Page 1: Hibiki-nada could be a world-leading wind power …hibikiwindenergy.co.jp/pdf/hwe_english.pdfLarge-scale offshore wind farm to be built in Sea of Hibiki-nada – The first tendered

P RO J E C T O U T L I N E

Hibiki Wind Energy Co., Ltd.

Hibiki Wind Energy Search

Hibiki-nada could be a world-leading wind power industrial town

2-4-8 Watanabe-dori, Chuo-ku, Fukuoka, 810-0004 JapanPhone: +81-92-983-5873

-Site investigation-Construction, Operation, Maintenance and Decommissioning

Offshore wind farm

-Temporary storage of components and turbine assembly-Pre-shipping inspection

Storage Site for Wind Turbine Components

-Receiving and loading of turbine components-Loading of turbine foundations

Quay side for wind turbine installation vessels

-Base for operation and maintenance-Manufacturing of turbine foundations

Back yard

Operation and maintenance management center of Hokutaku

Image as a general hub port foroffshore wind turbines

h t t p : / / h i b i k iw i n d ene r g y . c o . j p /

In addition to the construction of an offshore wind farm in the City of Kitakyushu port area, we would like to contribute to regional development through the realization of the “Green Energy Port Hibiki” project promoted by the City of Kitakyushu since 2010.As a part of such activity, Hokutaku Co., Ltd, a member of our consortium, has opened an operation and maintenance center, focused on future offshore wind farm operation.In order to make the Hibiki-nada region an international hub port, we will utilize the existing port infrastructure for loading of turbines and components.We are aiming to create a project which regional stakeholders will be pleased to have in their region, based on a spirit of working and growing together with the region.

Source of information: “Guidebook for Green Energy Port Hibiki” published by the City of Kitakyushu with some modification and addition made by our company

2019.8

Inquiries

Page 2: Hibiki-nada could be a world-leading wind power …hibikiwindenergy.co.jp/pdf/hwe_english.pdfLarge-scale offshore wind farm to be built in Sea of Hibiki-nada – The first tendered

Wind turbineinstallation

area

Shirashima Island Ainoshima Island

Planned site for naturalgas �red power plantPlanned site for naturalgas �red power plantPlanned site for naturalgas �red power plant

J-POWER

J-POWERJ-POWER

Wakato Tunnel

WakatoBridge

Hibiki ContainerTerminal

NS Wind Power Hibiki Co., Ltd.

City of KitakyushuEco-Town CenterCity of KitakyushuEco-Town Center

Base area for windturbine industriesBase area for windturbine industriesBase area for windturbine industries

Coal receiving terminalCoal receiving terminal

Shirashima Exhibition CenterShirashima Exhibition Center

Zone for windturbine supplier

Zone for research and deployment(Deployment of small and large wind turbines)

Anse quay sideAnse quay side

HokutakuHokutakuHibiki-nada South quay sideHibiki-nada South quay side

LNG Receiving TerminalLNG Receiving Terminal(Hibiki LNG Co., Ltd.)(Hibiki LNG Co., Ltd.)

City of Kitakyushu Hibiki-nada biotope City of KitakyushuHibiki-nada biotope

Port A

rea of

City

of K

itaky

ushu

MutsurejimaIsland

Umashima IslandShirasu Lighthouse

Waters of the Port of Kitakyushu

*Image

Hibiki Wind Energy Co., Ltd.

Wakamatsu District, City of Kitakyushu

Representative Director Kohei Tsuji

Feasibility study work for powergeneration by offshore wind farm 2 billion yen (Paid Capital) + 2 billion yen (Capital Reserve)

President of Kyuden Mirai Energy Co., Inc

Name

Location

Representative

Business Portfolio

Capital

Date of establishment

Shareholders & ratio of capital contribution

April 17, 2017

Kyuden Mirai Energy Co., Inc. 30%Electric Power Development Co., Ltd.(J-POWER)         40%

Hokutaku Renewable Energy Service 10%Saibu Gas Co., Ltd. 10%Kyudenko Corporation 10%

As of August 2019

Hibiki-nada Offshore Wind FarmProject has started

“Hibiki Wind Energy” was selected as the project developer in February 2017 through the tendering procedure for “The developer and operator of Hibiki-nada Offshore Wind Farm”

announced by the City of Kitakyushu.

“Hibiki Wind Energy” was formed by Kyuden Mirai Energy, Electric Power Development (J-POWER), Hokutaku, Saibu Gas and Kyudenko. We have substantial experience in the wind farm business and

a very close relationship with the City of Kitakyushu as locally-oriented companies.

The aim of this project is to construct an offshore wind farm with a maximum capacity of approx. 220,000kW. However, our aim is not limited to just construction and operation of

this offshore wind farm. We would like to make a meaningful contribution to the plan of “Revitalization of the City of Kitakyushu through wind power business” promoted by the City of Kitakyushu,

utilizing the Sea of Hibiki-nada which is a very valuable resource for local residents.

We would like to progress the project steadily toward realization of the offshore wind farmwith regional stakeholders, and the City of Kitakyushu.

Kyuden Mirai Energy

J-POWER

Saibu Gas Kyudenko

Hokutaku

Summary of project

Project Schedule

Large-scale offshore wind farm to be built in Sea of Hibiki-nada – The first tendered project under the revised Laws of Port Management in Japan –

Note:The above project schedule is as of September 2017

Site Investigation

Wind Measurement

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027YearWorks tobe executed

Facility Design Pre-construction works(obtaining of permissions, etc.)Pre-construction works(obtaining of permissions, etc.)Pre-construction works(obtaining of permissions, etc.)

工事開始、順次運転開始Commencement of construction works and sequential start of operation. Commencement of construction works and sequential start of operation. Commencement of construction works and sequential start of operation. Commencement of construction works and sequential start of operation.

Fukuoka Pref.

City of Kitakyushu

Hibikinada

Onga-gun

Karita Town

Wind Measurement(June 2017 -)

Site Investigation(July 2017 -)

Project sea area: Approx. 2,700ha Designated offshore wind farm area underthe tender

EnvironmentalImpact Assessment

Construction Works

Facility Design, etc.

This project is the first tendered project in accordance with the Law of Port Management, revised in July 2016, and approx. 2,700ha in the Kitakyushu port zone has been designated as the project site.Wind measurement, site investigation, and environmental impact assessment have been commenced since 2017, and based on the results, detailed project planning will be decided.Our aim is to prepare the most favorable business plan which will be beneficial for regional stakeholders while giving them peace of mind, with the best wind farm layout, considering the seaweed bed and fishery reef.

Page 3: Hibiki-nada could be a world-leading wind power …hibikiwindenergy.co.jp/pdf/hwe_english.pdfLarge-scale offshore wind farm to be built in Sea of Hibiki-nada – The first tendered

Wind turbineinstallation

area

Shirashima Island Ainoshima Island

Planned site for naturalgas �red power plantPlanned site for naturalgas �red power plantPlanned site for naturalgas �red power plant

J-POWER

J-POWERJ-POWER

Wakato Tunnel

WakatoBridge

Hibiki ContainerTerminal

NS Wind Power Hibiki Co., Ltd.

City of KitakyushuEco-Town CenterCity of KitakyushuEco-Town Center

Base area for windturbine industriesBase area for windturbine industriesBase area for windturbine industries

Coal receiving terminalCoal receiving terminal

Shirashima Exhibition CenterShirashima Exhibition Center

Zone for windturbine supplier

Zone for research and deployment(Deployment of small and large wind turbines)

Anse quay sideAnse quay side

HokutakuHokutakuHibiki-nada South quay sideHibiki-nada South quay side

LNG Receiving TerminalLNG Receiving Terminal(Hibiki LNG Co., Ltd.)(Hibiki LNG Co., Ltd.)

City of Kitakyushu Hibiki-nada biotope City of KitakyushuHibiki-nada biotope

Port A

rea of

City

of K

itaky

ushu

MutsurejimaIsland

Umashima IslandShirasu Lighthouse

Waters of the Port of Kitakyushu

*Image

Hibiki Wind Energy Co., Ltd.

Wakamatsu District, City of Kitakyushu

Representative Director Kohei Tsuji

Feasibility study work for powergeneration by offshore wind farm 2 billion yen (Paid Capital) + 2 billion yen (Capital Reserve)

President of Kyuden Mirai Energy Co., Inc

Name

Location

Representative

Business Portfolio

Capital

Date of establishment

Shareholders & ratio of capital contribution

April 17, 2017

Kyuden Mirai Energy Co., Inc. 30%Electric Power Development Co., Ltd.(J-POWER)         40%

Hokutaku Renewable Energy Service 10%Saibu Gas Co., Ltd. 10%Kyudenko Corporation 10%

As of August 2019

Hibiki-nada Offshore Wind FarmProject has started

“Hibiki Wind Energy” was selected as the project developer in February 2017 through the tendering procedure for “The developer and operator of Hibiki-nada Offshore Wind Farm”

announced by the City of Kitakyushu.

“Hibiki Wind Energy” was formed by Kyuden Mirai Energy, Electric Power Development (J-POWER), Hokutaku, Saibu Gas and Kyudenko. We have substantial experience in the wind farm business and

a very close relationship with the City of Kitakyushu as locally-oriented companies.

The aim of this project is to construct an offshore wind farm with a maximum capacity of approx. 220,000kW. However, our aim is not limited to just construction and operation of

this offshore wind farm. We would like to make a meaningful contribution to the plan of “Revitalization of the City of Kitakyushu through wind power business” promoted by the City of Kitakyushu,

utilizing the Sea of Hibiki-nada which is a very valuable resource for local residents.

We would like to progress the project steadily toward realization of the offshore wind farmwith regional stakeholders, and the City of Kitakyushu.

Kyuden Mirai Energy

J-POWER

Saibu Gas Kyudenko

Hokutaku

Summary of project

Project Schedule

Large-scale offshore wind farm to be built in Sea of Hibiki-nada – The first tendered project under the revised Laws of Port Management in Japan –

Note:The above project schedule is as of September 2017

Site Investigation

Wind Measurement

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027YearWorks tobe executed

Facility Design Pre-construction works(obtaining of permissions, etc.)Pre-construction works(obtaining of permissions, etc.)Pre-construction works(obtaining of permissions, etc.)

工事開始、順次運転開始Commencement of construction works and sequential start of operation. Commencement of construction works and sequential start of operation. Commencement of construction works and sequential start of operation. Commencement of construction works and sequential start of operation.

Fukuoka Pref.

City of Kitakyushu

Hibikinada

Onga-gun

Karita Town

Wind Measurement(June 2017 -)

Site Investigation(July 2017 -)

Project sea area: Approx. 2,700ha Designated offshore wind farm area underthe tender

EnvironmentalImpact Assessment

Construction Works

Facility Design, etc.

This project is the first tendered project in accordance with the Law of Port Management, revised in July 2016, and approx. 2,700ha in the Kitakyushu port zone has been designated as the project site.Wind measurement, site investigation, and environmental impact assessment have been commenced since 2017, and based on the results, detailed project planning will be decided.Our aim is to prepare the most favorable business plan which will be beneficial for regional stakeholders while giving them peace of mind, with the best wind farm layout, considering the seaweed bed and fishery reef.

Page 4: Hibiki-nada could be a world-leading wind power …hibikiwindenergy.co.jp/pdf/hwe_english.pdfLarge-scale offshore wind farm to be built in Sea of Hibiki-nada – The first tendered

P RO J E C T O U T L I N E

Hibiki Wind Energy Co., Ltd.

Hibiki Wind Energy Search

Hibiki-nada could be a world-leading wind power industrial town

2-4-8 Watanabe-dori, Chuo-ku, Fukuoka, 810-0004 JapanPhone: +81-92-983-5873

-Site investigation-Construction, Operation, Maintenance and Decommissioning

Offshore wind farm

-Temporary storage of components and turbine assembly-Pre-shipping inspection

Storage Site for Wind Turbine Components

-Receiving and loading of turbine components-Loading of turbine foundations

Quay side for wind turbine installation vessels

-Base for operation and maintenance-Manufacturing of turbine foundations

Back yard

Operation and maintenance management center of Hokutaku

Image as a general hub port foroffshore wind turbines

h t t p : / / h i b i k iw i n d ene r g y . c o . j p /

In addition to the construction of an offshore wind farm in the City of Kitakyushu port area, we would like to contribute to regional development through the realization of the “Green Energy Port Hibiki” project promoted by the City of Kitakyushu since 2010.As a part of such activity, Hokutaku Co., Ltd, a member of our consortium, has opened an operation and maintenance center, focused on future offshore wind farm operation.In order to make the Hibiki-nada region an international hub port, we will utilize the existing port infrastructure for loading of turbines and components.We are aiming to create a project which regional stakeholders will be pleased to have in their region, based on a spirit of working and growing together with the region.

Source of information: “Guidebook for Green Energy Port Hibiki” published by the City of Kitakyushu with some modification and addition made by our company

2019.8