high volume production contrl activity
TRANSCRIPT
![Page 1: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/1.jpg)
HIGH VOLUME PRODUCTION ACTIVITY CONTROL
![Page 2: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/2.jpg)
DO WE KNOW THE ANSWER FOR THE FOLLOWING QUESTIONS?
1. What will be the production quantity ?
2. Characteristics of the products to be manufactured
3. The availability of the equipment and what kind of equipment are to be purchased?
4. What kinds of labor are required?
5. What should be the level of automation?
6. Make or buy the components required
If the answer to the above questions are known, then the next step in the process
of conversion of raw materials in to finished products is to decide on how each
component is to be manufactured and the sequence of operations to be performed
on it.
![Page 3: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/3.jpg)
PRODUCTION ENVIRONMENT
1. MAKE TO STOCK
2. ASSEMBLE TO ORDER
3. MAKE TO ORDER
![Page 4: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/4.jpg)
PRODUCTION METHODS/SHOP FLOOR TYPES
Mass Production creates a homogeneous product through a continuous series of standard procedures.
Batch Production produces discrete groups (batches) of products. Each item in the batch is similar.
Job shop Production involves the fabrication of discrete products in accordance with customer specifications.
![Page 5: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/5.jpg)
INTRODUCTION-ELEMENTS OF THE FLOW SHOP
An assembly line is a classic example of flow shop Every cars go through all the stations one by one in the same sequences; Same tasks are performed on each car in each station; Its operations scheduling is simplified as assembly line balancing; An assembly balancing problem is to determine the number of stations and to
allocate tasks to each station.
Flow shop: Each of the n jobs
must be processed through the m machines in the same order.
Each job is processed exactly once on each machine.
![Page 6: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/6.jpg)
![Page 7: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/7.jpg)
INTRODUCTION-JOB SHOPTurnning Center Drilling Center
Milling CenterGrinding Center
A job shop is organized by machines which are grouped according to their functions.
![Page 8: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/8.jpg)
Job Shop: Vol. - low Skilled labor are required Layout - product is moved to various work
centers Production usually does not begin before an
order, materials purchased after an order Production scheduling - intensive
scheduling and routing on the shop floor
![Page 9: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/9.jpg)
9
I. Shop Typea. (Flow Shop : Uni-direction)
b. (Job Shop : Multi-direction)
c. (Open Shop: No direction)
M1 M2 M3 M4
M1M2
M3M4
![Page 10: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/10.jpg)
Batch Production
![Page 11: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/11.jpg)
Volume
Variety
JobShop
BatchProducti
on
FlowShop
![Page 12: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/12.jpg)
The major problem is to attain the desired production rate. To this the problems to be addressed are:1. Sequencing of operations2. Ordering of stations3. Number of stations required
Process planning helps in doing this.
![Page 13: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/13.jpg)
Process planning:
![Page 14: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/14.jpg)
![Page 15: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/15.jpg)
Factors effecting Process planning:
![Page 16: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/16.jpg)
Some definitions:
Workstation: A workstation is a location on assembly line where given amount of work is done
Cycle time : It is the amount of time the product (In - process) spends at each workstation.
Cycle time (CT) = Available Time period / Output units required per period
Task: The smallest grouping of work that can be assigned to a workstation
Predecessor Task: A task that must be performed before performing another task.
Balance delay: Percentage of total idle time on the line to total time spent by the product from the beginning to end of line
![Page 17: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/17.jpg)
Balance Delay
BD = (Total idle time for all workstations)/ (Total available working time on all stations)
= (n.CT - ∑ti ) * 100/ (n.CT)
n = Number of workstations ti = station time of specific workstation ∑ti = Total standard station time
BD indicates the inefficiency of the system, which is induced by the idle time
![Page 18: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/18.jpg)
The problem of line balancing arises due to the following factors:
1. The finished product is the result of many sequential operations
2. There is a difference in production capacities of different machines (The /p from different machines is not identical)
Line Balancing: It is the apportionment of sequential work activities in to workstations in order to gain a high utilization of labor and equipment so as to minimize the idle time.
![Page 19: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/19.jpg)
Heuristic methods of line balancing:
• This method tries to reach an acceptable solution rather than an optimal solution .
• Used where optimal solutions are not feasible or are too costly
Procedure:1. Draw the precedence diagram• Numbers are assigned to each operation to denote how many
predessors it has• Operations showing the lowest predecessor number are taken first
on the workstation2. Select feasible cycle time3. Assign work elements to work stations• sum of elemental times should not exceed cycle time• If it does identify the WE due to which this happens and carry it
forward to next station
![Page 20: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/20.jpg)
1. Make a precedence diagram for the following problem and calculate Balance delay, if the Cycle time is 8 min.
Work elements
precedence process
Time
1 0 42 1 23 2 34 1 25 2 56 5 4
![Page 21: High Volume Production Contrl Activity](https://reader034.vdocuments.us/reader034/viewer/2022051404/577ccf511a28ab9e788f71c7/html5/thumbnails/21.jpg)