highway 105 corridor study · typical cross sections highway 105 corridor study 9’ 12’ 10’...

2
Typical Cross Sections Highway 105 Corridor Study 6’ 0’-10.5’ 8’ 12’ 12’ 6’ 6’ 12’ 12’ 8’ 0’-10.5’ 6’ .5’ 2.5’ 2.5’ .5’ VARIES SHLD. LANE LANE MEDIAN LANE LANE SHLD. VARIES WALK (TYP) WALK (TYP) 76’ PAVEMENT 115’ MAX-VARIES ROW STD. PROP. COUNTY R/W STD. PROP. COUNTY R/W C L HIGHWAY 105 2% 2% 2% 2% CURB CURB 21’ 12’ 10’ SHLD. 12’ LANE 6’ 6’ MEDIAN 12’ LANE 10’ SHLD. 12’ 21’ 56’ PAVEMENT 126’ ROW STD. PROP. COUNTY R/W STD. PROP. COUNTY R/W 2’ 2’ APPROX. EXIST. R/W APPROX. EXIST. R/W C L HIGHWAY 105 2% 2% TOP OF CUT EXISTING GROUND TOE OF SLOPE 4:1 3:1 MAX 4:1 3:1 MAX Ultimate Urban 4-Lane I-25 To Lake Woodmoor Ultimate Urban 4-Lane I-25 To Lake Woodmoor Interim Rural 2-Lane Standard Cut/Fill Option Lake Woodmoor To SH 83 Interim Rural 2-Lane Standard Cut/Fill Option Lake Woodmoor To SH 83

Upload: others

Post on 14-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Highway 105 Corridor Study · Typical Cross Sections Highway 105 Corridor Study 9’ 12’ 10’ 12’ 12’ 6’ 6’ 12’ 12’ 10’ 12’ 9’ 80’ PAVEMENT 126’ ROW SHLD

Typical Cross

Sections

Highway 105 Corridor Study

6’ 0’-10.5’ 8’ 12’ 12’ 6’ 6’ 12’ 12’ 8’ 0’-10.5’ 6’

.5’ 2.5’ 2.5’ .5’

VARIES SHLD. LANE LANE MEDIAN LANE LANE SHLD. VARIESWALK

(TYP)

WALK

(TYP)

76’ PAVEMENT

115’ MAX-VARIES ROW

STD. PROP.

COUNTY

R/W

STD. PROP.

COUNTY

R/W

CL

HIGHWAY 105

2%2% 2% 2%

CURB CURB

21’ 12’ 10’

SHLD.

12’

LANE

6’ 6’

MEDIAN

12’

LANE

10’

SHLD.

12’ 21’

56’ PAVEMENT

126’ ROW

STD. PROP.

COUNTY

R/W

STD. PROP.

COUNTY

R/W

2’ 2’

APPROX.

EXIST.

R/W

APPROX.

EXIST.

R/W

CL

HIGHWAY 105

2% 2%

TOP OF CUT

EXISTING

GROUND

TOE OF SLOPE

4:1

3:1 MAX

4:1

3:1 MAX

Ultimate Urban 4-LaneI-25 To Lake WoodmoorUltimate Urban 4-LaneI-25 To Lake Woodmoor

Interim Rural 2-LaneStandard Cut/Fill OptionLake Woodmoor To SH 83

Interim Rural 2-LaneStandard Cut/Fill OptionLake Woodmoor To SH 83

Page 2: Highway 105 Corridor Study · Typical Cross Sections Highway 105 Corridor Study 9’ 12’ 10’ 12’ 12’ 6’ 6’ 12’ 12’ 10’ 12’ 9’ 80’ PAVEMENT 126’ ROW SHLD

Typical Cross

Sections

Highway 105 Corridor Study

9’ 12’ 10’ 12’ 12’ 6’ 6’ 12’ 12’ 10’ 12’ 9’

80’ PAVEMENT

126’ ROW

SHLD. LANE LANE MEDIAN LANE LANE SHLD.

2’ 2’

STD. PROP.

COUNTY

R/W

STD. PROP.

COUNTY

R/W

APPROX.

EXIST.

R/W

APPROX.

EXIST.

R/W

CL

HIGHWAY 105

2% 2%

TOP OF CUT

EXISTING GROUND

TOE OF SLOPE

4:1

3:1 MAX

3:1 MAX

4:1

3.42’10’

SHLD.

12’

LANE

12’

LANE

6’ 6’

MEDIAN

12’

LANE

12’

LANE

10’

SHLD.2’

80’ PAVEMENT

126’ ROW

STD. PROP.

COUNTY

R/W

STD. PROP.

COUNTY

R/W

APPROX.

EXIST.

R/W

APPROX.

EXIST.

R/W

CL

HIGHWAY 105

2% 2%

EXISTING GROUND

FILL SLOPE

RETAINING

WALL

CUT SLOPE

RETAINING WALL

GUARDRAIL

(AS REQUIRED)

Ultimate Rural 4-LaneStandard Cut/Fill OptionLake Woodmoor To SH 83

Ultimate Rural 4-LaneStandard Cut/Fill OptionLake Woodmoor To SH 83

Ultimate Rural 4-LaneStandard Cut/Fill OptionWith Retaining WallsLake Woodmoor To SH 83

Ultimate Rural 4-LaneStandard Cut/Fill OptionWith Retaining WallsLake Woodmoor To SH 83