how to choose between maintenance policies 2

Upload: orlandoduran

Post on 04-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    1/13

    The analytic hierarchy process applied to maintenance strategy selection

    M. Bevilacquaa, M. Bragliab,*

    aDipartimento di Ingegneria Industriale, Universitadegli Studi di Parma, Viale delle Scienze, 43100 Parma, ItalybDipartimento di Ingegneria Meccanica, Nucleare e della Produzione, Universitadegli Studi di Pisa, Via Bonanno Pisano 25/B, 56126 Pisa, Italy

    Received 12 October 1999; accepted 24 March 2000

    Abstract

    This paper describes an application of the Analytic Hierarchy Process (AHP) for selecting the best maintenance strategy for an important

    Italian oil refinery (an Integrated Gasification and Combined Cycle plant). Five possible alternatives are considered: preventive, predictive,

    condition-based, corrective and opportunistic maintenance. The best maintenance policy must be selected for each facility of the plant (about

    200 in total). The machines are clustered in three homogeneous groups after a criticality analysis based on internal procedures of the oil

    refinery. With AHP technique, several aspects, which characterise each of the above-mentioned maintenance strategies, are arranged in a

    hierarchic structure and evaluated using only a series of pairwise judgements. To improve the effectiveness of the methodology AHP is

    coupled with a sensitivity analysis. 2000 Elsevier Science Ltd. All rights reserved.

    Keywords: Maintenance; Process plant; Failure mode effect and criticality analysis technique; Analytic hierarchy process

    1. Introduction

    Many companies think of maintenance as an inevitable

    source of cost. For these companies maintenance operations

    have a corrective function and are only executed in emer-gency conditions. Today, this form of intervention is no

    longer acceptable because of certain critical elements such

    as product quality, plant safety, and the increase in main-

    tenance department costs which can represent from 15 to

    70% of total production costs.

    The managers have to select the best maintenance policy

    for each piece of equipment or system from a set of possible

    alternatives. For example, corrective, preventive, opportu-

    nistic, condition-based and predictive maintenance policies

    are considered in this paper.

    It is particularly difficult to choose the best mix of main-

    tenance policies when this choice is based on preventive

    elements, i.e. during the plant design phase. This is thesituation in the case examined in this paper, that of an Inte-

    grated Gasification and Combined Cycle plant which is

    being built for an Italian oil company. This plant will

    have about 200 facilities (pumps, compressors, air-coolers,

    etc.) and the management must decide on the maintenance

    approach for the different machines. These decisions will

    have significant consequences in the short-medium term for

    matters such as resources (i.e. budget) allocation, technolo-

    gical choices, managerial and organisational procedures,

    etc. At this level of selection, it is only necessary to define

    the best maintenance strategy to adopt for each machine,

    bearing in mind budget constraints. It is not necessary to

    identify the best solution from among the alternatives thatthis approach presents. The maintenance manager only

    wants to recognise the most critical machines for a pre-

    allocation of the budget maintenance resources, without

    entering into the details of the actual final choice. This

    final choice would, in any case, be impossible because the

    plant is not yet operating and, as a consequence, total

    knowledge of the reliability aspects of the plant machines

    is not yet available. In other words, the problem is not

    whether it is better to control the temperature or the vibra-

    tion of a certain facility under analysis, but only to decide if

    it is better to adopt a condition-based type of maintenance

    approach rather than another type. The second level of deci-

    sion making concerns a fine tuned selection of the alterna-tive maintenance approaches (i.e. definition of the optimal

    maintenance frequencies, thresholds for condition-based

    intervention, etc.). This level must be postponed until data

    from the operating production system becomes available.

    Several attributes must be taken into account at this first

    level when selecting the type of maintenance. This selection

    involves several aspects such as the investment required,

    safety and environmental problems, failure costs, reliability

    of the policy, Mean Time Between Failure (MTBF) and

    Mean Time To Repair (MTTR) of the facility, etc. Several

    of these factors are not easy to evaluate because of their

    Reliability Engineering and System Safety 70 (2000) 7183

    0951-8320/00/$ - see front matter 2000 Elsevier Science Ltd. All rights reserved.

    PII: S0951-8320(00) 00047-8

    www.elsevier.com/locate/ress

    * Corresponding author. Fax: 39-050-913-040.

    E-mail address: [email protected] (M. Braglia).

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    2/13

    intangible and complex nature. Besides, the nature of the

    weights of importance that the maintenance staff must give

    to these factors during the selection process is highly subjec-

    tive. Finally, bearing in mind that the plant is still in the

    construction phase, some tangible aspects such as MTBF

    and MTTR can be only estimated from failure data concern-

    ing machines working in other plants (in this case oil refi-

    neries) under more or less similar operating conditions.

    Furthermore, they will affect each single facility analysed

    in a particular way and, as a consequence, the final main-

    tenance policy selection.

    It is therefore clear that the analysis and justification of

    maintenance strategy selection is a critical and complex task

    due to the great number of attributes to be considered, many

    of which are intangible. As an aid to the resolution of this

    problem, some multi-criteria decision making (MCDM)

    approaches are proposed in the literature. Almeida and

    Bohoris [1] discuss the application of decision making

    theory to maintenance with particular attention to multi-

    attribute utility theory. Triantaphyllou et al. [2] suggestthe use of Analytical Hierarchy Process (AHP) considering

    only four maintenance criteria: cost, reparability, reliability

    and availability. The Reliability Centered Maintenance

    (RCM) methodology (see, for example, Ref. [3]) is probably

    the most widely used technique. RCM represents a method

    for preserving functional integrity and is designed to mini-

    mise maintenance costs by balancing the higher cost of

    corrective maintenance against the cost of preventive main-

    tenance, taking into account the loss of potential life of the

    unit in question [4].

    One of the tools more frequently adopted by the compa-

    nies to categorise the machines in several groups of risk isbased on the concepts of failure mode effect and criticality

    analysis technique (FMECA). This methodology has been

    proposed in different possible variants, in terms of relevant

    criteria considered and/or risk priority number formulation

    [5]. Using this approach, the selection of a maintenance

    policy is performed through the analysis of obtained priority

    risk number. An example of this approach has also been

    followed by our oil company, which has developed its

    own methodology internally. This approach makes it

    possible to obtain a satisfying criticality clustering of

    the 200 facilities into three homogeneous groups. The

    problem is to define the best maintenance strategy for

    each group.To integrate the internal self-made criticality approach,

    this paper presents a multi-attribute decision method based

    on the AHP approach to select the most appropriate main-

    tenance strategy for each machine group. In this procedure,

    several costs and benefits for each alternative maintenance

    strategy are arranged in a hierarchic structure and evaluated,

    for each facility, through the use of a series of pairwise

    judgements. Finally, considering that the maintenance

    manager can never be sure about the relative importance

    of decision making criteria selected when dealing with

    this complex maintenance problem, to improve the AHP

    effectiveness the methodology is coupled with a sensitivity

    analysis phase.

    2. The API oil refinery IGCC plant: a brief description

    The Integrated Gasification and Combined Cycle(IGCC) plant [6], currently being assembled at The

    Falconara Marittima API oil refinery, will make it

    possible to transform the oil refinement residuals into

    the synthesis gases which will be used as fuel to

    produce electricity. The IGCC plan will be placed in

    a 47,000 m2 area inside the oil refinery.

    The electricity produced by the IGCC plant will be sold to

    ENEL (Italian electrical energy firm) while some

    65,000 ton/h of steam will be used inside the oil refinery

    for process requirements. The total cost of the project

    amounts to about 750 million dollars.

    In recent years, economic and legislative changes

    have led to increased co-operation between petrochem-

    ical and electrical firms. The adoption of strict environ-

    mental standards, both in Europe and in the United

    States, is forcing oil refinery firms to reduce the emis-

    sions of pollutants from the process plants and reduce

    the potential pollution of the refined products. The same

    pollution control requirements, mainly a reduction in the

    level of nitrogen and sulphur oxides, together with the

    increasing need to control operating and investments

    costs, is pushing electrical firms to search for more

    economic and cleaner production methods.

    The combined effect of the above-mentioned factors has

    led several oil refineries to adopt IGCC technology for oilrefinement heavy residuals processing. IGCC technology

    has proved to be a valid solution to the market requirement

    of efficient, clean, low consuming and environmentally

    orientated production technologies.

    The API oil refinery uses a thermal conversion process

    and has a production capacity of about 4,000,000 tons of oil

    per year (80,000 barrels per day). The production cycle is

    typical of oil refineries with a similar production capacity:

    the current distilled yield is higher than 70% and the resi-

    duals are used to produce fuel oil and bitumen. Oil refine-

    ment heavy residuals with a high sulphur content will be

    partly converted into the synthesis gases syngas (whichwill be cleaned in the IGCC gasifiers) and partly used to

    produce bitumen.

    The three main objectives of the oil refinery management

    are the following:

    1. the elimination of heavy residuals used to produce fuel

    oil with high and low sulphur content;

    2. the ability to process almost every type of heavy oil with

    a high sulphur content;

    3. the substitution of the present low efficiency thermoelec-

    trical power plant with a more efficient system, with

    lower levels of pollutant emissions.

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 71 8372

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    3/13

    3. Possible alternative maintenance strategies

    Five alternative maintenance policies are evaluated in this

    case study. Briefly, they are the following.

    Corrective maintenance. The main feature of corrective

    maintenance is that actions are only performed when a

    machine breaks down. There are no interventions until afailure has occurred.

    Preventive maintenance. Preventive maintenance is

    based on component reliability characteristics. This

    data makes it possible to analyse the behaviour of the

    element in question and allows the maintenance engineer

    to define a periodic maintenance program for the

    machine. The preventive maintenance policy tries to

    determine a series of checks, replacements and/or

    component revisions with a frequency related to the fail-

    ure rate. In other words, preventive (periodic) mainte-

    nance is effective in overcoming the problems

    associated with the wearing of components. It is evidentthat, after a check, it is not always necessary to substitute

    the component: maintenance is often sufficient.

    Opportunistic maintenance. The possibility of using

    opportunistic maintenance is determined by the nearness

    or concurrence of control or substitution times for differ-

    ent components on the same machine or plant. This type

    of maintenance can lead to the whole plant being shut

    down at set times to perform all relevant maintenance

    interventions at the same time.

    Condition-based maintenance. A requisite for the appli-

    cation of condition-based maintenance is the availability

    of a set of measurements and data acquisition systems to

    monitor the machine performance in real time. Thecontinuous survey of working conditions can easily and

    clearly point out an abnormal situation (e.g. the exceed-

    ing of a controlled parameter threshold level), allowing

    the process administrator to punctually perform the

    necessary controls and, if necessary, stop the machine

    before a failure can occur.

    Predictive maintenance. Unlike the condition-based

    maintenance policy, in predictive maintenance the

    acquired controlled parameters data are analysed to find

    a possible temporal trend. This makes it possible to

    predict when the controlled quantity value will reach or

    exceed the threshold values. The maintenance staff willthen be able to plan when, depending on the operating

    conditions, the component substitution or revision is

    really unavoidable.

    4. The IGCC plant maintenance program definition

    An electrical power plant based on IGCC technology is a

    very complex facility, with a lot of different machines and

    equipment with very different operating conditions. Decid-

    ing on the best maintenance policy is not an easy matter,

    since the maintenance program must combine technical

    requirements with the firms managerial strategy. The

    IGCC plant complex configuration requires an optimal

    maintenance policy mix, in order to increase the plant avail-

    ability and reduce the operating costs.

    Maintenance design deals with the definition of the best

    strategies for each plant machine or component, depending

    on the availability request and global maintenance budget.

    Every component, in accordance with its failure rate, cost

    and breakdown impact over the whole system, must be

    studied in order to assess the best solution; whether it is

    better to wait for the failure or to prevent it. In the latter

    case the maintenance staff must evaluate whether it is better

    to perform periodic checks or use a progressive operating

    conditions analysis.

    It is clear that a good maintenance program must define

    different strategies for different machines. Some of these

    will mainly affect the normal operation of the plant, some

    will concern relevant safety problems, and others will

    involve high maintenance costs. The overlapping of theseeffects enables us to assign a different priority to every plant

    component or machine, and to concentrate economic and

    technical efforts on the areas that can produce the best

    results.

    One relevant IGCC plant feature is the lack of historical

    reliability and maintenance costs data (the plant start-up is

    proposed for March 2000). Initially, the definition of the

    maintenance plan will be based upon reliability data from

    the literature and on the technical features of the machines.

    This information will then be updated using the data

    acquired during the working life of the plant. The analysis

    system has been structured in a rational way so as to keepthe update process as objective as possible. This has been

    accomplished through the use of a charting procedure, using

    well-understood evaluations of different parameters and a

    simple and clear analysis of corrective interventions. The

    maintenance plan developed for the machines of the IGCC

    plant is based on the well-known FMECA technique [7,8].

    The analysis results have provided a criticality index for

    every machine, allowing the best maintenance policy to

    be selected.

    4.1. The maintenance strategy adopted by the oil refinery

    company

    The internal methodology developed by the company to

    solve the maintenance strategy selection problem for the

    new IGCC plant is based on a criticality analysis which

    may be considered as an extension of the FMECA techni-

    que. This analysis takes into account the following six

    parameters:

    safety;

    machine importance for the process;

    maintenance costs;

    failure frequency;

    downtime length;

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 ( 2000) 71 83 73

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    4/13

    operating conditions;

    with an additional evaluation for the

    machine access difficulty.

    Note that, the six parameters presented below derived

    from an accurate pre-analysis to select all of the relevant

    parameters that can contribute to the machine criticality. As

    reported by the maintenance manager, 12 criteria have initi-

    ally been considered:

    a.Safety.Considering the safety of personnel, equipment,

    the buildings and environment in the event of a failure.

    b. Machine importance for the process. The importance

    of the machine for the correct operation of the plant. For

    instance, the presence of an inter-operational buffer to

    stock the products can reduce the machine criticality

    since the maintenance intervention could be performed

    without a plant shutdown.

    c.Spare machine availability.Machines that do not have

    spares available are the most critical.

    d. Spare parts availability. The shortage of spare partsincreases the machine criticality and requires a replenish-

    ment order to be issued after a failure has occurred.

    e. Maintenance cost. This parameter is based on

    manpower and spare parts costs.

    f. Access difficulty. The maintenance intervention can be

    difficult for machinesarranged in a compact manner,placed

    in a restrict area because they are dangerous, or situated at a

    great height (for example, some agitators electric motors

    and air-cooler banks). The machine access difficulty

    increases the length of downtime and, moreover, increases

    the probability of a failure owing to the fact that inspection

    teams cannot easily detect incipient failures.

    g.Failure frequency.This parameter is linked to the meantime between failures(MTBF) of the machine.

    h.Downtime length.This parameter is linked to the mean

    time to repair(MTTR) of the machine.

    i.Machine type.A higher criticality level must be assigned

    to the machines which are of more complex construction.

    These machines are also characterised by higher mainte-

    nance costs (material and manpower) and longer repair

    times.

    l. Operating conditions. Operating conditions in the

    presence of wear cause a higher degree of machine

    criticality.

    m. Propagation effect. The propagation effect takes into

    account the possible consequences of a machine failure

    on the adjacent equipment (domino effect).

    n. Production loss cost. The higher the machine importance

    for the process, the higher the machine criticality due to a

    loss of production.

    To restrict the complexity (and the costs) of the analysisto be performed, the number of evaluation parameters is

    reduced by grouping together those that are similar and by

    removing the less meaningful ones. An increase in the

    number of parameters does not imply a higher degree of

    analysis accuracy. With a large number of parameters the

    analysis becomes much more onerous in terms of data

    required and elaboration time. Besides, the quantitative

    evaluation of the factors described is complex and subject

    to the risk of incorrect estimates. The following clusters

    were created.

    The spare machine availability mainly affects the unin-

    terrupted duration of the production process and can there-

    fore be linked to the machine importance for the process

    and the production loss cost. In terms of spare parts, the

    maintenance cost can include the machine type factor,

    while the manpower contribution to the maintenance cost

    can be clustered with the downtime length attribute.

    System safety, failure frequency, access difficulty

    and operating conditions are considered to be stand-

    alone factors by the maintenance staff.

    For every analysed machine of the new IGCC plant, a

    subjective numerical evaluation is given adopting a scale

    from 1 to 100. Finally, the factors taken into consideration

    are linked together in the following criticality index CI:

    CI S 15 IP 25 MC 2 FF 1

    DL 15 OC 1 AD 1

    where Ssafety, IPmachine importance for the process,

    MCmaintenance costs, FFfailure frequency, DL

    downtime length, OCoperating conditions, ADmachine access difficulty.

    In the index, the machine access difficulty has been

    considered by the management to be an aggravating aspect

    as far as the equipment criticality is concerned. It is there-

    fore suitable to evaluate the effect of the machine accessdifficulty as an a posteriori factor. For this reason with

    this approach the machine criticality index has been multi-

    plied by the machine access difficulty.

    A rational quantification of the seven factors has been

    defined and based on a set of tables. In particular, every

    relevant factor is divided into several classes that are

    assigned a different score (in the range form 1 to 100) to

    take into account the different criticality levels. For the sake

    of brevity, only the evaluation of the machine importance

    for the process attribute is reported as an example in

    Appendix A.

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 71 8374

    Table 1

    Weight values assigned to the relevant parameters considered in FMECA

    analysis

    Parameter Weight

    Safety 1.5

    Machine importance for the process 2.5

    Maintenance costs 2Failure frequency 1

    Downtime length 1.5

    Operating conditions 1

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    5/13

    The weighted values assigned by the maintenance staff to

    the different parameters are shown in Table 1.

    The weight assigned to safety is not the highest because in

    an IGCC plant danger is intrinsic to the process. The oper-

    ating conditions are weighted equal to one in accordance

    with the hypothesis of a correct facility selection as a func-

    tion of the required service. The breakdown frequency is

    weighted equal to one in virtue of the fact that failure

    rates are currently estimated values only.

    The CI index has been used to classify about 200

    machines of the plant (pumps, compressors, air coolers,

    etc.) into three different groups corresponding to threedifferent maintenance strategies, as shown in Table 2.

    Note that only corrective, preventive and predictive main-

    tenance strategies have been taken into account by the refin-

    ery maintenance management.

    The main features of the three groups are the following:

    Group 1. A failure of group 1 machines can lead to

    serious consequences in terms of workers safety, plant

    and environmental damages, production losses, etc.

    Significant savings can be obtained by reducing the fail-

    ure frequency and the downtime length. A careful

    maintenance (i.e. predictive) can lead to good levelsof company added-value. In this case, savings in

    maintenance investments are not advisable. This

    group contains about the 70% of the IGCC machines

    examined.

    Group 2. The damages derived from a failure can be

    serious but, in general, they do not affect the external

    environment. A medium cost reduction can be

    obtained with an effective but expensive mainte-

    nance. Then an appropriate cost/benefit analysis

    must be conducted to limit the maintenance invest-

    ments (i.e. inspection, diagnostic, etc.) for this type

    of facilities (about the 25% of the machines). For this

    reason a preventive maintenance is preferable to amore expensive predictive policy.

    Group 3. The failures are not relevant. Spare parts

    are not expensive and, as a consequence, low levels

    of savings can be obtained through a reduction of

    spare stocks and failure frequencies. With a tight

    budget the maintenance investments for these types

    of facilities should be reduced, also because the

    added-value derived from a maintenance plan is

    negligible. The cheapest corrective maintenance is,

    therefore, the best choice. Group 3 contains 5% of

    the machines.

    4.2. Critical analysis of oil company maintenance MCDM

    methodology

    Some aspects of the criticality index CI proposed and

    prepared by the maintenance staff are open to criticism.

    Eq. (1) represents a strange modified version of the

    weighted sum model (WSM), which probably represents

    the simplest and still the most widely used MCDM method[2]. But, in this case, there are some weaknesses.

    (a) The WSM is based on the additive utility supposi-

    tion [2]. However, the WSM should be used only when

    the decision making criteria can be expressed in identical

    units of measure.

    (b) The AD factor should be added and not used as a

    multiplying factor.

    (c) Dependencies among the seven attributes should be

    carefully analysed and discussed.

    (d) The weight values reported in Table 1 are not justified

    in a satisfying manner. The maintenance staff also have

    serious doubts about these values, which would suggest

    that they have little confidence in the final results

    obtained by the MCDM model. Moreover, no sensibility

    analyses have been conducted to test the robustness of the

    results. This fact is probably due to (i) a sensitivity analy-

    sis is not an easy matter, and (ii) the absence of a software

    package supporting this request.

    Despite these problems, the classification produced using

    the CI index has made it possible to define three homoge-

    neous groups of machines. The composition of the clusters

    confirms the expectations of the maintenance staff and is

    considered to be quite satisfactory. On the other hand, the

    doubts of the maintenance staff mainly concern the main-

    tenance strategy to adopt for each group of machines. This

    factor has been used as the starting point for the develop-

    ment of an AHP approach to assign the best maintenance

    strategy to each cluster element, taking into account several

    possible aspects.

    5. The analytic hierarchy process

    The AHP [911] is a powerful and flexible multi-criteria

    decision making tool for complex problems where both

    qualitative and quantitative aspects need to be considered.The AHP helps the analysts to organise the critical aspects

    of a problem into a hierarchical structure similar to a family

    tree. By reducing complex decisions to a series of simple

    comparisons and rankings, then synthesising the results, the

    AHP not only helps the analysts to arrive at the best deci-

    sion, but also provides a clear rationale for the choices

    made.

    Briefly, the step-by-step procedure in using AHP is the

    following:

    1. define decision criteria in the form of a hierarchy of

    objectives. The hierarchy is structured on different levels:

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 ( 2000) 71 83 75

    Table 2

    Maintenance policy selection based on criticality index

    Criticality index Maintenance policy

    395 Predictive

    290395 Preventive

    290 Corrective

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    6/13

    from the top (i.e. the goal) through intermediate levels

    (criteria and sub-criteria on which subsequent levelsdepend) to the lowest level (i.e. the alternatives);

    2. weight the criteria, sub-criteria and alternatives as a func-

    tion of their importance for the corresponding element of

    the higher level. For this purpose, AHP uses simple pair-

    wise comparisons to determine weights and ratings so

    that the analyst can concentrate on just two factors at

    one time. One of the questions which might arise when

    using a pairwise comparison is: how important is the

    maintenance policy cost factor with respect to the

    maintenance policy applicability attribute, in terms of

    the maintenance policy selection (i.e. the problem

    goal)? The answer may be equally important, moder-ately more important, etc. The verbal responses are then

    quantified and translated into a score via the use of

    discrete 9-point scales (see Table 3);

    3. after a judgement matrix has been developed, a priority

    vector to weight the elements of the matrix is calculated.

    This is the normalised eigenvector of the matrix.

    The AHP enables the analyst to evaluate the goodness of

    judgements with the inconsistency ratio IR. The judgements

    can be considered acceptable ifIR 01In cases of incon-

    sistency, the assessment process for the inconsistent matrix

    is immediately repeated. An inconsistency ratio of 0.1 or

    more may warrant further investigation. For more details onIR, the reader may refer to Saaty [9].

    After its introduction by Saaty [9], AHP has been widely

    used in many applications [12]. Designed to reflect the way

    people actually think, the AHP was developed more than 20

    years ago and it is one of the most used multi-criteria deci-

    sion-making techniques. This fact is probably due to some

    important aspects of AHP such as [13]: (1) the possibility to

    measure the consistency in the decision makers judgement;

    (2) it does not, in itself, make decisions but guides the

    analyst in his decision making; (3) it is possible to conduct

    a sensitivity analysis; (4) AHP can integrate both

    quantitative and qualitative information; and (5) it is well

    supported by commercial software programs. However, it is

    necessary to remember some possible problems with AHP

    (rank reversal, etc.) which are currently debated in the litera-

    ture [1416].

    6. The hierarchy scheme

    In designing the AHP hierarchical tree, the aim is to

    develop a general framework that satisfies the needs of the

    analysts to solve the selection problem of the best mainte-

    nance policy. The AHP starts by breaking down a complex,

    multi-criteria problem into a hierarchy where each level

    comprises a few manageable elements which are then

    broken down into another set of elements. Considering the

    critical aspect of this step for the AHP methodology, the

    structure has been created following suggestions from the

    maintenance and production staff of the oil refinery (Fig. 1).

    The AHP hierarchy developed in this study is a five-leveltree in which the top level represents the main objective of

    maintenance selection and the lowest level comprises the

    alternative maintenance policies.

    The evaluation criteria that influence the primary goal are

    included at the second level and are related to four different

    aspects: damages produced by a failure, applicability of the

    maintenance policy, added-value created by the policy, and

    the cost of the policy. These criteria are then broken down

    into several sub-criteria as shown in Fig. 1.

    The definition of the hierarchy scheme described above

    has been developed using a brainstorming process. All the

    people concerned with maintenance problems in the oilrefinery where the IGCC plant is being built have been

    included in the study. In particular, we have involved the

    maintenance engineering personnel (who perform the criti-

    cality analyses and develop the maintenance improvement

    procedures), the MON (Maintenance On Site) and MOF

    (Maintenance Off Site) staff (who manage the maintenance

    operations for the transfer and the mixing of the oil refinery

    products).

    The hierarchy scheme has been based on the fees due

    during the oil refinery maintenance management. In this

    way the four criteria of the first level of the hierarchy

    have been immediately identified. Possible differences of

    opinion expressed by maintenance supervisors have beensmoothed using the Delphi technique. In this way we

    have tried to maximise the advantages of group dynamics

    and reduce the negative effects due to the subjectivity of

    opinions.

    The formal tool used during the hierarchy structure defi-

    nition was the Interpretive Structural Modelling (IMS)

    [17,18] approach. IMS is a well-established interactive

    learning process for identifying and summarising relation-

    ships among specific factors of a multi-criteria decision-

    making problem, and provides an efficient means by

    which a group of decision-makers can impose order on

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 71 8376

    Table 3

    Judgement scores in AHP

    Judgement Explanation Score

    Equally Two attribute contribute equally to the upper-

    level criteria

    1

    2

    Moderately Experience and judgement slightly favour oneattribute over another

    3

    4

    Strongly Experience and judgement strongly favour one

    attribute over another

    5

    6

    Very strongly An attribute is strongly favoured and its

    dominance demonstrated in practice

    7

    8

    Extremely The evidence favouring one attribute over

    another is of the highest possible order of

    affirmation

    9

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    7/13

    the complexity of the problem. The steps of this methodol-ogy are briefly the following [18]:

    a. identification of elements which are relevant to the

    decision making problem;

    b. a contextually relevant subordinate relation is chosen;

    c. a structural self-interaction matrix (SSIM) is developed

    based on pairwise comparison of elements;

    d. SSIM is converted into a reachability matrix and its

    transitivity is checked;

    e. once the transitivity has been achieved, the conversion

    of an object system into a well-defined matrix model is

    obtained;

    f. the partitioning of the elements and the extractionof the structural model, termed ISM is then

    performed.

    The relevant factors defining the damage criteria are iden-

    tified as loss of production, damages to facilities, to product,

    to environment, to people, and to company image. The

    production loss is linked to facility downtime derived

    from a failure (time required for detection, repair or repla-

    cement and re-starting) and divided in MTBF and MTTR in

    a successive hierarchy level. The facility damages are

    divided into direct and indirect: the direct damage deals

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 ( 2000) 71 83 77

    Fig. 1. The AHP hierarchy scheme adopted.

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    8/13

    with the tangible effects of the failure on the machine,

    the indirect damage takes into account the possible

    influences (i.e. reduction) of the failure on the working

    life of the plant as a consequence of a domino effect

    on other facilities and instruments. Finally, the environ-

    mental damage is divided into internal and external to

    the plant.

    For the maintenance policy applicability factor, twosub-criteria are taken into account: the costs required

    for the policy implementation and the reliability. The

    maintenance costs are divided into hardware (i.e.

    sensors), software (i.e. a reliability commercial soft-

    ware), and training costs. The reliability criterion

    includes the technical aspect of the maintenance strat-

    egy adopted in terms of fault detection capability and

    facility restoring capability.

    The added-value criterion deals with the indirect benefit

    of a particular maintenance policy. This category includes

    the improvements in terms of product quality, safety, and

    internal skills (i.e. an overall better knowledge of themachines employed).

    With respect to the policy cost factor, four sub-

    criteria have been considered for the successive hierar-

    chy level: MTBF, MTTR, saving in the stock of spare

    parts, and assurance aspects (i.e. possible decreases in

    insurance premiums that can be obtained by adopting a

    particular maintenance policy). Note that the investment

    required to implement the policy is not included as sub-

    criterion. This is due to the fact that the maintenance

    investment for a single machine is negligible with

    respect to the other sub-criteria of the policy cost

    factor. For this reason, the investment required attri-

    bute has been introduced only as sub-criterion of thepolicy applicability factor in the hierarchy.

    The proposed hierarchy must not be intended as a

    general for any process plant application, with some

    choices concerning only the particular IGCC plant

    here analysed. Besides, it is possible to note how

    some possible dependencies among the attributes have

    not been treated. These structure simplification choices

    derive from the necessity to obtain a good trade-off

    between a suitable level of detail and a manageable

    complexity of the hierarchy structure for actual

    industrial applications.

    7. The AHP analysis

    Once the hierarchy structure of the maintenance decisionmaking problem has been defined, the priorities of the

    scheme have been calculated using pairwise comparisons

    and the Delphi technique.

    The three machine groups previously described have

    been analysed through the use of the AHP methodology.

    In this situation five different alternative maintenance poli-

    cies have been considered. The pairwise judgements used to

    perform the AHP analysis were stated by the oil refinery

    maintenance management that developed the modified

    FMECA analysis shown in Section 4.

    Table 4 gives an example of the damages factor for the

    machines of Group 1, with the relative judgements of impor-tance (IR results equal to 003 01 obtained by adopting

    the quantitative scale showed in Table 3.

    It is clear that the most important aspect, in terms of

    damages, is the plant damage attribute. This consid-

    eration is due to the fact that the highest cost derived

    from an accident is due to production plant damages

    (direct and indirect, i.e. domino effect). Environmen-

    tal damage is the least important element because of the

    presence of modern and sophisticated safety systems

    that guarantee limited consequences for the environ-

    ment.

    Fig. 2 shows the global priority indices for each criterion,

    sub-criterion and alternative included in the AHP hierarchystructure for a particular Group 1 machine (a 23MW power

    air compressor).

    As can be seen, the overall inconsistency index is equal to

    0.046, which is less than the critical value of 0.1. For brev-

    ity, the partialIRvalues are not shown in the figure. Never-

    theless, all theIR values result lower than 0.1.

    Table 5 shows the final ranking for three machines, each

    representative of a different group.

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 71 8378

    Table 4

    Pairwise comparison example with respect to damages attribute for machines of Group 1. Note: row element is x(or 1/x) times more (or less) important than

    column element

    Production loss Plant damage Product damage Environmental damage People damage Image damage Local Priority

    Production loss 1/7 3 1/5 1/7 1 0.050

    Plant damage 9 3 1 9 0.352

    Product damage 1/7 1/9 1 0.030Environmental damage 1/3 7 0.181

    People damage 9 0.352

    Image damage 0.035

    Fig. 2. Global priority indices obtained for a Group 1 facility.

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    9/13

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    10/13

    As shown, the AHP results generally confirm the FMECA

    indications. Once again, for the Group 1 facility the best

    maintenance policy proves to be the predictive one. For

    these machines the most expensive and sophisticated stra-

    tegies (i.e. predictive and condition-based) are highly

    preferable with respect to the others because of the critical

    aspect of their failures.

    The Group 2 machine shows a slight preference for

    opportunistic maintenance even if preventive and predictive

    policies should not be neglected.

    The analysis performed for the machine belonging to

    Group 3 shows that corrective and preventive maintenance

    are equally appropriate. So, the decision to use corrective

    maintenance for this group of machines should be carefully

    considered. The limited failure consequence in terms of

    production loss is not sufficient to clearly and immediately

    state that no maintenance action should be performed before

    the failure.

    The three machines selected for the AHP analysis can be

    considered as representative of the corresponding groups. Inother words, they represent more or less the average char-

    acteristics of the facilities which belong to the same cluster.

    For this reason, the results obtained for this representative

    equipment have been extended to all facilities of the groups.

    This position has been considered sufficient and satisfactory

    by the maintenance staff. In any case, a more detailed analy-

    sis requiring a new set of pairwise judgements for each

    facility of each group can be always performed. This is

    probably the best solution for the extreme equipment

    characterised by the CI values near to the limit of the

    belonging cluster.

    8. Sensitivity analysis

    Although the ranking solution showed a possible scenario

    where, for example, damages aspects are clearly the most

    important criteria for Group 1 machines (see Fig. 2), the

    AHP solution can change in accordance with shifts in

    analyst logic. To explore the response of model solutions

    (i.e. the solution robustness) to potential shifts in the priority

    of maintenance strategies, a series of sensitivity analyses of

    criteria weights can be performed by changing the priority

    (relative importance) of weights. Each criterion can be char-

    acterised by an important degree of sensitivity, i.e. the rank-ing of all strategies changes dramatically over the entire

    weight range [19]. The problem is to check whether a few

    changes in the judgement evaluations can lead to significant

    modifications in the priority final ranking. For this reason,

    sensitivity analysis is used to investigate the sensitivity of

    the alternatives to changes in the priorities of the criteria at

    the level immediately below the goal. The analysis proposed

    emphasises the priorities of the four first-level criteria in

    the AHP model reported in Fig. 1 and shows how changing

    the priority of one criterion affects the priorities of the

    others. It is clear that as the priority of one of the criteria

    increases, the priorities of the remaining criteria must

    decrease proportionately, and the global priorities of the

    alternatives must be recalculated. All the results reported

    in Tables 68 were obtained using the Expertchoice soft-

    ware, a multi-attribute decision making tool which was used

    to support all the AHP applications reported in this paper.

    For example, from Table 6, one can clearly see the

    robustness of the predictive maintenance strategy for the

    machines that belong to Group 1. This policy remains the

    best solution, increasing or decreasing the priorities of each

    criterion. It is only when one increases the priority of the

    applicability factor to an improbable 96% that we obtain a

    change in the final ranking with the condition-based main-

    tenance strategy.

    For the Group 2 machines (Table 7), the final solution is

    less stable. Opportunistic and predictive maintenance stra-

    tegies show some alternations in priority positions. In parti-

    cular, the maintenance staff must take into consideration

    applicability and added-value priority evaluations.

    There are no situations where catastrophic changes in thefinal ranking are observed.

    An analysis of the Group 3 machines (Table 8), highlights

    more reversals in the final ranking. Corrective, opportunistic

    and predictive maintenance strategies can all be considered

    to be the best solution, depending on which weighting

    criteria are used. It can, therefore, be seen that the sensitivity

    analysis shows how, in the case study under examination,

    the maintenance staff should concentrate their attention on

    the pairwise evaluation of the four criteria. It is clear that a

    few changes in the judgement evaluations can lead to modi-

    fications in the final priority ranking. But it must also be

    remembered that the importance of corrective maintenancenever goes away. In other words, we have three different

    strategies, all of which can provide the best solution, and the

    differences among them are never of great importance.

    Summarising the considerations discussed above, one can

    affirm that the AHP selections presented in Section 7, which

    concern the best possible maintenance strategies for the

    IGCC machines, can be accepted with a good degree of

    confidence by the company maintenance staff.

    We conclude this section with two final considerations.

    First, the sensitivity analysis proposed here is only relevant

    to the priorities of the four first-level criteria. Second,

    because we have changed each attribute weight one at a

    time, only the main effects have been considered. Inother words, interaction effects of the changes made to

    two or more weights have been ignored. These simplifica-

    tions have been adopted for the following reasons:

    1. the final solution is mainly sensible to changes in the

    priorities at the highest level of the hierarchy;

    2. the introduction of the interaction effects makes the

    sensitivity analysis too complex for actual applications.

    Nevertheless, one should note that the main effects are

    generally the most important aspects in a sensitivity

    analysis.

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 71 8380

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    11/13

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    12/13

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 (2000) 71 8382

    Table 6

    Observations derived from sensitivity analysis of the criteria priority values with machines of Group 1

    Criteria Decreasing Relative priority value

    in final solution (%)

    Increasing

    Damages Predictive maintenance is always the best

    strategy

    56.6 Predictive maintenance is always the best

    strategy

    Applicability Predictive maintenance is always the beststrategy

    36.8 Predictive maintenance strategy is reachedand overcame by condition-based

    maintenance but only when applicability

    priority is equal to 96%.

    Added-value Predictive maintenance is always the best

    strategy

    36.8 Predictive maintenance is always the best

    strategy

    Cost Predictive maintenance is always the best

    strategy

    26.7 Predictive maintenance is always the best

    strategy

    Table 7

    Observations derived from sensitivity analysis of the criteria priority values with machines of Group 2

    Criteria Decreasing Relative priority value

    in final solution (%)

    Increasing

    Damages Opportunistic maintenance is always the

    best strategy

    26.2 Opportunistic maintenance strategy is

    reached and overcame by predictive

    maintenance when damages priority is

    equal to 34.2%.

    Applicability Opportunistic maintenance strategy is

    reached and overcame by predictive

    maintenance just when applicability

    priority is reduced to 50.5%.

    56.5 Opportunistic maintenance is always the

    best strategy

    Added-value Opportunistic maintenance is always the

    best strategy

    5.5 Opportunistic maintenance strategy is

    reached and overcame by predictive

    maintenance when added-value priority is

    equal to 11.5%.

    Cost Opportunistic maintenance is always the

    best strategy

    11.8 Opportunistic maintenance strategy is just

    reached and overcame by predictive

    maintenance when cost priority is equal

    to 19.8%.

    Table 8

    Observations derived from sensitivity analysis of the criteria priority values with machines of Group 3

    Criteria Decreasing Relative priority value

    in final solution (%)

    Increasing

    Damages Corrective maintenance is always the best

    strategy

    15.1 Corrective maintenance is reached and

    overcame by opportunistic maintenance just

    when damages priority is became to

    17.1%. Predictive is the new best strategy

    when priority is equal to 53.1%

    Applicability Corrective maintenance is reached and

    overcame by opportunistic maintenance justwhen applicability priority is reduced to

    61.5%. Predictive is the new best strategy

    when priority is reduced to 47.5%

    63.5 Corrective maintenance is always the best

    strategy

    Added-value Corrective maintenance is always the best

    strategy

    6.2 Corrective maintenance is reached and

    overcame by opportunistic maintenance

    when damages priority is became to

    10.2%. Predictive is the new best strategy

    when priority is equal to 20.2%

    Cost Corrective maintenance is always the best

    strategy

    11.8 Corrective maintenance is reached and

    overcame by opportunistic maintenance

    when damages priority is became to

    19.1%. Predictive is the new best strategy

    when priority is equal to 33.1%

  • 8/13/2019 How to Choose Between Maintenance Policies 2

    13/13

    Acknowledgements

    We would like to thank the referees for their constructive

    comments that enabled us to improve the quality of this

    paper.

    Appendix A

    An example of evaluation of a factor of Eq. (1) is reported

    below. The machine importance for the continuity of the

    IGCC plant operations is evaluated through the analysis of

    the Process Flow Diagrams (PFDs) and Piping and Instru-

    mentation Diagrams (P&IDs) of the plant, taking into

    account the availability of spare machines.

    The scores are assigned in accordance with Table A1,

    which is drawn up with the oil refinery maintenance staff

    and process engineers.

    Low impact equipment are those items characterised by

    minor functions or which operate in circuits where it is

    possible to provide the products with intermediate storage.

    In the latter case, the buffer can provide the plant with the

    necessary operating autonomy so that maintenance can be

    performed without a plant shut-down. Machines with highor very high impact on the process have also been assigned a

    high score for the availability of a spare part to take into

    account the possible failure of the spare machine to start.

    References

    [1] Almeida AT, Bohoris GA. Decision theory in maintenance decision

    making. Journal of Quality in Maintenance Engineering

    1995;1(1):3945.

    [2] Triantaphyllou E, Kovalerchuk B, Mann L, Knapp GM. Determining

    the most important criteria in maintenance decision making. Journal

    of Quality in Maintenance Engineering 1997;3(1):1624.

    [3] Rausand M. Reliability centered maintenance. Reliability Engineer-

    ing and System Safety 1998;60:12132.

    [4] Crocker J, Kumar UD. Age-related maintenance versus reliability

    centered maintenance: a case study on aero-engines. Reliability Engi-neering and System Safety 2000;67:1138.

    [5] Gilchrist W. Modelling failure modes and effects analysis. Interna-

    tional Journal of Quality and Reliability Management 1993;10(5):16

    23.

    [6] Del Bravo R, Starace F, Chellini IM, Chiantore PV. Impianto IGCC

    da 280 MW di Api Energia in Italia. Lenergia elettrica

    1997;74(2):1724.

    [7] Countinho JS. Failure-effect analysis. Transactions NY Academic

    Science 1964;26(II):56484.

    [8] Holmberg K, Folkeson A. Operational reliability and systematic

    maintenance. London: Elsevier, 1991.

    [9] Saaty TL. The analytic hierarchy process. New York: McGraw-Hill,

    1980.

    [10] Saaty TL. Decision making for leaders. Belmont, CA: Lifetime

    Learning Publications, 1982.

    [11] Saaty TL. How to make a decision: the analytic hierarchy process.

    European Journal of Operational Research 1990;48:926.

    [12] Vargas LG. An overview of the analytic hierarchy process and its

    applications. European Journal of Operational Research 1990;48:28.

    [13] Madu CN, Kuci C-H. Optimum information technology for socio-

    economic development. Information Management and Computer

    Security 1994;2(1):411.

    [14] Belton V, Gear T. On a short-coming of Saatys method of analytic

    hierarchies. Omega 1983;11(3):22830.

    [15] Dyer JS. Remarks on the analytic hierarchy process. Management

    Science 1990;36(3):25968.

    [16] Saaty TL. An exposition of the AHP in reply to the paper: remarks on

    the analytic hierarchy process. Management Science

    1990;36(3):25968.[17] Sage AP. Interpretive structural modelling: methodology for lar. New

    York: McGraw-Hill, 1977.

    [18] Mandal A, Deshmukh SG. Vendor selection using interpretive struc-

    tural modelling (IMS). International Journal of Operations and

    Production Management 1993;14(6):5259.

    [19] Min H, Melachrinoudis E. The relocation of a hybrid manufacturing/

    distribution facility from supply chain perspective: a case study. Inter-

    national Journal of Management Science 1999;27:7585.

    M. Bevilacqua, M. Braglia / Reliability Engineering and System Safety 70 ( 2000) 71 83 83

    Table A1

    Scores for the evaluation of machine importance for the process factor

    Impact on the process With spare machine Without spare machine

    Low 10 50

    Medium 30 70

    High 70 90

    Very high 80 100