How to TECO the production orders

Use transaction :COHV

Mass processing production orders

Note: This is the best and easiest way to TECO the production orders in one go.

Page 2: How to teco the production orders - Murali Krishna Nookella

Enter the transaction code: COHV and press enter

Page 3: How to teco the production orders - Murali Krishna Nookella

You will come to this screen

Page 4: How to teco the production orders - Murali Krishna Nookella

Enter the data mentioned here and scroll down

Page 5: How to teco the production orders - Murali Krishna Nookella

Actual start date is the date of actual confirmation

Actual finish date is the date of actual final confirmation done or production received.

Page 6: How to teco the production orders - Murali Krishna Nookella

Click on execute icon

Page 7: How to teco the production orders - Murali Krishna Nookella

System will display all the production orders in the mentioned dates.And it displays the orders that do not have status of TECO and PCNF.

Note: We need to TECO the orders that are confirmed and delivered.

Status: REL,CNF,DLV

Page 8: How to teco the production orders - Murali Krishna Nookella

Click here to select all the orders.

Page 9: How to teco the production orders - Murali Krishna Nookella

Choose the above path

Page 10: How to teco the production orders - Murali Krishna Nookella

System will pop up the above window.

Page 11: How to teco the production orders - Murali Krishna Nookella

Choose Technically complete from the above list

Page 12: How to teco the production orders - Murali Krishna Nookella

Click on execute icon

Page 13: How to teco the production orders - Murali Krishna Nookella

Click on refresh icon

Page 14: How to teco the production orders - Murali Krishna Nookella

Check the status now. All the orders have status have TECO,CNF and DLV status.

Now these orders can be settled and period end closing can be done.