DEWATS for Sustainable Wastewater Managementand Water Optimization @ Hotel Country Villa ,
Nagarkot
-
8/8/2019 Hotel country villa
2/16
-
8/8/2019 Hotel country villa
3/16
Basic information
Estabished date: 1995 ADTotal bed nos: 70Staff : 30Occupancy : 70% through out the year
Wat er Consump ti on
Water source = SpringPeak hour= 10 h/dPer bed water consumption= 400L
(including staff and kitchen)Peak hour flow= 2.8m3/h (based on per
bed water consumption)
Spring Source
-
8/8/2019 Hotel country villa
4/16
Separate wastewater dischargepipeNo proper septic tank onlysoak pitNo proper discharge of wastewater
Wa s tew at er inform ati on
Showerdisposal
Soak Pit( Toilet water)
-
8/8/2019 Hotel country villa
5/16
Proposed Wa s tew at er D is t r ibu ti on
BOD ,COD (mg/L)Unit1 - 300 and 600Unit2 - 50 and 100
Separate collection of Bathroom waste
2.3m3/h (80% peak water flow) Wastewater
Unit-1( 70%)
Toilet Kitchen
Unit-2( 30%)
Bathroom
-
8/8/2019 Hotel country villa
6/16
` Soil condition : sandy clay with gravel (loose type)` Slopy terrain surrounded with forest` Total land area = 12500 sqm` Available land for construction=3000sqm
S it e Inform ati on
-
8/8/2019 Hotel country villa
7/16
SETTLER
Proposed DE WAT S Are a
-
8/8/2019 Hotel country villa
8/16
Proposed DEWATS Layout
Total built up area for DEWATS= 160m2
-
8/8/2019 Hotel country villa
9/16
DE WAT S Wat er Qu ality Achi eved
Component BOD in COD in BODout
CODout
Settler (Kitchen + Toilet) 300 600 225 460
Settler (Shower) 50 100 37 76
ABR 225 460 76 138
AF 76 138 41 80
PGF (Combined) 40 79 30 60
-
8/8/2019 Hotel country villa
10/16
O&M of the system
Operation` Pumping of treated water` Caretaking of the system
M aintenance` De-sludging of Settler and ABR (30 months)` Cleaning of filter media ( 5 yrs)` Replacement of filter material during cleaning filter
medium(10%)
-
8/8/2019 Hotel country villa
11/16
T re at ed Wat er Reuse Op ti on
` Gardening` Irrigation` Ponds` Outer floor Cleaning` Toilet Flushing (after further treatment)
-
8/8/2019 Hotel country villa
12/16
Fin a nci al A n alys i sEx penditures (NRs)
` Cost of Construction 120,000x23= 2,800,000` Annual Operation and Maintenance of Structure 1.5x2,800,
000= 4 2,000`
Interest 10 % of Cost of the Structure 280,000` Return on Capital Investment Annually For 20 Years 14 0,000` Net Expenditure Annually 46 2,000
S avings (NRs)` Annual Saving on Water Uses 23x100x365day=
839,500= 800,000` Saving Per Year (800,000-462,000) = 338,000` Net Saving on Investment 33 8,000
-
8/8/2019 Hotel country villa
13/16
O ther Be n ef i ts
` Ecologically Balanced It helps in bringing tourists moreand hence helps more earnings
` Environment improved`
Social Encouragement` Water sources are protected
-
8/8/2019 Hotel country villa
14/16
Oth er Benef it s
Integration of Bio-digester` Total water Generated (Kitchen waste @0.25 kg, Night soil@ 0.2 kg/person) = 45 kg` Gas Production (Kitchen waste @0.03m3/kg, Night soil@ 0.05 m3/kg) = 1.75 m3` Size of Bio-digester = 9.04 m3` Adopted Bio-digester = 10 m3` Biogas Consumption of Stove (BSP Model)= 0.44 m3/hr` Biogas burning hour = 3.98 hr
It is sufficient to meet the cooking energy need of family with 6 members.
-