how project managers can prevent the next arch … project managers can prevent the next arch deluxe...

38
How Project Managers Can Prevent the Next Arch Deluxe Jon Haverly, PMP Garnet River, LLC.

Upload: dinhque

Post on 19-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

How Project Managers Can Prevent the Next Arch Deluxe

Jon Haverly, PMP – Garnet River, LLC.

Presentation Goals Develop an understanding of:

1. Why a great project does not always produce the right product

2. Why consumers need to be considered during Project Origination

3. Why a Project Manager’s most critical contribution occurs before the project is initiated

Provide tips for developing a convincing Business Case

Project Origination First Phase of the Project Management Life Cycle

Investment Decisions are made

Project Origination1. Identification of a Business Problem or Opportunity

2. Development of a Business Case/Project Proposal

3. Evaluation of the Business Cases/Project Proposals

4. Selection of Projects

The Business Case Used to facilitate investment decisions

Minimum needed:

Business Need (Problem/Opportunity)

What are we trying to solve?

Proposed Solution

How will we solve?

Justification (Cost/Benefit)

Why should we solve?

The Business Case Should also include:

Alternatives Considered

How else could we solve?

Stakeholder Impacts

Whose life will change?

Risks

What could prevent us from addressing the need?

Strategic Plan Alignment

Assumptions/Constraints

Business Case Evaluation Consistent evaluation criteria should be used

Typical criteria include:

Alignment to Business

Value (Costs vs. Benefits)

Criticality

Stakeholder Impact

Risks

Organizational specific criteria

Project Selection Results in:

Projects approved to move forward

Projects dropped from further consideration

Relative priorities

Consistent process

Consistent criteria

Project Origination – PM’s Role Help organizations select the right projects by:

Understanding

business needs

root causes of problem

consumers

Identifying

potential solutions

best solution to meet needs

approach and estimates

Documenting a Business Case

The Business Case

Business Need Includes

Business problem (opportunity)

Impacts to internal and external stakeholders

Baseline data – “current payment process take 3 business days and 15 staff hours to complete”

Need to uncover the root cause of the problem

Serves as basis for Business Requirements

Does not include any references to a solution

Business Need Tips

Work with business representatives and stakeholders to define this section (i.e. - not IT)

Complete this section first and seek agreement

Describe what will happen if problem is not addressed, i.e. will the impacts worsen?

Appeal to emotions

Business Objectives Address an identified need

Align with Org. Goals

List any needs not addressed by project

Are measurable

Reduce payment process to 1 business day and 5 staff hours

Maintain full vendor support (upgrades)

Comply with mandates

Business Objectives Tips

Make sure each Business Objective maps directly to an identified Business Need

There is never a business objective to create a new/updated software application

Build a new software application

Reduce payment process to 1 business day and 5 staff hours

Solutions Considered Describes

Process used to evaluate alternatives, such as

Research

Demonstrations

Proof of Concepts

Interview users of solution

Others

Each alternatives and reasons why not selected

Listed before or after Proposed Solution

Consider at least 3 solutions!

Solutions Considered Tips

Develop and reach agreement on comparison criteria before identifying alternatives

Business Requirements

Costs (development and recurring)

Necessary staff resources

Other specific considerations

Develop an Alternative Solutions Worksheet

Identify and agree on alternatives to be considered

Tips

Consumer Research/Involvement

Inversely proportionate to level of innovation

Link to the consumer

Understand the consumer

Solutions Considered

Proposed Solution Satisfies (only!) Business

Objectives and Needs

Focus on solution being proposed

Not the benefits

Not a justification

Not other solutions considered

Proposed Solution Include all aspects of solution

Training

Implementation

Documentation

Conversion

Establish Steering Committee

Decommissions

Procurement

Proposed Solution Tips

Validate the solution will satisfy all Business Objectives

Validate the solution will satisfy only the Business Objectives

Don’t be afraid to ask which objective a segment of the solution is satisfying

Complete Alternative Solutions Worksheet before this section

Make failure survivable

Stakeholder Impacts Proposed Solution causes impacts

to Stakeholders

Involve Stakeholder when developing Business Case

Internal and External to the organization

Consumers, Consumers, Consumers!

Stakeholder Impacts Need to consider

New/Improved services

Eliminated/Reduced services

Reduced staff time on process tasks

Increased staff time on existing or new tasks

Tips

Ask what is being taken away

Ask what is being pushed to someone else

Benefits Proposed Solution provides Benefits

Quantification of Impacts

Staff time savings times hourly cost of staff

Improved services

Cost Savings/Avoidance

Tips

Small benefits add up!

List Intangible Benefits (Morale, Good Will)

Costs Proposed Solution incur Costs

Need to derive Total Costs

Include:

Personal Services (Staff Costs)

Project Team (BA’s, Programmers)

Subject Matter Experts

Technical Support (Servers, Network,…)

Contract Support

Info. Security/Biz Continuity Groups

Sponsors

End Users (for items such as training)

“It takes a village to raise a project”– Jon Haverly

Costs Also include:

Non-Personal Services

Consultants

Hardware

Software

Travel

Materials

Facilities

Land

Costs Consider:

Costs from Stakeholder Impacts (services lost)

Product Development Costs

Annual Support Costs

Average or total for number of years in future

Support Contracts

Maintenance Contracts

Cost/Benefit Analysis Make your case!

Compare Quantified Costs to Quantified Benefits

Return on Investment

Payback Period

Add any additional justifications

On paper the numbers don’t look good, but…..

Risks Proposed Solutions contain

Risks

Project specific risks

Schedule - Mandated deadlines

Customers – Change

Risks Solution specific risks

Technology

Complexity

Contract

Tips

Any assumption is also a Risk

Think about customer acceptance

Writing Tips Include an Executive Summary

Keep focus on specific section

Language Matters

Complete and review in sections, such as: Need/Objectives

Comparison Criteria

Alternate Solutions

All other sections

Content Tips Don’t assume technology is the best way to solve a

business problem

Wear your enterprise hat (common solutions)

Presentation Goals Revisited Do you understand:

1. A great project does not always produce the right product?

2. Why consumers need to be considered during Project Origination?

3. Why a Project Manager’s most critical contribution occurs before the project is initiated?

Did you receive:

1. Tips for developing a convincing Business Case?

References and Recommended Reading Links Adapt, by Tim Harford

Switch, by Chip and Dan Heath

The Wal-Mart Effect, by Charles Fishman

How We Decide, by Johan Lehrer

The Upside of Irrationality, by Dan Ariely

www.walletpop.com

Questions

Jon Haverly, PMPGarnet River, LLC.E-mail: [email protected]: http://jonhaverly.blogspot.com/