hitachi’s smart grid solutionseneken.ieej.or.jp/data/4549.pdfhow hitachi’s solution worked on...
TRANSCRIPT
1 Copyright © 2012, Hitachi, Ltd., All rights reserved. 1
Shin-ichi INAGE
Renewable Energy & Smart Grid Division,
Power Systems Company, Hitachi Ltd.
Energy Efficiency Policies and
Technologies in South Africa Workshop
September 6th, 2012
Hitachi’s Smart Grid Solutions
2 Copyright © 2012, Hitachi, Ltd., All rights reserved. 2
Activities of Self Healing System
(FDIR)
3 Copyright © 2012, Hitachi, Ltd., All rights reserved. 3
How Hitachi’s Solution Worked on 3/11
3/11-2011, massive quake and tsunami damaged lots of power plants (total 25GW) and
transmission/distribution systems, which caused wide range blackout.
3/11 quake: Center point and intensity of each area Tsunami
Damaged transmission tower
Damaged distribution line
Source: Tohoku Electric Power Company’s website.
Source: Tohoku Electric Power Company’s website.
4 Copyright © 2012, Hitachi, Ltd., All rights reserved. 4
How Hitachi’s Solution Worked on 3/11
After the quake, power outage recovered rapidly due to power utilities’ hard work for damage recovery and DMS’s self healing function, etc.
※ Picked up the number from Tohoku Electric Power Company’s website. ※ This is not the total blackout number in Japan. Blackout occurred not only in these six prefectures above.
Number of houses / consumers of blackout in six prefectures
Exact and detailed outage information was available on the internet, which helped the rescue and disaster recovery activity.
5 Copyright © 2012, Hitachi, Ltd., All rights reserved. 5
ON ON ON
ON Power
ON OFF OFF
Fault Occurs
Power failure OFF
ON OFF OFF ON ON OFF OFF
ON
Which is effective? Which is stable? ・ ・
1) Normal operation 2) After fault isolation
Why self healing system should be required?
ON
OFF ON
Restoration-1)
OFF
Restoration-2)
Power Power
Power Power
Power Power
Power Power
Isolation Isolation
(18)
6 Copyright © 2012, Hitachi, Ltd., All rights reserved. 6
Distribution management system
DMS Master Station
On-line Server
FEP
Operator’s
Console
(On-line)
Printers Interface Server
Off-line
Server
WAN
Other systems (EMS, GIS, etc.)
GPS Projection Server
Substation RTU
■ FDIR : Automatic Power Restoration upon a fault on a distribution line
High Voltage
Customers
Distribution Line (6.6kV /22kV)
Remote Switch
Rear
Projector
200/100V
Transformer
Residential
Customers
FTU
FTU: Field Terminal Unit
Optional
RTU: Remote Terminal Unit
Operator’s
Console
(Off-line)
Communication Network
Communication Line FTU
Remote Switch
FDIR function
(17)
7 Copyright © 2012, Hitachi, Ltd., All rights reserved. 7
DMS receives fault information
(Trip of Feeder CB. Relay information)
Change color of discharged line to
green)
DMS locates faulty section & outage section
and those sections are displayed in different
colors
(Red: charged, Yellow: faulty,
Green: outage without fault)
Remote switch
(Normally open)
Remote switch
(Normally Close)
Outage section
without fault
Faulty section
Human-Machine Interface of FDIR (1/2)
(20)
8 Copyright © 2012, Hitachi, Ltd., All rights reserved. 8
DMS creates Switching Order automatically to
isolate the faulty section and restore power to
“outage sections without fault” by GA.
DMS executes the Switching Order.
Power is restored to the outage sections
excluding faulty section.
(Purple: Restored)
Switching Order
Case SS Line Tr. Section
Outage
CB/Pole No. Off/On Operation Overload
Create Order Execute Field Operation Print Menu Close
Power restored
in “outage section
without fault”
Outage remains
In faulty section
Human-Machine Interface of FDIR (2/2)
GA : Genetic Algorithm
Close this switch Open this switch
(21)
9 Copyright © 2012, Hitachi, Ltd., All rights reserved. 9
Activities of Renewable Energy
and distributed power
10 Copyright © 2012, Hitachi, Ltd., All rights reserved. 10
Activities of Wind Power Plant
■
■
11 Copyright © 2012, Hitachi, Ltd., All rights reserved. 11
Container
Head Cover
Positive Plate Negative
Plate
Retainer
Terminal
Pole
Safety Valve Specifications of Battery
Energy Storage (Lead Acid Battery)
Specifications LL1500W-S
Voltage 8V
Battery Capacity (10hr) 1500Ah
Energy Capacity 12kW
Installation Horizontal
Dimensions
Heights 473mm
Widths 799mm
Depths 500mm
Weights(4 cells) 485kg
Expected life time
(under 25℃) 17 years
Recycling rate 90%
Storage Of Charge range 30-90% Structure of Lead Acid Battery
2010 ©Hitachi,Ltd.2011. All rights reserved
12 Copyright © 2012, Hitachi, Ltd., All rights reserved. 12
Bifacial PV Module
13 Copyright © 2012, Hitachi, Ltd., All rights reserved. 13 13
Application of Bifacial PV
Building rooftop fences - Experience
Noise barrier fences - Experience
14 Copyright © 2012, Hitachi, Ltd., All rights reserved. 14
Activities of Gas Turbine (H-25)
- Heavy duty design
- High fuel flexibility
- Low NOx emission level
- Various system application
- High reliability
- Easy maintenance
- Worldwide long-term
maintenance support
Cogeneration Plant
Power Output
29,910 kW
Heat Output (6 MPa/ 300 C)
60 Ton/Hr
Overall Efficiency
More than
80 % (LHV)
Product of Hitachi Quality
Supply Experience
Unit Natural Gas
Output kW 32,000
Efficiency %(LHV) 34.8
Performance
15 Copyright © 2012, Hitachi, Ltd., All rights reserved. 15
Activities of Grid Solution
(HVDC)
16 Copyright © 2012, Hitachi, Ltd., All rights reserved. 16
HVDC technology
Thyristor Valves
60Hz 50Hz
Hokkaido-Honshu HVDC
Shin-Shinano FC
Sakuma FC
Higashi-shimizu FC
Minami-Fukumitsu BTB
・Location :
Kansai area – Shikoku area
(Western area of Japan)
・Capacity :
StageⅠ 1400MW(±250kV,2800A)
Next StageⅡ 2800MW(±500kV,2800A)
Shikoku
Kansai
Kii-Channel HVDC
■HVDC has cost benefit because it reduces transmission loss compared
to AC when it is used for long distance or submarine cables transmission.
■Hitachi supplied the main equipment for this system, such as thyristor
valves, converter transformers, and control & protection panels.
©Hitachi,Ltd.2011. All rights reserved
17 Copyright © 2012, Hitachi, Ltd., All rights reserved. 17
Activities of Grid Solution
(Micro Grid System & FEMS)
18 Copyright © 2012, Hitachi, Ltd., All rights reserved. 18
Micro Grid System in Aich Expo (Japan)
■Demonstration of micro grid system with 6-types distributed
powers
NEDO Pavilion
PAFC SOFC
PV
Power
NaS Cell Control room MCFC
Biomass Plant
Micro Grid Communication line
Micro Grid System of Aichi Expo (Total Output:1MW)
Japan Pavilion
Demonstration results Conventional Technologies
Main Power
Grid
・Output variation < 100kW
・Prevention of reverse power flow
・ON-line measurement of systems
・High electricity quality
・ Prediction and planning of CO2
emissions within tolerance of 2%
Optimal
Operations
Demand/Supply
Balance
Electricity Quality
FC:Fuel Cell
・Operation without secondary battery
(Large variation of output)
・OFF-line measurement at local point
Connected Point
Harmonics Flicker Voltage
Fluctuations
0
1
Average
Max
Items
Norm
aliz
ed L
imited
Valu
e (-
)
Verification of systems
・Output variation ~300kW
・Potential of reverse power flow
19 Copyright © 2012, Hitachi, Ltd., All rights reserved. 19
IGCS : Intelligent Grid Control System
Electric Vehicle Station
(High Voltage Charger)
Weather Satellite
Power Demand
BEMS: Building Energy Management
System
FEMS: Factory Energy Management
System
National Grid
Control by Weather Forecast
Stable Power Supply
Wind Turbine
Maximum
Usage of
Renewable
Energy
Solar Power
Battery Gas Engine
Storing Power
Respond in a secon
Power Factor Control
Respond in a minute
Our own experience of FEMS
■On the lat summer, -15% energy saving was achieved.
20 Copyright © 2012, Hitachi, Ltd., All rights reserved. 20
Conclusions
1) Hitachi is willing to respect the existing power gird, utilities
and technologies of the customers.
2) We are intending to contribute to achieve "Best Mix" of
the customers' existing power grids and our leading edge
technologies as WIN-WIN solution.
Trough our Smart Grid technologies, high reliability, low loss,
and high share renewables can be expected.
21 Copyright © 2012, Hitachi, Ltd., All rights reserved. 21
Thank you for your attention!