Hospital of the FutureConstruction Update as of Dec. 3, 2010

Page 2: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

West side of the building.

Page 3: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

View of brick work from Springfield Street.

Page 4: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

Green Roof (install spring 2011).

Page 5: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

Basement boiler started early Nov. to provide temporary heat during construction.

Page 6: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

Basement air handler unit started in early Dec. for temporary heat during construction.

Page 7: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

Endovascular procedure rooms support steel duct installation ongoing.

Page 8: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

Endovascular procedure room coordination complete, released for fabrication.

Page 9: Hospital of the Future Construction Update as of Dec. 3, 2010

Endovascular procedure room coordination (each room = 200 hours of configuration).

Page 10: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

2nd Floor: CARE area drywall underway.

Page 11: Hospital of the Future Construction Update as of Dec. 3, 2010

Hospital of the Future

3rd Floor: Rough-in complete; drywall underway.

Page 12: Hospital of the Future Construction Update as of Dec. 3, 2010

2011

Facility Milestones to Come:

•Finished ceilings begin. •Exterior landscaping begins. •Final painting begins.•Phase 1 construction complete.

2012

NEW PATIENT AREAS OPEN!