall arrest equipment been visually checked for:

- damage/wear or defects? - control tag with the latest control date?

5. If a ladder is used, is the ladder free of visual damage and secured? During securing of the ladder one person shall secure the ladder at the bottom until the ladder is secured at the top

6. Has the fall arrest equipment, system and anchor point been checked by a colleague?

7. Is there a person in the work area that can initiate basic rescue, if a fall should occur?

8. Are equipment / tools used at height controlled and adequately secured against dropping? And not left behind finishing the work?

9. Are underlying areas closed off and pressurized/sensitive equipment protected against dropped objects?

10. Are lighting, noise and weather conditions satisfactory for the task?

11. Are there any other risks and have they been evaluated and found acceptable? Use the 4 – Point Risk assessment

12. Have the involved persons completed a course in fall arrest methods?

13. Have all items on the checklist been answered YES without comments? If NO, the work shall not be started. Contact the line manager to find alternative methods to perform the work.

ADDITIONAL COMMENTS : Note! Work over open sea also require the use of “Duties for the safety guard during work over sea” (attachment1) Date: Area technician (Work w/o WP): Performing technician(s): Closure of work

14. Are all loose tools/equipment removed from the workplace?

Performing technician (s):

END END