BASEBUILDERS
How The Best Firms Get Better
Practical Business and Project Management Strategies
BASEBUILDERS
Doug Rawson, PE (YourFriend)
Education • Bachelor of Science in Electrical Engineering!
• Masters from School of Hard Knocks ~ Working on PhD!
Jobs • College Days: Gold Miner, Copy Maker, Box Tosser!
• Electrical Engineer ~ 1998-1995 (6 years)!
Founder • Pinnacle Engineering, Inc ~ 1995-2005 (10 years)!
• Base Builders, LLC ~ 2002-Today
BASEBUILDERS
Scary Facts
• 40% of all new business fail in first year
• 80% done by end of 5 years
• 80% of the surviving 20% fail by end of 10th year
• Only 4% of business last past 10 years
BASEBUILDERS
On The Menu
• Profit vs. Cash Flow
• Cash Flow Enhacement
• Increasing and Managing for Profit
BASEBUILDERS
Profit vs. Cash Flow
BASEBUILDERS
What is Profit?
• Profit is what you report on your taxes
• Profit affects, but is not, your bank balance
• Profit is a good thing
• You won’t last long without it
BASEBUILDERS
Operating Profit
Gross Revenue - Direct Expenses
Net Revenue - Direct Labor Gross Income
- Indirect Labor - Other Overhead
Operating Profit
Your Fees
Sub Consultants, Prints, Models
This Levels All Projects/Firms
Labor Charged to Projects
Monies Left for Profit & OH
Marketing, Vacation, Etc.
Rent, Insurance, Benefits
Available for Distribution
BASEBUILDERS
What is Cash Flow?
• Cash Flow determines viability
• Negative Cash Flow causes bankruptcy
• Cash Flow is what happens in your checking account
• Happiness is a positive cash flow!
BASEBUILDERS
Cash Flow
Opening Balance + Income From Sales
+ Investor Capital + Loans
Available Funds - Expenses
- Debt Service - Capital Purchases
- Distributions Closing Balance
Money In The Bank - Start
From Your Accounts Receivable
From Your Pockets
Bank, Credit Card, LOC
How Much You Can Spend
From Bills Paid & Things Bought
Bank, Credit Card, LOC
Assets Bought
Into Your Pockets
Money In The Bank - End
Diff
eren
ce
BASEBUILDERS
Profit vs. Cash Flow
• Negative Profit and Negative Cash Flow!
• Negative Profit and Positive Cash Flow!
• Positive Profit and Negative Cash Flow!
• Positive Profit and Positive Cash Flow
BASEBUILDERS
Neg Profit ~ Neg Cash Flow
• Too Much Overhead/Too Many Expenses!
• Typical for a start up!
• Slow reaction to economic slowdown!
• Action - Cut Now and Cut Fast
BASEBUILDERS
Neg Profit ~ Pos Cash Flow
• Credit Card Balance Growth!
• Not paying sub consultants!
• Asset Depreciation!
• This should raise some red flags
BASEBUILDERS
Pos Profit ~ Neg Cash Flow
• Debt Reduction (Mandatory/Voluntary)!
• Back payments to Sub Consultants!
• Share Holder Distributions!
• This should raise some red flags!
• Can lead to major financial challenges
BASEBUILDERS
Pos Profit ~ Pos Cash Flow
• What a Great Place to be...
BASEBUILDERS
Cash Flow Enhancement Part 1
Getting Paid and Speeding Up the Inflow
BASEBUILDERS
Time Line of Cash FlowStaff
Perform the work and your fee is earned. This is your
Earned Value!Day 1
Payday comes and you pay
your staff!Day 7 Client
is invoiced for the work!Day Client
feels generous and pays your invoice!
Day 80
Timeline of Cash Flow
BASEBUILDERS
Acceleration of In Flow
• Increase Billing Frequency
• Delegate Billing and Collection to PMs
• Prep the Client
• Follow Up
BASEBUILDERS
Increase Billing Frequency
• When a deliverable is completed - deliver it with an accompanying invoice.
• Do not wait until the end of the month to do your billing.
• Do not allow for your billings to fall through the cracks. I know you hate doing it - do it anyways.
• Forecast your invoicing and set goals.
BASEBUILDERS
Celebration Fridays
• Celebrate the week’s accomplishments by billing your clients.
• Not every project can be billed each week, but each week there is usually something that can should be billed!
BASEBUILDERS
Delegation Rocks
• Empower Your Project Managers with the Responsibility of Invoicing Their Projects.
• Provide Your Project Managers with Real Time Data.
BASEBUILDERS
Prep Your Client
• Don’t let your bill be a surprise.
• Start by letting you client know that you plan to send an invoice out this week and you want to know if that will be alright?
• Then let them know how much (dollars or percentage) you plan to invoice and ask for their blessing.
BASEBUILDERS
Follow Up
• Ask the client if they received your invoice.
• Ask them if they have reviewed it and do they have any questions.
BASEBUILDERS
Two Tricks
• Put Your Reimbursable Items on a Separate Invoice From Your Design Fee.
• If an Invoice is Being Issued for March and it is April 3rd, Date the Invoice March 31st.
BASEBUILDERS
Slow Payers
• I’m updating my Cash Flow Forecast and was wondering when...
• We hate to be a pain but…
• Will you be able to pay our invoice or should we start accruing interest?
BASEBUILDERS
Summary
• Bill Frequently
• Communicate with Your Client
• Make Invoicing a PM Responsibility
• Be the Squeaky Wheel
BASEBUILDERS
Cash Flow Enhancement Part 2
Managing Expenses and Slowing Down the Outflow
BASEBUILDERS
Five Percent!
• You can always find 5% that you can cut.
• Where do you start?
• Start with the Largest Accounts - these typically have the most fat.
BASEBUILDERS
Expenses by vendor
Vendor Amount
Model Builders 34,620
Network Services 6,699
Clean Windows Express 933
Black Lines Tomorrow 3,473
Left Side Out 2,500
East Side Printers 17,947
Pretty Good Provider 1,800
CYA Insurers 1,296
Interior Design by You Know Who 24,926
How Many Vendors Can There Be 4,823
BASEBUILDERS
Expenses by vendor
Vendor Amount
Model Builders 34,620
Interior Design by You Know Who 24,926
East Side Printers 17,947
Network Services 6,699
How Many Vendors Can There Be 4,823
Black Lines Tomorrow 3,473
Left Side Out 2,500
Pretty Good Provider 1,800
CYA Insurers 1,296
Clean Windows Express 933
BASEBUILDERS
Negotiation
• First Review Pricing and/or Rates and See if You Can Negotiate
• Second You can Request Extended Terms
• Can You Consolidate? If you Currently Do Business with Two Reprographic Companies, Will One of Them Give You Better Rates for ALL of Your Business?
BASEBUILDERS
Negotiation
• First Review Pricing and/or Rates and See if You Can Negotiate
• Second You can Request Extended Terms
• Can You Consolidate? If you Currently Do Business with Two Reprographic Companies, Will One of Them Give You Better Rates for ALL of Your Business?
Caution! Nobody Likes a
Cheapskate
BASEBUILDERS
Review Insurance
• Get a Fresh Set of Quotes on Health Insurance.
• Shop Around for Liability and Errors & Omissions Coverage.
BASEBUILDERS
Health Benefits
• Nearly 20% of Americans Have Secondary Insurance. This Means That They are Covered Under Two Plans.
• Modifying Your Insurance Benefit to Require Employee Participation Will Encourage Some Employees to Move to Their Spouse’s Coverage.
BASEBUILDERS
Review Employee Compensation
• Owner and Principals!
• Less Salary and More Profit Sharing!
• Staff Salaries!
• Rather Than Raises, Implement a Bonus Plan
BASEBUILDERS
Reduce Overhead
• Read Chapter 9!
• Fire Someone Today by Bob Pritchett
• Reduce Staff - cut the dead wood
• Change Benefits
• Reduce Turnover
• Improve Efficiencies
• Become More Effective
BASEBUILDERS
Increasing Profits
BASEBUILDERS
Increasing Profits
• There are only two ways to increase Profits
• Method One: Increase Revenue
• Method Two: Cut Expenses
BASEBUILDERS
Increasing Profits
• Target Better Projects!
• Pareto Principal (80/20 Rule)!
• Strategic Planning: Know Thyself – A Case Study by Michael Webber!
• Ramp Up Marketing Efforts!
• Raise Fees and/or Rates!
• Focus on Flat Fee ProjectsPSMJ
BASEBUILDERS
Increasing Profits
• Target Better Projects!
• Pareto Principal (80/20 Rule)!
• Strategic Planning: Know Thyself – A Case Study by Michael Webber!
• Ramp Up Marketing Efforts!
• Raise Fees and/or Rates!
• Focus on Flat Fee ProjectsPSMJ
Annual Revenue
Generation
Business Development
Budget
Repeat Clients 80% 20%
New Clients 20% 80%
BASEBUILDERS
Profit Centers
• Profit Centers are how you categorize your projects and revenue
• Project Type, Client Type, Project Size, Geographical Location, etc
• Net Revenue, Operating Profit, % Profit
BASEBUILDERS
Profit Centers
TypeNet
RevenuePercent of
Net RevenueOperating
ProfitPercent of Total Profit
Profit Percentage
Retail 100,000 14% 18,000 15% 18%
Office 140,000 20% 23,000 19% 16%
K12 200,000 28% 38,000 32% 19%
Barber 60,000 9% 18,000 15% 30%
Church 120,000 17% 10,000 8% 8%
Medical 85,000 12% 12,000 10% 14%
705000 100% 119000 100% 17%
TypeNet
RevenuePercent of
Net RevenueOperating
ProfitPercent of Total Profit
Profit Percentage
Retail 100,000 14% 18,000 15% 18%
Office 140,000 20% 23,000 19% 16%
K12 200,000 28% 38,000 32% 19%
Barber 60,000 9% 18,000 15% 30%
Church 120,000 17% 10,000 8% 8%
Medical 85,000 12% 12,000 10% 14%
705000 100% 119000 100% 17%
BASEBUILDERS
Profit Centers
FundingNet
RevenuePercent of
Net RevenueOperating
ProfitPercent of Total Profit
Profit Percentage
Private 320,000 35% 38,000 27% 12%
Federal 120,000 13% 8,000 6% 7%
State 200,000 22% 38,000 27% 19%
School 60,000 6% 23,000 16% 38%
County 140,000 15% 23,000 16% 16%
City 85,000 9% 12,000 8% 14%
925000 100% 142,000 100% 15%
TypeNet
RevenuePercent of
Net RevenueOperating
ProfitPercent of Total Profit
Profit Percentage
Private 320,000 35% 38,000 27% 12%
Federal 120,000 13% 8,000 6% 7%
State 200,000 22% 38,000 27% 19%
School 60,000 6% 23,000 16% 38%
County 140,000 15% 23,000 16% 16%
City 85,000 9% 12,000 8% 14%
925,000 100% 142,000 100% 15%
BASEBUILDERS
Profit Centers
Delivery Method
Net Revenue
Percent of Net Revenue
Operating Profit
Percent of Total Profit
Profit Percentage
Design Build 200,000 20% 47,000 31% 24%
Plan Spec 600,000 60% 68,000 45% 11%
Design Assist 200,000 20% 36,000 24% 18%
1000000 100% 151,000 100% 15%
BASEBUILDERS
Finding Your Sweet Spot
Profitability Delivery Method
Design FeaturesType
BASEBUILDERS
Finding Your Sweet Spot
Profitability
Delivery Method
Design Features
Type
BASEBUILDERS
Ideal Client
• Home Owner!
• General Contractor!
• Public Works!
• Sub-Contractor!
• Big Business!
• Developer!
• Non-Profit
How do you define an ideal client?
BASEBUILDERS
Ideal Project
• Large Project!
• Small Project!
• Primary Residence!
• Vacation Home!
• Office Building!
• Church!
• Restaurant!
• Retail Center
How do you define an ideal project?
BASEBUILDERS
Ideal Project
• Large Project!
• Small Project!
• Primary Residence!
• Vacation Home!
• Office Building!
• Church!
• Restaurant!
• Retail Center
How do you define an ideal project?
Riches are in Niches
BASEBUILDERS
Managing for Profit
BASEBUILDERS
Managing for Profit
• When is a Project’s Profit Determined?
• How Do You Set Your Fees?
• How Do You Know How Much To Charge?
BASEBUILDERS
Setting Fees
• Review Your Own Historical Data
• Industry Data Is Great But Yours is Better
• San Diego’s Daily Average Temp is 70.5℉• Develop Matrices to Compare Projects
BASEBUILDERS
Matrices
• $ per Drawing
• $ per Area Unit (Sq Ft, Sq M)
• Hours per Drawing
• Hours per Area Unit
• $ per Hour
• % of Construction Cost
BASEBUILDERS
Budgeting Hours
Phase
SD
DD
CD
BD
BN
CA
Percent
15%
20%
30%
10%
5%
20%
1
Fee
4,500
6,000
9,000
3,000
1,500
6,000
30000
BASEBUILDERS
Budgeting Hours
Phase
SD
DD
CD
BD
BN
CA
Percent
15%
20%
30%
10%
5%
20%
1
Fee
4,500
6,000
9,000
3,000
1,500
6,000
30000
40% = PM 40% = Production 20% = Admin
$120/hr @ 40% = 48 $80/hr @ 40% = 32 $60/hr@ 20% = 12
Average = 92
BASEBUILDERS
Budgeting Hours
Phase
SD
DD
CD
BD
BN
CA
Percent
15%
20%
30%
10%
5%
20%
1
Fee
4,500
6,000
9,000
3,000
1,500
6,000
30000
Hours
49
65
98
33
16
65
326
BASEBUILDERS
Tracking Progress
• Review Progress Against Budgets
• Adjust Course
• Move Forward
BASEBUILDERS
Tracking Progress
Phase % DoneHours
Budgeted Hours Actual $ Hours Difference
SD 100% 49 52 106% -6%
DD 50% 65 41 63% -13%
CD 0% 98 0 0% 0%
BD 0% 33 0 0% 0%
BN 0% 16 0 0% 0%
CA 0% 65 0 0% 0%
Phase % DoneHours
Budgeted Hours Actual $ Hours Difference
SD 100% 49 52 106% -6.1%
DD 50% 65 41 63% -13.1%
CD 0% 98 0 0% 0.0%
BD 0% 33 0 0% 0.0%
BN 0% 16 0 0% 0.0%
CA 0% 65 0 0% 0.0%
BASEBUILDERS
Tracking Progress
Phase % DoneHours
Budgeted Hours Actual $ Hours Difference
SD 100% 49 52 106% -6%
DD 50% 65 41 63% -13%
CD 0% 98 0 0% 0%
BD 0% 33 0 0% 0%
BN 0% 16 0 0% 0%
CA 0% 65 0 0% 0%
Phase % DoneHours
Budgeted Hours Actual $ Hours Difference
SD 100% 49 52 106% -6.1%
DD 50% 65 41 63% -13.1%
CD 0% 98 0 0% 0.0%
BD 0% 33 0 0% 0.0%
BN 0% 16 0 0% 0.0%
CA 0% 65 0 0% 0.0%
Phase % DoneHours
Budgeted Hours Actual % Hours Difference
SD 100% 49 52 106% -6.1%
DD 75% 65 41 63% 11.9%
CD 0% 98 0 0% 0.0%
BD 0% 33 0 0% 0.0%
BN 0% 16 0 0% 0.0%
CA 0% 65 0 0% 0.0%
BASEBUILDERS
Monitor Everything
• What gets measured gets managed