Alcatel RRH2x40 commisioning steps

TRANSCRIPT

  • In user name : commteIn password : bts2siteNow you can able to connect with BTS commissioning software

  • In the "BTS Interface settings" window select the appropriate interface.6. If the RS232 serial interface is used select the appropriate COM Portand Baud rate, as required.7. If the IP connection is used select the Ethernet and enter the IP Address ofthe BTS: 192.168.255.249

  • From the menu bar, select:Configuration -> BTS Software DownloadThe "Software Download" window opens.Select the required master file, the CPF file and the CODA file using thefolder icon button.3. Click on [ OK ] to start the software download.

  • The "SUM Initial Settings" window allows you to:Display the board HW and SW informationSet the CRC CheckModify the Clock Reference.To open the "Initial Settings" window, select:Configuration -> Transmission Settings... -> SUM Initial Settings

  • The second Abis interface is supported only by SUMA board and in order touse this interface, the Environment for Abis 1 must be declared as Chain- end position.To open the "SUM Board Configuration" window, select:Configuration -> Transmission Settings... -> SUM Board Configuration

  • Click on [ Start Commissioning ] to activate the commissioning tasks.

  • Click on the [ Start ] button corresponding to the Edit Q1 Address task.The "Q1 Address Setting" window is displayed,

  • Click on the [ Start ] button corresponding to the Edit Remote Inventory task.The "Edit Remote Inventory" window is displayed,

  • Click on the [ Start ] button corresponding to the change logical site name

  • Click on the [ Start ] button corresponding to the Edit Sector Mapping task.The "Sector Mapping" window is displayed,

  • From the "BTS Commissioning" window, click on the [ Start ] buttoncorresponding to the MC_RRH Sector Mapping.

  • From the "BTS Commissioning" window, click on [ Start ] buttoncorresponding to the Twin - TRA Settings task.

  • From the "BTS Commissioning" window click on [ Start ] buttoncorresponding to the Multicarrier Settings task.

  • From the "BTS Commissioning" window click on [ Start ] buttoncorresponding to the Overbooking Settings task.

  • Click on [ Start ] button corresponding to the Init All Sectors taskThe "Init All Sectors" window is displayed

  • Click on [ Start ] button corresponding to the Init Single Sector taskThe "Init Single Sector" window is displayed,Select the available sector to be initialized and click on [ > ] to move thesector in the "Selected Sector" window.Click on [ OK ] to initialize the sector.When the initialization is finished the "Init Single Sector" window is closed.

  • Click on [ Start ] button corresponding to the Init Single TRE taskThe "Init Single TRE" window is displayed,Select the available TRE to be initialized and click on [ > ] to move theTRE in the "Selected TRE" window.3. Click on [ OK ] to initialize selected TREs.When the initialization is finished the "Init Single TRE" window is closed.

  • Click on [ Start ] button corresponding to the VSWR measurement task.The "VSWR Measurement"Select the following measurement parameters:ANX Dvie: ANX** (** = ANX position)Frequency Band: available frequencyPort A FrequencyPort B Frequency Output Power Attenuation: 0 dB (maximum power)Measuring Period: 10 seconds.Urgent Alarm Threshold Value: 33. Click on [ Start ] to start VSWR measurement. The measurement status isdisplayed in the status bar of the "BTS Commissioning"

  • Click on [ Start ] button corresponding to the Write Inventor task.The "Write Inventor" window is displayed,

  • Click on [ End Commissioning ].The "Stop Commissioning" window is displayed, as shown in the followingfigure.