how xcel energy developed a the largest community solar
TRANSCRIPT
HOW XCEL ENERGY DEVELOPED THE LARGEST COMMUNITY SOLAR GARDEN PROGRAM IN THE COUNTRY
© 2020 Xcel Energy 1
Ed Shannon | Principal DER Engineer
Alan Urban | DER Engineer
November 4, 2020
2
AGENDA• Introduction
• Program History
• Technical Review Process
• Screening
• DER Impact Studies
• Commissioning
© 2020 Xcel Energy
• Operational Challenges
• Non-Technical Challenges
• Non-Technical Challenges
• Where We Are
• Where are we headed next
• Questions
Xcel Energy DER Integration Team (North)Chris Punt – Manager of DER Integration
John Harlander – DER Integration
Project Manager
Ed Shannon – DER Integration Engineer
Alan Urban – DER Integration Engineer
Steve Bye – DER Integration Engineer
3 full time contract employees
2 Consulting Engineering Firms
© 2020 Xcel Energy 4
Minnesota Solar*Rewards Community®
Active applications – 362
New applications in 2020 – 330
Completed Project – 337 project for 739MW
Design and Construction – 102 project for 103 MW
In study/screen process – 197 for 194MW
72 MW have scheduled ISD in Q4
© 2020 Xcel Energy 5
Note: Xcel Energy also has 100 MWs of gardens not part of the SRCMN program and X MW of Customer Sited DER
.https://www.xcelenergy.com/staticfiles/xe-responsive/Working%20With%20Us/Renewable%20Developers/SRCMN_Dashboard.pdf
Key Moments in CSG History
• 2013: Xcel files petition with MN PUC under docket 13-867, per requirements of Minn. Stat. §216B.1641 as part of MN Solar Energy Standard
• 2014: Official Program launched in Dec 2014: 1 MW nameplate capacity limit; co-location allowed
No “soft launch” to program: no limitation on program wide capacity (ITC credits at risk)
Received 431 MW of applications a month into program
• 2015: Substantial changes to program rules Sun setting capacity limits on co-location
Reporting requirements
Process clarifications/CSG-specific study timelines
© 2020 Xcel Energy 8
Initial Wave of Applications
No cap on co-location
- Up to 40MW!
- Comparable to the PPAs being discussed in our Solar RFP Dockets
- “…was intended to create opportunities for residential and small-business customers to participate in distributed solar generation…”*
- New Cap: 5 MW, reducing to 1 MW after Sept 2015
© 2020 Xcel Energy 9
*Xcel Energy, January 13th, 2015 Docket E-002/M-13-867
Technical Review Strategy
Complete Application Recieved
Technical Screens
Process Track
Power Flow Study
Interconnection Agreement
Screen Eligible?
Study Eligible?
Fail
PassGoal: safety, reliability, and power quality
- Faster, simple screens for lower impact projects
- More detailed studies for complex projects
© 2020 Xcel Energy 12
Technical Screens General philosophy: Is a power flow model needed to evaluate certain criteria?
- If not, screen it!
© 2020 Xcel Energy 14
Pros
• Expedient • 10-20 Days, faster w/
automation• Less Costly
• Baked into application fee• Data needed is less than study
Cons
• Not precise • Requires some conservatism to
offset increased risk• Decreasing usability at higher
penetrations• Prescribing mitigations
inappropriate for larger projects
Technical Screens
2014- 2019
- No defined screening process in MN Interconnection Rules (written in 2003)
- < 1 MW DER eligible
- Failure = additional review or full study
© 2020 Xcel Energy 15
Prior to MN Interconnection Rules UpdateNumber Description
1 Is the PV interconnected to a Secondary Network?
2 Is the Short Circuit Current Contribution Ratio (SCCCR) [2] < 10 %
3 Is the voltage variation calculation3 < 2%
4 Minimum daytime load to aggregate generation nameplate, on a line segement delineated by protective device, ratio greater than 125%?
5 Is certified equipment used for power electronics interfaces?
6 Is the PV system configuration and voltage correct?
8 Is the installation on a shared secondary service4?9 Does the installation create a transformer or conductor
overload?10 If > 25 kW, Is the PV system three-phase?11 Does PV cause any protective device to exceed 87.5% of it's
interrupting capability rating? 12 Does the PV cause reverse power flow across a voltage
regulation device?
Technical Screens
- SGIP-based process
- Defined set of screens at state level rather than utility level
- Eligibility based on size, distribution voltage, distance from substation
© 2020 Xcel Energy 16
Updated MN Distributed Interconnection Process (2019- MN DIP)
© 2020 Xcel Energy 17
Implementation ChallengesTechnical Screens
Planning Data
Feeder/Sub Loads
Equipment Ratings
Customer Portal
Generator Information
Customer Information
In Queue Generation
Geospatial
Conductor
Service Transformer
ExistingGeneration
Screen Results
Customer Comms
Data Aggregation
- Manual process to gather data• Inefficient (still faster than
studies)
Future Looking:
- Opportunities to connect data sources
- Integrate into automated interconnection portal
Brief evolution of load-flow tools
© 2020 Xcel Energy 19
~2014 – 2015 PSS/E & Open DSS:7.5 MW DER
~2015, SKM Power Tools: 11.5 MW DER
~2017-18, SKM Power Tools → SynerGi Electric~20.5 MW DER
~2020+, SynerGi Electric: 32.5+ MW DER
Data RequirementsDER Oneline DER Site Plan
© 2020 Xcel Energy | Image source: https://www.xcelenergy.com/working_with_us/how_to_interconnect20
Technical information regarding the DER: equipment ratings & connectivity, grounding bank calculations, primary/secondary service voltages, etc.
Locational information regarding the DER: address/GPS coordinates, cross streets, equipment layout, etc.
Data RequirementsSubstation Information
© 2020 Xcel EnergyImage Source: Burke, J. J. (2017). Power distribution engineering: Fundamentals and applications.
21
Device Information Needed
Transformer Rating, impedance, no load losses, voltage ratios, etc.Voltage regulation equipment LTC setpoint, or voltage regulator settings (setpoint, bandwidth, LDC, etc.)Protective equipment Ratings, settings, bus Thevenin impedancesSubstation bus Conductor type & ratings
Usually obtained from substation drawing, transformer nameplate or test report, TR loading database and breaker/recloser settings files.
Data RequirementsFeeder Information
© 2020 Xcel Energy22
Device Information Needed
Regulators Rating, settings, setpoint, bandwidth, mode of operationCapacitor banks Rating, metered phase, PT ratios, switched vs fixed, control settingsProtective equipment Ratings, settings, locationConductor Conductor type & ratings, impedances
DER on feeder Size, power factor setting, generation type (PV, wind, bio, etc.)
Usually obtained from feeder maps, GIS, and/or volt-var management system.
Data RequirementsLoading Information
© 2020 Xcel Energy23
For peak loads, the substation coincident peak should be less than or equal to the non-coincident feeder peaks:
𝑆 _ 𝑆 𝑆 𝑆 ⋯ 𝑆 𝑆
• Substation transformer loading limits
• Feeder loading limits
• Historical native transformer and feeder peak loads
• Historical native transformer and feeder daytime minimum loading (DML)• DML for fixed PV units: 10 AM – 4 PM• DML for tracking PV units: 8 AM – 6 PM• ~20% of peak load is used for DML where no data exists (based on analysis)
• Ideally by-phase loading and power factor information is obtained
𝑆 _ 𝑆 𝑆 𝑆 ⋯ 𝑆 𝑆
For minimum loads, the substation coincident minimum should be less than or equal to the non-coincident feeder minimums:
Study Analysis
© 2020 Xcel Energy
24
Study Scenarios Description Steady state voltage
Equipment overloads
Potential islanding
Reverse power flow
Voltage fluctuation
Power factor control
Base Case 1 Existing system without DER x x
Base Case 2 Existing DER ON, new DER OFF x x x x
Base Case 3 Existing DER ON, new DER ON x x x x x x
Case 4 Max new DER size with PF changes and/or system upgrades x x x x x x
Case 5 Max new DER size without system upgrades x x x x x x
Threshold Criteria DescriptionSteady state voltage ANSI C84.1 Range A high voltage limit
Equipment overloads Any equipment loaded beyond its normal rating
Potential islanding Downstream DML/generation ratio at any reclosing device < 120% requires VSR
Reverse power flow Reverse current on voltage regulators, LTC, or substation bus
Voltage fluctuation Individual: < 2% for LTC or voltage regulating device, < 3% anywhere else on the systemAggregate: < 5% anywhere on the system
Power Factor control Yes/No: Were power factor changes applied to existing or new DER
Each study scenario is performed under both peak loading, and daytime minimum loading
Fault contributions from the substation and DER are also studied. (SLG, 3ph, X/R positive & zero sequence values)
Study Analysis
© 2020 Xcel Energy25
Mitigations/solutions are proposed only for specified threshold violations and are applied only to the point of clearing the threshold violations. (Minimized DER interconnection cost)
Voltage mitigations/solutions hierarchy:
1. Power factor controls (unity – 0.95 absorbing) DER in study only, no reconductoring
2. Power factor controls (unity – 0.95 absorbing) any DER, no reconductoring
3. Power factor controls with reconductoringa. Engineering Judgment used and trial and error used to determine best mitigation
a. Reconductor largest impedance conductor between PCC and the substationb. Reconductor starting at the DER facility working back towards the substation
4. Power factor controls, reconductoring, and DER curtailment
Reverse power flow mitigations/solutions: cogen mode control for all regulators experiencing reverse flow
Equipment overload mitigations/solutions: upgrade equipment to next standard size or curtail DER if upgrade is not available
Study Analysis
© 2020 Xcel Energy26
Protection Feasibility Studies• Verify garden can be adequately
protected at proposed size and location
• Verify the interconnecting garden does not cause reduction of reach issues
• Determine what changes are need to accommodate the proposed DER
• No settings are issued
Protection settings and final design is done during the design and construction phase.
Challenges
© 2020 Xcel Energy27
Data integrity• multiple sources, SCADA, modelling issues, field verification, ahead in queue construction, equipment
assumptions (cap bank, regulators, LTC setpoints & settings)
New Processes Required• Daytime minimum load – new process for planning to pull and validate as part of the load forecasting
process
• Phase II Studies – Study required to look at TR upgrades or dedicated infrastructure
• How to spread the knowledge of all projects going on. Same feeder might have upgrades for DER interconnections, a capacity planning project, and/or a reliability project.
Consultant challenges• Newer space in the consulting world
• Training
• QA studies & re-studies
Challenges
© 2020 Xcel Energy28
Types of system impact studies• Sequential review (serial review of queued DER one at a time)
• Batch studies (serial review of multiple sequentially queued DER in one report)
• Cluster studies (simultaneous review of multiple sequentially queued DER)
Resource availability• Studies tend to come in waves, this can overwhelm available resources (internally & externally)
Highly penetrated feeders/substations • Inability to close-off feeders to additional DER interconnections
• Create complex studies where feeder may have as many as 25+ projects and as much as 35 MWs of generation
Extremely complex and time intensive to complete
Daytime Minimum load included in studies• Changes in DML cause systems issues in the existing gen case
This requires mitigations to be completed before current project study starts
Commissioning
All DER are required to perform a Witness Test
• Xcel Energy witnesses and records results• Site construction matches approved drawings
• Functional test of anti-islanding and open phase responses
• Verification of settings
Electrical Contractor witnesses on behalf of Xcel Energy
• 1-4 hours onsite per test
• Capacity for 6 tests per day, 4 days a week.
© 2020 Xcel Energy 30
Operational Challenges
Despite the large amount of DER interconnected over the last 5 years, we have had relatively small number of operational issues.• High Voltage This was the most common issue experienced
Usually due to DER producing instead of consuming Vars
Regulators set to bi-directional mode instead of cogen mode
• Voltage fluctuation Inverter control loop parameters too strong
Identified by harmonic problems and inconsistent power factor
Resolved by Inverter manufacture changing control loop response time and decreasing control loop gain
© 2020 Xcel Energy 32
Power Quality/Reliability
Operational Challenges
Feeder switching can take an entire day• Some feeders with 20+ individual sites Abnormal configuration impacts not studied: need to remove gardens
Risk during Hotline Work increases, remove to return risk to expected levels
• Some sites using only fuses 3 operations to isolate site
Now requiring reclosers at every new site
• Easy to establish clearance
• SCADA control in the future
© 2020 Xcel Energy 33
Operating the System
Study Deadlines
Pre-MN DIP deadline was 50 days from deemed complete• 5 projects all submitted on the same feeder and applications deemed complete on the same day
all had the same due date. Caused multiple deadlines to be missed
• Required the assumption that the previous in queue DER moved forward, this caused a significant numbers of restudies as projects withdrew
• Post MN DIP deadline is 30 business days Study process needs to be near perfect to be hit the deadline
Model complication, RFIs, QA failures, complication due to queue depths have caused multiple deadlines to be missed
© 2020 Xcel Energy 35
DER System Capacity
• One program can take up all DER capacity on sub/feeder
• Need to consider Customer options
Operational flexibility
Changing load characteristics
© 2020 Xcel Energy 36
An Energy Policy Discussion
*Steady state voltage or rapid voltage change limits may be reached before thermal capacity
Maximum Thermal DER Capacity*
??%Contingency?
??%Reserved Capacity?
??%First Come/First Serve
Equipment Ratings Daytime Min Load
100% of CapacityFirst Come/First ServeTo
day
Future
At risk loads could create overloads!
How does non-export DER effect capacity?
State Of The Program
• In 5 years Xcel Energy has interconnected approximately 750 MWs of Community Gardens. Interconnected on only 15% of our total feeders.
• There is currently an additional 100+ MWs in design and construction.
• There is an additional 200+ MWs in the screen or study process.
• It is currently the largest SRC program in the country
• Successful!
© 2020 Xcel Energy 38
Where Are We Headed NextHosting Capacity Analysis
• Move towards using Hosting Capacity results for some screens
More Automation of Screens
Advanced Inverter functions• Where and how to use• Standard vs Unique vs localized settings
Time Series Analysis
MISO & Transmission Studies
????• Batteries, EV, FERC 2222 ancillary markets, Benefits from ADMS implementation
Community Garden programs ramping up in other states (Colorado)
© 2020 Xcel Energy 40