Page 1: How do you get accurate visibility  on a  multi-team project?

How do you get accurate

visibility on a

multi-team project?

Page 2: How do you get accurate visibility  on a  multi-team project?

Success of an Agile project depends on the

Page 3: How do you get accurate visibility  on a  multi-team project?

Cooperation Coordination

Success of an Agile project depends on the

and

of multiple teams

Page 4: How do you get accurate visibility  on a  multi-team project?

As such, visibility of the progress of each team and the program as a whole

Page 5: How do you get accurate visibility  on a  multi-team project?

is critical

As such, visibility of the progress of each team and the program as a whole

Page 6: How do you get accurate visibility  on a  multi-team project?

Rollups are not the answer

Page 7: How do you get accurate visibility  on a  multi-team project?

Rollups are not the answer

Why?

Page 8: How do you get accurate visibility  on a  multi-team project?

Rollups hide valuable information about individual team and program progressThe problem with

Rollups

#1

Page 9: How do you get accurate visibility  on a  multi-team project?

They inaccurately forecast when the program may be completeThe problem with

Rollups

#2

Page 10: How do you get accurate visibility  on a  multi-team project?

They set incorrect expectationsThe problem with

Rollups

#3

Page 11: How do you get accurate visibility  on a  multi-team project?

For example...

Page 12: How do you get accurate visibility  on a  multi-team project?

Team Chicago

Team Bangalore

The problem with Rollups

Example

Page 13: How do you get accurate visibility  on a  multi-team project?

Common Goal

Team Chicago

Team Bangalore

The problem with Rollups

Example

Page 14: How do you get accurate visibility  on a  multi-team project?

Common Goal 40 stories

Team Chicago 5 stories

Team Bangalore 35 stories

The problem with Rollups

Example

Page 15: How do you get accurate visibility  on a  multi-team project?

Progress of Team Chicago

The problem with Rollups

Example

Page 16: How do you get accurate visibility  on a  multi-team project?

5 stories done

Progress of Team Chicago

The problem with Rollups

Example

Page 17: How do you get accurate visibility  on a  multi-team project?

5 stories done on Jan 1st

Progress of Team Chicago

The problem with Rollups

Example

Page 18: How do you get accurate visibility  on a  multi-team project?

All work complete

5 stories done on Jan 1st

Progress of Team Chicago

The problem with Rollups

Example

Page 19: How do you get accurate visibility  on a  multi-team project?

Progress of Team Bangalore

The problem with Rollups

Example

Page 20: How do you get accurate visibility  on a  multi-team project?

10 stories done

Progress of Team Bangalore

The problem with Rollups

Example

Page 21: How do you get accurate visibility  on a  multi-team project?

Progress of Team Bangalore10 stories done on Jan 5th

The problem with Rollups

Example

Page 22: How do you get accurate visibility  on a  multi-team project?

Forecasted end date Jan 21st

Progress of Team Bangalore10 stories done on Jan 5th

The problem with Rollups

Example

Page 23: How do you get accurate visibility  on a  multi-team project?

The problem with Rollups

Example

Rollups of both teams

Page 24: How do you get accurate visibility  on a  multi-team project?

The problem with Rollups

Example

Incorrect forecasted end date of Jan 15th

Rollups of both teams

Page 25: How do you get accurate visibility  on a  multi-team project?

The problem with Rollups

Example

Rollups of both teamsIncorrect forecasted end date of Jan 15th

when it should be Jan 21st

Page 26: How do you get accurate visibility  on a  multi-team project?

The problem with Rollups

Example

Rollups of both teamsIncorrect forecasted end date of Jan 15th

when it should be Jan 21st

with no visibility of individual team progress

Page 27: How do you get accurate visibility  on a  multi-team project?

What do we recommend for better

visibility of your program’s progress?

Page 28: How do you get accurate visibility  on a  multi-team project?

Correlate progress of program objectives with project progress

For better program visibility

Page 29: How do you get accurate visibility  on a  multi-team project?

Track the progress of each project without masking information

Correlate progress of program objectives with project progress

For better program visibility

Page 30: How do you get accurate visibility  on a  multi-team project?

Track the progress of each project without masking information

Get alerts when attention is needed to project schedules

Correlate progress of program objectives with project progress

For better program visibility

Page 31: How do you get accurate visibility  on a  multi-team project?

Forecast the e!ects of scope changes on project timelinesFor better program

visibility

Track the progress of each project without masking information

Get alerts when attention is needed to project schedules

Correlate progress of program objectives with project progress

Page 32: How do you get accurate visibility  on a  multi-team project?

What helps you get

visibility of your program?

Page 33: How do you get accurate visibility  on a  multi-team project?

Agile workers talk o!en and welcome change. Mingle creates a shared space to make quick decisions and track details, even when the team can’t be together.

See how Mingle can help you e!ectively track the progress of your project or program