PSE&G CMMS (Computerized Maintenance Management System) Foundation for Smart Grid Modernization Presented by: Richard Wernsing Manager, Asset Strategy

Upload: others

Post on 21-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

PSE&G CMMS

(Computerized Maintenance Management System)

Foundation for Smart Grid

Modernization

Presented by:

Richard Wernsing – Manager, Asset Strategy

Page 2: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Agenda

• About PSE&G

• Problem

• Functional Areas

• Substation (CBM) Conditioned Based

Maintenance

• Benefits of CBM

• Engineering Desktop

• Expanding CBM to Underground Network

Page 3: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

PSE&G Background

• Utility Overview

– New Jersey Based

– Total Assets ~ $14 Billion

– Total Revenue ~ $7 Billion

• Service Territory

– 323 Municipalities

– 70% of New Jersey’s population

– 2.2 million Electric customers

– 1.7 million Gas customers

– 2,600 Square Miles

Page 4: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Problem

• No predictive maintenance program or strategy

• Significant liability risk and system outage potential from

old equipment vulnerable to failure

Limited assessment tools for determining asset condition

Decreasing expertise in both field maintenance and engineering

No formalized capital spending program

Asset Information in a variety of disparate systems

Page 5: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Benefits Breakdown

These annual expenditures protect $1.7 B of inside plant assets and

full benefits after approximately five years.

Note:

Illustration depicts overall

changes in maintenance

investment strategy.Preventive

Maintenance

Corrective

Maintenance

Capital Rep.

Calendar Based

Preventive

Maintenance

Corrective

Maintenance

Failures

Condition Based

Preventive

Maintenance

Historical Today

Failures

Capital Rep

10%-20% Overall Reduction

Page 6: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Functional Areas of CMMS

• Data Collection and Consolidation– Diagnostic and Inspection Data – Time-series Data– Relational Data– Maintenance Data

Data Collection

Analysis & Reporting

Maintenance Management

Raw data

Measurement points

Notification

Feedback

Asset Analysis and Reporting– Condition & Criticality Assessment– Equipment Ranking– Work Prioritization

Maintenance Management– Measurement Points– Work Order Generations– Maintenance Planning

Page 7: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Condition Based Maintenance (CBM)

• Provides better insight into condition of assets

based on available data

– Operational

– Diagnostic

– Maintenance

– Nameplate/Characteristic

• Support system that assists in making repair,

maintain and replace decisions.

– It is NOT a “crystal ball” that predicts failures

– It does NOT put the process on “cruise control”

– It is NOT a “budget slashing” tool

Page 8: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Consolidate Data

PI PI

MV90

Hydran

Doble

SAP-PM

Diagnostic data

Delta-X

MDT

Transmission SCADA

Distribution SCADA

Transformer loads

PI Manual Logger

Substation Inspections

SAP maintenance and

equipment & locations

Gas & Oil

analysis

Gas Results

Breaker Tests

Electrical test results

GIS

Ratings, Solar &

Circuit Lengths

OMS

POR and

PPC

Page 9: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Build Asset Model and Correlate Data in PI AF

Page 10: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Build Algorithms in PI AF

Page 11: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Calculation Framework• Calculation Structure

– CA = F1(M1) + F2(M2) + F3(M3) + …

– Factors driven by data available

– Example Factors

• CM Cost & Count for Past 6 Months

• Count of Operations for Past 6/12 Months

• Gas Analysis Change over time

• Average Load over Time

• Peer Groups– Apply calculations by peer group; Voltage, Class, Type

– Example Groups:

• 26KV – 69KV GCB

• 138KV+ Power Transformer

• LTC Vacuum Tanks

Page 12: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Run Algorithms

Page 13: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

CMMS Save helped avert an in service failure

Excessive gassing and over heating found on 3/1//2011

History of

CBM Score

Page 14: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Action and Results

T20 LTC excessive gassing and overheating problem identified by CMMS on 3/1/2011

Inspection showed coking contacts

Assembly cleaned and new contacts installed

Great find because T20 contacts would have failed when additional load was added during replacement of T10 transformer

Conservative Failure Avoidance Cost Saving = $1.5M– LTC = $150k cost & labor

– Transformer = $1.5M cost & labor

Final CBM score after refurbishment

Page 15: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

CBM Benefits

• Extremely valuable system when you have

– You have $1.6B of installed assets with a

replacement value of $5.7B

– Average age of the assets exceeds 40 years

– All equipment is expected to be used and useful all

the time

– Maintenance expenditures erode earnings and

capital replacement provides for no new revenue?

• Justify millions of dollars in saving over past 7

years in equipment failure avoidance

Page 16: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Engineering Desktop Demo

Page 17: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Summary of Worst Performing LTCs

Page 18: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

SME Knowledge of Asset

Page 19: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Algorithm Details

Page 20: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

History

Page 21: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Assessing Asset Condition

Assessing Asset Condition

CircuitsSAIFI

UndergroundNetwork

Reliability

SubstationReliability

PoorestPerforming

Devices (PPD)

Advanced Loop

Scheme (ALS)

VisibilityMonitoring

Dynamic Transformer Monitoring

TransformersBreakers/Relays

Page 22: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Asset Health Score

Page 23: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Asset Health Score – Drill down

Page 24: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Assessing Asset Condition

Assessing Asset Condition

CircuitsSAIFI

UndergroundNetwork

Reliability

SubstationReliability

PoorestPerforming

Devices (PPD)

Advanced Loop

Scheme (ALS)

VisibilityMonitoring

Dynamic Transformer Monitoring

TransformersBreakers/Relays

Page 25: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

SAIFI

Industry vs. PSE&G

0

0.2

0.4

0.6

0.8

1

1.2

2007 2008 2009 2010 2011 2012

PSE&G

Industry

Page 26: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Traditional 13 kV Recloser Loop Scheme

Self-Healing Loops

TieFdr #1 Fdr #1

Station #1 Station #2

Existing Configuration

Page 27: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Advance Loop Scheme (ALS)

451S

451S

651R 651R 651R 651R 651R

651R

651R651R651R651R

Station #1

Station #2

R FR

1

R

tie

FR

2

FR

3

FR

4

FR

5

FR

1

FR

2

FR

3

FR

4

Fiber

Optic

Cable

High Speed

Communications

Page 28: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Summary of Reliability BenefitsInnovations Current System Smart Grid

Customer

Segmentation

(SAIFI)System Average Interruption

Frequency Index

Average 1500

customers Impacted per

outage

Average 500 Customers

Impacted per outage

Single Phase

Tripping

(SAIFI) < 5 Minutes

System Average Interruption

Frequency Index

Not Implemented

Average 1500

customers Impacted per

outage

Average 167 single

phase customers

impacted per outage

Make Before Break

(MAIFI) >5 Minutes

Momentary Average Interruption

Frequency Index

Momentary Interruption

30-60 seconds

No Momentary

Interruptions

Page 29: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Comparing – SAIFI Improvements

Options Cost

Traditional Approach

Trim tree’s, replace equipment $6 - 12 M per loop

Smart Grid Technology

Limit risk, add communications (fiber), and

leverage technology$2 - 4 M per loop

Both options produce similar SAIFI results for the first year

Page 30: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Enhancements to SAIFI assessment

and asset management programs…

OpportunityRising SAIFI Trends are not adequately

being addressed with current

Asset Management Programs

SolutionLeverage

opportunitiesto improve toolsfor investment prioritization

BarriersCulture Change

System upgradesDedicated personnel

Securing funding

OutcomeA device based

program that has optimized

SAIFI reduction and spend

…will mitigate rising electric distribution SAIFI trends.

Page 31: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Poorest Performing Device (PPD) Program

Targeting extended customers interrupted, a two part

asset evaluation algorithm was developed, modeled after

our current inside plant CMMS system structure.

Frequency

•Number of occurrences

30%

CustomersInterrupted

•Number of customer interruptions

60%

Remediation Complexity

•Variance of cause codes

10%

I. Incident Evaluator Algorithm:

Device Health Score provides the basis for an initial prioritization of potential projects, subject to further field inspections and cost estimates as described below.

SAIFI Yieldon Investment(Yield Score)

Remediation Cost Estimate

SAIFI Benefit Validation

•Scope of work assessment by field

engineering / asset management

–SAIFI benefit validation

–Remediation cost estimates

II. Field Inspection, SAIFI validation and Cost Estimates:

Scope of work assessment in field provides basis for cost estimate and validation of SAIFI benefit.

Benefits and costs form basis for SAIFI Investment Yield calculation and final prioritization of projects.

Page 32: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Incremental SAIFI Benefit vs. Cumulative Cost

0.00

0.05

0.10

0.15

0.20

0.25

0.30

$- $20.0 $40.0 $60.0 $80.0 $100.0 $120.0 $140.0

Cost in $Millions

Inc

rem

en

tal

SA

IFI

Be

ne

fit

Reliability Base Spend plus Incremental Device Approach Spend ($M)

SAIFI Benefit

attained from Incremental Spend

Page 33: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Remediation Options Prioritized by SAIFI Yield

0

0.02

0.04

0.06

0.08

0.1

0.12

0.14

0.16

1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96 101 106 111 116 121 126

Prioritized Remediation Projects

Yie

ld (

SA

IFI/$

Millio

n In

ve

ste

d

= Metro

= Central = Palisades

= Southern

SAIFI Yield (SAIFI Benefit/ $ Invested)

Page 34: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

SAIFI Trending

Non-Weather Day (Blue Sky) vs Weather Day

0.63 0.64

0.69 0.69

0.76

0.70

0.84

0.78

0.66

0.43

0.470.45

0.500.47

0.510.48

0.54

0.210.18

0.24 0.250.23

0.19

0.35

0.24

0.70

0.420.42

0.24

0.27

48 49

95

7067

68

65 62 6253

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012

SA

IFI

0

50

100

150

200

250

300

350

400

450

500

Da

ys

Overall SAIFI Non-Weather Day SAIFI (Blue Sky) Weather Day SAIFIWeather Days Log. (Weather Days) Log. (Overall SAIFI)Log. (Non-Weather Day SAIFI (Blue Sky)) Log. (Weather Day SAIFI)

* Weather Day Definition -

Temp >=90

OR any two of the following:

- 1" Liquid Precip

- Thunderstorms

- Sustained Wind >= 30 mph

- Wind Gusts >= 35 mph

Note: 2012 data is pro-rated based on 5 Year AverageData through 9/30/2012

0.49

0.30

0.19

59

Page 35: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Assessing Asset Condition

Assessing Asset Condition

CircuitsSAIFI

UndergroundNetwork

Reliability

SubstationReliability

PoorestPerforming

Devices (PPD)

Advanced Loop

Scheme (ALS)

VisibilityMonitoring

Dynamic Transformer Monitoring

TransformersBreakers/Relays

Page 36: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Networking Monitoring System

(NMS)

• Reduce restoration time for underground cables.

• Pattern recognition to determine type of fault.

• Visibility to all key underground network assets

• Consolidated asset inspection, test and maintenance data

• Consistent information base for comparative analysis

Page 37: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

System Visualization

Page 38: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Vault Summary KVA, Amps and Status

Page 39: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Protector Backfeed

Page 40: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Networking Monitoring System

(NMS) Benefits

• Provides control and indication• Provides Condition Assessment for transformers

and network protector• Remote access to network relays for settings and

validation.• O&M savings

– OT savings (5% reduction in CM)– “Day priors” can be done via system rather than

by field crew– Improved response & turnaround during faults

Page 41: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

26KV Underground Network Display

Page 42: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

UG Transmission Action & Lifecycle

Strategy

Lifecycle

Analysis

Pipes

Average Circuit Score By

Asset

Condition Assessment at Asset Level to identify

troubled assets

Replacement Strategy at

Circuit Level

SplicesPumping

PlantsTerminators

Gas/Physical

Analysis

Age/DesignFluid/X-Ray

AnalysisFluid

Analysis

Page 43: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

OH Transmission Action & Lifecycle

Strategy

Lifecycle

Analysis

Average Circuit Score By

Asset

Condition Assessment at Asset Level to identify

troubled assets

Replacement Strategy at

Circuit Level

TowersConductors

Age

Hardware Condition

Insulator Condition

Age

Structure Design

Hardware/Foundation

Condition

Paint Condition

Page 44: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Future Vision

• Cyber Security

• Asset Reliability Management System

• Outage Management

• Graphic Information System

• Mobile Data

• Risk Management

Page 45: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

Asset Reliability Management

SystemTo Be Virtual Dispatch Center

CMMS PI SystemHDW

Metro

CentralPalisades

Southern

ESOC

OMS

GIS Asset Mgr’sEngineers/Planners DERC

Advanced

Applications

The overall initiative focuses on utilizing, improving and augmenting the overall capabilities of the Transmission Operation System while incorporating new technology, methodology, recognizing and capitalizing on business drivers and opportunities along the way.

Page 46: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

© Copyr i g h t 2013 OS Iso f t , LLC .

The Future of GIS and OMS

Desktop Server Mobile Online

Promoting easy flow of information for better business

decisions

Asset

Management

Planning &

Analysis

Field

Mobility

Operational

Awareness

Collect, organize

& exchange data

Transform data

Into actionable

information

Get the

information

where it is most

needed

Foster a culture

That disseminates

knowledge

Page 47: How to Use This Presentation Template · • Utility Overview –New Jersey Based –Total Assets ~ $14 Billion –Total Revenue ~ $7 Billion • Service Territory –323 Municipalities

Thank you

© Copyright 2013 OSIsoft, LLC.

777 Davis St., San Leandro, CA 94577